ONCOR INTERCONNECTION APPLICATION AND PROCESS FOR DISTRIBUTED RESOURCES

Similar documents
Get Connected: Distributed Generation

Delaware Electric Cooperative Generator Interconnection Application Long Form (For Use with Generators Greater than 100 kw)

DG Interconnection Procedures Collaborative. January 20, 2017

DISTRIBUTED ENERGY RESOURCE INTERCONNECTION PROCESS REQUIREMENTS

REVISION NO.: 8 EFFECTIVE: 03/26/18

What You Need to Know Before Requesting Interconnection

Net Energy Metering 2.0 Solar PV Interconnection Handbook. Effective January 1, 2017

Net Energy Metering 2.0 Solar PV Interconnection Handbook. Effective December 1, 2017

Illinois Distributed Generation (DG) Procurement. Presented by the Illinois Solar Association and Carbon Solutions Group

effective date 1/8/01

SMALL GENERATION SYSTEM APPLICATION (10 kw OR LESS)

Feed-in-Tariff (FIT) Connection Application Guidelines

LEVEL 2 Application For Interconnection And Net Metering

Business Practice Manual for Distributed Generation Deliverability. Version

Your guide to interconnecting to the We Energies distribution system

LEVEL 1 Application for Interconnection and Net Metering

DISTRIBUTED GENERATION INTERCONNECTION PROCEDURES. June 21, 2011

TRI-COUNTY RURAL ELECTRIC COOPERATIVE, INC. Policy Bulletin No Appendix A SAFETY & INTERCONNECTION REQUIREMENTS FOR ALTERNATE ENERGY PRODUCTION

ENERGEX Inverter Energy Systems

Interconnection Application

CHOPTANK ELECTRIC COOPERATIVE, INC. P.S.C. Md. No. 3 Fifth Revised Page No. 59 COGENERATION AND SMALL POWER PRODUCTION RATE SCHEDULE X

INTERCONNECTION APPLICATION AND AGREEMENT

ERCOT in 2018: Challenges & Opportunities

Original Cal. P.U.C. Sheet No E San Diego Gas & Electric Company San Diego, California Canceling Cal. P.U.C. Sheet No.

Net Energy Metering Aggregation (NEM-A) Welcome Guide

NEW JERSEY BOARD OF PUBLIC UTILITIES N.J.A.C. 14:4-9 Net Metering and Interconnection Standards for Class I Renewable Energy Systems

Solar PV User Guide for Residential Consumers

Generator Interconnection Process. Wholesale Distribution Overview

Experimental Advanced Renewable Program (EARP) Anaerobic Digester. David Ronk

Distributed Generation. Technical Requirements and Interconnection Agreements

Customer-Side Distributed Generation. Net Metering and Small Power Producers

DISTRIBUTED RENEWABLE ENERGY GENERATION POLICY

Peterborough Distribution Incorporated TARIFF OF RATES AND CHARGES Effective and Implementation Date May 1, 2015

Distributed Energy Resources Roadmap

SCE s Renewable Market Adjusting Tariff (Re-MAT) Bidders Conference September 18, 2013

ISO New England 2003 Demand Response Programs

Distributed Renewable Energy Generation Interconnection Policy

Distributed Energy Resources

Transmission Interconnection Requirements. Table of Contents

CALL FOR COMBINED HEAT AND POWER (CHP) PROJECTS. Program Guide

Cluster Study Process

THE POTOMAC EDISON COMPANY Electric P. S. C. Md. No. 53 Fifth Revision of Original Page No. 28 Canceling Fourth Revision of Original Page No.

