Conceptual Engineering Report Collier County Beaches, Florida

Similar documents
Public Information Meeting 7 MARCH 2017

BEACH AND INLET PROJECTS UPDATE

MEETING AGENDA ALTERNATIVE SAND SOURCE INVESTIGATION DADE COUNTY, FLORIDA BEACH EROSION CONTROL & HURRICANE PROTECTION PROJECT

Shore Protection. Atkins Team Overview. Coastal Engineering Consultant Services for Segment III. Atkins originated in Miami in 1960

MARTIN COUNTY, FLORIDA INTER-OFFICE MEMORANDUM To the Honorable Board of County DATE: August 14, 2015

Town of Duck North Carolina

Town of Duck North Carolina

REQUEST FOR ADDITIONAL INFORMATION (RAI #1) JCP

James Gray M.S. Tem Fontaine M.S., P.E.

ATTACHMENT 2 PROJECT NEED AND JUSTIFICATION

A World of Solutions

LEE COUNTY, FLORIDA GASPARILLA ISLAND SEGMENT SHORE PROTECTION PROJECT 2013 BEACH RENOURISHMENT POST CONSTRUCTION MONITORING REPORT.

VILLAGE OF BALD HEAD ISLAND SHORELINE PROTECTION PROJECT DRAFT ENVIRONMENTAL IMPACT STATEMENT

APPENDIX C DESIGN & ENGINEERING

Canaveral Harbor, Florida Federal Navigation Project -- Final Mitigation for Beach Impacts

City of Naples Beach Restoration & Water Quality Improvement Project

The release of the Final Environmental Impact Statement (FEIS) for the Bogue

APPENDIX I DRAFT COMPENSATORY MITIGATION PLAN

Florida Inland Navigation District: Permitting and Construction of the M 5 Island Offloading & Crossroads Maintenance Dredging and the NA 1 Upland

USACE (IP-SLN)

MARCH 4, protection office oro tecttr ebeach com

Final General Reevaluation Report and Final Environmental Impact Statement. Hurricane Protection and Beach Erosion Control

REUSE OF DREDGED SEDIMENTS

APPENDIX A SECTION 404(B)(1) EVALUATION TYBEE ISLAND, GEORGIA SHORE PROTECTION PROJECT RENOURISHMENT

Mississippi Coastal Improvements Program (MsCIP) Comprehensive Barrier Island Restoration Plan

Biological Monitoring: An Underwater Perspective

The State of New Jersey s Shore Protection Program

Sand Relocation Project

Asharoken Coastal Storm Damage Risk Reduction Feasibility Study

NORTH CAROLINA TERMINAL GROIN STUDY. Feasibility and Advisability of the Use of a Terminal Groin as an Erosion Control Device

CEC Coastal Permitting Workshop

02 APRIL PUBLIC NOTICE U.S. Army Corps of Engineers, Savannah District

Nags Head Beach Nourishment Project

Photo on 22 October 2016 Post Matthew. Nags Head Shoreline Management Committee Public Meeting April 15, 2017


CONSOLIDATED JOINT COASTAL PERMIT AND INTENT TO GRANT SOVEREIGN SUBMERGED LANDS AUTHORIZATION

Harbour Constructions

NATIONAL OCEAN SERVICE

Construction Challenges in Restoring Louisiana s Barrier Islands

BENEFICIAL REUSE OF DREDGE MATERIAL SOUTH BAY SALT POND RESTORATION PROJECT PHASE 2

SEDIMENT QUALITY CONTROL/QUALITY ASSURANCE PLAN FOR BEACH RESTORATION OR NOURISHMENT USING AN OFFSHORE BORROW AREA. [FDEP Permit No.

