T-145 batch vs. Continuous. Technical Paper T-145. batch vs. continuous. by E. Gail Mize and Greg Renegar

Similar documents
ITEM 302 AGGREGATES FOR SURFACE TREATMENTS

OMT Asphalt Plant Inspection Checklist

Mix Blending Enhancement System ASTEC INTELLI-PAC. Mix Blending Enhancement System 1

DESIGN OF BITUMINOUS MIXTURES

It has been revised to eliminate All Other (i.e. BAM) mixtures. This special provision should be inserted into all HMA contracts.

2006 NCAT Pavement Test Track Reconstruction Plant Production of Experimental Mixes SECTION 412 TEST TRACK PAVEMENT TEST SECTIONS

ITEM 340 HOT MIX ASPHALTIC CONCRETE PAVEMENT

2011 HMA Production Training & Seminar Programs

Modern Asphalt Plants

This special provision should be inserted in all HMA contracts, including those using the I-FIT test.

The Cardiac Arrest of Hot Mix Asphalt Pavements

SPECIAL SPECIFICATION 3280 Paver-Laid Surface Treatment

USE OF HYDROGEN FROM RENEWABLE ENERGY SOURCE FOR POWERING HOT-MIX ASPHALT PLANT

QSD/ Anas Recycling Case Study

SECTION 402 PLANT MIX BITUMINOUS SURFACE LEVELING

CHAPTER 5 BLENDING AGGREGATES

CITY OF SAN ANGELO ITEM 340 HOT MIX ASPHALTIC CONCRETE PAVEMENT

A NEW METHOD FOR HOT RECYCLING OF ASPHALT

Dryer Drum Plant Certification Report

INDEX DESCRIPTION MATERIALS CONSTRUCTION MEASUREMENT PAYMENT 6

Apr 17, 2000 LAB MANUAL TRIAL MIX PREPARATION BATCHING - PROPORTIONING TRIAL MIXES - FORMULAS

Report on the use of High RAP Asphalt Concrete Mixes in 2007 for the RICHMOND DISTRICT. Richmond District Plant Mix Schedule-Goochland Schedule

1995 Metric CSJ SPECIAL SPECIFICATION ITEM Hot Mix Asphaltic Concrete Pavement Containing Reclaimed Roofing Shingles

Re: The Responsible Use of Recycled Materials in Asphalt Mixtures Critical Look

DESIGN OF BITUMINOUS MIXTURES

SPECIAL SPECIFICATION 3427 Ultra Thin Bonded Wearing Course

ROARING FORK & EAGLE VALLEY (RFEV) SECTION 4 ASPHALT MIXTURE REQUIRMENTS

ITEM 342 PLANT MIX SEAL

ISO INTERNATIONAL STANDARD. Road construction and maintenance equipment Asphalt mixing plants Terminology and commercial specifications

Technical Paper T-129. STOCKPILES by George H. Simmons, Jr.

MSCAA /04 ITEM P-219 RECYCLED CONCRETE CRUSHED AGGREGATE BASE COURSE DESCRIPTION MATERIALS

Tex-204-F, Design of Bituminous Mixtures

The Cardiac Arrest of Hot Mix Asphalt Pavements. Timothy R. Murphy, P.E., M. ASCE President

Construction Specification 62 Grouted Rock Riprap

SPECIFICATIONS FOR BONDED WEARING COURSE

CONSTRUCTION SPECIFICATION FOR COLD MIXED, COLD LAID, OPEN AND DENSE GRADED BITUMINOUS MIX TABLE OF CONTENTS

1993 Specifications Projects MC & STP 94(106)R SPECIAL SPECIFICATION ITEM 3022

Superpave Design Guidelines for Using Hot-Mix Recycled Asphalt Pavement and Recycled Asphalt Shingles

Reduce Noise. How to. Gallagher Materials strives to become a better neighbor by rebuilding its Joliet plant. By Kimberley Schmitt, associate editor

ATTACHMENT 06 DETAILED SPECIFICATIONS COLD PATCH

asphalt (PWMA) processes in accordance with these Specifications. PWMA processes include organic 9

FULL DEPTH RECLAMATION

The State of RAP. in America

GENERAL DEFINITIONS 2

Chapter 6 Tex-204-F, Design of Bituminous Mixtures

MICHIGAN DEPARTMENT OF TRANSPORTATION

Reclaimed Asphalt Pavement (RAP)

Dr. Randy West, P.E. Director

ASPHALTIC CONCRETE FRICTION COURSE (ASPHALT-RUBBER):

Scanning Tour of Japan. Brian K. Wood, P.E.