Open Data Access Framework

GRENLEC s Renewable Standard Offer

Rule 21 Sheet 1 GENERATING FACILITY INTERCONNECTIONS

APPLICATION FOR COMBINED HEAT AND POWER INCENTIVES

MKT IBO Training. Updated: 29 November 2016

Chapter 5 Embedded Generation Information Pack

Demand Response and Energy Efficiency Programs In the Deregulated Texas Electric Market

Adobe Value Incentive Plan (VIP) Channel FAQ

GATS Subscriber Group Meeting 2010 PJM EIS

Revised Draft Final Proposal for Participation of Non-Generator Resources in California ISO Ancillary Services Markets

Distributed Energy Resources (DER) Queue Management

Renewable Energy Impact to Distribution Network Performance and Reliability. ENGR. ROBERTO D. ISIP JR. Head, Network Asset Planning, MERALCO

Dated: April 16, 2002

Everything Online Green Aug 2019

TARIFF FOR WHOLESALE TRANSMISSION SERVICE SHARYLAND UTILITIES, L.P. SHARYLAND UTILITIES, L.P North Akard Dallas, Texas 75201

RE: Evidence Submission (2/4) on Community Solar to AUC DCG Review (22534)

(2) isolated operation with standby service provided by the Company by means of a doublethrow

Grid connected Renewable Generators and Net-metering Amendment Policy

PG&E s Bidders Webinar

METER UPGRADE MANUAL

Generator Interconnection Procedures Overview

E. Helm R. Mundy D. Bernaudo (U 338-E) Before the. Public Utilities Commission of the State of California

Generation Attribute Tracking System (GATS) Overview of PJM-EIS

Session 9: Photovoltaic System Case Studies And Electric Distribution Planning for DER October 21, 2015 Santiago, Chile

Smart Grid Small Generator Interconnection Procedure (SGIP) Updates. December 06, 2016

Union Power Cooperative

20 Nov IEEE Chapters Seminar Grid Energy Storage: Policies. John Martin, AESO

Green Power Connection. Interconnection Process Updates for Contractors in New Jersey

atlantic cit~ elect,ic

An Introduction to Interconnection Policy in the United States

VALUING ROOFTOP SOLAR

SCHEDULE AL-TOU2 Sheet 1 N

RESIDENTIAL SERVICE CLASSIFICATION

CUSTOMER GUIDE FOR THE INTERCONNECTION DISTRIBUTED RESOURCES TO THE PUBLIC SERVICE COMPANY OF OKLAHOMA DISTRIBUTION SYSTEM

Net Metering Inter Connection agreement

Everything Online Green Jun 2019

Non Registered Embedded Generation Information Pack

Everything Online Green Oct 2019

Revision: 67. Prepared by

Relevant changes will be made to corresponding sections of OA and RAA.

Portland General Electric Company First Revision of Sheet No P.U.C. Oregon No. E-18 Canceling Original Sheet No. 26-1

U N I V E R S I TY. FormFire Broker Guides and Training Videos. FormFire Broker Guides. Welcome and Introduction Guide - Click to view

California Independent System Operator Corporation Fifth Replacement Tariff

Technical Requirements for Distributed Generation Connection

PJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, Prepared by Interconnection Planning Department

Ariba Network Online Invoice Guide

Market Opening IT Programme. Market Opening Programme. Supplier Communications Resulting from DUoS Billing & Invoicing

Supplier Registration Form Delaware and Maryland. Please send the completed executed form along with your remaining registration documents to:

3M Ariba Light Account Network Collaboration for Suppliers

INTERCONNECTION REQUIREMENTS FOR CLOSED-TRANSITION TRANSFER OF STANDBY GENERATORS

Supplier Registration Form Maryland and District of Columbia

RATE 665 RENEWABLE FEED-IN TARIFF

Texas CREZ Policy and Transmission Expansion Update. Mark Dreyfus December 2, 2010

Session of HOUSE BILL No By Committee on Energy, Utilities and Telecommunications 1-26

Electric Supply Enrollment Form

Create and Dispatch a Job to a Job Lead

EmployerAccess Plan administration online manual anthem.com/ca

Plan administration online manual anthem.com/ca

Transcription:

ONCOR INTERCONNECTION APPLICATION AND PROCESS FOR DISTRIBUTED RESOURCES 2016 Commercial and Residential Solar Programs Kickoff Meeting November 11-12, 2015 Ken Brunkenhoefer Oncor Asset Planning

OVERVIEW 1. GENERAL INFORMATION 2. TARIFF APPLICATION AND INTERCONNECTION AGREEMENT STEPS & TIMELINES 3. What happened to the energy I generated? 2

