Managing Rainwater at the Window-Wall Interface

Similar documents
Evaluating effectiveness of window/wall interface details to manage rainwater Selected Results from US Window Installation Practice

Results on Assessing the Effectiveness of Wall-Window Interface Details to Manage Rainwater

How do you install yours?

THE EFFECT OF WINDOW-WALL INTERFACE DETAILS ON WINDOW CONDENSATION POTENTIAL

NRC Publications Archive Archives des publications du CNRC

WeatherSmart Air Barrier Installation Guide

Designing Exterior Walls According to the Rainscreen Principle

INSTALLING WATER-RESISTIVE BARRIERS & FLASHING

WARRANTY PROVIDER ACCEPTED A REFERENCE GUIDE OF TYPICAL RAINSCREEN WALL AND WINDOW DETAILS

Incorporating Insulating Sheathing into the Design of the Thermal and Moisture Management System of the Building Enclosure

Evolution of Wall Design for Controlling Rain Penetration

5.7 DESIGN OF THE WALL-WINDOW INTERFACE 1

Evaluation Report CCMC R Surround HouseWrap - Air Barrier Material

The Disclaimer located on the reverse side of the title page of the OAA Rain Penetration Practice Guide applies to each section of the Guide.

Weatherproofing ICF Walls Lessons from BC Research

Innovating Continuous Exterior Insulation. Theresa A. Weston, PhD. 1

The better way to build TM. Installation Manual NAILBASE PANELS

We met at the parapet and it was transition at first sight. Christine Cronin, Building Science Corporation

RevealShield SA Penetrations

FMA Installation Committee

A Study of the Rainscreen Concept Applied to Cladding Systems on Wood

12 - V0 CFP-12 PANEL INDEX. Delta Series CONCEALED FASTENED PANELS BUILDING PRODUCTS VERTICAL PANELS

Building Enclosure Design Fundamentals, Components, and Assemblies

Installation Guidelines

FMA / AAMA / WDMA Installation Committee Update. Jim Katsaros / DuPont Building Innovations FMA Installation Committee April 24, 2012

ELEVATION FOR DETAIL REFERENCE ONLY

Aqua Coast Engineering

FMA/WDMA FMA/WDMA

2006 Building Code Flashing Changes & Challenges. Builder Breakfast and Luncheon Series Presented by:

PRELIMINARY RESULTS FROM FIELD EXPERIMENTAL STUDY OF RAIN LOAD AND PENETRATION INTO WOOD-FRAME WALL SYSTEMS AT WINDOW SILL DEFECTS

DuPont Tyvek Air Barrier Installation Guidelines. Canadian Version. Version 2

Pella 250 Series. Wood Frame Construction with Vinyl Siding... V250-ID-888 Wood Frame Construction with Brick Veneer...

Building Science Control Layer Glossary. Façade Visible exterior face of a building, usually vertical or nearly so, but imprecisely used.

In addition to performing as an interior vapor retarder, MemBrain the Smart Vapor Retarder may be installed as a continuous, interior

ICF Field Testing Report RAFT

Building Envelope Solutions, Inc. Identifying solutions for better building performance

Evaluation Report CCMC R Tyvek HomeWrap - Air Barrier Material

Insight. Drainage, Holes and Moderation. By Joseph W. Lstiburek, Ph.D., P.Eng., Fellow ASHRAE

WrapShield SA Brick Tie Penetration

ELEVATION FOR DETAIL REFERENCE ONLY

NEXT GENERATION HIGH PERFORMANCE WALLS

ELEVATION FOR DETAIL REFERENCE ONLY

Rainscreen Walls: Field Monitoring and Performance in British Columbia

Project No: Pakenham Branch Library, Pakenham, Ontario Section January, 2017 Page 1 of 7

ELEVATION FOR DETAIL REFERENCE ONLY

Revised January buildingscience.com. Water Management Details. Housewraps/Flashings/Windows buildingscience.com

U.S. Department of Housing and Urban Development Office of Policy Development and Research

FACE CFP - HORIZONTAL PANELS - OPTION 'B'