SPECIAL SPECIFICATION 3157 Cold Processed - Recycled Paving Material (RPM) for Use as Aggregate Base Course

SR-191. Five Ways to Save Your Asphalt!... And Still Build a Sexy Pavement By Dave Newcomb

Item P-219 Recycled Concrete Aggregate Base Course

EFFECT OF AGGREGATE GRADATION ON MEASURED ASPHALT CONTENT

Warm Mix Asphalt (WMA)

SPECIAL SPECIFICATION 3347 Ultra Thin Hot Mix Bonded Wearing Course

1995 Metric CSJ's SPECIAL SPECIFICATION ITEM 3034 SUPERPAVE HOT MIX ASPHALTIC CONCRETE PAVEMENT

Investigation of reclaimed asphalt pavement batching process in an asphalt mixing plant

Warm Mix Asphalt (WMA)

ASPHALT MIXING PLANTS

Trouble-Shooting Asphalt Content Problems

Chapter 3. Bituminous Patching Materials SECTION ACCEPTANCE OF PRE-MIX PATCH MATERIAL

CONSTRUCTION SPECIFICATION FOR COLD MIXED, COLD LAID, OPEN AND DENSE GRADED BITUMINOUS MIX

PAVER PLACED SURFACE TREATMENT

Section 3 Specification 3.20 Slurry Seal TABLE OF CONTENTS

Continuous Production for All Types of Concrete. CEI Enterprises

Recycled Asphalt Pavement

Warm Mix Asphalt (WMA)

SPECIAL SPECIFICATION 3318 Crumb Rubber Modified (CRM) Hot Mix Asphaltic Concrete Pavement

1995 Metric CSJ SPECIAL SPECIFICATION ITEM Superpave Hot Mix Asphaltic Concrete Pavement

Suggested Best Practices for PAVER OPERATORS

SPECIAL SPECIFICATION 3317 Crumb Rubber Modified (CRM) Hot Mix Asphaltic Concrete Pavement

Appendix C Training Materials for the Draft Appendix to AASHTO R 35

Plant Control & Quality Innovations in Equipment & Technology: NCAUPG Technical Conference 2012 Indianapolis, IN

TECHNICAL SPECIFICATIONS

Work shall also include preparation and protection of subgrade, subbase and leveling course specific to PHMA/PWMA.

Table of Contents. Chapter 1 : Introduction 1. Chapter 2 : Structure and design 15

SPECIAL SPECIFICATION 3419 Ultra Thin Hot Mix Bonded Wearing Course

Aggregate Specifications

Recycling: a circular economy for roads. The Recycle Technology of Asphalt Pavement in Japan

Puerto Rico. Pavement Preservation Conference and Technology Implementation. US. Department of Transportation Federal Highway Administration

Warm Mix Asphalt (WMA) Guide Specification for Highway Construction

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 850 CEMENT TREATED FREE DRAINING BASE APRIL 18, 2008

CHAPTER 2: HOT MIX DESIGN

SPECIAL SPECIFICATION. Item Micro-Surfacing (Polymer Modified)

Section 506 SLURRY SEAL Description. Prepare the surface and apply a properly proportioned slurry seal mixture.

Suggested Guidelines for Hot Mix Asphalt (HMA) Underlayment in Track by AREMA Committee l-sub Committee No. 2 - Ballast.

STUDY QUESTION ANSWERS

RECONSTRUCTION OF DISTRESSED PAVEMENTS Full-Depth Rehabilitation (FDR) (Portland cement)

SPECIFICATIONS FOR ASPHALT-RUBBER SURFACE TREATMENT WITH AGGREGATE COVER

Report on the Use of High RAP Asphalt Concrete Mixes for the 2007 Lynchburg District Plant Mix Contracts

SECTION BITUMINOUS CONCRETE PAVEMENT. 1. Aggregate base and subbase course; Section a. Heat Stable Anti-Stripping Additive

LIME IN HOT MIX ASPHALT THE TEXAS EXPERIENCE. Darren Hazlett P.E. Retired Director Texas Department of Transportation Construction Division

UTILIZATION OF AUTOMATION AND REAL-TIME TESTING TO IMPROVE QC/QA PROCEDURES FOR HOT MIX ASPHALT

Section 506. SLURRY SEAL

Inspection of Full Depth Modified Dense-Graded Aggregate Base, Plant Mixed (Tennessee Project)

Cement Stabilized Soil (CSS) (Portland cement)

Asphalt Rubber Chip Sealing DRAFT MAINTENANCE SPECIFICATION. March 22, 2007

Ohio Department of Transportation COS/GUE - SR 541 Warm Mix Asphalt Field Trial

SECTION 28 AGGREGATE BASE COURSE (FAA P-208) [For base course under runway and taxiway surfaces, use Section 29, FAA Item P-209.]

