Distribution System Operator (DSO) Construct as a Bridge for End-to-End Transactive Operation

Similar documents
Open Access Technology International, Inc. (OATI)

Roadmaps for Demand Response & Storage

MAUI SMART GRID PROJECT

Integrating Renewables and Distributed Energy Resources into California s Electricity Markets

Distributed Energy Resources Roadmap

Demand Response Architecture Integration into the Distribution Management System ABB Corporate Research, Raleigh, NC. ABB Group March 3, 2011 Slide 1

SPP at a Glance. Located in Little Rock. Approximately 600 employees

Distributed Energy Resource Management System (DERMS)

Pacific Northwest Utilities Conference Committee

DER: NYISO Operations Perspective

CAISO-IOU Technical Design Session

Emerging Utility Models The role of the Distribution Platform Optimizer. Nov 2015

Transactive Energy Challenge Kickoff Workshop: Tata Consultancy Services Ltd. (TCS)

NERC Reliability Functional Model

About Schneider Electric

Roadmap to the Future: Integrating Substation InformationandEnterprise Level Applications

FERC Order 841 Electric Storage Resource Compliance Straw Proposal Overview

IDE4L project overview and ANM concept. Distributed automation system

Electrification and its Implications for the California Electricity System

NYISO Market Initiatives Distributed Energy Resource (DER) Roadmap & Integrating Public Policy (IPP)

OMS/DMS Implementation at SDG&E

The Evolution of the PJM Market in the United States: Looking Back to Look Forward

Overview of PJM: Looking Back to Look Forward Tokyo Power Market Summit

Micro-Grid Technology To improve Distribution Reliability and accessibility. Dhananjay Ketkar. Sudesh Kr. Nehru. November 2012

Dynamic Price, Product and Messaging Specification

Raj kumar Rastogi TATA Power Delhi Distribution Limited CII Meet 02-Nov 2012

Smart Grid Enterprise Applications Interoperability Needs Assessment and the MultiSpeak Specification

Source: EEI. Rankings Among Electric Utilities (12 mos. ended 12/31/2007) Assets 11 Customers 5 Revenues 11 Market Cap (as of 2/29/08) 7

Innovation & Grid Modernization at ComEd. Laura García García Grid Strategy & Analytics Commonwealth Edison

2018 Draft Policy Initiatives Roadmap. Market and Infrastructure Policy December 7, 2017

xxx Ancillary services in the distribution network: Where are the opportunities? Assoc. Prof. Andrej Gubina

NYISO Pilot Program Update

Roundtable I: Energy Markets: The Rise of Community and Institutional Scale Resources

Distributed Energy Resources Management Systems

2018 CAISO Policy Initiatives Roadmap

Reliability and the Future of the Electricity Grid: A North American Bulk Power System Perspective

Siemens White Paper. Transactive Energy System. The information presented in this White paper is current as of: August siemens.

Value of the Integrated Grid Utility Integrated Distributed Resource Deployment

The transmission and distribution grids are distinct systems, with inherently different structures, characteristics, functions, operating principles,

PJM Markets. Energy and Ancillary Services. PJM State & Member Training Dept. PJM /29/2014

Integrating Wind Power Efficiently into Electricity Markets Poses New Regulatory Challenges

Transactive Energy Systems Research, Development and Deployment Roadmap

Demand Response Availability Data Systems Definitions

Smart Grid Concept, Applications and Lessons Learned from Recent Deployments

Grid Strategy Perspectives Integrating Grid Modernization, DER and Grid Operations Objectives

Dynamic Price, Product and Messaging Specification

Dispatchable Load SmartDR Assessment

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

Communications Systems

MANAGING ENTERPRISE INFORMATION FOR SMART METERS AND SMART GRID

Demand Response Working Group and Stakeholder Meeting Agenda January 15, 2009

Competitive Wholesale Electricity Market, Transactions, Pricing and LMP Decomposition

INFORMATION TECHNOLOGY PROGRAM DESCRIPTIONS OPERATIONAL INVESTMENTS

Energy Markets - The Basics

Distributed energy resource management - the way forward

Policy and Regulatory Approaches to Grid Integration of Renewable Energy in the US

Digital Grid. MSGS June 26-28, Unrestricted Siemens AG 2015

NYISO Pilot Program Guide

Meter Data Management Systems. Position. Vice President, Product Management. November 29 December 1, 2010 Santo Domingo Dominican Republic

Distribution GIS & Grid Model Data Management

Alternative Transmission Solutions. Can Distributed Generation, Energy Storage and Load Control be Selected and Compensated as Transmission?

