Excavation for Natural Gas Mains and Services

Similar documents
SECTION UTILITY BACKFILL MATERIALS

SECTION 500 STRUCTURES

TRENCH EXCAVATION AND BACKFILL

Section SITE CLEARING. B. Description of Work: 1. The extent of site clearing is shown on the drawings.

Handling and Installation Instructions

SECTION EXCAVATION, TRENCHING AND BACKFILL

SECTION FILL AND BACKFILL

PD - 6 THRUST RESTRAINT DESIGN EQUATIONS AND SOIL PARAMETERS FOR DUCTILE IRON AND PVC PIPE

TRENCH EXCAVATION AND BACKFILL

SECTION TRENCHING, BACKFILLING AND COMPACTION. B. Provide necessary sheeting, shoring and bracing.

INSTALLATION INSTALLATION

CONTENTS INSTALLATION DETENTION SYSTEMS PHYSICAL PROPERTIES AGRICULTURE INSTALLATION GUIDE

B. Borrow: Satisfactory soil imported from off-site for use as fill or backfill.

CITY OF LETHBRIDGE SECTION Construction Specifications SIDEWALK CONSTRUCTION PAGE 1 of 5

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

CONNECTION TO INSPECTION CHAMBERS PRAKTO

EXCAVATION AND BACKF1LL

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS IN OPEN CUT

SECTION TRENCHING

Civil Geotechnical Surveying

BID REQUEST COVER SHEET

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

SOIL MECHANICS Assignment #2: Soil Classification Solution.

SECTION 02215BP TRENCHING AND BACKFILLING


CONTRACT 5E-2 APPENDIX A - TEST HOLE LOGS DYREGROV ROBINSON INC. PORTAGE AVE WINSTON DR BOURKEVALE CAVELL PARKSIDE DR ASSINIBOINE AVE

TABLE LATERAL SOIL LOAD UNIFIED SOIL CLASSIFICATION

SECTION STRUCTURAL EXCAVATION FOR STRUCTURES

Thi_ Qar University College of Engineering/Civil Engineering Department. Highway Lectures. Fourth Class. Part #2: - Subgrade Soil

Concrete basement walls are

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING TOOLS AND STRUCTURES

All tests from the new Cells 3 and 4 passed the licence requirements. Please provide approval to begin using the new Cell 3 and Cell 4.

PROPOSED SEGMENTAL RETAINING WALLS ARGONAUT RETAIL VILLAGE - PHASE I PENSACOLA, FLORIDA

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

Introduction to Road Soil

SECTION AGGREGATES

In preparation for constructing buildings on a property, the builder. Site Preparation CHAPTER

TECHNOLOGY CENTER WAREHOUSE ADDITION ADMINISTRATIVE SERVICE CENTER MOORE PUBLIC SCHOOLS 1500 S.E. 4 th Street Moore, Oklahoma

Standard Practice for Underground Installation of Thermoplastic Pipe for Sewers and Other Gravity-Flow Applications 1

Community Services Dept., City of Mississauga Subdivision Requirements Manual Page 1 of 5 Specifications Revised: September 26, 2005

Installation Guidelines

C. Foundation stabilization for pipe and utility structures.

Rethinking Water Management Systems

SECTION 1 GENERAL NOTES

SECTION A1 EXCAVATION AND BACKFILL GENERAL

Typical Subsurface Profile. November 28, 2016

WATER INDUSTRY SPECIFICATION

SECTION SEGMENTAL CONCRETE UNIT MASONRY RETAINING WALL MAXIMUM HEIGHT OF 5-0 HIGH


SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING

SECTION EARTHWORK. B. Removal of subsoil and excavating all classes of material encountered.

Armopanel Concrete Wall System. Design Guide B-3.1. BASEMENT WALLS

1.01 GENERAL. l.02 PIPELINE TRENCH EXCAVATION PIPELINES AND STRUCTURES REVISION: SECTION 1 PAGE : 1-1

BASED ON DFD MASTER SPECIFICATION DATED 2/24/2014

PVC. System Specifications TABLE 1 TABLE 2

Site Location. Figure 1: Site Location Map US-24 and I-275 Interchange Ash Township, Monroe County, Michigan

VOCs, including fuel oxygenates, via EPA Analytical Method The second soil sample from MW-24 (MW ) was analyzed for Total Organic Carbon.

SECTION 10.0 PIPE TRENCHES Excavation and Preparation of Trench

LETTER OF TRANSMITTAL AS REQUESTED FOR REVIEW AND COMMENT FOR APPROVAL PLEASE RECYCLE

Technical Data Sheet NEC/GRAN/95:01

SECTION 10 - TRENCHING AND BACKFILLING

Anchorplex retaining wall construction guide. Building. Anchorplex. Retaining Wall Systems

Building. Anchorplex. Retaining Wall Systems

SANITARY GRAVITY SEWER LINES. A. Sanitary sewer lines, manholes, fittings, accessories, and bedding

SECTION UNCLASSIFIED EXCAVATION AND GRADING

SECTION CONCRETE SEGMENTAL RETAINING WALL SYSTEM

Table of Contents. Section Trench Excavation and Backfill Section Includes Description of Work 1. 1.