Transcription:

T-145 batch vs. Continuous Technical Paper T-145 batch vs. continuous by E. Gail Mize and Greg Renegar

ASTEC encourages its engineers and executives to author articles that will be of value to members of the Hot Mix Asphalt (HMA) industry. The company also sponsors independent research when appropriate and has coordinated joint authorship between industry competitors. Information is disbursed to any interested party in the form of technical papers. The purpose of the technical papers is to make information available within the HMA industry in order to contribute to the continued improvement process that will benefit the industry.

CONTENTS INTRODUCTION... 2 ADVANTAGES OF continuous mix technology... 4 final analysis... 7 APPENDIX... 10 1

F1 I. INTRODUCTION On many occasions, it becomes necessary for a producer of hot mix asphalt paving materials to determine whether to invest in another batch plant or to change to a continuous type plant. A continuous plant takes on several configurations. F2 The older continuous plants are parallel flow drum mixers where the materials proceed in the same direction as the hot gases. These devices, illustrated in Figure 1, either have a center entry port for RAP or not, depending on the customer's requirements. A later vintage of this plant type is the counterflow drum mixer with the burner head placed part way into the drum to allow mixing with liquid asphalt to occur behind the burner, out of the gas stream (Figure 2). This prevents some hydrocarbon emissions and increases fuel efficiency over the parallel flow drum mixer. F3 2 The most recent and most technologically advanced version of this is Astec s Double Barrel drum mixer, which has a counterflow style drum. It has increased mixing time due to the mechanical method of mixing similar to a batch plant. The Double Barrel drum mixer depicted in Figure 3, provides the highest level of thermal efficiency of any continuous mixer on the market today, and has the greatest ability to handle RAP efficiently. Mechanical mixing of 45 to 60 seconds provides a very uniform product of the highest quality. The internal counterflow dryer in the

Double Barrel drum mixer gives the best thermal efficiency available today in a continuous plant. Most people think, erroneously, that the batch plant is able to deal with inconsistent blends of aggregates better than the continuous plant. To understand why this is not the case, one must become familiar with the mix design process. This paper explains why the continuous mixer will handle the job as effectively as the batch process. Sieve Size Percent Passing S. A. Factor Surface Area 3/4 100-2.0 3/8 90 - - No. 4 75 2 1.5 No. 8 60 4 2.4 No. 16 45 8 3.6 No. 30 35 14 4.9 No. 50 25 30 7.5 No. 100 18 60 10.8 No. 200 10 160 16.0 Total 48.7 The total surface area of all sieve sizes is 48.7 square feet per pound Standard Surface Area Calculation First and foremost is the underlying principle of mix design theory. In mix design, a calculation is made to determine the surface area that needs to be coated with asphalt cement, also called the binder. A normal film thickness of approximately ten microns is used so that the quantity of asphalt for this mixture can be determined. Various additives (polymers, fibers) have been used to increase film thickness without drainage. The amount of surface area determines the amount of asphalt cement that is to be used. In a batch plant, the amount of material that is used in the mix is predominantly from Bin 1. In most cases the Bin 1 material is from forty to fifty percent (by weight) of the total mixture. With this in mind, let us look at several different mix designs and determine the surface areas based on material that is less than the normal bottom deck screen size in a batch plant. This screen opening size is normally 3/16 inch (5 mm). The gradation of the aggregate or blend of aggregates employed in the mix is used to calculate the surface area of the aggregates. This calculation consists of multiplying the total percent passing each sieve size by a surface area factor as set forth in Figure 4. Add the products thus obtained and the total will represent the equivalent surface area of the sample in terms of square feet per pound. It is important to note that all the surface area factors must be used in the calculation. Also, if a different series of sieves is used, different surface area factors are necessary. The noteworthy surface area factor for Portland cement is 300 and for hydrated lime is 400. F4 3