1. GENERAL INFORMATION 2. TARIFF APPLICATION AND INTERCONNECTION AGREEMENT STEPS & TIMELINES 3. What happened to the energy I generated? 3

GENERAL INFORMATION What has changed since last year? 1 2 3 Oncor introduced etrack Increase of applications submitted Decrease in overall process time 4

GENERAL INFORMATION What has changed since last year? 1 2 3 Oncor introduced Increase of applications submitted Decrease in overall process time 5

General Information 1 Oncor introduced What it means for Installers Allows Installers to have administrative control of projects Know the status of the project in real time Receive email notification, as the project moves through the workflow Check the meter and profile status Download agreements and permission to operate letters as soon as the documents become available Documents for the projects are all ways available in etrack 6

GENERAL INFORMATION 7

General Information 1 Oncor introduced What it means for Oncor Decreases the amount of time for processing applications and agreements Files stored in a centralized location Improves data sharing among departments and with installers Track the growth of parallel operation interconnected with the Oncor grid Improves accuracy of reporting Provide better overall service to our customers 8

General Information What has changed since last year? 1 2 3 Oncor introduced etrack Increase of applications submitted Decrease in overall process time 9

General Information 2 Increase of applications submitted Classes of Systems 0 500 kw Generally classified as small 501-10,000 kw Generally Classified as large Larger systems normally require Impact Study Fees (See Impact Study Fee schedule in tariff application) Network Systems are downtown grid connected systems (Downtown Dallas and Fort Worth; see Impact Study Fee schedule in tariff application) 10

GENERAL INFORMATION 2 Increase of applications submitted DG FACILITIES INTERCONNECTED WITH ONCOR Type Residential Facilities Residential kw C&I Facilities C&I kw Total Facilities Total kw Wind 208 899 49 2,714 257 3,613 Solar 4,703 28,005 438 30,267 5,141 58,272 Other 2 9 1 20 3 29 Subtotal 4,913 28,913 488 33,001 5,401 61,914 Synchronous 0 0 112 554,398 112 554,398 Total 4,913 28,913 600 587,399 5,513 616,312 September 28, 2015 11

General Information 2 Increase of applications submitted Solar Interconnection Updates as of September 2015 Solar Number of Facilities kw of Facilities Facilities 2009 270 2,499 Facilities in 2010 469 4,807 Facilities in 2011 341 7,895 Facilities in 2012 303 6,328 Facilities in 2013 920 9,419 Facilities in 2014 1,572 17,094 Total YTD 2015 1,266 10,230 5,141 58,272 12

General Information www.oncor.com/solar 13

General Information www.oncor.com/solar 14

General Information What has changed since last year? 1 2 3 Oncor introduced etrack Increase of applications submitted Decrease in overall process time 15

General Information 3 Decrease in overall process time What it means for Installers Overall average application time was up to 6 weeks Application initial review time has decreased to approximately 10 days Average processing time for Oncor finalizing Agreement and issuing PTO is now up to 5 days 16

1. GENERAL INFORMATION 2. TARIFF APPLICATION AND INTERCONNECTION PROCESS FOR DISTRIBUTED RESOURCES 3. What happened to the energy I generated? 17

ONCOR INTERCONNECTION STEPS FOR DISTRIBUTED RESOURCES 1. Customer Application 2. Oncor Initial Screening 3. Oncor System Impact Assessment 4. Interconnection Agreement (IA) 5. Customer Signed IA 6. Construction, Commissioning, and Metering 7. Executed IA & Permission to Operate (PTO) 8. ERCOT Profile Changes 18 11/05/2015 Presented by Ken Brunkenhoefer at the 2016 Commercial and Residential Solar Programs Kickoff Meeting

1. CUSTOMER APPLICATION Customer Submits Tariff Application (TA) to Oncor Tariff Application available at www.oncor.com/dg Applications submitted through etrack https://oncor.anbetrack.com by third party installers signed up by sending email to dg@oncor.com Considerations Submitted by customer or customer s installer Application requirements for small and large systems: Customer information Equipment data Communication contact One-line diagram Relay functional diagram Sequence of operation Breaker failure scheme Preliminary relay settings Layout sketch Study fee Timing Oncor customer starts the process Customer possible delays due to incomplete applications 19