FMA/AAMA/WDMA Installation Committee Update FMA Conference St. Petersburg, Florida / May 18, Jim Katsaros FMA/AAMA/WDMA Installation Committee

Industry Standards for Robust Installation of Emerging Window/Wall Systems California Energy Commission April 28, 2016

WEB BASED APPLICATION SPECIFIC INSTALLATION INSTRUCTIONS

Wall Energy Rating Impact of Air Leakage on Energy Performance

Evaluation Report CCMC R StoGuard (w/ Sto Gold Coat and Sto Gold Fill ) sheathing membrane

Evaluation Report CCMC R Sto Guard - Air Barrier Material

March 5, Tatley Grund, Inc. Building Repair Specialists 1115 No. 97 th Street Seattle, WA Stace Grund, President

Stucco Detailing for Buildings With Unique Geometry

STRATUM GUARD I AND II An Exterior Insulation and Finish System with Drainage DSC106C. Stratum Guard I and II System Installation Details

2001 Building Failures Study

Rain. Building Science. Rain is the largest source of moisture We need better control for better insulation and airtightness Rain penetration control

RESIDENTIAL INSULATED SHEATHING COMFORTBOARD. Installation Guide

Insulation. First Revison October DC14 Drainage Mat INSTALLATION GUIDE FOR RESIDENTIAL & COMMERCIAL APPLICATIONS

RESIDENTIAL INSULATED SHEATHING INSTALLATION GUIDE. Residential Insulated Sheathing Installation Guide ROXUL COMFORTBOARD 80

2015 IECC Air Sealing Multifamily For Code Compliance Funding for Energy Code Training

Building Envelope Enclosures That Work, What Owners Want!

Ultra Wall System. CAD Detail Sets

PICK YOUR POISON AND HOW TO GET THERE. Presented By Robby Schwarz

A Methodology to develop moisture management strategies for wood-frame walls in North America: application to stucco-clad walls

SECTION STAINLESS STEEL WALL PANELS

The Role of Control Layers in Building Enclosure Design

Keene Building Products

CWCT CURTAIN WALL INSTALLATION HANDBOOK

Tender No Section St. James - Assiniboia Centennial Pool Fitness Facility Addition Page 1

BUILDING ENVELOPE By Sabrina D Ambra

Henri Fennell, CSI/CDT ABX 2015

BUILDING ENCLOSURE AIR TIGHTNESS TESTING Course Number: BCLUNA018-01P

Guide Specification for the OSI QUAD Window and Door Flashing System

Evaluation Report CCMC R FOAMULAR CodeBord Air Barrier System (CABS)

MID-CONSTRUCTION BLOWER DOOR TESTING February 15, 2017

How-to: Commissioning Design Reviews for the Building Envelope

Product and System Specifications DuPont Flashing Systems

Building Enclosure Details and Assemblies for Wood-Frame Buildings

Table Air Barrier and Insulation Inspection Component Criteria

Window Installation Instructions Series 1000 Steel Replica Window

FirstEnergy Program Overview

FMA_AAMA_WDMA Installation Committee Update FMA Conference May 8, Naples, FL. Jim Katsaros FMA_AAMA_WDMA Installation Committee

EIFS Rain Control EIFS. Face Sealed Perfect Barrier. Beware of EIFS: They must be done correctly They leak at joints Avoid moist sensitive substrate

FMA/AAMA Standard Practice for the Installation of Windows with Flanges or Mounting Fins in Wood Frame Construction

National Master Specification (NMS) Section Publisher: Spex.ca Page 1. Approved: RELATED REQUIREMENTS.1 Section [ ].

Pebbletex Wall System Class PB Exterior Insulation and Finish System providing a primary moisture barrier. Typical Details

ELEVATION FOR DETAIL REFERENCE ONLY

AcroWall-ES System. Class PB Exterior Insulation and Finish System providing a primary moisture barrier. Typical Details

