Wastewater Flow Monitoring Services

Similar documents
3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES

PRELIMINARY WASTEWATER CAPACITY STUDY

Section 8 System Evaluation and Capacity Assurance Plan (SECAP)

Wastewater Collection System

SSO- WDR Compliance Workshop Electronic Reporting: Reporting Requirements & Tips. Sewer System Management Plan Chapter

UCSD. Sanitary Sewer Overflow Emergency Response. Field Guide

Plaza Mexico Residences 3000 E Imperial Highway Lynwood, CA KPFF Job #

Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7: Hydraulic Design of Sewers and Storm Water Drains

WASTEWATER & STORM WATER COLLECTION AND REMOVAL

City of Moss Landing, CA Sanitary Sewer Flow Monitoring SFE File #C Installation Report. Submitted To:

Streamlining I/I Repairs in Berlin Charter Township

Office of Environment, Health and Safety (EH&S) - Sanitary Sewer Overflow Incident Form (rev. 07/2016)

2018 Sewer Collection Master Plan Update

MENIFEE VALLEY CAMPUS MASTER PLAN DRAFT EIR MT. SAN JACINTO COMMUNITY COLLEGE DISTRICT. Appendices

DIVISION 5 STORM DRAINAGE CRITERIA

PART 3 - STANDARDS FOR SEWERAGE FACILITIES DESIGN OF STORM SEWERS

Sanitation District No.1 Cost Effectively Reduces Overflows Into the Ohio River

Sewer system- Design Criteria

Springfield, MO SSO Control Program: Using Big Data to Chart Progress

CHECKLIST FOR STREETS, INLETS, AND STORM SEWER DESIGN

PLANNING FOR THE FUTURE: A REGIONAL MASTER PLAN APPROACH WITH THE OPPORTUNITY TO MINIMIZE FUTURE OPERATION AND MAINTENANCE CONCERNS

Chapter 8. Inlets. 8.0 Introduction. 8.1 General

Exhibit A. Scope of Services for Flow Monitoring Program 2015 Flow Monitoring City of Lawrence, Kansas

Introduction to Storm Sewer Design

3.9 times the average 3.8 times the average 3.6 times the average

WEF Collection Systems Conference 2017

TECHNICAL SPECIFICATIONS FOR INTERCEPTOR AND SIPHON INSPECTION/CLEANING

Wastewater Master Facility Report. (Project Name) (Project Basin Location)

CHAPTER 4 DESIGN CRITERIA

MWRD Sewer Flow Metering Services

Environmental Task Force SSSMP Summary, September 18, 2011 Scheduled for City Council Approval September 26, 2017

CHAPTER 6 COLLECTION SYSTEM HYDRAULIC MODEL

Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans)

PRIVATE STORM DRAINAGE FACILITIES REQUIREMENTS

LEHIGH COUNTY REGIONAL SEWER SYSTEM

RETENTION BASIN EXAMPLE

I - 15 CORRIDOR CAMPUS MASTER PLAN DRAFT EIR MT. SAN JACINTO COMMUNITY COLLEGE DISTRICT. Appendices

GRAVITY CALIBRATION: A SIGNATURE ACCOMPLISHMENT

Chapter 9 Sanitary Sewers

EAST VALLEY WATER DISTRICT Wastewater Collection System Master Plan. Table 4-1 Capacity Evaluation d/d Criteria

Report. Inflow Design Flood Control System Plan Belle River Power Plant East China, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI

Sanitary Sewer Extensions, Lift Stations, and Force Mains Engineering Report Form. I. General Information. 1. Name of Facility:

Basics of Wastewater Collection System

MBARI Sanitary Sewer Analysis Report

Learning objectives. Upon successful completion of this lecture, the participants will be able to:

WASHOE COUNTY COMMUNITY SERVICES DEPARTMENT GRAVITY SEWER COLLECTION DESIGN STANDARDS

City of Clovis Sewer System Management Plan

City of Lawrence, Kansas

Hancor, Inc. Drainage Handbook Hydraulics 3-1

Infiltration and Inflow. Michael Sassaman Phone

Sanitary Sewer Service Alternatives. Presented by Paul Dietz, III, PE PD Cubed LLC Prepared in cooperation with Value Engineering Inc

Golder Associates Inc W. Laburnum Avenue, Suite 200 Richmond, VA USA Tel: (804) Fax: (804)

SEWER SYSTEM DESIGN GUIDELINES

City of Logan Sanitary Sewer Design Standards

L3. Design Criteria of wastewater collection system

SPILL ESTIMATION. Not Just A Guess Anymore

Type of Area Density (persons/ha) Large lots 5-7 Small lots, single family 75 Small lots, two family 125 Multistory apartments min.