II. ADVANTAGES OF CONTINUOUS MIX TECHNOLOGY This paper will demonstrate that the vast majority of the surface area of a mix is not controlled by the sizing screens in a batch type facility. What this basically means is that the important surface area considerations (and thus the quantity of asphalt cement to be used in a mixture in a hot mix facility) is a function of what exists in the cold feed and is uncontrollable thereafter. Let's clarify the differences in the way aggregate is processed, with respect to gradation, in a batch and continuous plant. In a batch plant, sized aggregate is placed in cold feed bins and blended to some degree depending on the particular plant, before being sent to the dryer. When the aggregate exits the dryer, the aggregate blend is carried to a large screen and separated into four or more blends. The mix gradation called for in a particular batch is created by "pulling" an appropriate amount of aggregate from each of the bins, commonly called hot bins, since they contain hot aggregate. It is generally assumed that a batch plant can accommodate inconsistent aggregate blends in the cold feed due to the screening operation that takes place at an intermittent point in the process. This paper explains why this is not so. In contrast, a continuous plant blends aggregates at the cold feed system as the computer controls "tell" each cold feed bin feeder exactly how much aggregate is required to satisfy the mix design requirements. The blending at this point in the process is very precise. This mixture is then dried, mixed with liquid AC (bitumen), and transferred to a surge bin or storage silo. If RAP is added, it is first fractionated into hard-to-segregate sizes and treated just like the virgin aggregate. It is placed into two or more RAP feed bins and precisely blended before being mixed with the hot virgin aggregate. The virgin aggregate and RAP are mixed together before the virgin AC (bitumen) is added. Of course, a consistent mix depends on consistent aggregates in the cold feed bins, but a batch plant must also have consistent aggregates at the cold feed end of the process in order to produce a consistent product, as this paper will prove. Since consistent aggregates are required for both a continuous and batch process, the continuous plant becomes the plant of choice with respect to initial cost, operating cost, maintenance cost, portability, and RAP processing capabilities. Now let us look at four different mix designs that are standard designs in the State of Georgia. These designs are standard designs used by the Georgia Department of Transportation. A maximum density curve as well as a surface area calculation is included for all four mix designs. The surface area calculation for Georgia Base Mix is as shown in Figure 5. In this Georgia Department of Transportation Base Mix, 10.4 percent 4

of the surface area (SA) is above the No. 8 sieve and 89.6 percent of the surface area is No. 8 sieve size and smaller. Therefore, it is safe to say that in this mix, a batch plant screen has control of about 10 percent of the surface area and the rest is under the control of the cold feed bins. In short, in both the batch plant and the continuous mixer, the cold feed proportioning control system controls 90 percent of the surface area in this mix. Sieve Size Percent Passing S. A. Factor Surface Area +No. 4-2 2.0 -No. 4 47.0 2 0.9 No. 8 36.0 4 1.4 No. 16 26.0 8 2.1 No. 30 20.0 14 2.8 No. 50 15.0 30 4.5 No. 100 9.0 60 5.4 No. 200 5.5 160 8.8 Total 27.9 F5 Let s now look at a Georgia Department of Transportation B Modified Binder mix. In this Georgia Department of Transportation Modified Binder Mix, 10.3 percent of the surface area (SA) is above the No. 8 sieve and 89.7 percent of the Surface Area is No. 8 sieve size and smaller (Figure 6). Therefore, it is safe to say, once again, that in this mix a batch plant screen has control of about 10 percent of the surface area and the rest is under the control of the computer blending system of the cold feed bins. Surface Area Calculation for a GA Base Mix Sieve Size Percent Passing S. A. Factor Surface Area 3/4 92.5 2 2.0 3/8 74.5 - - No. 4 58.0 2 1.2 No. 8 46.0 4 1.8 No. 16 33.0 8 2.6 No. 30 24.0 14 3.4 No. 50 17.5 30 5.3 No. 100 10.0 60 6.0 No. 200 5.5 160 8.8 Total 31.1 Surface Area Calculation for B Modified Binder Mix F6 5