Limited Leak Assessment

Building Construction and Water Intrusion

A New Paradigm for the Design of Sustainable Buildings

Moisture Considerations for Insulated Building Assemblies

6. Moisture Design. Objectives: 3. Prevent vapor condensation (surface, concealed) 4. Prevent rain penetration

Perimeter Relief and Control Joints in Fire-Rated Gypsum Board

KARRIER PANEL - BRICK

Building Enclosure Assemblies that Work for Taller Wood Buildings

REPORT HOLDER: R.L. ADAMS PLASTICS, INC CROSSROADS COMMERCE PARKWAY WYOMING, MICHIGAN EVALUATION SUBJECT: POLYCORE BRAND INSULATION

Transcription:

Managing Rainwater at the Window-Wall Interface Prepared by : Silvio Plescia (CMHC) and Michael Lacasse (NRC) ANHWP, Edmonton and Calgary, 23-24 September 2009 CMHC SCHL

Introduction The problems you know what they are but to summarise...results from BE surveys Wall- Window interface details Key elements from laboratory studies Thermal performance at the interface Does this work? Visual evidence from the laboratory

Introduction, cont d CMHC Surveys of Building Envelope Performance 1995 Survey of Building Envelope Failures in the Coastal Climate of British Columbia 1999 Wall Moisture Problems in Alberta Dwellings 2001 Study of High-Rise Envelope Performance In The Coastal Climate of British Columbia

Surveys of Building Envelope Performance The Survey - Why Did Walls Fail? Inappropriate balance between wetting and drying mechanisms Exposure - walls got wet Details - let water in Sensitivity of assemblies - inability to drain or dry Wetting Drying

Surveys of Building Envelope Performance, cont d Finding: (at least) 25% of the moisture problems associated with water ingress into wall assemblies were directly attributed to penetration through the windows or the window-wall interface

Windows and the Building Envelope Rain penetration is a major problem with glazing and must be controlled. Glazing Design - Canadian Building Digest #55 (CBD55) published in July 1964 Many inquiries concerning rain penetration of exterior wall are received by the B.C. Regional Station. and are focused on window installation practices. Rain Leakage of Residential Windows in the Lower Mainland of British Columbia Building Practice Note No. 42 (BPN42) Division of Building Research, National Research Council of Canada November 1984.reports on window performance problems in Atlantic Canada.. Building Research Note No. 210 (BRN No. 210) - 1984

2002 Water Penetration Resistance of Windows STUDY OF MANUFACTURING, BUILDING & INTERFACE DESIGN, INSTALLATION AND MAINTENANCE FACTORS WINDOW TERMINOLOGY SUMMARY OF STUDY WINDOW INSTALLATION GUIDE STUDY OF CODES, STANDARDS, TESTING AND CERTIFICATION RDH

Partial Conclusions and Recommendations Most frequent leakage path L5 (L5 : Through window-wall interface to adjacent wall assembly) L4 and L5 are considered high risk for consequential damage (L4 : through window to adjacent wall assembly) Minor variation exists between window types with respect to leakage paths L3 L2 L6 L1 L4 L5

Partial Conclusions and Recommendations The CSA A440 B rating performance criteria does not address the current dominant leakage paths that are associated with installed windows Leakage Paths Risk of Consequential Damage Rating Applicability of A440 Testing to Leakage Path L3 L2 L1 - Through fixed unit to interior Moderate Good L6 L2 - Around operable unit to interior Moderate Good L1 L3 - Through window to wall interface to interior Moderate Never L4 L4 - Through window assembly to adjacent wall assembly High Sometimes* L5 L5 - Through window to wall assembly interface to adjacent wall assembly High Never L6 - Through window assembly to concealed compartments within window assembly Minor Good Depends on where window frame is attached to test frame

Partial Conclusions and Recommendations Manufacturers have to focus on the design of the entire installed window. This includes the interface with the perimeter building walls. Windows need to be installed with redundant assemblies. The addition of sub sill drainage to interface design e.g. would improve water penetration performance of installed windows Designers need to increase their focus on interface detailing, considering continuity of all of the critical barriers.. Installers need to have greater understanding of the manufacturing and building design strategy. The creation of a mandated or generally accepted certification protocol, would have a positive impact on quality control issues.