SECTION 4 STORM DRAINAGE

Report. Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI

SECTION 2 - DESIGN STANDARDS FOR GRAVITY SANITARY SEWERS

Clean Water 2020 Program

PART V - STORM DRAIN DESIGN CRITERIA

PART V - STORM DRAIN DESIGN CRITERIA

Chapter 7. Street Drainage. 7.0 Introduction. 7.1 Function of Streets in the Drainage System. 7.2 Street Classification

Section 5 - Inflow and Infiltration Analysis

Appendix J Effluent Pump Station

T a b l e o f C o n t e n t s

CITY OF ANAHEIM SEWER DESIGN MANUAL

To review the above SSO report, log into the CIWQS system using the following URL:

Request for Proposals. City of Elyria. Flow Monitoring and Infiltration/Inflow Field Testing Assistance

CITY OF ENCINITAS CITY COUNCIL AGENDA REPORT Meeting Date: June 15, 2011

Technical Memorandum No. 1

Chapter 8 Addressing I/I Issues and High Flows

CITY OF PANAMA CITY BEACH Utilities Administration & Engineering Offices 116 South Arnold Road Panama City Beach, FL 32413

SECTION TEMPORARY SEWER BYPASS PUMPING

Regional Hydraulic Model Plan

Water supply components

WASHOE COUNTY DEPARTMENT OF WATER RESOURCES GRAVITY SEWER COLLECTION DESIGN STANDARDS

1. Overview 2 2. Definitions 2 3. Laboratory Testing Criteria 2. A. Laboratory Qualifications 2. B. Analysis of TSS Samples 2. C.

Assessing SWMM 5 Hydrologic Parameter Benefits for Model Calibration

Capacity Assurance in Charlotte s Central Business District

CHAPTER 4 SYSTEM DESIGN CRITERIA

2010 System Evaluation and Capacity Assurance (SECAP) Update

Municipal Wastewater Flows and Concentrations

APPENDIX J-3. Orcem Stormwater Management and Treatment Facilities Design Summary

BOROUGH OF ALBURTIS SEWER DEPARTMENT

CITY OF LOS ANGELES. Sewer System Management Plan (SSMP) Biennial Self-Audit Report

Rehabilitating a 105-inch Interceptor Innovations and Lessons Learned

CONSTRUCTION PLAN CHECKLIST

FORT COLLINS STORMWATER CRITERIA MANUAL Hydrology Standards (Ch. 5) 1.0 Overview

Sag Pipe (depressed sewers, or Inverted siphons) Dr. Sataa A. Al-Bayati(10-11)

STORAGE BASIN AND PUMPING PLANT DESIGN (G 500)

SEWER SYSTEM MANAGEMENT PLAN (SSMP)

TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements

Before 1990, roughly 116 wastewater

Estimation of Parameters and Flow Characteristics for the Design of Sanitary Sewers in Malaysia

PROJECT UNDERSTANDING

Detention Pond Design Considering Varying Design Storms. Receiving Water Effects of Water Pollutant Discharges

STEERING COMMITTEE MEETING #6

Section 7 Design Criteria Irrigation and Drainage Facilities

Transcription:

Wastewater Flow Monitoring Services For San Gabriel, CA July 13, 2015 through July 21, 2015 Revised October 9, 2015 Leaders in Sewer Flow Monitoring Services 601 N. Parkcenter Dr., Suite 209 Santa Ana, CA 92705 Phone: 714-542-1004 Fax: 714-542-1332 www.uscubed.com www.sewerflow.com

Table of Contents Tab 1: Tab 2: Tab 3: Tab 4: Tab 5: Overview & Site Specific Information 1.1 Overview 1.2 Project Description 1.3 Site Maps 1.4 Summary of Site 1.5 Statistical Analysis 1.6 Proposed Flow Generation 1.7 Conclusions Calibration Sheets, Flo-Ware Graphs & CCTV Report Methods & Procedures & Equipment 3.1 Methods & Procedures 3.2 Equipment 3.3 Benefits 3.4 How it Works 3.5 Accurate Flow Measurements DVD with Raw Flow Monitoring Data and CCTV Photos US 3 Company Information Utility Systems Science & Software

