BASED ON DFD MASTER SPECIFICATION DATED 2/24/2014

Similar documents
SECTION STRUCTURAL EXCAVATION FOR STRUCTURES

SECTION TRENCHING

EXCAVATION, TRENCHING & BACKFILLING..1 The section refers to excavation, trenching, backfilling and all Work pertaining thereto.

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

TRENCH EXCAVATION AND BACKFILL

Union County Vocational - Technical Schools Scotch Plains, New Jersey

SECTION 10 - TRENCHING AND BACKFILLING

SECTION 1100 GRADING 1102 MATERIALS AND DEFINITIONS.

B. Base Course: Aggregate layer placed between the subbase course and hot-mix asphalt paving.

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

C. Foundation stabilization for pipe and utility structures.

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING

B. Borrow: Satisfactory soil imported from off-site for use as fill or backfill.

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION TRENCHING AND BACKFILL

SECTION TRENCHING & BACKFILLING

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL

SECTION TRENCHING, BACKFILLING AND COMPACTION. B. Provide necessary sheeting, shoring and bracing.

EXCAVATION AND BACKF1LL

1.02 RELATED WORK: Refer to the following sections for related work: Section 4000-Concrete Materials and Methods

SECTION EXCAVATION AND FILL

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION SOILS REPORT

Excavate drilled shafts in accordance with Item 416, Drilled Shaft Foundations.

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

1.01 GENERAL. l.02 PIPELINE TRENCH EXCAVATION PIPELINES AND STRUCTURES REVISION: SECTION 1 PAGE : 1-1

ITEM 430 CONSTRUCTION OF UNDERGROUND UTILITIES

SECTION EARTHWORK. B. Removal of subsoil and excavating all classes of material encountered.

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

Construction Specification for General Excavation

SECTION SITE GRADING. Part 1 - General Work Included Related Requirements Reference Standards...

SECTION EXCAVATION AND FILL

SECTION UNCLASSIFIED EXCAVATION AND GRADING

The developer/contractor shall be responsible for replacing all fences which must be disturbed for the installation of sanitary sewer or water lines.

SECTION TRENCHING AND BACKFILLING. A. Earth excavation and backfilling for construction of pipe and appurtenances, and for required removals.

STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 300 EARTHWORK, GRADING, AND GRAVELING

City of Brandon Division 2 Standard Construction Specifications Section January 2007(Revision 1) Page 1 of 8 ROADWAY EXCAVATION AND GRADING

DIVISION 4100 SITEWORK

SECTION EXCAVATION, BACKFILLING AND COMPACTING

SECTION 10.0 PIPE TRENCHES Excavation and Preparation of Trench

SECTION TRENCHING, BACKFILL AND COMPACTION

A. Backfill: Soil material or controlled low-strength material used to fill an excavation.

2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

SECTION STRUCTURE EXCAVATION AND EARTHWORK

TRENCH EXCAVATION AND BACKFILL

SECTION EARTHWORK

The Six-Inch Layer Compaction Method

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis.

SECTION GENERAL EXCAVATION

SECTION EXCAVATION, TRENCHING AND BACKFILL

SECTION TRENCI-JING PART 1 GENERAL

Installation Guidelines

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES

SECTION 13 - EXISTING FACILITIES TABLE OF CONTENTS

B. Backfill and compact utility bedding and fill placed in the utility trenches between the top of the utility bedding and the subgrade elevation.

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

SECTION EARTHWORK

17.0 CONSTRUCTION OF OPEN DRAINAGE SYSTEMS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

SECTION 02215BP TRENCHING AND BACKFILLING

SECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

TECHNOLOGY CENTER WAREHOUSE ADDITION ADMINISTRATIVE SERVICE CENTER MOORE PUBLIC SCHOOLS 1500 S.E. 4 th Street Moore, Oklahoma

SUB WATER DEPARTMENT STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION EXCAVATION AND BACKFILL, GENERAL

DUKE UNIVERSITY CONSTRUCTION STANDARDS

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS

SECTION EARTHWORK; EXCAVATION, FILLING AND GRADING. A. Excavating soil and other material for surface improvements.

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS IN OPEN CUT

ITEM 481 MONOLITHIC REINFORCED CONCRETE BOX SEWERS

SECTION INTERLOCKING PRECAST CONCRETE UNIT PAVERS

CITY OF LETHBRIDGE SECTION Construction Specifications Page 1 of 7 BACKFILL REGULATIONS FOR PUBLIC RIGHT-OF-WAYS

Chapter 3: Permit Procedures and Requirements

EXCAVATION & BACKFILLING GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

SECTION CONTROLLED LOW STRENGTH MATERIAL

Section SITE CLEARING. B. Description of Work: 1. The extent of site clearing is shown on the drawings.