Sieve Size Percent Passing S. A. Factor Surface Area +No. 4 100.0 2 2.0 -No. 4 30.0 2 0.6 No. 8 7.5 4 0.3 No. 16 6.0 8 0.5 No. 30 5.0 14 0.7 No. 50 4.0 30 1.2 No. 100 3.5 60 2.1 No. 200 3.0 160 4.8 Total 12.2 Surface Area Calculation for Open Graded Surface D Mix Sieve Size Percent Passing S. A. Factor Surface Area 3/4 100.0 2 2.0 3/8 95.0 - - No. 4 65.0 2 1.3 No. 8 47.0 4 1.9 No. 16 36.0 8 2.9 No. 30 26.0 14 4.2 No. 50 19.5 30 5.9 No. 100 12.0 60 7.2 No. 200 5.5 160 8.8 Total 34.2 Surface Area Calculation for Dense Graded Surface F Mix F7 F8 Lets now look at a Georgia Department of Transportation Open Graded Surface D Mix. In this Georgia Department of Transportation Open Graded D Mix, 21.3 percent of the surface area (SA) is above the No. 8 sieve and 78.7 percent of the surface area is No. 8 sieve size and smaller (Figure 7). Therefore, in this sample mix, a batch plant screen has control of about 20 percent of the surface area. The rest is under the control of the cold feed bin blending system. Now let s look at the last mix design to be presented in this section. It is a Georgia Department of Transportation Dense Graded Surface F Mix. In this Georgia Department of Transportation Dense Graded Surface F Mix, 9.7 percent of the surface area (SA) is above the No. 8 sieve and 90.3 percent of the surface area is No. 8 sieve size or smaller (Figure 8). Therefore, it is safe to say, once again, that in this mix a batch plant screen has control of about 10 percent of the surface area and the rest is under the control of the cold feed bin blending system. The above four mixes represent a wide range of all the mixes produced in the hot mix business. When considering the surface area control of the batch plant versus a cold feed computer blending system, which is always part of a modern continuous plant, it is easy to understand why the continuous plant now dominates the plant type chosen by contractors 6

and operators in the United States today. It is also easy to understand that the continuous plant will eventually take over as producers realize that the continuous plant is a more energy efficient, less expensive to maintain, and provides the control necessary at the cold feed bins to consistently produce mix that meets the most stringent specifications. III. FINAL ANALYSIS In the final analysis, what is in the cold feed bins is what will be produced with either a continuous or batch process. So what are the batch plant advantages? 1. Multiple mixes can be produced in small quantities. However, the continuous plant can also produce multiple mixes with multiple long term storage silos. 2. To meet specifications that require a batch plant. 3. A marketing advantage when properly applied in selling a multitude of different mix designs to many different market segments. The primary reason for the purchase of a batch plant today is a lack of understanding of the continuous process. This is coupled with too little knowledge of how the batch process works. How the continuous plant performs and its tremendous ability to make a uniform product is now widely known in North America, the world's largest market for hot mix asphalt. The screens in the batch plant may also create a problem with final mix gradation. It is caused by changing screen efficiency, or override. This occurs when the bed thickness varies on the screen deck. This fluctuation is a function of the feed rate to the screen, the material characteristics, the number of decks and the material depth on the cloth. The Appendix on page10 represents a standard screen sizing chart. All the manufacturers publish a chart similar to this with similar factors for screening of aggregates. This chart, like all the others, utilizes an equation in which you insert the various factors from the table to arrive at the tons per hour and efficiencies of the screen. The equation rearranged is: Area of Deck(S) x Screening Factors(A x B x C x D x E x F) = Through Flow Tonnage(T) 7

After a screen is in place on a batch plant it is obvious that the area of the deck cannot change. Therefore, the deck area becomes a constant. See Appendix for factors A through F. Factor A is determined by the cloth size, which will not change after sizing. Factor B will not change when the feed from the cold feed is kept in the same proportions. Factor D will not change for the same reason that Factor B will not change. Factor E is not used. Factor F will not change since you will be using the same deck for comparison. On a batch plant running the same cold feed blend, the only variable factor in Factors A through F is Factor C, which is the screening efficiency. Therefore, when the Through Flow Tonnage is varied, the only factor that can change on an operating batch plant is Factor C. Simply put, the equation looks like this: S (constant) x C = T Consequently, C varies with T and the screening efficiency goes up and down with the tons per hour that is fed to the deck. The bottom deck is the critical deck on a batch plant since what is placed into Bin 1 is controlled by this deck. By examining Factor C and the desired efficiency columns in Appendix A it becomes clear that the amount of Bin 1 material in Bin 2 can vary greatly when the feed rate to the bottom deck changes. By assuming that the production rate through the dryer doubles, it is easy to see that as much as 20 percent of Bin 1 material can be placed into Bin 2. This will affect the surface area in the mix since Bin 1 material is placed in the mix when Bin 2 is discharged into the weigh hopper. The amount of asphalt cement should be changed since the gradation of the mix changed. It fact, the specification band (range) of the mix design could be effected for some sizes of aggregates. Varying the gradation in the bins means full width bin samples should be taken from the hot bins to make certain that the correct gradation is being removed from the hot bins. In a typical North American style batch plant, provisions are made between the hot bin gates and the aggregate weigh hopper to take a full width bin sample to verify the gradation of materials in the hot bins. In European style plants there is often no provision for full width sampling or any sampling of the hot bins. In the United States, the state Departments of Transportation that specify the design formulas have a mandatory requirement for full width hot bin sampling. Lack of hot bin sampling would lead one practiced in the art of mix design to assume that 8