Tab 1: Overview & Summary of Site 1.1 Overview The City of San Gabriel owns and operates over 72 miles of sewer and 1,300 manholes. The main sewer system is located below public streets and, in some cases, within easements that run along the back of private properties. Untreated wastewater is collected in the system and delivered to the trunk line system of the County Sanitation Districts (CSD). The CSD then treats and discharges the wastewater. The City's sewer collection system is operated under a state-issued permit and must comply with Federal and State water quality laws. The City is responsible for properly managing, operating, and maintaining all portions of their wastewater collection system, as well as providing adequate capacity to carry peak capacity flows, protection of surface and ground water supplies, protection of public health by minimizing the frequency of Sewer System Overflows (SSO s), mitigating the impacts that are associated with all SSO s that may occur, and complying with all applicable regulatory notification and reporting requirements. Therefore, the City of San Gabriel prepared a comprehensive study of the public sewer system in 2009. The study included an inventory of the pipes and manholes that make up the system, an evaluation of the sewer flows and capacity of the system, and an assessment of the condition of the system. 1.2 Project Description As a condition of development, sewer flow monitoring is required as a means of continually updating the City database with the most current sewer capacitance information. Utility Systems Science & Software, Inc. (US 3 ) was contracted by to install flow monitoring equipment at a specifically selected sewer manhole downstream from the proposed development at 237 E. Las Tunas Dr. This sewer system assessment was developed for the current conditions to determine existing capacitance. The selected manhole (MH 621) was located at the intersection of E. Las Tunas Dr and St. Francis St. The manhole and project locations as well as the sewer lines are shown on maps in Section 1.3. US 3 performed an initial site inspection to assess traffic control requirements and evaluate the site hydraulics at MH 621. Note: Each wastewater collection system is different, and some of the differences that affect flow monitoring include: slope of sewer line; age, condition and material of sewer line; number and type of connections; and sewer design, specifically the proximity of baffles, drop structures, pumps, siphons, and weirs. An elevated lateral was discharging flow from the west into MH 621, which created hydraulics that were not conducive to flow monitoring; therefore, the next downstream manhole (MH Utility Systems Science & Software 1

555R) was inspected. The hydraulics within this manhole were found to be acceptable; therefore, it was determined that MH 555R should provide an accurate representation of the flow patterns within the upstream sewer line. The City approved of the installation site. Prior to installation of flow monitoring equipment, Downstream Services was contracted to clean the sewer lines adjacent to the proposed project and perform visual inspections using CCTV technology. Therefore, the lines were cleaned and inspected from MH 133 east to MH 621, from MH 193 south to MH 194, from MH 194 west to MH 621, and from MH 621 south to MH 555R. Installation of flow monitoring equipment at MH 555R followed the cleaning and inspection process on 7/13/2015. The manhole was equipped with Hach Marsh- McBirney Flo-Dar AV Sensor and Logger. With the installation and removal of the equipment, the manhole was opened and confined space entry was limited to crossing the plane with hands and arms, but not actually entering the manhole. Even though US 3 personnel did not enter the manhole during installation, they were fully trained and certified in Confined Space Entry and CPR, and in accordance with safety standards, gas readings were taken and recorded throughout the duration of the installation and removal process. In summary, US 3 performed the following services as part of this project: Sewer Flow Monitoring o Detailed preliminary investigation Assessment of traffic control requirements Inspection and evaluation of the site o Installation of a Marsh-McBirney Flo-Dar AV Sensor and Logger Validation of hydraulic suitability Calibration of MM Meter Record of detailed site data o Flow monitoring between 7/13/2015 and 7/21/2015 o Removal of flow monitoring equipment Validation of flow monitoring data Evaluation of the sanitary sewer line at the selected site Development of a report to discuss the flow monitoring data, including system statistics and graphs and the CCTV inspection results Utility Systems Science & Software 2

1.3 Site Maps Figures (above & below): The temporary wastewater flow monitoring location is at the intersection of E. Las Tunas Dr and St. Francis St. MH 555R is located at latitude 34.102994 and longitude -118.097072. Utility Systems Science & Software 3

Figure above: Sewer Map with cleaning, inspection and monitoring locations identified from City of San Gabriel Engineer. Utility Systems Science & Software 4

1.4 Summary of Site Figures below: The photos show MH 555R at the intersection of E. Las Tunas Dr and St. Francis St, which was a commercial/residential area with light traffic. Therefore, appropriate traffic control was required by the field team (cones and signs). Figure above (MH 621) & right (MH 555R): Both manholes had elevated laterals entering from the west, but the lateral in MH 555R appeared abandoned while the lateral in MH 621 was discharging into the center of the downstream flow. Since this was noticeably disrupting the hydraulics, MH 555R was used for monitoring. Utility Systems Science & Software 5