Virginia Beach Comprehensive Sea Level Rise and Recurrent Flooding Planning Study

PUBLIC NOTICE NO. FP13-AB03-05 August 30, 2013 CESAM-PD-EC JOINT PUBLIC NOTICE

COASTAL STRATEGIES FOR DRAINAGE RESILIENCE

SEDIMENT QUALITY ASSURANCE/QUALITY CONTROL PLAN DUVAL COUNTY BEACH NOURISHMENT PROJECT. FDEP Permit No JC

FSBPA Chip Baumberger, Project Scientist Dustin Myers, UAV Coordinator Brent Gore, GIS Coordinator

Comprehensive Barrier Island Restoration Plan

SEDIMENT QUALITY CONTROL/QUALITY ASSURANCE PLAN FOR BEACH RESTORATION OR NOURISHMENT USING AN OFFSHORE BORROW AREA. [FDEP File No.

Kiawah Island 2016 Beach Monitoring

PA-03. Honorable Mike Kelly. Pennsylvania 114th Congress. 3rd Congressional District. Miles

Ecotourism Business Owner

DREDGING FOR BENEFICIAL USE

Lessons Learned, Innovations, and Successes from U.S. Great Lakes Areas of Concern Sediment Cleanups

July 22, Dear Mr. Garis:

Fernando Camargo, Hull & Associates, Inc. On behalf of Joe Cappel Toledo-Lucas County Port Authority. Thursday, December 7, 2017

NEW RIVER INLET CHANNEL REALIGNMENT PROJECT UPDATE NOVEMBER 1, 2012

AT A GLANCE. Cairns Shipping Development Project. Revised Draft Environmental Impact Statement Fact Sheet July 2017.

The Clean Water Act and 404/401 Process in Hawaii

AMENDMENTS TO BAYFIELD COUNTY ZONING ORDINANCE. Lake Superior Shoreland Lot Development Requirements.

Interstate 73 FEIS: I-95 to the Myrtle Beach Region Chapter 4. Public Involvement and Agency Coordination

Construction of Offshore Stormwater Discharges Using HDD Technologies. Karyn Erickson, D.CE., PE, President Erickson Consulting Engineers, Inc.

ROTAWN ENERGY AND LOGISTICS DREDGING PROFILE

Collaboration: Sea-level Marin Adaptation Response Team (C-SMART)

SEDIMENT CHOREOGRAPHY

PUBLIC NOTICE. Attn: Mr. Greg Rudolph, Carteret County Shore Protection office Post Office Box 4297 Emerald Isle, North Carolina 28594

SANDY HOOK CHANNEL, NEW YORK HARBOR FEDERAL NAVIGATION PROJECT MAINTENANCE DREDGING

Executive Summary. Monterey Peninsula Water Management District. Sand City Desalination Project Feasibility Study. Executive Summary.

Source Control Early Action Focused Feasibility Study

Final General Reevaluation Report and Final Environmental Impact Statement. Hurricane Protection and Beach Erosion Control

PUBLIC NOTICE. Figure 8 Beach Homeowners Association, Inc. C/o: Mr. David Kellam (Administrator) 15 Bridge Road Wilmington, North Carolina 28411

FINAL ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT TYBEE ISLAND, GEORGIA SHORE PROTECTION PROJECT RENOURISHMENT

Vessel Impacts to Shallow Water Habitat: Groundings and Prop Scarring in the Florida Keys National Marine Sanctuary

Coastal Green Infrastructure Techniques for the Protection of SR 1 Vulnerability Assessment and Demonstration

Initial Construction and Maintenance Costs

Notice of Availability (NOA) of the Draft Environmental Impact Statement. (DEIS) and the Announcement of a Public Hearing for the Installation of a

BOEM s Offshore Energy Leasing Programs

Matrix of Potential Coastal Adaptation Strategies

Encinitas-Solana Beach Coastal Storm Damage Reduction Project. San Diego County, California. Appendix D. 404(b)(1) Evaluation

U.S. Army Corps of Engineers Jacksonville District Sediment Quality Control/Quality Assurance Plan For Maintenance Dredging with Beach Placement

Utilizing Dredge Material in Wetland and Estuarine Restoration. Bartholomew Wilson P.G. Delaware Center for the Inland Bays

Restore America s Estuaries October 24, 2012

Big Sarasota Pass and New Pass Inlet Management Plan 2008 Peer Review Report

Team Member Affiliation WEDA Member Role

40 YEARS OF MARINE OPERATIONS & ENGINEERING IN HAWAII. Makai Research Pier, Waimanalo, Hawaii. 863 N. Nimitz Hwy, Honolulu Harbor