Retail-Level Transactive Control Linked to Wholesale LMPs

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Impact of innovation on renewables Integration on renewables

The Internet of Energy A Strong Smart Grid Platform as Key Enabler

DATA AND THE ELECTRICITY GRID A ROADMAP FOR USING SYSTEM DATA TO BUILD A PLUG & PLAY GRID

Smart Grid New Industry Challenge. August 7, 2009 Eugene Litvinov Senior Director, ISO New England IEEE Region 1 Meeting, Springfield, MA

Volume II Market Redesign & Technology Upgrade

Implementing the Smart Grid: Enterprise Information Integration

New Architectures for Interacting with Demand Side Resources in Ancillary Services Markets

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

Conseptualizing Flexibility In Power Systems

SMART GRID SCENARIO. Marina Egea,

PID 276 Feasibility Study Report 4.4MW Distribution Inter-Connection Mermentau Substation

Walk-through of long-term utility distribution plans: Part 1 - Traditional Distribution Planning

POWIN ENERGY MILLIKAN I PROJECT

Smart Grid, Integration of Renewable Sources and Improvement of Power Quality

May 5, ABB acquires Ventyx. ABB Group. May 5, 2010

Workshop: Development of SGAM for OpEN project. Open Energy Networks Project 24 th September to 2 nd October 2018

An Oracle White Paper June Microgrids: An Oracle Approach

Advanced Metering Infrastructure for Seattle City Light

Joint Workshop on Multiple-Use Applications and Station Power for Energy Storage CPUC Rulemaking and CAISO ESDER 2 Stakeholder Initiative

Virtual power Plant Concept in Electrical Networks

PJM Wholesale Markets. Hisham Choueiki, Ph.D., P.E. Ohio PUC Staff October 20-24, 2014 Tbilisi, Georgia

SUMMARY Table 1 presents the proposed 2010 Smart Grid costs for Operations and Information Technology. Operations Projects 3,

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION POST-TECHNICAL CONFERENCE COMMENTS OF SOUTHERN CALIFORNIA EDISON COMPANY

Residential PV Generation: Impacts (Positive and Negative!) on Transmission & Distribution Networks and Operations

SMART GRID CONCEPTUAL MODEL

California ISO Energy Imbalance Market Operations Overview. June 10, 2014 Webinar

Regulation Energy Management Market Simulation. June 14, 2011

Energy Imbalance Market

Briefing on 2018 Policy Initiatives Roadmap and Annual Plan

2012 Grid of the Future Symposium. Evolution of the US Power Grid and Market Operations through the next Decade

Digital for Power & Utility Bottom Line Success. Solutions for Traders, Fuel and Portfolio Managers

Components of A Successful Industrial Demand Response Strategy

Delivering Innovation: Demand Side Management. Bob Hammond, Energy Services Director City of Richland

PJM Overview: PJM Structure and Cross-Border Examples PJM 2010

Integrating High Levels of Variable Renewable Energy Sources

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF Sheet No. 691 ORIGINAL VOLUME NO. III

Transcription:

Distribution System Operator (DSO) Construct as a Bridge for End-to-End Transactive Operation Farrokh Rahimi, Ph.D. Senior Vice President Market Design and Consulting Ali Ipakchi, Ph.D. Senior Vice President Smart Grid and Green Power GWAC/CAISO Meeting and Workshop Lake Natoma Inn, Folsom, CA September 10-11, 2014

Trade Secret This document and attachments contain confidential and proprietary information of Open Access Technology International, Inc. This information is not to be used, disseminated, distributed, or otherwise transferred without the expressed written permission of Open Access Technology International, Inc. Proprietary Notice All OATI products and services listed are trademarks and service marks of Open Access Technology International, Inc. All rights reserved. Proprietary and confidential. Do not copy or distribute without permission from OATI. 2014 Open Access Technology International, Inc. 2

Topics Opportunities and Challenges for Demand-Side Participation in End-to-End Transactive Operations The DSO Concept: Bridging Bulk Power and Prosumer Side Operations DSO Roadmap and Enabling Technologies Proprietary and confidential. Do not copy or distribute without permission from OATI. 2014 Open Access Technology International, Inc. 3