MagnumStone Specifications Gravity

Table of Contents. Section Trench Excavation and Backfill Section Includes Description of Work 1. 1.

Table of Contents. Section Trench Excavation and Backfill Section Includes Description of Work 1. 1.

Union County Vocational - Technical Schools Scotch Plains, New Jersey

and Construction: A Design Consultant's Perspective Mark Popik, M.Eng.,P.Eng. Applied Research

SECTION PIPE INSTALLATION

SECTION MEASUREMENT AND PAYMENT

EXHIBIT G GEOTECHNICAL REPORT (DRAFT)

UNHSC Bioretention Soil Specification February, SOIL PREPARATION (PERFORMANCE SPECIFICATION) for Bioretention Systems

NORTH CAROLINA DEPARTMENT OF HEALTH AND HUMAN SERVICES DIVISION OF PUBLIC HEALTH ENVIRONMENTAL HEALTH SECTION ON-SITE WATER PROTECTION BRANCH

TS 803 DUCTS DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE

BIG 'O' HDPE Tubing CORRUGATED TUBING FOR AGRICULTURAL, RESIDENTIAL AND HIGHWAY DRAINAGE. Proudly owned and operated in Canada. aquaq.

SECTION 6. ROAD CONSTRUCTION STANDARDS

QUOTE DOCUMENTS FOR GREENWOOD ELEMENTARY GREASE INTERCEPTOR PROJECT TH STREET. Des Moines, Iowa QUOTE #7421. Owner

CITY OF GARDEN PLAIN, KANSAS STANDARDS AND SPECIFICATIONS FOR GAS YARD LINES & METER SETS

BIG O HDPE TUBING HDPE CORRUGATED TUBING FOR AGRICULTURAL, RESIDENTIAL AND HIGHWAY DRAINAGE INCREASE CROP YIELDS LOWER PRODUCTION COSTS

SECTION EARTHWORK

A. This section is intended to provide design guidelines for Utility Direct Buried Piping and Conduit Systems.

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SPECIAL SPECIFICATION 4425 Thermoplastic Pipe

General bids will be received at the Office of the Board of Selectmen/Town Manager, no later than 11:00 AM, Wednesday, October 12, 2011.

San Antonio Water System Standard Specifications for Construction ITEM NO. 804 EXCAVATION, TRENCHING AND BACKFILL

San Antonio Water System Standard Specifications for Construction ITEM NO. 804 EXCAVATION, TRENCHING AND BACKFILL

SECTION CONCRETE SEGMENTAL RETAINING WALL SYSTEM

WILLMER ENGINEERING INC. Willmer Project No Prepared for. Clark Patterson Lee Suwanee, Georgia. Prepared by

A. Backfill: Soil material or controlled low-strength material used to fill an excavation.

ITEM 430 CONSTRUCTION OF UNDERGROUND UTILITIES

SECTION TRENCHING & BACKFILLING

SECTION EARTH MOVING

American Concrete Pipe Association. Precast Box Culvert Installation Procedures

SECTION EXCAVATION, BACKFILLING AND COMPACTING

SPECIAL SPECIFICATION 4653 Polypropylene Pipe

Transcription:

Excavation for Natural Gas Mains and Services

Trench Padding & Backfilling Requirements for Mains General Install mains with a minimum of 36 of cover. Exceptions may be made within state and federal codes with the prior approval of the Operations Manager. Install plastic pipe with slack so external loading or thermal contraction will not place unnecessary stress on the pipe or joints. In cases where a stopper fitting or other new material is added to an older main such that the main has less than 24 of cover (or 36 of cover in a Massachusetts state road), the Company or contractor should provide permanent protection such as concrete. Whenever a main will be installed with less than 24 of cover, notify the Operations Manager or his/her designee so that they can request approval from the Department of Public Utilities. Requirements - See figure 1 Remove all excess water from the trench with pumps or equivalent. Place a layer of sand 4 deep in trench bottom before laying the pipe in the trench. The Operations Manager or Company field representative may allow use of clean fill material* instead of sand provided it is clean and free of any objects that may impinge on the pipe. For plastic pipe, install number 12 AWG solid copper wire (tracer wire) with yellow insulating jacket along the length of the main. Keep the tracer wire at least 4 away from the plastic pipe. This wire is used to locate the pipe. If the installation is trenchless, tracer wire may be less than 4 away from the plastic pipe. Place a minimum of 6 of sand over the pipe. The Operations Manager or Company field representative may allow use of clean fill material* instead of sand, provided it is clean and free of any objects that may impinge on the pipe. Place warning tape in the trench not more than 12 below finished grade. The standard warning tape is yellow, non-detectable tape, 6 wide. No warning tape is required if pipe installation is trenchless. Fill the rest of the trench with clean fill material, using the spoil where suitable and acceptable. If the original spoil material is not suitable for use as a sub-grade material when restoring road surfaces, use material required by state or local agencies. Remove all excess spoil in the accepted manner. Properly compact the trench to insure the trench will not settle. (*See Gas Standard GS10.03 for a description of suitable materials for pipe bedding and final backfill.)