SECTION EXCAVATING, BACKFILLING AND COMPACTING

SECTION GRADING AND SITE PREPARATION CITY OF LEE S SUMMIT, MISSOURI STANDARD SPECIFICATIONS

This specification supplements the requirements of the Occupational Health and Safety Act, and its Regulations and the Ontario Building code.

SECTION 1 GENERAL NOTES

SECTION 18 - EARTHWORK TABLE OF CONTENTS

Municipality of Waterville Public Sidewalk Repair Policy

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

CITY OF AUBURN STANDARD SPECIFICATIONS SECTION 13 EXCAVATION AND BACKFILL

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

Dodge City s, General Information For Driveway/Sidewalk Permits, Utility Permits.

SECTION 14 EMBANKMENT

A. Work of this Section is affected by unit prices for earth moving specified in Section "Unit Prices."

SPECIFICATIONS FOR STREET CONSTRUCTION WITHIN THE TOWN OF PLAINVILLE

ITEM 706 PIPE SLOPE DRAIN

SECTION 32 EXCAVATION, BACKFILL, COMPACTION AND GRADING

EXCAVATION & BACKFILL SPECIFICATION

SECTION FILL AND BACKFILL

A. Excavation consists of the removal of material encountered to subgrade elevations and the reuse or disposal of materials removed.

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

CONSTRUCTION SPECIFICATION FOR CONCRETE UNIT PAVERS

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

SECTION 18 - EARTHWORK TABLE OF CONTENTS

CONSTRUCTION SPECIFICATION FOR SITE RESTORATION FOR UNDERGROUND UTILITIES

SECTION MECHANICALLY STABILIZED EARTH RETAINING WALLS

REGIONAL CONSTRUCTION STANDARDS

Transcription:

1 0 1 0 1 0 1 SECTION 1. TRENCHING BASED ON DFD MASTER SPECIFICATION DATED // P A R T 1 - G E N E R A L SCOPE The work under this section shall consist of providing all work, materials, labor, equipment, and supervision necessary to complete trenching for utilities and other work, as required in these specifications, on the drawings and as otherwise deemed necessary to complete the work. Included are the following topics: PART 1 - GENERAL Scope Related Work Submittals Record Drawings Quality Assurance Permits/Fees Survey and Staking PART - MATERIALS Utility Bedding and Cover Free Draining Fill Earth Backfill Controlled Backfill Flowable Fill Crushed Stone Bedding Crushed Stone Screenings Bedding Sand Cement Slurry Grout PART - EXECUTION Preparation Underground Locates Connections to Existing Utilities Dewatering Excavation Support of Existing Utilities Insulation for Existing Utilities Bedding & Utility Cover Backfill and Compaction Grading Grading Around Trees Temporary Berms and Storm Sewers Restoration RELATED WORK Applicable provisions of Division 1 govern work under this Section. Section 1 00 Erosion Control Section 1 Dewatering Section 1 00 Erosion Control Applicable provisions of Division 1 shall govern all work under this section. SUBMITALS Provide copies of record drawings. 1. -1

1 0 1 0 1 0 1 Provide samples of each type of soil or aggregate proposed for use on the project. Samples shall consist of a minimum of 0 pounds of soil. The contractor shall be responsible for delivering soil samples to the testing agency as designated by the DFD Construction Representative. Provide samples a minimum of weeks prior to starting construction. Provide copies of material testing reports. RECORD DRAWINGS Maintain record drawings showing actual locations of utilities and other features encountered, modifications to proposed grades and site features, and other deviations from the original design. QUALITY ASSURANCE The Contractor shall complete quality assurance testing as outlined in Table 1.-1: Material Test Required Test/Sample Frequency I.E. Granular Fill ASTM D- Modified Proctor Test 1 test/00 lf trench Table 1.-1 PERMITS/FEES Contractor shall be solely responsible for obtaining all permits necessary to complete trenching work. The Contractor shall pay all fees associated with obtaining permits. These include, but are not limited to permits to work within right-of-way, utility connection permits, plumbing permits, electrical permits and other building permits. SURVEY AND STAKING Owner or A/E will provide benchmarks and control points for the project. Contractor shall be responsible for transferring benchmarks, control points, lines and grades as necessary to complete his work. P A R T - M A T E R I A L S UTILITY BEDDING AND COVER Class B stone chip bedding. Use bedding free from clumps, rocks, organic and frozen materials. Use crushed stone chips meeting the following for all direct buried utilities and utility tunnel: Gradation Sieve Size % passing (by weight) 1 inch 0 / inch 0 to 0 1/ inch --- / inch to No. 0 to No. 0 to No. 0 --- Lifts not-to-exceed see Table 1.- for final compacted lift height Each lift compacted to 0 percent of dry density in accordance with ASTM D FREE DRAINING FILL Comply with ASTM C grading requirements. Washed gravel or crushed stone, 1/ inch minimum, / inch maximum. EARTH BACKFILL 1. -

