THE BRACE CONNECTION THE BOLTED OPTION FIGURE 1 MODEL SHOWING THE BOILER AND THE STRUCTURAL SUPPORT SYSTEM (BOILER BUILDING)

Similar documents
Survey and Testing of Pre-1988 Braced Frame Structures From The West Coast of the United States

Supplemental Structural Correction Sheet Steel Moment Frame Design (2017 LABC)

2016 AISC Standards. Specification for Structural Steel Buildings & Code of Standard Practice for Steel Buildings and Bridges.

CHAPTER 14 SLOTTEDWEB (SW) MOMENT CONNECTION

manualwise BRACED FOR BETTER SEISMIC DESIGN

Figure 1 Example of HSS column splice

THE PLAZA AT PPL CENTER ALLENTOWN, PA

STEEL REACTION FRAME

22. DESIGN OF STEEL BRACED FRAMES Eccentrically Braced Steel Frames

Interpretation of SECTION 12 DESIGN AND DETAILING FOR EARTHQUAKE LOADS IS

SEISMIC PERFORMANCE OF SCBF BRACED FRAME GUSSET PLATE CONNECTIONS

Tech Tips SidePlate Connections FAQ 09/30/2017

Supplemental Structural Correction Sheet Steel Brace Frame Design (2017 LABC)

BUILDING RETROFITS: BREATHING NEW LIFE INTO EXISTING BUILDING STRUCTURES

Types Of Roofs - Vault

ICC-ES Evaluation Report Issued November 1, 2011 This report is subject to renewal November 1, 2012.

Supplement No. 1 to AISC Prequalified Connections for Special and Intermediate Steel Moment Frames for Seismic Applications

Top Things To Know About HSS Connections

THE USE OF DUCTILITY IN NUCLEAR FACILITIES

steelwise WHAT S NEW WITH PREQUALIFIED CONNECTIONS? A look at the latest version of AISC 358.

OCTAGONAL SHAPE REDUCES AIRPLANE HANGAR COSTS

DIVISION: METALS SECTION: STRUCTURAL STEEL FRAMING REPORT HOLDER: CAST CONNEX CORPORATION

SECTION PLATE CONNECTED WOOD TRUSSES

ISSUE A Code Change # 2 Class 3 and Class 4 Buildings

CYCLIC BEHAVIOR OF AN INNOVATIVE STEEL SHEAR WALL SYSTEM

DIVISION: METALS SECTION: STRUCTURAL STEEL FRAMING REPORT HOLDER: SEISMIC STRUCTURAL DESIGN ASSOCIATES, INC.

APPENDIX B. LOAD FRAME. This Appendix will describe the philosophy in the design and operation of the loading system.

Overview of Presentation. SCBFs are Conceptually Truss Structures

JONES AIRWAY, LLC CLEVELAND REGIONAL JETPORT SECTION STRUCTURAL STEEL

VOLUNTARY - EARTHQUAKE HAZARD REDUCTION IN EXISTING HILLSIDE BUILDINGS (Division 94 Added by Ord. No. 171,258, Eff. 8/30/96.)

Ductility of Welded Steel Column to Cap Beam Connections Phase 2

Investigation of Structural Steel Webs for Punching Shear

EngDoc.ir. Page 1 of 51

steelwise A Closer Look at Steel Plate Shear Walls

THE EFFECTS OF FRAME DEFORMATION ON WELDED GUSSET PLATES FOR DIAGONAL BRACING ELEMENTS LOADED IN TENSION

James Hauck 1 and Christine Moe 2

CHEVRON BRACED FRAMES WITH YIELDING BEAMS: EXPERIMENTS AND NUMERICAL ANALYSIS

Originally Issued: 09/28/2017 Valid Through: 09/30/2018

Council on Tall Buildings

Brent Ellmann Structural Option 200 Minuteman Park, Andover, MA Structural Consultant: Dr. Hanagan