Riverine Sand Mining Scofield Island Restoration Project (BA-40)

Coastal Hazards Vulnerability and Fiscal Impact Study Report:

Construction of Offshore Stormwater Discharges using HDD Technologies

SUSTAINABLE SOLUTIONS FOR DREDGED MATERIAL MANAGEMENT IN OHIO

Shingle Creek Watershed Management Commission Wetland 639W Outlet Modifications Summary Feasibility Report

J O I N T P U B L I C N O T I C E

Shrewsbury River Basin, Sea Bright, New Jersey Coastal Storm Risk Management Feasibility Study

May 4, Applicant: Lake Charles Harbor and Terminal District 150 Marine Street Lake Charles, Louisiana 70602

PEARCE CREEK CONFINED DISPOSAL AREA MODIFICATION

Coastal Science and Engineering Collaborative (CSEC) Overview

SECTION 6.0 AVOIDANCE, MINIMIZATION AND MITIGATIVE MEASURES

Protect, Accommodate, or Retreat? Integrating Adaptation Strategies and Ecosystem Services into the Cape Cod Coastal Planner

GREAT EGG HARBOR INLET TO TOWNSENDS INLET STORM DAMAGE REDUCTION PROJECT CAPE MAY COUNTY, NJ DRAFT ENVIRONMENTAL ASSESSMENT (EA)

PRELIMINARY SHORELINE PROTECTION STUDY Parking Lot D to the JFK Library

Climate change and the coast: CZM efforts to improve community resilience. Bruce K. Carlisle Director Massachusetts Office of Coastal Zone Management

Public Notice U.S. ARMY CORPS OF ENGINEERS, GALVESTON DISTRICT AND TEXAS COMMISSION ON ENVIRONMENTAL QUALITY

Transcription:

Conceptual Engineering Report Collier County Beaches, Florida Presented to Collier County Coastal Advisory Committee October 13, 2011 Steve Keehn, PE, CPE

Topics Goals Monitoring & Performance Summary 3 Major Hot Spots Findings Modeling Results Recommended Project Combination of Existing and New Practices Cost and Cost Saving Next Step

Goals: The purpose of the study was to develop conceptual designs that addresses the effectiveness of existing structures and beach fill design templates, and changes needed to solve hot spots and improve project performance and durability. Beach fill alternatives with a higher and wider beach berm were evaluated with structural modifications to achieve these goals.

Hot Spot Ranking Matrix Hot Spot Erosion Rates Maintain Beach Width Groin Impacts Hardbottom Limitations Management Practices Relative Importance Code Barefoot Beach R14-R16 XX NA X 3 M, N Delnor Wiggins State Park X 1 I Vanderbilt Beach R27 & R31 X X X 3 S, * Pelican Bay R35-R36 X X 2 I Clam Pass Park R42-R44 XX NA X X 4 M, N Seagate Drive R45-R46 X X X 3 S & G Park Shore R51-R54 X X X 4 S, * South of Doctors Pass R58 XX XX X X X 7 M, Str South of Lowdermilk Park R62-R64 X X X 3 S & G South Naples R71 XX 2 I Code S More sand or feeder beach likely solution G Shorten or remove groin likely solution M Management change needed Str New structure needed N Nourishment I Not a problem * Structures as fall back solution Priority Yellow, blue, green.

Major Finding The performance of the beach in avoiding hardbottom coverage has exceeded permit expectations, and the results of four years of physical monitoring indicate that the beach can be widened without a significant increased risk of hardbottom impacts. The analysis and modeling indicate that the recommended plan with a 10 year project life is feasible with the use of minimal new structures.

Bases of Conceptual Design Excellent Performance 25 ft. advance at MHW Versus 37 ft. retreat at -11 ft. NAVD 63 feet Total Advanage 25.0 Park Shore Hot Spot Solution

CHANGE INLET MANAGEMENT MODIFY DISOSAL AREA COORDINATE INLET MANAGEMENTND AND BEACH NOURISHMENT ELIMATE/REDUCE STRUCTURES (Groins) Return Disposal Area Here, but Upland South of Doctors Pass Extend Disposal Area to Here Clam Pass Park and Seagate Drive

In general, if sufficient sand can be placed on the beach through nourishment and inlet bypassing, then a structures are less important.