Problem Formulation Changing Electric Industry Paradigm Increasing use of renewable energy at bulk and distributed New technologies Increased demand-side capabilities Bidirectional Flow of Energy, Information, and Money Utility Perspective Explore new products and services to compensate for loss of revenue due to distributed customer side resources Revise operational procedures to maintain distribution system reliability in the face of distributed Demand Response/Distribute Energy Resource (DR/DER) Leverage distributed resources (including DR/DER, storage) to create derivative tradable products for bulk power/market operation Proprietary and confidential. Do not copy or distribute without permission from OATI. 2014 Open Access Technology International, Inc. 4

Problem Formulation (Continued) Balancing Authority/ISO/RTO Perspective Need for increased/new products and services (regulation, ramping, load following, etc.) to maintain bulk power operation Need to rely on demand-side assets to participate in providing such products and services to reduce need for conventional generation How to ensure DR/DER will perform Consumer Perspective Resiliency (MicroGrids) Economic/Transactive Opportunities (MicroGrids, Building Energy Management Systems, HAN, Intelligent Devices, etc.) Proprietary and confidential. Do not copy or distribute without permission from OATI. 2014 Open Access Technology International, Inc. 5

End-to-End Operational Transactions ISO and Wholesale Markets Day-Ahead Real-Time Trans. Constraints Wholesale Prices and Energy Ancillary Services Capacity DR, Ancillary Services Legend Data Pricing Electricity Bulk Power Operation DR Info. and Dist. constraints Settlement Charges Supply Distribution System Direct Load Control Retail Prices Supply and Demand Response Customers Proprietary and confidential. Do not copy or distribute without permission from OATI. 2014 Open Access Technology International, Inc. 6

Linking Demand-Side Capabilities to Wholesale Operations Virtual Power Plant (VPP) Construct Bulk Power Products Hour-Ahead Firm Non Spin Spinning Reserves Market-Based Prices Virtual Power Plant Grid Location P MAX, P MIN Ramp Rate Min/Max Up and Down Time Incremental Cost Curve Capability Data Telemetry Dispatch Instructions Retail Tariff Direct Load Control Time of Use Critical Peak Price Dynamic Pricing Commercial and Industrial Curtailment Contracts Etc. Proprietary and confidential. Do not copy or distribute without permission from OATI. 2014 Open Access Technology International, Inc. 7

Consideration of Power System Characteristics for End-to-End Operation Power system characteristics can impact delivery of transacted quantities from distributed DR/DER assets Reactive power/voltage impacts Phase unbalance impacts Impact of distribution losses Impact of distribution congestion Bulk Power/Wholesale Operator is oblivious to such distribution system impacts associated with its DR/DER resource scheduling and dispatch Distribution Management Systems (DMS) can help determine such impacts Distribution System Operator (DSO) can act as facilitator to ensure such impacts are avoided or mitigated Proprietary and confidential. Do not copy or distribute without permission from OATI. 2014 Open Access Technology International, Inc. 8

Example: Distribution Grid Volt/Var Effect on Available DR Use Case Feeder Voltage: 13.8 kv Feeder Base Load: 9 MW with Unity Power Factor: 3 MW Constant Impedance (Z); 3 MW Constant Current (I); 3 MW Constant Power (P) Participating DR: 900 kw with 0.8 Lag Power Factor Remaining load after deployment of DR: 8,100 kw with Lead Power Factor Feeder Voltage Increase due to Lead Power Factor: 1.5% Increase in base load due to voltage increase: 135 kw Net Demand Reduction: 900-135 = 765 kw Voltage Increase (%) Z Load I Load P Load Total 1.5% 3% 1.5% 0% 90 kw 45 kw - 135 KW Proprietary and confidential. Do not copy or distribute without permission from OATI. 2014 Open Access Technology International, Inc. 9

Example: Operational Impact of Phase- Unbalanced DR Use Case: Feeder Voltage: 13.8 kv Feeder Base Load: 9 MW phase-balanced (3 MW per phase) Participating Demand Response: 900 kw with different amounts on each phase: 300 kw on Phase A; 100 kw on Phase B; 500 kw on Phase C For simplicity, assume both the base load and the DR are unity power factor When the 900 kw DR is deployed, the remaining load will no longer be phase-balanced This results in neutral current and losses for the remaining load; thus reducing the effective DR For a system operator, it is important to know the expected effective DR beforehand With 1% Neutral Losses for Remaining Load, Net Demand Reduction: 900-1%*8,100 = 819 kw Proprietary and confidential. Do not copy or distribute without permission from OATI. 2014 Open Access Technology International, Inc. 10

