Significant Unavoidable Adverse Impacts

Similar documents
4.8 ENVIRONMENTAL HEALTH - ELECTRIC AND MAGNETIC FIELDS

LONG TERM (OPERATION) IMPACTS AND POTENTIAL MITIGATION

Short-term (Construction) Impacts and Potential Mitigation

Appendix E: Supplemental Information: Plants & Animals

CHAPTER 7. ERRATA. 1) Chapter 1 Introduction and Summary:

Welcome! EnergizeEastsideEIS.org. Agenda. Phase 1 Draft EIS Public Hearing

Energize Eastside Transmission Capacity Project April 13, 2016

CHAPTER 7. ENERGY AND NATURAL RESOURCES

Environmental Analysis, Chapter 4 Consequences, and Mitigation

Lynnwood Link Extension 2013 Draft EIS Comments and Responses. Page 275

Lynnwood Link Extension 2013 Draft EIS Comments and Responses

DRAFT ENVIRONMENTAL IMPACT STATEMENT AND DRAFT SECTION

Chapter 4 Cumulative Effects

SECTION 6.0 Alternatives to the Proposed Project

SOUTHWEST CONNECTICUT RELIABILITY PROJECT

Puget Sound Energy Energize Eastside Project

City of Federal Way City Center Planned Action Draft EIS

SMUD S COMMENTS ON THE DRAFT 2030 PUBLIC FACILITIES ELEMENT SACRAMENTO COUNTY GENERAL PLAN PUBLIC FACILITIES ELEMENT SECTION VIII ENERGY FACILITIES

Eastside Solution Study Executive Summary

Energize Eastside. South Sub-Area Committee Workshop #1. Andy Wappler. Vice President, Corporate Affairs, Puget Sound Energy

Draft Supplemental Environmental Impact Statement

6. Cumulative Impacts

NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT

Lynnwood Link Extension 2013 Draft EIS Comments and Responses. Page 216

16.1 Significant and Unavoidable Impacts

TABLE OF CONTENTS. LIST OF FIGURES Figure 4-1: Alternative 1 System Overview Figure 4-2: Alternative 3 System Overview...

Chapter 6 Avoidance, Minimization, and Mitigation

SUPPLEMENTAL MUNICIPAL CONSULTATION FILING FOR THE CONNECTICUT PORTION OF THE INTERSTATE RELIABILITY PROJECT THE CONNECTICUT LIGHT AND POWER COMPANY

CHAPTER 4. GREENHOUSE GAS EMISSIONS

4.9 ENVIRONMENTAL HEALTH PIPELINE SAFETY

5. Other Environmental Consequences

Appendix C - Highway 400 Widening and Interchange Evaluation Summary Tables

Draft Environmental Impact Report for The Farm at Alamo Creek Specific Plan Project

DORAN STREET AND BROADWAY/BRAZIL SAFETY AND ACCESS PROJECT PROJECT STUDY REPORT (EQUIVALENT) Appendix H Preliminary Environmental Evaluation

6 ALTERNATIVES 6.1 INTRODUCTION

Chapter 5 Transportation Draft

EVALUATION OF ALTERNATIVES CARRIED FORWARD

I. CONSIDERATION OF 2020 LRDP FEIR (1/05) AND ADDENDUM #8 1

Attachment 3 UC MERCED 2020 PROJECT

Board Policy on Construction of Transmission and Distribution Projects

DRAFT Subject to Modifications

Therefore, each of the alternatives to the Specific Plan addressed in this EIR were selected based on the following factors:

Draft Environmental Impact Report

South Landfill Annual Cover Rate Screening Criteria Checklist

King County Flood Control District approves grants for flood prevention projects Regional projects to benefit from district funds

SECTION 9.0 Effects Found Not To Be Significant

Chapter 5 - Transportation

Eastside Needs Assessment Report Transmission System King County Executive Summary December 2013

5.0 ALTERNATIVES 5.1 INTRODUCTION

Attachment E2 Noise Technical Memorandum SR 520

5.0 PRELIMINARY ENVIRONMENTAL REVIEW

FINAL ENVIRONMENTAL IMPACT STATEMENT. Final EIS in Focus

SUMMARY OF MAJOR POLICY IMPLEMENTATION TOPICS From 2016 COUNTY Comprehensive Plan