Much Sand and No Structures Better Beach

Alternatives Considered Alternative 1: FEMA Project Alternative 2: 2006 Project w/ 3 Reaches Alternative 3: 2013-14 Design with 10- Year Life in 5 Reaches Higher and Wider Beach Alternative 4: Structures Removal Modification

Summary of Modeling Results and Final Plan In general, the modeling shows a 10-year nourishment interval is feasible and most of the groins can be removed, resulting in improved performance of the beach. Modeling shows that a wider fill placement and removal of some of the existing structures is the most practical and direct solution, while many of the structures modeled had less convincing performance.

Calibration for Vanderbilt Beach

Naples with and without structures after 3 years

Aerial photography dated of 2008 and 2009 taken at the Double pipeline outfall and groin combination

Park Shore with and without structures after 3 years

The 2013-14 design without structures is the recommended plan, in conjunction with increased sand placement near hot spots identified by the modeling. This selection is a combination of Alternative 3 and M9 to M11. For economy, gaps in fill placement should be allowed in the project area to reduce the amount of fill needed and its associated cost.

10-Year Life Add n Fill @ R-29 Gaps Vanderbilt Recommended Plan

10-Year Life Remove Structures Modify Bypassing to R45 Gaps Park Shore Recommended Plan

10-Year Life Remove Structures Modify Bypassing Disposal Build Groin Spur Gaps Naples Recommended Plan

Net Sediment Transport with and without Spur & Volume Gain

If sufficient sand can be placed on the beach through nourishment and inlet bypassing, then a structural solution is less important. In general, the modeling shows a 10-year nourishment interval is feasible and most of the groins can be removed, resulting in improved performance of the beach. Modeling shows that a wider fill placement and removal of some of the existing structures is the most practical and direct solution, while many of the structures modeled had less convincing performance. The consideration of new structures should also be delayed until sufficient monitoring of the expanded project is performed.

DESIGN VOLUMES REACH Vanderbilt R22 to R31 N. Park Shore R45 to R48 Park Shore R49 to R55 DESIGN VOLUME (C.Y.) ALT. 1 ALT. 2 ALT. 3 40,000 41,733 58,056 21,000 40,881 49,729 30,000 97,251 136,337 Naples Beach 84,000 302,166 413,008 R58A to R79 SUBTOTAL 175,000 482,031 657,130 Barefoot Beach 100,000 R14 to R16 Clam Pass R42 to R44 30,000 TOTAL 175,000 482,031 787,130

Recommended project: Combination of existing practices and new alternatives using 2013-14 Design Alternative 3 without structures and modification to inlet management practices Continuation of Existing Practices. Beach fill Vanderbilt Beach R22.5 to R31.5 Park Shore R45.5 to R54 Naples Beach R58 to R79 Inlet Bypassing at Wiggins, Clam and Doctors Passes

New Elements Widen & raise the beach to support a 10-year life. Nourish Barefoot Beach (R14 R16) and ebb shoal. Nourish Clam Pass Park as feeder beach for Park Shore. Return to pre-2005 disposal area for Doctors Pass dredging Remove structures from beach sequentially from those with the largest impact, lowest cost and easiest to address outfall solution. Start with the structures located closest to Clam and Doctors Passes. Add a spur to the south Doctors Pass jetty Delay other structures

Higher & Wider Profile Typical Naples Beach Profile 2006 vs 2010 Template Comparison 8 6 4 2010 Profile 2006 Template Expanded Template Elevation (ft, NAVD 2 0-2 10 1 15 10 1 1-4 -6-8 -10 50 100 150 200 250 300 350 400 450 500 Distance (ft)

Gaps No Fill Needed R-22 to R-24 R-50 R-66 to R-69 R-31 R-54 R-73 to R-75 R-49 R-55 R-77 to R-79