Figure above: Four sewer lines entered MH 555R (one from the east, one from the north and two from the west) and one sewer line discharged to the south. Gas levels were good. The flow monitoring equipment was set to monitor the upstream 8 inch pipe, which entered the manhole from the north. Follow up on this installation confirmed equipment calibration. 1.5 Statistical Analysis Figure below: Site graph of flow, level & velocity and scatter plot of level in relation to velocity from US 3 Flow Monitoring Website (http://flodar.uscubed.com) Utility Systems Science & Software 6

The capacity evaluation method involves the following process: 1. Collect 15-minute interval depth and velocity data points in the pipe over the entire monitoring period and determine the depth vs. velocity relationship or pipe curve based on Manning s equation. 2. Determine statistically the minimum, maximum and average depths and flow rates in the pipe during the monitoring period. 3. Calculate the maximum theoretical unobstructed flow rate for the pipe. 4. Determine remaining capacity at peak flow conditions in the pipe, using the ratios of actual daily flow depths to pipe diameter. The scatter plot above shows the depth vs. velocity data points for the monitored pipe. The pattern of velocity and depth data points for a sewer operating in free-flow conditions over an extended period of time should conform to the depth-velocity relationship of the Manning Equation, which is the basis for evaluating flow meter data. This equation (shown below) defines a commonly used theoretical relationship between depth and velocity in pipes operating under free flow conditions: v = 1.486/n x R 2/3 x S 1/2 Where, v = velocity (fps) n = pipe roughness, defined as the Manning s Roughness Coefficient R = hydraulic radius, defined as wetted area (ft 2 ) divided by wetted perimeter (ft) S = hydraulic slope Level vs Velocity 0.6 in 0.5 in Figure at right: This theoretical pipe curve was generated for an 8 inch pipe with a slope of 0.25%. 0.4 in 0.3 in 0.2 in 0.1 in 0. in 0. fps 0.2 fps 0.4 fps 0.6 fps 0.8 fps 1. fps 1.2 fps 1.4 fps Utility Systems Science & Software 7

The flow monitoring data includes flows from 0.18 ft through 0.40 ft in depth with velocities from zero to 1.68 fps. Therefore, the data points in the scatter plot for MH 555R do not resemble the above theoretical hydraulic operating curve, which was based on the site specific characteristics of the monitored pipe. To summarize the site statistics presented on the following page: During the peak flow, 67.9% of the pipe s capacity was utilized at 128.95 gpm. Average flows utilized 32.7% of the pipe s capacity. According to common sewer design, velocity shall not be less than 2 fps a minimum of once per day to provide sufficient scouring action for self-cleaning. The maximum velocity at MH 555R was 1.68 fps, which only occurred for 0.5 hrs on 7/20, while the average was 0.93 fps. Therefore, this site is likely to have blockage due to settlement of normal system solids. Where 2 fps velocity cannot be provided at least once per day, the slope should be at least 0.01 ft/ft. According to common sewer design, the depth versus diameter (d/d) ratio for gravity drains of 10 inches in diameter or less should be no greater than 0.50 for the ultimate peak flow condition. The average d/d ratio for the site during this study was 0.41 and the maximum was 0.60. Therefore, this site has no available capacity at peak flow. The following is a graphical representation of the site statistics from the data analysis: Flow Stats Level Stats Velocity Stats 0.3 mgd 0.25 mgd 0.2 mgd 0.15 mgd 0.1 mgd 0.05 mgd 0. mgd 0.27 0.19 EST. Cap Max Flow Average Flow 0.09 5 in. 4 in. 3 in. 2 in. 1 in. in. 4.82 3.45 Max Level Average Level Min Level 2.20 1.75 fps 1.5 fps 1.25 fps 1. fps 0.75 fps 0.5 fps 0.25 fps 0. fps 1.68 Max Velocity Averge Velocity Min Velocity 0.93 0.00 Utility Systems Science & Software 8