Key Points Test results indicate dominant water leakage paths as: CMHC-NRC (with industry partners) initiate WWI project to evaluate water management performance of various window installation details L4 : through window to adjacent wall assembly Possibility to evaluate different interface details and L5 their : Through ability window-wall to manage rainwater interface entry to adjacent evaluate wall robustness assembly of design Development High frequency of a of standards occurrence and approach consequential in a damage laboratory L4 & L5 not setting addressed precursor by current to window a field standards certification protocol Benchmark performance of proposed designs

NRC/IRC Test Program Detail A Variation Develop procedure to assess rainwater ingress Evaluate specific window-wall interface details to determine how effective they manage rainwater intrusion

Test Specimen

Effectiveness of Seals at Window Frame/Sheathing Membrane Joints Several approaches to seal the joints between the window and the wall against water ingress were examined: Seal the back of the window flange against the sheathing membrane

Self-adhered Membranes Strip of self-adhered flashing membrane over the joint between the window flange and the sheathing membrane (not at sill)

Self-adhered Membranes

Test Observations Reverse lapping Shingle-lapping Large water accumulation on the window head Water accumulation at head NO Water accumulation at head

Test Observations Fish mouths and reverse lapping allowed water ingress

Sequencing is Critical Reverse lapping can channel water behind the plane of water resistance, and risk of damage increases Shingle lapping is essential Rough sill flashing laps OVER the sheathing membrane Sheathing membrane laps OVER the drip cap head flashing Rough jamb membrane laps OVER the corner upstand of the sill flashing

Flash and drain the rough opening Lesson #1: The Rough Opening Will Get Wet: Drain it Out Protect moisture-sensitive materials from water absorption Provide a drainage path to the outside Sloped rough sill Back dam Water impermeable rough sill; up 150 mm on the jambs Ease of drainage out of rough sill, and out of wall assembly Integration with other elements contributing to the control of rainwater ingress (i.e. shingle lapping, sequencing) ROUGH SILL FLASHING SYSTEM

Ensure positive drainage: Do not caulk back of window flange Do not tape front of flange sill joint Install window on shims or on furring strips to create a clear gap (plus enhanced venting) - Provide drainage at sill no seal along flange Facilitate Drainage at Rough Sill of Flanged Windows Window installed Shims over created furring a gap strips

Specimen Details- W3 Window installed over furring strips Shims created a gap

Air Pressure Difference Effect on water accumulation on rough sill of: Location of highest air pressure drop in relation to location of plane of wetness Air leakage rate

Observations: Lesson #2: Location of Higher Pressure Drop in WWI should be DRY A typical technique for sealing window flange to sheathing membrane created a plane of high resistance to air flow on exterior but was not 100% resistant to water flow. High pressure drop occurred across that imperfect seal, which was also covered by a film of water. Air pressure difference drove water through interface seal - resulting in higher water accumulation onto rough sill. A technique consisting of maintaining sheathing membrane/ window flange connection but having lower resistance to air flow than interior air barrier resulted in lower water accumulation on rough sill.

Fabrication of V-side ASTM Back side of flange is caulked

Observations Effects of Air Pressure Distribution Specimen B-W1 (V-side; ASTM): High pressure drop ( P) across wetted airtight external plane Bead of sealant at back of window flange No venting or drainage at sill 55 Pa Exterior 302 Pa P = 302 55 247 Pa Self-adhered membrane Tighter plane of the assembly Pressure tap to measure air pressure in the cavity behind the siding (cavity) Higher water deposition on the rough sill 0 Pa Interior Jamb detail (horizontal view) Pressure tap to measure air pressure in the stud cavity (stud) Intended interior air barrier leakier than exterior wet layers of wall specimen

Observations Effects of Air Pressure Distribution Specimen B-W1 (B-side): Lower pressure drop across wetted vented external plane No seal behind flange Vented and drained 185 Pa at the sill Exterior 302 Pa P = 117 Pa Self-adhered membrane Airtightness at this plane of wall assembly not as tight as V-side (ASTM method) Pressure tap to measure air pressure in the cavity behind the siding (cavity) Lower water deposition on the rough sill 0 Pa Interior Pressure tap to measure air pressure in the stud cavity (stud) Intended assembly air barrier leaks as much as V-side Jamb detail (horizontal view)