1 0 1 0 1 0 1 Sand/gravel non-cohesive non-expansive, free of vegetable matter, clay, rubbish, rock larger than inches, boulders, concrete, paving, masonry debris, waste, frozen materials, other inorganic and deleterious materials. Existing material meeting these requirements can be reused. CONTROLLED BACKFILL Sand or pit-run sand/gravel, meeting the following above all direct buried utility and utility tunnel: Gradation Sieve Size % passing (by weight) -1/ inch 0 1 inch 0 to 0 / inch 0 to 0 No. 0 to 0 No. 0 or less FLOWABLE FILL Controlled low strength material (CLSM) or flowable slurry fill. Cement: Any Type, 0 lb/cu. yd & 0 lb. per cu. yd. Aggregate: None required for slurry fill, sand for utility support. Strength: 0 0 + psi @ days. Slurry: As necessary. Fly Ash: Any class in quantity equal to cement. Thoroughly mix in a clean ready mix truck; run mixer at mixing speed for one minute just prior to placement to insure an even mixture. CRUSHED STONE BEDDING Clean material meeting the requirements of ¾ Crushed Stone Chips as defined in Section..(a), regardless of pipe size, of Standard Specifications for Sewer and Water Construction. CRUSHED STONE SCREENINGS Crushed stone free of organic material, concrete, asphalt and other debris. Material shall meet the requirements of Crushed Stone Screenings as defined in Section..(b) of Standard Specifications for Sewer and Water Construction. BEDDING SAND Sand meeting the requirements of Bedding Sand as defined in Section..(c) of Standard Specifications for Sewer and Water Construction. CEMENT SLURRY GROUT Portland cement based grout having a slump of -1 and the following mix proportion (per CY): Type 1 Portland Cement 0# Class C Fly Ash 00# Fine Aggregate 00# Water 00# Air Entraining Admixture oz Similar mix designs that are suitable for the intended use will be considered. P A R T - E X E C U T I O N PREPARATION General Contractor shall excavate and backfill the following utilities in accordance with this section: -Steam box conduits, sump & dewatering discharge piping, and pits. -Underground chilled water pipe -Underground primary/signal vaults and ductbanks -Storm and sanitary piping. -Direct buried power and signal conduits. Remove excavated materials throughtout day. 1. -

1 0 1 0 1 0 1 No stockpiling of excavated materials on site. Review plans and prepare work plan and schedule. Coordinate any necessary interruptions in utility service with DFD Construction Representative, in accordance with other specification sections. Layout work. Establish and transfer line and grade as necessary to complete the work. Remove topsoil from work area. Saw cut and remove pavement from the work area. UNDERGROUND LOCATES Contractor shall include ALL underground utility locates. Locates shall include excavation, backfill, survey and pictures of existing utilities within the construction limits. Survey information shall include size, elevation, GPS location, materials and height and width of utility. Locates shall be authorized by DFD Representative. CONNECTIONS TO EXISTING UTILITIES Connect to existing utilities in accordance with the requirements of other pertinent specification sections. DEWATERING Dewatering shall be completed in accordance with Section 1 - Dewatering EXCAVATION Excavate to elevations and dimensions necessary to complete construction. Excavations shall be sufficiently deep to provide for bedding beneath pipes and structures, to provide steam tunnel water proofing and as otherwise required to complete the work as shown. For pipes less than 1 in diameter, maximum trench width at the top of the pipe shall be. For pipes greater than 1 in diameter, the maximum trench width at the top of the pipe shall be no greater than the outside diameter of the pipe plus. The trench width at the ground surface shall be minimized to the extent possible through the use of trench boxes, shields, or shoring, and as necessary to protect features and improvements that are shown to be protected on the drawings. The trench width at the ground surface shall not exceed the width of the trench at the top of the pipe by more than without prior approval by the DFD Construction Representative. Provide a minimum clearance of from outside of pipe to the closest of either the sidewall of trench or inside wall of trench box, shield or shoring. Notify DFD Construction Representative if trench subgrade consists of unstable soil, organic material, debris or other undesirable material. Segregate the various materials excavated. Reserve material meeting the requirements of backfill for the location. Excavated material that does not meet the requirements of backfill, and excess excavated material, shall be removed from the site and disposed by the contractor, unless directed otherwise by other specification sections or the DFD Construction Representative. Locate bedding, backfill and spoil piles in accordance with OSHA requirements, and so that it does not interfere with public travel, adjacent landowners or other construction activities. Trench excavation shall be limited to that which can be excavated and backfilled within the same workday. The same trench may obstruct no more than one street crossing at one time. 1. -