CEILING MOUNTED ARTICULATING JIB CRANE

Seismic Steel Design 12/9/2012

IBC 2015 and Cold-Formed Steel Design Standards and Design Aids. Roger LaBoube Wei-Wen Yu Center for Cold-Formed Steel Structures

SECTION COLD-FORMED METAL FRAMING

Cold-Formed Steel Special Bolted Moment Frames: Cyclic Testing and Numerical Modeling of Moment Connections

CHAPTER 1 INTRODUCTION 1.1 MOMENT END-PLATE CONNECTIONS

SEISMIC BEHAVIOR AND DESIGN OF STEEL SHEAR CONNECTIONS WITH FLOOR SLABS

CAST STEEL YIELDING FUSE FOR CONCENTRICALLY BRACED FRAMES ABSTRACT

Trusted ICC ES TEK USA, Evaluation. report, or as to any. ICC-ES Evaluation

Question 8 of 55. y 24' 45 kips. 30 kips. 39 kips. 15 kips x 14' 26 kips 14' 13 kips 14' 20' Practice Exam II 77

Lectures Notes (Steel I - CT122) Higher technological institute 10 th of Ramadan city Dr. Essam Abd Elaty Mohamed Amoush.

The Church of Jesus Christ of Latter-day Saints, Brent Maxfield

(800) (562) A Subsidiary of the International Code Council

CYCLIC BEHAVIOR OF TRADITIONAL AND INNOVATIVE COMPOSITE SHEAR WALLS

THE AISC SEISMIC PROVISIONS: PAST, PRESENT AND FUTURE

Drift Compatibility of Corner Joints. NEES Webinar #2 December 12, 2014

PERFORMANCE-BASED SEISMIC DESIGN OF BRACED-FRAME GUSSET PLATE CONNECTIONS

COMPOSITE CONCRETE FILLED HSS: DESIGN CONSIDERATIONS

RESILIENT INFRASTRUCTURE June 1 4, 2016

SECTION VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

THE PLAZA AT PPL CENTER ALLENTOWN, PA

EXAMPLE STATEMENT OF SPECIAL INSPECTIONS (SSI)

twenty one Steel Construction 1 and design APPLIED ARCHITECTURAL STRUCTURES: DR. ANNE NICHOLS SPRING 2018 lecture STRUCTURAL ANALYSIS AND SYSTEMS

Full-scale Testing of the Cast Steel Yielding Brace System

Composite Steel/Concrete

ACHIEVING DUCTILE BEHAVIOR OF MOMENT CONNECTIONS PART II

WALL MOUNTED ARTICULATING JIB CRANE

NODIA AND COMPANY. GATE SOLVED PAPER Civil Engineering Design of Steel Structure. Copyright By NODIA & COMPANY

Structural System. Design Criteria Fire Resistance Concrete designed for 2 HR rating (worst case) Geotechnical Report Allowable Bearing Capacity

MAHALAKSHMI ENGINEERING COLLEGE TIRUCHIRAPALLI

PEER Tall Building Seismic Design Guidelines

Lateral System Analysis and Confirmation Design

Experimental Testing of Vulnerable Concentric Braced Frames PI: STEVE MAHIN GRADUATE STUDENT RESEARCHER: BARB SIMPSON UC BERKELEY

AISC Live Webinars. Thank you for joining our live webinar today. We will begin shortly. Please standby.

MOUNTAIN STATE BLUE CROSS BLUE SHIELD HEADQUARTERS

Principles of STRUCTURAL DESIGN. Wood, Steel, and Concrete SECOND EDITION RAM S. GUPTA. CRC Press. Taylor& Francis Group

Structural Tests and Special Inspections Form. Inspection of Fabricators (1704.2)

Displacement Based Assessment and Improvement of a Typical New Zealand Building by an Average Engineer

There are countless ways to improve constructability on your next project. Here are 50 of them. the need for it or specify it on the design drawings.