Reservoir Water Entry - 08 ABS Observations Effect of Location of Plane of Airtightness Rate of water deposition on the rough sill (ml/min) 140 120 100 80 60 40 Airtight plane on exterior- WET Same rate of air leakage across specimen, 2 different designs 20 DRY- Airtight plane on interior of joint 0 0 100 200 300 400 500 600 700 800 Chamber Pressure (Pa)

Lesson #3: Keep Air Barrier Tight and Dry Current practice aims at sealing joints that can get wet: joint between window frame (flange) and sheathing membrane Imperfect seals that got wet and were subjected to higher pressure difference sucked water through seal imperfections Plane of higher pressure drop (Air Barrier System) should be in a dry location, further inside and towards interior of joint

Effect of Leakage Rate of Interior ABS Leakier intended air barrier system resulted in higher water deposition on rough sill (exterior plane was sealed) Rate of water deposition on the rough sill Higher air leakage rate on interior ABS Lower air leakage rate on interior ABS 0 Pa 700 Pa

Other Factors to Consider Location of window in relation to thermal plane of wall Thermal effects of draining sill Effect of placing insulation into wall/window joint cavity on drainage capability

Other Factors to Consider Location of window in relation to thermal plane of wall Vancouver, -5 C outside; 20 C inside 3.0 C 7.0 C

To Foam or not to foam? Is that the question? Photos from Gas Technologies Institute

To Foam or not to foam? Is that the question? Photos from Gas Technologies Institute

To Foam or not to foam? Is that the question? Photos from Gas Technologies Institute

Three Points to Remember Correctly install a subsill flashing system to protect moisture-sensitive materials in R.O. The rough opening will get wet during service life Ensure first and second line of defense against water penetration are not most airtight layers of wall. Air barrier must be dry. Rain screen principle applies to WWI too Ensure all elements are shingle-lapped to outside - Ensure proper sequencing takes place. Review those responsible for installation

Does this approach work? Visual evidence from the laboratory The following video is courtesy of Mario Goncalves at Patenaude-Trempe and Air-Ins Inc. Varennes, Québec.

Project literature Phase A Interface details typical of Canadian practice Phase Further B reading Variations incorporating a drainage Lacasse, M.A.; Rousseau, medium M.Z.; Cornick, S.M.; Plescia, S."Assessing the effectiveness of wall-window interface details to manage rainwater," 10 Phase C Use of flexible self adhered flashing th Canadian Conference on Building Science & Technology (Ottawa, ON, May 12 2005), pp. 127-138, membrane (NRCC-47685) Phase Lacasse, M.A. D et al., Results Installation Assessing the variations Effectiveness of for Wall-Window light Interface Details to Manage Rainwater, 11 commercial design th Canadian Conference on Building Science and Technology, Banff, Alberta, 2007 Cornick, S.M.; Lacasse, M.A. "A Review of climate loads relevant to assessing the watertightness performance of walls, windows and wall-window interfaces,"journal of ASTM International, Vol. 2 (10), Nov/Dec 2005, pp. 1-16 (NRCC-47645)

Project literature Phase B Variations incorporating a drainage medium Lacasse M., Armstrong, M., Ganapathy, G., Rousseau, M., Cornick, S., Bibee, D., Shuler,D., Hoffee, A., Assessing the Effectiveness of Wall-Window Interface Details to Manage Rainwater Selected Results from Window Installation to a Wall Sheathed in Extruded Polystyrene, JAI (October 2009) Volume: 6, Issue 9, DOI: 10.1520/JAI101270 Lacasse, M., Rousseau, M., Cornick, S., Armstrong, M., Ganapathy, G., Nicholls, M., Williams M., Laboratory Tests of Water Penetration through Wall-Window Interfaces Based on U.S. Residential Window Installation Practice, JAI (September 2009), Volume: 6, Issue 8; DOI: 10.1520/JAI101428 M. A. Lacasse, S. M. Cornick, M. Rousseau, M. Armstrong, G. Ganapathy, M. Nicholls, and S. Plescia, Towards Development of a Performance Standard for Assessing the Effectiveness of Wall-Window Interface Details to Manage Rainwater Intrusion ; JAI (October 2009) Volume: 6, Issue 9, DOI: 10.1520/JAI101446