Groin Removal Remove Groins In Sequence North to South starting with: Three groins South of Clam Pass Vicinity of R44.5 & R45.5 First 2 groins South of Doctors Pass R58 & R59+300

Cost and Cost Savings

Price Estimate Item Alt. 1 FEMA Design Alt. 2 Existing Design Alt. 2A Existing Design Alt. 3 10-yr Nourishmen t Interval Fill Volume 175,000 482,031 612,031 787,130 Fill Cost for 2006 Project Limits $9,218,501 $18,497,995 $18,497,995 $24,345,324 Barefoot and Clam Pass Parks $0 $0 $3,751,300 $3,751,300 Structure Modification & Removal $0 $0 $400,000 $1,600,000 Design, Permit & Monitoring $906,950 $906,950 $1,265,301 $1,490,987 Sub-total $10,125,451 $19,404,945 $23,914,595 $31,187,611 Potential Savings -$1,233,490 -$1,818,586 -$2,016,322 -$2,850,000 Reduction to 8-Year Proj. Life $0 $0 $0 -$2,764,001 5% Contingency $444,598 $879,318 $1,094,914 $1,278,680 Total $9,336,559 $18,465,677 $22,993,187 $26,852,290

Optimizing Project Cost. Schedule and Synchronize Coastal Components & Management Bidding and Contract Methods Administrative Technical Refine Design New Programmatic Biological Opinion

Schedule and Synchronize Coastal Management in County Inlet Dredging Beach Nourishment Beneficial Use of Sand Joint use of restricted disposal areas. Combine similar projects Marco, Caxambus and Doctors Pass

Savings Bidding and Contract methods Joint Project with bidding guarantees. Use unit price to manage sand volumes and cost Early availability of draft Plans and Specifications Partnered Maximize dredger time and flexibility Include best weather months in construction period. Highest dredge availability Best weather during sea turtle season Year Round Dredging Including Calmer Months

Complementary Tasks Outfalls Pipes Permit Issue Hot spots stays until outfall solved. Make changes to Inlet Management

New Programmatic Biological Opinion Allows Year Round Construction

¼ Mile Long Submerged Pipeline Being Emplaced Needs a Flat Water Day

2006 Construction Overview 92 days (60 Days Pumping) 8.2 miles of beach 664,000 CY construction volume Borrow area 33 to 38 miles away Equipment Great Lakes Dredge & Dock Company - 2 Hopper Dredges - 2 offshore booster pumps - 3+ miles of subline - Pipeline collars over reef areas

Environmental Monitoring Seek Reduction In Monitoring 14 miles of reef characterization Over 500 acres of hardbottom survey using Side Scan Sonar Diver edge verification Digital video documentation and reef data collection over 36 permanent monitoring transects, each 150 meters in length. Hard coral census and stress level assessments Complex and thorough marine resource investigation that it is ongoing annually for the next 3 years, then every other year until 2011.

Next Step Set Schedule Meet with FDEP Start Design & Permit Modification Develop Cost Saving and Bidding Plan Negotiate Reduced Monitoring Implement Plan

Task to Implement Project Permit Design, Plans and Specification for 2013-14 Project Pre-Application Meeting FDEP Map 3 New Pipeline Corridor and with Dredge Operational Areas Special Design Survey for Profiles, Structures, ECL & 3D Design Elements 3-D Design Update (around hardbottom) with larger fill section and new reaches Design Clam Pass Park and Barefoot Beach Address Hot Spots and Hardbottom Avoidance with intermediate profile line Run model with refinements and to revalidate design and Spreading magnitude Design structure modifications and removals Prepare BOEM Environmental Assessment Prepare & submit permit modification to 2005 Permit with new Permit Sketches RAI Cycle with Meetings Update biological and physical monitoring plans Develop Hardbottom Impact Assessment Develop Plans and Specifications Bidding and Award Pre-, During- and Post-Construction Task Pre-Construction Survey & Biological Monitoring Hardbottom mapping using side scan Construction Services Pipeline Corridors Monitoring Shore Bird Sea Turtle Monitoring Post-Construction Survey, Report and Certification Post-Construction Biological Monitoring and Report

The End