Executive Summary Building Description: Introduction... 13

DIN EN : (E)

Angle Cleat Base Connections

Hysteretic Characteristics of Braced Frames in Modular Steel Buildings

SECTION STRUCTURAL METAL FRAMING

50 Tips for Designing Steel Framed Buildings September 27, AISC Live Webinar. AISC Live Webinars

STATE UNIVERSITY CONSTRUCTION FUND. UNIVERSITY CON DIRECTIVE 5-1 Issue date: October 2014

CISC HANDBOOK OF STEEL CONSTRUCTION REVISIONS LIST NO. 1 - MAY 2011

Case Study in Steel adapted from Structural Design Guide, Hoffman, Gouwens, Gustafson & Rice., 2 nd ed.

DIVISION 5 METALS SECTION STRUCTURAL STEEL

HIGH RISE CONDO SOHO, NEW YORK, NY

AISC Live Webinars. Thank you for joining our live webinar today. We will begin shortly. Please standby.

SECTION (16071) - VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

REPORT HOLDER: MITEK USA, INC. EVALUATION SUBJECT:

BRACED FRAME USING ASYMMETRICAL FRICTION CONNECTIONS (AFC)

PROJECT: TULSA COMMUNITY COLLEGE BOOKSTORE RENOVATION PROJECT NUMBER: ISSUE: CONSULTANT: SEAL: SHEET NUMBER: GENERAL NOTES

Xyston Inn. NY. Proposal. Xiaodong Jiang. Structure Option. Advisor: Dr. Linda Hanagan

Xyston Inn. NY. Proposal. Xiaodong Jiang. Structure Option. Advisor: Dr. Linda Hanagan

Steel Design Guide Series. Steel and Composite Beams with. Web Openings

fifteen steel construction: materials & beams ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SUMMER 2016 lecture

AISI S E1 AISI STANDARD. Errata to North American Specification. for the Design of Cold-Formed. Steel Structural Members.

Transcription:

Comparative Study of Bolted versus Welded SCBF Connections Authors: Robert P. Krumpen III P.E., Bechtel Corporation, rpkrumpe@bechtel.com Dr. Peter J. Carrato P.E. S.E., Bechtel Corporation, pcarrato@bechtel.com INTRODUCTION Many large industrial projects are located in remote areas where the local labor pool does not include a significant number of skilled welders. As a result, field bolted connections are favored over field welded connections. Special Concentrically Braced Frames (SCFB) are a preferred structural system for many industrial structures. However to meet the detailing requirements for a SCBF structure in which member performance dictates the connection design loads, bolting can become complicated. The decision to use bolted versus welded field connections in industrial projects needs to be carefully evaluated before proceeding. A comparison of utilizing field bolted versus field welded connections for vertical braces is explored. A recent fossil power plant project employed a SCBF in a seismic design category D. It became evident in preliminary reviews of this project that the complexity of bolted bracing connections would create a challenge for the erector. The final conclusion for the project was that field bolted connections would be employed. However the actual design of the connections has cause the authors to revisit this decision and to closer evaluate alternatives for the next project that will require SCBF detailing.