200 180 160 140 120 100 80 60 40 20 - Operational Impact of Phase-Unbalanced DR (Continued) Phase C 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 50 kva Single Phase Residential 25 kva 25 kva 138 kv Substation 12.47 kv 400-A peak 600-A emergency Feeder rating 21 MVA 138/12.47 Voltage Regulator Single Phase Residential Lateral 1.5 MVA 120 A Fuse Primary Feeder 25 kva Secondary Distribution 50 kva 12.47kV/220V Phase A 200 180 160 140 120 100 80 60 40 20-1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Three-Phase Residential Three-Phase Residential Lateral 1.5 MVA Recloser Single Phase Residential 50 kva 12.47kV/208Y/120 Three Phase Commercial Lateral - 2 MVA 5 MVA 12.47 kv 1 MVA 12.47kV/4160/480V 1.5 MVA 12.47kV/4160/2.4kV Open Tie Neutral current for 10% phase unbalance 3000/2700/3300 kw Neutral current for 10% DR phase unbalance 300/270/330 kw Neutral current for 20% DR phase unbalance 300/240/360 kw DR release: Neutral current for 10% phase unbalance 1200/1080/1320 kw 150 A 7.5 A 15 A 87 A Proprietary and confidential. Do not copy or distribute without permission from OATI. 2014 Open Access Technology International, Inc. 11

The DSO Construct Linking Bulk Power and Distributed Resource Operations DSO to ISO/RTO Forecast Net Load and Dispatchable Products Schedules and Bids Metering and Telemetry DSO Functions Distribution Planning Distribution Reliability Operations Scheduling Forecasting (Load, DR, DER) Scheduling (DR, DER, Market) Dispatch and Real-Time Control Retail Metering and Settlements Retail Market Administration ISO/RTO to DSO Schedules Dispatch Instructions Prices Settlements Proprietary and confidential. Do not copy or distribute without permission from OATI. 2014 Open Access Technology International, Inc. 12

DSO Construct Basic Responsibilities Distribution System Planning Distribution System Reliability/Protection Possible Responsibilities as Linkage Between Bulk Power/Wholesale and End-Use/Retail Market Operations Scheduling Forecasting and Availability Assessment (Load; DR; DER) Aggregation; Virtual Power Plant Creation (Aggregation of distributed demand-side capabilities for provision of different products such as Energy, Ancillary Services, Flexible Ramping, etc.) Scheduling/Bidding into Wholesale Market Dispatch and Real-Time Control DR/DER Resource Dispatch Real-time Control Interchange Management (MSS or Pseudo-BA function) Proprietary and confidential. Do not copy or distribute without permission from OATI. 2014 Open Access Technology International, Inc. 13

DSO Construct (Continued) Possible Responsibilities as Linkage Between Bulk Power/Wholesale and End-Use /Retail Market (continued) Metering and Settlements Interval Metering Measurement and Verification Settlement with Bulk Power/Wholesale Market Operator Settlement with DR/DER asset operators Retail Market Administration DR/DER Programs DR/DER offers (single buyer) Bilateral DR/DER (Full Transactive) Proprietary and confidential. Do not copy or distribute without permission from OATI. 2014 Open Access Technology International, Inc. 14

Different DSO Models DSO-Lite Reliability & Protection Pseudo BA DSO Reliability & Protection Planning Forecasting & Scheduling Planning Forecasting & Scheduling Settlements Dispatch & Control Settlements Dispatch & Control Retail Market Retail Market Comprehensive DSO Reliability & Protection Maximalist (Fully Transactive) DSO Reliability & Protection Planning Forecasting & Scheduling Planning Forecasting & Scheduling Settlements Dispatch & Control Settlements Dispatch & Control Retail Market Retail Market Proprietary and confidential. Do not copy or distribute without permission from OATI. 2014 Open Access Technology International, Inc. 15

Functions Functionality Timeline Timeframes Months Ahead Days Ahead Hours Ahead Real-Time Post Operations Planning & Resource Adequacy Forecasting Market/TE Facilitation Scheduling Dispatch & Control M&V and Settlements Proprietary and confidential. Do not copy or distribute without permission from OATI. 2014 Open Access Technology International, Inc. 16

DSO Key Application Requirements Customer Service Resource & Market Operations Grid Operations Bulk Power Interfaces Forecasting Billing & Settlements CIS Scheduling & Dispatch Retail Market/TE Facilitation GIS OMS MDMS Distribution Assets and Operations Data DERMS DMS Field/Customer Interfaces AMI End-Use Customer Portal R-SCADA D-SCADA Proprietary and confidential. Do not copy or distribute without permission from OATI. 2014 Open Access Technology International, Inc. 17