the continuous plant would certainly be a better choice than a batch plant that has no provision for checking accuracy on a frequent basis. Another area of concern in a batch plant that has large hot bins is Bin 1 segregation. The Astec patented partition in the hot bin minimizes segregation (Figure 9). Note the location of the partition. It allows the material on the sloping surface of Bin 1 to feed in proportion to the coarser material that passes through the screen later and collects on the other side of the partition. A less attractive solution is to place a sloping plate or baffle under the screen to move the fines over to the center of the bin (Figure 10). This works to a more limited degree. In the case of very large hot bins, the first solution is definitely the best. SCREEN DECKS BAFFLE BIN #4 BIN #3 BIN #2 BIN #1 ANTI-SEGREGATION BIN PARTITION WALL Anti-Segregation Bin Partition F9 F10 In conclusion, a higher quality HOT BINS product due to less variation can be produced from a continuous plant. State of the art computer controls, accurate belt scales, asphalt (bitumen) metering system, and the cold feed blending system will assure that a consistent product is produced. In Batch Plant Hot Bin Segregation addition, recycling, an economic requirement of the future, is able to be handled much better in the continuous facility. It dramatically lowers mix cost and reuses an otherwise waste product. 9

10 To determine the size of the screen, obtain screen cloth area (S) needed by dividing the through-flow tonnage (T) by factors A, B, C, D, E, & T A x B x C x D x E x F S = Factor A Cap. in TPH passing thru 1 sq. ft. of screen cloth based on 94% efficiency with 25% oversize. 1/8" 3/16" 1/4" 5/16" 3/8" 1/2" 5/8" 3/4" 7/8" 1" 1-1/4" 1-1/2" 2" 2-1/2" 3" 4" 5" Size of Sq. Opening Gravel.90 1.12 1.35 1.55 1.75 2.10 2.42 2.70 2.90 3.20 3.62 4.00 4.80 5.60 6.40 7.90 8.30 Stone.70.90 1.10 1.30 1.50 1.75 2.00 2.25 2.45 2.65 3.00 3.35 3.87 4.20 5.40 6.70 7.50 Wet screening Deck Factor F Factor D Amount of feed less than 1/2 size of opening Factor C Desired Efficiency Factor B Factor E Size of Opening Amount of Oversize (per deck) 10% 1.05 60% 2.10 10%.55 1/32" 1.25 Top 1.00 20% 1.01 70% 1.70 20%.70 1/16" 1/75 Second.90 30%.98 75% 1.55 30%.80 1/8" 2.00 Third.80 40%.95 80% 1.40 40% 1.00 3/16" 2.00 50%.90 85% 1.25 505 1.20 5/16" 1.75 60%.86 90% 1.10 69% 1.40 3/8" 1.50 70%.80 92% 1.05 70% 1.80 1/2" 1.30 80%.65 94% 1.00 80% 2.20 3/4" 1.20 85%.50 96%.95 90% 3.00 90%.30 98%.90 100% NOTE: Factor C Slight inaccuracies are seldom objectionable in screening aggregate and perfect separation (100% efficiency) is not consistent with economy. For finished products, 98% efficiency is the extreme and practicable limit and 94% is usually satisfactory. 60% to 75% efficiency is usually acceptable for scalping purposes. NOTE: Factor F If material is dry, use factor 1.00. If there is water in material, or if water is sprayed on screen, use proper factor given above. Wet screening means the use of about 3 to 5 G.P.M. of water per ton of material per hour. Rinsing requires about 1-1/2 to 3 G.P.M. per ton of material per hour. Through-Flow Tonnage Method Appendix

11

12

ASTEC 2009 Printed in usa