FIGURE 1 MODEL SHOWING THE BOILER AND THE STRUCTURAL SUPPORT SYSTEM (BOILER BUILDING) THE BRACE CONNECTION The example used in doing the comparison study consists of a typical vertical brace associated with a boiler building. To give a sense of scale this structure is intended to support a coal fired boiler which is hung from the roof of the building at a height of approximately 300 feet. The brace is a 400mm x 400mm (16 x16 ) built up box section with a wall thickness of 18mm (approximately 11/16 thick). The material used was Chinese grade Q235 that has a yield stress of 32.6 ksi.. For this brace the connection needs to be designed to exceed the ductile capacity of the member, R y A g F y. Due to the variable nature of this material an R y of 1.5 was used, similar to ASTM A36. The connection therefore is required to be designed for a minimum capacity of 2167 kips. The connection is required to either provide the ability to resist the flexural capacity of the brace (Section 13.3 C AISC Seismic Provisions 1 ) or to permit inelastic rotation and withstand the compressive capacity of the brace (F cr A g ). The compression capacity of this brace is a significant load, around 750 kips. Providing a connection that has the necessary flexural rotational ability but is strong enough to withstand the compressive capacity is a bit tricky. With these requirements in place the two types of connection options can be described. THE BOLTED OPTION The bolted concept shown in Figure 2, consists of several elements; some typical for both seismic and non-seismic vertical brace connections and some that are unique to seismic connections. The brace is slotted with the knife plate welded to the brace. At the slot additional makeup plates are required to avoid tension rupture of the brace at the connection. Dual plates called sandwich plates are bolted to the knife plate and are also bolted to the gusset. The sandwich plates keep the load concentric along the axis of the brace and connection, and allow for the bolts to act in double shear to minimize the required number of fasteners. The gusset is stiffened by a series of plates. The load being carried from the brace to the column is such that it is advantageous for the beam intersecting the brace to be pulled back and replaced with a builtup stub beam. This is done to avoid the design problems in trying to transmit the large capacity loads of the brace into the floor system. The knife plate has a gap of two times the thickness of the plate to accommodate the inelastic rotation. Since the knife plate has to accommodate the rotation but be sufficiently strong to resist the compressive load and tensile capacity of the brace these plates tends to be thick. To ensure that the hinge is in the knife plate and not near the bolted areas, the sandwich plates are also stiffened.

FIGURE 2 BOLTED VERTICAL BRACE TO GUSSET OPTION Summary of Bolted Option Connection Brace to Knife Plate Weld - 5/8 Partial Joint Penetration Weld, 4 sides at 32 inches for a total effective length of 640 inches Knife Plate - 2 Thick Q345B (Similar to ASTM A572 Gr 50) 850 lbs Knife Plate to Sandwich Plate Bolts - (18) 1 1/4 A490SC Bolts Sandwich Plate - (2) 1 Thick Q345B (Similar to ASTM A572 Gr 50) 660 lbs Sandwich Plate Stiffener Welds 5/8 Fillet both sides at 26 inches for a total effective length of 1040 inches Sandwich Plate to Gusset Plate Bolts - (18) 1 1/4 A490SC Bolts Gusset Plate - 2 Thick Q345B (Similar to ASTM A572 Gr 50) 2000 lbs Total Effective Length of All Welds = 1680 inches Total Bolt Count = 36 bolts Total Weight of Connection = 3510 lbs THE WELDED OPTION The welded option shown in Figure 3 consists of a slotted brace field welded to the gusset. At the slot additional makeup plates are required to avoid tension rupture just like in the bolted option. Since the load being designed for is significant, the gusset is extended down and the intersecting beam is also pulled back. Stiffeners are required to strengthen the gusset plate. A gap three times the thickness of the gusset is provided to have a hinge.

FIGURE 3 WELDED VERTICAL BRACE TO GUSSET OPTION Summary of Welded Option Connection Brace to Gusset Plate Weld - 5/8 Partial Joint Penetration Weld, 4 sides at 32 inches for a total effective length of 640 inches Gusset Plate - 2 Thick Q345B (Similar to ASTM A572 Gr 50) 3700 lbs Total Effective Length of All Welds = 640 inches Total Bolt Count = 0 bolts Total Weight of Connection = 3700 lbs (Based on Rectangular Dimensioning) THE IMPACT TO THE ENGINEER While the two brace connection options have very different limit states, there are some worth comparing. The bolted option will trend to larger connection materials due to the reduction in effective cross sectional areas. For our example if we look at tension rupture, the bolted option has (6) 1 ¼ dia bolts. These holes effectively reduce the capacity of the plate to around 73% to that of a solid plate. Another example is based on block shear. Both the bolted option and welded option have block shear failure modes. With the bolt pattern shown in Figure 2, the bolted option has an effective area of around 66% to that of a solid area. The magnitude of the brace loads typically requires the beam to column connection to be pulled away from the column. This presents some unique issues. If the continuity of the member is to be maintained to the centerline of the column, then the beam to column connection needs to be a moment connection. An alternative is to maintain the connection as a simple shear connection