2. ONCOR INITIAL SCREENING (smaller systems) Oncor Reviews Application Advising Customer of the Process Application reviewed for completeness, customer provides site location, desired in-service date, connected capacity and equipment details etrack email notification whether the application is approved or returned back to the customer for additional details Considerations (smaller systems review) Review of ownership and legal name for Interconnection Agreement (IA) Review of equipment certification Review of contact information Review of one-line sketch Review of layout sketch Review of placard specifications Timing Oncor majority of applications reviewed within 10 days Customer mutual urgency for transparent exchange of information 20

3. ONCOR SYSTEM IMPACT ASSESSMENT Assessment of System Impacts and Upgrades for Reliable Interconnection Service study is performed by Oncor Review site specific information to determine potential systems impacts Metering, feeders, substation, and system protection Considerations Small projects (generally 5 kw or less) are approved and the system impact assessment is done in aggregate All other projects are studied on a case-by-case basis considering the capability of Oncor facilities and desired DG capacity Timing Oncor small projects within 5 days, others as schedule with customers Customer decision to proceed if upgrades are necessary 21

4. INTERCONNECTION AGREEMENT (IA) Oncor Prepares an Interconnection Agreement Interconnection Agreement language is approved by the PUC, continues to be evaluated, and generally non-negotiable IA provisions for private or federal governmental entities Considerations IA prepared with direct customer input including all customer information, equipment data, one-line diagram and layout sketch For small systems, etrack forwards the IA electronically to the customer (or customer s third party installer) for customer approval and signature Oncor utilizes electronic signatures through etrack or can accommodate the entire process manually for individual customers as needed Timing Oncor IA prepared within 3 days Customer dependent on customer approval and signature 22

5. CUSTOMER SIGNED IA Customer Returns Signed Interconnection Agreement (IA) An interconnection agreement is required for all distributed resources that operate in parallel with the Oncor delivery system Distributed resources that never connect electrically in parallel do not have any interconnection requirements by Oncor Considerations Signed IA uploaded into etrack by customer or customer s agent If the agreement is not signed and returned (generally within 90 days) it will be cancelled and deleted from etrack Timing Oncor project on hold awaiting customer signature Customer dependent on customer approval and signature 23

6. CONSTRUCTION, COMMISSIONING, AND METERING Oncor Proceeds with Construction, Commissioning and Metering Oncor orders equipment and schedules resources following the fully executed IA and payment for system upgrades Peak demands greater than 700 kw or distributed resources greater than 1,000 kw require Interval Data Recorder (IDR) metering ERCOT Polled Settlement (EPS) metering is optional unless the distributed resource capacity exceeds 10 MW then it is required Considerations Majority of distributed resources (small certified systems) use AMS metering and do not require system upgrades or commissioning AMS meters are currently field programmed to enable an out-flow channel so both in-flow and out-flow of energy are reported Timing Oncor most within 10 days after the IA is signed Customer dependent on customer commissioning of equipment 24

METERING Obtaining Energy Data Test ENERGY CONSUMED Today's reading minus previous reading and result (encourage charting history) Demand Not Used for Residential Oncor FAQ From Website ENERGY SENT TO THE GRID Can I get a list of common questions relating to metering? How do I read my DRG Meter? 11/05/2015 Presented by Ken Brunkenhoefer at the 2016 Commercial and Residential Solar Programs Kickoff Meeting 25 25

7. EXECUTED IA AND PERMISSION TO OPERATE (PTO) Oncor Approves IA and Sends Permission to Operate Final signature approval and date by Oncor fully executes the IA and with the PTO, the customer may operate their distributed resource Credits from the out-flow of energy to the grid will not be reported to ERCOT until the first full monthly billing cycle following either the date of the executed IA or the meter reprogram date Considerations Permission to Operate (PTO) notification is sent automatically from etrack by email following the fully executed IA The electronic communication from etrack is directed by customer input to their designated contacts Timing Oncor within 5 days for most projects and etrack sends the PTO same day following the fully executed IA Customer dependent on when customer chooses to operate 26