Trench Padding & Backfilling Requirements for Mains Trench, Padding, & Backfilling Requirements for Polyethylene Gas Mains figure 1

Trench Padding & Backfilling Requirements for Services General Install services with a minimum of 24 of cover. Exceptions may be made within state and federal codes with the prior approval of the Operations Manager. Install plastic pipe with slack so external loading or thermal contraction will not place unnecessary stress on the pipe or joints. Requirements - See figure 2 Remove all excess water from the trench with pumps or equivalent. Place a layer of sand 4 deep in trench bottom before laying the pipe in the trench. The Operations Manager or Company field representative may allow use of clean fill material* instead of sand provided it is clean and free of any objects that may impinge on the pipe. For plastic pipe, install number 12 AWG solid copper wire (tracer wire) with yellow insulating jacket along the length of the service. This wire is used to locate the pipe. Do not physically attach the wire or allow the wire to touch the plastic pipe. Keep the tracer wire at least 4 away from the plastic pipe. If the installation is trenchless, the tracer wire may be less than 4 away from the plastic pipe. Place a minimum of 6 of sand over the pipe. The Operations Manager or Company field representative may allow use of clean fill material* instead of sand, provided it is clean and free of any objects that may impinge on the pipe. Place warning tape in the trench not more than 12 below finished grade. The standard warning tape is yellow, non-detectable tape, 6 wide. Fill the rest of the trench with clean fill material, using the spoil where suitable and acceptable. If the original spoil material is not suitable for use as a sub-grade material when restoring road surfaces, use material required by state or local agencies. Remove all excess spoil in the accepted manner. Properly compact the trench to insure the trench will not settle. (*See Gas Standard GS10.03 for a description of suitable materials for pipe bedding and final backfill.)

Trench Padding & Backfilling Requirements for Services Trench Padding & Backfilling Requirements for Gas Services figure 2

Installing Service Sleeves

Pipe Bedding & Final Backfilling Material Standards Pipe bedding and final backfilling should be carried out so that each zone indicated in figure 3 below is in accordance with the recommendations given herein or as specified by the engineer. Unless otherwise specified by the engineer, the haunching and initial backfilling should be performed before the leak test is completed. The backfilling should be completed following a satisfactory test. In all cases, the haunching and initial backfill material should be placed and compacted to provide support as specified by the engineer. Soils for Pipe Bedding To achieve a satisfactory installation of pipe, it is essential to install the pipe with bedding, haunching, and initial backfill materials (see figure 3, below) of characteristics that provide stable and permanent support to the pipe. Soils have been grouped into five broad classes according to their suitability as bedding materials. This grouping with descriptions of soil type (GW, GP, etc.) as per ASTM D-2487, Standard Method for Classification of Soils for Engineering Purposes, is: Class I - Angular crushed stone, maximum size of particle, 1-1/2 inches, including materials of regional significance such as marl, coral, crushed shells, cinders, and slag. Class II - Naturally occurring gravels and coarse sands, containing minimum fines, maximum size of particles 1-1/2 inches, and non-cohesive when wet or dry. These include soil types GW, GP, SW, and SP. Class III - Naturally occurring fine sands, and mixtures of gravel-clay or sandy clay, including soil types GM, GC, SM, and SC. Class IV - Very fine soils such as silt, silty-clay, lean clay, and organic clays having a liquid limit of less than 50%, including soil types ML, CL, and OL. Other soils, such as clays of high plasticity, or having a liquid limit of more than 50%, or containing such a high organic content as soil types MH, CH, OH, or PT are not categorized by the preceding classification system as they are not recommended for bedding, haunching, or initial backfill. If their use is unavoidable, expert engineering guidance should be obtained as to how they should be used and what additional supporting structures may be required. Class I and II materials should preferably be used for bedding (if required), haunching, and initial backfill. For 6 and smaller pipe, maximum particle size should be 1/2. Care should be taken to insure that haunching material is well placed under the haunches of the pipe and that, in the process, the pipe is not disturbed. The initial backfill should be placed in 6 layers and extend to at least 6 above the top of the pipe. Bedding materials should be compacted as specified by the design engineer. Class III materials may also be used in the bedding zone. When so used they should be compacted as specified by the engineer, which generally will be to not less than 80% Proctor density as determined by the AASHO Method T99 for compaction and density of coils. This may normally be accomplished by walking on soil placed in 6-inch layers or by hand-tamping same with wooden tampers. Class IV materials should be used only with the specific approval of the engineer who will determine their acceptability, depending on the ease of Trench Construction & Terminology placement and compaction of the particular materials under consideration. Final Backfill General - The final backfill, unless otherwise specified, may consist of the excavated material provided it is free of unsuitable matter, such as lumps of clay, stones, construction debris, boulders, (stones over 8 inches in their longest dimension) and frozen clods. Final Backfill Under Roads - Trenches in the right-of-way of a road should be backfilled to finished grade with an approved granular material to a compaction density of 95% or as specified by the engineer. figure 3

55 Foundation Avenue Haverhill, MA 01835 columbiagasma.com Tel: 888-639-4270 Fax: 978-556-8928