and require the column to handle the moment being generated by the eccentricity of the connection. The later option can present several coordination problems and often requires revisiting the structural analysis. Therefore utilizing moment connections can be the clearest path forward. The constructability of utilizing moment connections can be improved if the opposite end of the beam is an extended shear tab connection. This configuration works provided the opposite end is not also part of another gusset plate (See Figure 6). FIGURE 4 BEAM TO COLUMN CONNECTION SHOWING THE MOMENT DEMAND THE CONNECTION REQUIRES FIGURE 6 BRACE FRAME CONFIGURATION THAT REQUIRES MOMENT CONNECTIONS ON BOTH ENDS OF THE BEAM REDUCING CONSTRUCTABILITY THE IMPACT TO THE FABRICATOR

SCBF vertical brace connections have an impact on the fabricators performance. The bolted option has some significant issues. There are stiffeners with the sandwich plates as well as the drilling of holes in both the plates. The latest seismic specification now permits an oversized hole in one ply which allows for more adjustability. Also all of the welds are required to be done in the shop. The welded option has significantly less complexity. The major issue associated with this option is that the gusset plate is required to be shaped to include the plastic hinge. Since the fabricated weight traditionally includes waste which in the case of gussets, the rectangular dimensions are used (The largest width times the larges height). While the physical gusset plate actually weighs 2400lb the fabricated weight is significantly higher at 3700 lbs. While it is surprising that the higher weight for the welded option is actually very similar to the bolted option, it is clear that the complexity of the bolted connection is the more costly fabricated connection. Since fabricated steel is purchased usually by the ton, the cost can be significant. Typically the average weight of a boiler building s connections is 10-13% of the total weight of fabricated steel, high seismic connections will increase this ratio to 20-25%. The reduced complexity of the welded option should result in lower fabrication cost for this option. THE IMPACT TO THE FIELD The field s impact on the choice of connection design is a function of a number of variables. In many industrial projects, the availability of adequate number of qualified welders to work in remote regions encourages the use of bolted connections. The bolted option is traditionally preferred based on that key factor. However the bracing connection associated with SCBF structures are significantly different from typical bracing connections and other aspects of constructability should be considered. Some issues of constructability can include erection tolerances, number of parts being handled, and clearance for installation. Depending on whether the bolted or welded option is selected other consideration include wrench clearance, welding position down hand or over hear, as well as associated inspection requirements. In focusing on comparing just the act of bolting versus field welding some basic evaluation can be done. If we assume that a 5/8 weld is a five pass weld and that the weld rate is 3 inch/min, then the field weld option would take 3.5 hours to perform. Also cleaning of slag between passes would further increase the weld time. If we assume that the bolt up rate is 10 bolts/hour then for the bolted option would take 3.6 hours. This does not include the initial fit up and inspection for either concept, but this does show that the installation time can be potentially similar.

FIGURE 7 PHOTO OF COMPLETED VERTICAL BRACE CONNECTION The bolted option has the issue of that it has more loose parts. More loose parts equates into more time in fitting up the connection. The welded option requires that the brace be knifed onto the gusset plate. Careful attention needs to be paid to being able to install the brace. CONCLUSION While traditional approach for industrial projects has been on bolted connections, it appears that field welded connections for SCBF may offer some competitive advantages. Concerns associated with the time required to perform the field welding needs to be weighed against the increased number of bolts and higher fabrication costs. REFERENCES [1] AISC S 341, SEISMIC PROVISIONS FOR STRUCTURAL STEEL BUILDINGS, AMERICAN INSTITUTE FOR STEEL CONSTRUCTION, CHICAGO.