5.0 ALTERNATIVE VARIATIONS

APPENDIX C TECHNICAL MEMORANDUM NO.2 ALTERNATIVE DESIGN CONCEPTS FOR PROSPECT PARK WPP EXPANSION

Puget Sound Energy Energize Eastside Narrative and Probable Significant Impacts

5.1 Introduction. 5.2 Geographic and Temporal Boundaries of Cumulative Analysis. Chapter 5 Cumulative Impacts

IMPACT ON LAND. 1. Will there be an effect as a result of a physical change to project site? Yes No

Welcome to our Information Centre

ADDENDUM TO THE CITY OF LAKEPORT GENERAL PLAN EIR

ENVIRONENTAL CHECKLIST

Carpinteria Valley Water District Carpinteria Advanced Purification Project

STAFF REPORT WASHINGTON STATE PARKS AND RECREATION COMMISSION COVERED SHELTERS AND BIKE RACKS

CEQA provides the following guidelines for discussing project alternatives:

Environmental Impact Statement for the Green Line to the Airport Project. ACTION: Notice of Intent to Prepare an Environmental Impact Statement (EIS).

Welcome to the Public Information Centre. Red Hill Business Park South Transportation Master Plan Addendum. June 25, :00 p.m. to 8:00 p.m.

NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT

APPENDIX A: NOTICE OF PREPARATION AND COMMENTS RECEIVED

DRAFT ENVIRONMENTAL IMPACT REPORT

SECTION 5: ALTERNATIVES TO THE PROPOSED PROJECT

CITY OF SEATTLE DETERMINATION OF NON-SIGNIFICANCE BY THE OFFICE OF PLANNING & COMMUNITY DEVELOPMENT (OPCD)

Leaside to Main Infrastructure Refurbishment Project Strengthening the transmission system in your neighbourhood

SEARs project justification and conclusion

3.1 Existing Setting Regulatory Framework Changes in Population, Employment, and Housing

I-70 East PACT DRAFT EVALUATION DATA

DRAFT ENVIRONMENTAL IMPACT REPORT/ ENVIRONMENTAL ASSESSMENT CONTENTS CENTINELA SOLAR ENERGY PROJECT

Capitol Expressway Light Rail Project Supplemental Environmental Impact Statement ANNOTATED OUTLINE

Conditional Uses 815

WSU SITE PROJECT BONNEY LAKE DRAFT ENVIRONMENTAL IMPACT STATEMENT

11 Joint Development Regulatory Context and Methodology

REGIONAL GROWTH STRATEGY

TRANSPORT and INFRASTRUCTURE

18 Cumulative Impacts and Interaction of Effects

Jean E. Vissering Landscape Architecture 3700 NORTH STREET MONTPELIER VERMONT Phone:

Overlake Plaza Master Plan

CONTAINER PORT GOALS 10-2

H. LAND USE City of Los Angeles L.A. CEQA Thresholds Guide 2006

Peninsula Corridor Electrification Project. Draft Environmental Impact Report

Seacoast Reliability Project Need and Proposed Solution. Madbury Planning Board Meeting February 4, 2015

LONG ISLAND RAIL ROAD EXPANSION PROJECT FROM FLORAL PARK TO HICKSVILLE DRAFT ENVIRONMENTAL IMPACT STATEMENT

Attachment 1. Ordinance

Northwest State Route 138 Corridor Improvement Project

Understanding and Applying the State Environmental Quality Review Act

Lloydminster to Spruce Lake 138kV Transmission Line Projects

ATTACHMENT B. Findings for Approval and Statement of Overriding Considerations Eastern Goleta Valley Community Plan

4.10 LAND USE ENVIRONMENTAL SETTING

EXECUTIVE SUMMARY RIVER VALLEY INTERMODAL FACILITIES FINAL ENVIRONMENTAL IMPACT STATEMENT ES-1

ROW: Siting, Vegetation Management, and Avian Issues - Program 57

RESOLUTION NO:

Research Design for Archaeological Fieldwork Draft 1

Transcription:

6 Significant Unavoidable Adverse Impacts

CHAPTER 6. SIGNIFICANT UNAVOIDABLE ADVERSE IMPACTS 6.1 LAND USE AND HOUSING Construction of the project would not require significant excavation, inhibit access to adjacent land uses, or create significant noise; therefore, any nuisance caused by the construction activities of Alternative 1 would be less-than-significant. Long-term impacts would also be less-than-significant for Alternative 1 because all of the segments and options and the proposed substation are land uses anticipated in city and subarea plans, and the project would not adversely affect existing or future land use patterns. Therefore, the project would not result in significant unavoidable adverse impacts to land use and housing. The No Action Alternative would not be consistent with city comprehensive plan policies, as discussed in the Phase 1 Draft EIS. The No Action Alternative could lead to unavoidable significant adverse land use impacts in the long term if unreliable power supply were to outweigh the regional factors amenable to growth and development, leading to development inconsistent with regional growth plans and targets. 6.2 SCENIC VIEWS AND THE AESTHETIC ENVIRONMENT The project could have significant adverse impacts to the aesthetic environment as a result of the Bypass Options 1 and 2, the Willow 1 Option, and the Newcastle Segment. There would be no significant adverse impacts to scenic views (Figure 6-1). Figure 6-1. Areas with Significant Impacts to the Aesthetic Environment PHASE 2 DRAFT EIS PAGE 6 1

Significant aesthetic impacts associated with Bypass Options 1 and 2 would occur where the project would be inconsistent with subarea plan policies: (1) along roadways in the Bel-Red Subarea, where street trees would need to be removed and could not be replanted; (2) where transmission line infrastructure would be introduced in key views identified in subarea plans; and (3) where the transmission line would be placed along Richards Road and would require substantial vegetation removal. Impacts along roadways in the Bel-Red Subarea and along Richards Road could be reduced through mitigation. For instance, if PSE were to place the poles closer to the roadway and cantilever the wires so that minimal vegetation removal would be required and street trees could be planted and maintained, impacts would be less-than-significant. Both of the Bypass Options would result in adverse aesthetic impacts to three key views: NE 5 th Street, NE 8 th Street, and the Lake Hills Connector. Impacts to these view corridors could only be mitigated if the line were placed underground. Significant impacts to the aesthetic environment could also be avoided by selecting the Existing Corridor Option for the Bellevue Central Segment. Significant aesthetic impacts associated with the Willow 1 Option would occur where it traverses the Somerset neighborhood. The Somerset neighborhood has neighborhood covenants that restrict building and vegetation height to protect views (i.e., the View Guideline for Somerset). These neighborhood covenants result in increased viewer awareness of the impact. The increased pole height under Willow 1 would contrast substantially with this unique neighborhood of low buildings and vegetation. Impacts could be avoided by selecting a different option for this segment or if the Somerset portion were placed underground. Significant aesthetic impacts associated with the Newcastle Segment would occur where the project would be inconsistent with the Newcastle Comprehensive Plan, which protects the scale and character of existing neighborhoods through policies that call for transmission lines to be sited and designed to minimize visual impacts to adjacent land uses. North of the May Creek ravine, impacts of the Newcastle Segment on the aesthetic environment would be significant because the new transmission line would change the neighborhood character. It would introduce a taller transmission line that would be closer to residential streets and homes and would be less concealed by vegetation. In addition, its location on the ridge would make it a defining feature that contrasts strongly with the existing built environment. This inconsistency with the Newcastle Comprehensive Plan could be mitigated if: (1) a different pole configuration were selected that placed poles more centrally within the transmission corridor and had shorter pole heights, or (2) the transmission line were placed underground. 6.3 WATER RESOURCES Impacts from construction of Alternative 1 would be temporary and minor with the implementation of BMPs, and all long-term impacts would be minor and could be fully mitigated through compliance with applicable regulations and implementation of BMPs. Therefore, there would be no significant unavoidable impacts to water resources. PHASE 2 DRAFT EIS PAGE 6 2