Illustrative Example S5 S6 S7 S13 S16 S17 S9 S8 SubStation-B 32 MVA 138-12.46 kv S15 S4 S12 S18 SubStation-A 32 MVA 138-12.46 kv S1 S20 S2 S14 S10 S11 S3 Proprietary and confidential. Do not copy or distribute without permission from OATI. 2014 Open Access Technology International, Inc.. 18

Distribution Switching Operation S5 S6 S7 S13 S16 S17 S9 S8 SubStation-B 32 MVA 138-12.46 kv S15 S4 S12 S18 SubStation-A 32 MVA 138-12.46 kv S1 S20 S2 S14 S10 S11 S3 Proprietary and confidential. Do not copy or distribute without permission from OATI. 2014 Open Access Technology International, Inc.. 19

Changing Load and Voltage Profiles S5 S6 S7 S13 S16 S17 S9 S8 SubStation-B 32 MVA 138-12.46 kv S15 S4 S12 S18 SubStation-A 32 MVA 138-12.46 kv S1 S20 S2 S14 S10 S11 S3 Proprietary and confidential. Do not copy or distribute without permission from OATI. 2014 Open Access Technology International, Inc.. 20

Distribution Congestion Management S5 S6 S7 S13 S16 S17 S9 S8 SubStation-B 32 MVA 138-12.46 kv S15 S4 S12 S18 SubStation-A 32 MVA 138-12.46 kv S1 S20 S2 S14 S10 S11 S3 Proprietary and confidential. Do not copy or distribute without permission from OATI. 2014 Open Access Technology International, Inc.. 21

Distribution Congestion Management S5 S6 S7 S13 S16 S17 S9 S8 SubStation-B 32 MVA 138-12.46 kv S15 S4 S12 S18 SubStation-A 32 MVA 138-12.46 kv S1 S20 S2 S14 S10 S11 S3 Proprietary and confidential. Do not copy or distribute without permission from OATI. 2014 Open Access Technology International, Inc.. 22

DSO - New Application Requirements Customer Service Resource & Market Operations Grid Operations Legend: Conventional New Bulk Power Interfaces Forecasting Billing & Settlements CIS Scheduling & Dispatch Retail Market/TE Facilitation GIS OMS Distribution Assets and Operations Data MDMS DERMS DMS+ End-Use Customer Portal AMI R-SCADA D-SCADA Proprietary and confidential. Do not copy or distribute without permission from OATI. 2014 Open Access Technology International, Inc.. 23

DSO as Retail/Transactive Facilitator Balancing Authority (ISO/RTO/Market Operator) Bids and Offers; Forecasts Dispatch Instructions Balancing Authority (Transmission Operator) Availability; Forecasts Deployment Instructions TX Substation TX Substation TX Substation TX Substation BEMS DSO BEMS BEMS DSO BEMS HAN HAN HAN HAN µgrid µgrid µgrid µgrid µgrid µgrid Proprietary and confidential. Do not copy or distribute without permission from OATI. 2014 Open Access Technology International, Inc. 24

Challenges and Opportunities Challenges Regulatory barriers Operator acceptance Free rider concerns Cost shifting concerns Opportunities The DSO construct helps promote use of preferred resources and avoid disruptive operational impacts The DSO construct supports Transactive Energy roadmap There are no technological barriers for implementation of fully transactive (maximalist) DSO Proprietary and confidential. Do not copy or distribute without permission from OATI. 2014 Open Access Technology International, Inc. 25

Concluding Remarks Electric industry landscape is changing due to proliferation of renewable resources and active demand-side participation Emerging technologies help improve efficiency and reduce environmental impacts of energy production and consumption, but create operational problems Preferred Resources (efficiency and environment viewpoints) Disruptive Technologies (operational viewpoint) The DSO construct helps promote use of preferred resources and avoid disruptive operational impacts The DSO and Transactive Energy roadmaps have important touch points in the emerging industry landscape There are no technological barriers for implementation of fully Transactive (maximalist) DSO Regulatory barriers do exist. DSO scope increases as regulatory barriers are lowered Proprietary and confidential. Do not copy or distribute without permission from OATI. 2014 Open Access Technology International, Inc. 26

Questions

Thank You Farrokh Rahimi Ali Ipakchi sales@oati.net 763.201.2000