The pipe capacity was estimated using a Manning s Circular Pipe Flow Capacity chart, where n=0.013 (minimum value for vitrified sewer with manholes, inlets, etc., Chow 1959). Actual velocities and levels were compared to theoretical hydraulic operating curves to determine which slope most closely correlates with data. The result was a slope of ~0.25% (S=0.0025) at MH 555R. Therefore, with the pipe completely full, the velocity should be ~1.215 fps, which when input into the Flow-Ware program produced a maximum capacity of 0.2736 mgd. This is a reasonable assumption based on the flows observed during this study. Site Level (depth) vs Pipe Diameter 1 0.8 d/d 0.6 0.4 0.2 0 7/13/2015 7/14/2015 7/15/2015 7/16/2015 7/17/2015 7/18/2015 7/19/2015 7/20/2015 7/21/2015 7/22/2015 1.6 Proposed Flow Generation The proposed project at 237 E. Las Tunas Drive is approximately 0.61 acres in size. With regard to sewerage service, the expected average wastewater flow (Q AF ) from the proposed project is 13 gallons per minute (gpm). In accordance with common sewer capacity study requirements, the peaking factor used to determine peak flow (Q PF ) for sewer diameters less than 15 inches is 2.5. Q AF (gpm) Q AF (mgd) 2.5 x Q AF = Q PF (mgd) Estimated Total Flow under Peak Flow Conditions (mgd) Proposed Project 13 0.0187 0.0468 0.2325 Utility Systems Science & Software 9

1.7 Conclusions According to the CCTV inspection, between MH 133 and MH 621, there was one deposit of attached ragging and two deposits of attached grease as well as two locations with fractures and three locations with cracks. Between MH 193 and MH 194, there were 18 locations with cracks. Between MH 194 and MH 621, there was one location with fractures and five locations with cracks, and between MH 621 and MH 555, there was also one location with fractures and five locations with cracks. No root intrusion was noted in any of the lines. The graphs for the site show regular daily flow patterns for the first seven days representative of a retired community with a commercial component. On the weekdays, the flow picked up in the mornings at ~0800 and slowed at night at ~2300. On the weekend, the flow picked up a little later in the day, but on the last two days of the study (Monday 7/20 and Tuesday 7/21), the pattern changed and there were increases in both the level and velocity. According to the nearest weather station (San Gabriel KCASANGA7), which is located ~1400 feet NW of the site on N. Del Mar Av, there was 0.17 inches of rain on 7/18 and 0.02 inches on 7/19. Therefore, this could have been the result of infiltration from the rain event. The peak flow of 0.1857 mgd occurred at 0830 on 7/20 and the d/d design criteria ratio of 0.5 was exceeded. In addition, there were two other days on which the 0.5 d/d design criteria ratio was exceeded, occurring on 7/14 from 0800 to 1015 and on 7/16 from 1000 to 1030. On 7/19, flows exceeded the 0.5 d/d ratio limit starting at 2345 until 0015 on 7/20, then continuing on 7/20 from 0530 to 1030 and ending with 2130 to 2230. However, throughout the monitoring period, only 5.4% of the data exceeded the 0.5 d/d design criteria ratio, and by less than 4% on all occasions except on 7/20. The velocities dropped below readable levels from 2.25 hrs to 4 hrs between 0145 and 0600 every day except for 7/19 and 7/21. Studies have shown that Flo-Dar sensors provide accurate velocity readings down to 0.4 fps, but below 0.4 fps, extremely laminar flow makes radar readings much less reliable. Therefore, the cutoff was set at 0.4 fps and any readings below that cutoff were recorded as zero. The consistently low velocities prevented good capacitance within the line and will promote settlement of normal system solids. Using the maximum velocity of 1.68 fps, MH 555R could convey 0.3784 mgd at full pipe and 0.1895 mgd at half pipe. However, since the velocity only reached 1.68 fps twice on 7/20, once at 1545 with a level of 3.61 inches and once at 1630 with a level of 3.55 inches, it is unlikely that this velocity can be expected during peak flow events. Therefore, using the velocity that accompanied the maximum level (4.82 inches) of 1.31 fps, the site could reasonably convey 0.2950 mgd at full pipe. Using the theoretical hydraulic operating curve Utility Systems Science & Software 10

that most closely correlates with the data, the velocity at half pipe should be 1.16 fps, which would convey 0.1309 mgd before the pipe exceeded its d/d design criteria limit of 0.50. Even though velocities occasionally exceed the expected theoretical values at different levels thereby skewing the scatter plot, it is not consistent. Therefore, even though the existing flows are within the conveyance capacity of the pipe, they occasionally exceed the common sewer design criteria with regard to d/d limitations. Due to the occasional d/d design criteria exceedance during the flow monitoring study, a spreadsheet was created showing the addition of the proposed peak flow generation and the estimated depth that can be expected during ultimate peak flow conditions. As shown in the following table, the average d/d ratio with 0.0468 mgd added to every data point was 0.526 and the maximum was 0.704. Utility Systems Science & Software 11