6.4 PLANTS AND ANIMALS Although the overall magnitude of impacts would vary by segment and option, Alternative 1 would not result in significant unavoidable adverse impacts to plants and animals. The primary impacts are related to the number of trees, including significant trees, that would be removed. Protected species are not known to occupy the habitat within the study area, and the overall urbanized settings throughout the study area are unlikely to provide suitable habitat for these species in the future. Therefore, no significant unavoidable adverse impacts are expected, within any of the segments or options. 6.5 GREENHOUSE GASES Construction-related GHG emissions would be less-than-significant because they would be temporary, would not represent a continuing burden on the statewide inventory, and would likely be below state reporting thresholds. Although Alternative 1 would result in long-term increases in fugitive SF6 emissions (from gas-insulated circuit breakers at substations) and CO2e sequestration losses due to tree removal, the emissions would be substantially below the State of Washington GHG reporting threshold. Therefore, there would be no significant unavoidable impacts to greenhouse gas emissions. 6.6 RECREATION For Bypass Options 1 and 2, and the Oak 1, Oak 2, and Willow 2 Options of Alternative 1, PSE may need to acquire easements within the following parks, which would result in a significant unavoidable impact: Bellevue Central Segment, Bypass Option 1: Wilburton Hill Park and Bellevue Botanical Gardens, Kelsey Creek Park, Eastside Rail Corridor, Richards Creek Open Space, and Bannerwood Ballfield Park. Bellevue Central Segment, Bypass Option 2: Wilburton Hill Park and Bellevue Botanical Gardens, Kelsey Creek Park, Eastside Rail Corridor, Richards Creek Open Space, and Woodridge Open Space. Bellevue South Segment, Oak 1, Oak 2, and Willow 2 Options: Coal Creek Natural Area These potentially significant impacts would be avoided if easements were not granted and poles were moved to the right-of-way, or if an alternate route such as the Existing Corridor Option is utilized. 6.7 HISTORIC AND CULTURAL RESOURCES Potential operational impacts to belowground protected archaeological resources or aboveground significant historic resources could be mitigated during the construction phase. Thus, no significant unavoidable adverse impacts to belowground archaeological resources or aboveground historic resources are anticipated. Mitigation measures for historic and cultural resources would be developed through consultation between PSE and DAHP, with involvement from KCHPP, affected Tribes, and municipal governments as applicable. PSE will consult with DAHP to request an eligibility determination for the Eastside Transmission System; if determined eligible, PSE will consult with DAHP regarding potential mitigation measures. PHASE 2 DRAFT EIS PAGE 6 3

6.8 ENVIRONMENTAL HEALTH ELECTRIC AND MAGNETIC FIELDS No adverse impacts are likely from power-frequency EMF at the levels of public exposure from the Energize Eastside project. It follows that no unavoidable significant impacts under SEPA would occur. 6.9 ENVIRONMENTAL HEALTH PIPELINE SAFETY A pipeline release or fire resulting from construction or operation of the Energize Eastside project would result in potentially significant adverse environmental impacts. The specific impacts would depend on the location and the nature of the incident. Section 3.9.1 explains the legal requirements to prevent, prepare for, and respond to a pipeline incident. Even with worst-case assumptions related to the increased risk during operation and construction, the likelihood of a pipeline release and fire would remain low, and no substantial increase in risk compared to the existing conditions was identified. It is likely that with the implementation of additional measures included in Sections 3.9.7 and 4.9.4, any increase in risks within the corridor can be fully mitigated. As a result, no significant unavoidable adverse impacts have been identified. 6.10 ECONOMICS The economic aspects of the project that are evaluated in this Phase 2 Draft EIS do not relate to construction impacts. Long-term impacts to economics are expected to be less-than-significant. The change in assessed property value would be relatively small compared to the total assessed value in any of the communities potentially affected, including the smallest community, the City of Newcastle. The City of Newcastle could maintain adequate public services without additional revenue, or if necessary, could maintain current funding levels through a minor change in the mil rate. Undergrounding a portion of the transmission line could result in significant economic impacts if the burden of paying for undergrounding is shared over a small number of property owners, or a minor impact if shared by a large enough number. The EIS does not determine whether or how much of the transmission line should go underground, or assess how many people should share the costs. Alternative 1 would require tree removal along the existing corridor and new corridor; however, the value of total ecosystem services lost as a result of tree removal would be minimal. PHASE 2 DRAFT EIS PAGE 6 4