8. ERCOT PROFILE CHANGES Oncor Assigns a Profile ID for Distributed Resources Normal load profile is changed to a distributed resource profile necessary for accurate wholesale settlement and customer billing Load profile changes enable the customer s Retail Electric Provider (REP) to recognize out-flow energy sent to the grid Considerations Changes to the distributed resources profile are submitted to ERCOT after the Oncor IA is fully executed Customer may operate with the understanding that credits for the out-flow of energy to the grid will not be available for billing until the first full month (billing cycle) following the latter of either the fully executed IA or the date the meter is reprogrammed to register out-flow Timing Oncor most within 30 days Customer transparent to the customer 27

SAFETY Electrical Equipment and Placard Requirements Oncor requires placards at the utility meter to help employees know there is a DG system on-site and where they can disconnect it if necessary PUC rule 25.212 requires customers furnish and install a disconnect device with visible break and capable of being locked in the open position Certified systems meet UL-1741 and the applicable provisions of IEEE1547 regarding safety and disconnect requirements For non-certified systems Oncor requires specific relaying elements for protection Oncor Personnel Training Oncor crews are trained to follow safe work procedures with all required personal protective equipment (PPE) This training includes isolate and ground procedures that treat everything as energized and this applies with or without DG systems 28

Real Example Worse Case Credit Timing 9-14-2015 Project Submitted 9-23-2015 Project Reviewed and Accepted by Oncor and requested Service Study 9-30-2015 Service Study Generated and approved 9-30-2015 Agreement generated and sent to customer 9-30-2015 Agreement signed by customer 10-1-2015 Agreement signed by Oncor 10-1-2015 Permission to operate granted 10-2-2015 Meter out-flow channel programmed 11-3-2015 ERCOT Profile Updated cannot change profile before 11-03-2015 Cycle Date 08-03-2015 09-01-2015 10-01-2015 10-30-2015 12-01-2015 Meter change First full month cycle with out-flow credits Total time was 41 working days to get to cycle where credits begin Worst case when meter set date was first day of cycle date Average would be 15 days less if you use mid-cycle example 29

1. GENERAL INFORMATION 2. TARIFF APPLICATION AND INTERCONNECTION AGREEMENT STEPS & TIMELINES 3. What happened to the energy I generated? 30

What happened to the energy I generated? I do not see my credits showing up on my bill. I am confused. I generated 600 kwhrs from my system, but my REP says I am getting credit for only 200 kwhrs. 31

What happened to the energy I generated? Month Long Period Oncor Distribution Grid In-flow Register Utility Meter Out-flow Register 2400 kwhrs How much did facility consume? 200 kwhrs 200 kwhrs 600 kwhrs 400 kwhrs Customer Owned Meter M DRG Facility 2800 kwhrs Customer Facility 32

What happened to the energy I generated? Go to www.oncor.com/solar then click Frequently Asked Questions How do I know if my distributed renewable generation (DRG) meter is working? When your meter is registering energy flow, the scroll bar moves across the bottom of the digital register display. When energy is coming in, the scroll bar progresses from left to right. When energy is going out to the grid, it progresses from right to left. One way to ensure your system is working is to turn off all energy-consuming devices, including your generation system. If everything is off, the scroll bar will stop. Once you ve verified that it s stopped, turn your generation system back online and the scroll bar should start to move from right to left. To determine if your system is operating as expected, take a reading of the 057 out-flow kwh register. If you have a three kw solar system operating at full capacity, then in one hour you should produce three kwh (3 kw x 1 hr = 3 kwh) and the out-flow register should have incremented by three units. 3 kw x 1 hr = 3 kwhr 33

What happened to the energy I generated? Oncor Metered Outflow to Grid Channel 057 Customer Load Energy Customer Owned Measurement Meter Customer Load Energy Oncor Metered Consumption Channel 001 34

QUESTIONS? Contacts: Email: dg@oncor.com On the web: www.oncor.com/solar www.oncor.com/dg www.oncor.com/drg etrack Registration for installers *: * Chris Gregory 214 486 5323 chris.gregory@oncor.com Ken Brunkenhoefer 214 486 5547 brunkenhoefer@oncor.com Julio Chavarria 214 486 3935 julio.chavarria@oncor.com 35