1 0 1 0 1 0 1 0 1 Where a new or existing utility pipeline, structure, box conduit or signal/power conduit requires support, or where existing utility lines are required to be abandoned in place, provide one of the flowable fill materials approved by the engineer and/or construction representative. Provide a dewatering sump with pump and emergency generator power in each excavation from the first day of excavation until the excavation is backfilled. Provide a sump with a pump and emergency generator power in each tunnel, new and existing steam pits from the first day of excavation until the excavation is backfilled and the permanent sump pumps are installed. The same trench may not obstruct more than one street crossing at one time. Do not interfere with degree bearing splay of foundations. Elevations for contours as shown on the plans, are subject to such revisions as may be necessary to fit field conditions and that the Owner's Project Representative reserves the right to adjust grades from those shown on the plans to fit field conditions. Unless otherwise provided in contract or permitted by the Engineer, the work of constructing sewers and allied works shall be done in open trenches and in a manner to protect the pipe lines or sewers from unusual stresses. When provided in the contract or permitted by the Engineer, the construction of sewers may be done by tunneling and/or jacking in lieu of open trenching; details of construction shall be indicated on the plan, specified in the contract, or established by the Engineer prior to beginning the work of tunneling and/or jacking. All of the work of construction sewers shall be done in accordance with the applicable provisions of the Wisconsin Administrative Code, applicable standards or requirements of the local authority having jurisdiction. The trenches shall be excavated in conformity with the required alignment and grades as shown on the plans and as laid out in the field by the Engineer. It shall be understood that the elevations for sewers, as shown on the plans, are subject to such revisions as may be necessary to fit field conditions and that the Engineer reserves the right to adjust the profile grades from those shown on the plan. No adjustment in compensation will be made for the grade adjustments not in excess of 1- foot above or below the elevations shown on the plans. Unless noted on the drawings, the Contractor shall remove all vegetation along the trench line to the width of the proposed trench before beginning excavation. Vegetation removed shall not be used as backfill in the trench, but shall be disposed of by the Contractor at no additional cost to the OWNER OR DFD. If the trench line is finished with pavement or other structures, removal of those items shall be incidental to the trench excavation. The width of the utility trench shall be such as to leave a clear space of not less than inches nor more than 1 inches between the earth wall, or the supporting sheeting or bracing where such is used, and the sides of the utility. The trench width established by this utility clearance, measured at the spring line, shall be applicable to that portion of the trench from 1-foot above the top of the utility to the bottom of the trench. On streets opened to traffic, on restricted easements, and in such other locations as the Engineer directs, the width of the trench at the surface of the ground shall be limited to the outside dimension of the utility plus feet plus the amount necessary for sheeting or bracing. Surplus material shall be considered to include vegetation from the trench line, excavated rock or boulders larger than inches in diameter, and all other material from excavation not needed or suitable for backfilling trenches. Unless otherwise specified, surplus material shall be the property of the Contractor, and shall be disposed of at Contractor s cost. Unless otherwise provided, the Contractor shall provide all trench soil retention, sheeting and/or bracing needed to protect the work, existing property, utilities, pavement, etc., and to provide safe working conditions in the trench. Such trench soil retention, sheeting and/or bracing shall be according to the Contractor s design and shall comply with the Wisconsin Administrative Code. Removal of any trench soil retention, sheeting and/or bracing from the trench shall be accomplished in such a manner as to fulfill the above requirements. Sheeting and bracing shall be removed unless specific permission is given by DFD to leave it in place. The DFD reserves the right to limit the extent of excavation in advance of utility installation and backfilling depending on the nature of the soil and other conditions affecting the work. 1. -

1 0 1 0 1 0 1 0 1 The DFD reserves the right to order additional excavation where unsuitable soil conditions exist to install utilities. When this condition arises, the excavation shall be carried to such depth as directed by the Engineer. The maximum width of the extra trench excavation shall be the outside of the proposed structure plus feet plus the amount necessary for trench soil retention, sheeting and/or bracing. Undercut backfill shall be shall be installed and mechanically compacted to replace the excavated materials to subbase grade. Work necessary to expose existing underground facilities that are part of the Contractor s statutory obligation during the normal storm sewer, sanitary sewer, chilled water, steam, condensate and compressed air utilities, electrical conduit or water main installation shall be considered as incidental to those respective items. SUPPORT OF EXISTING UTILTIES Contractor shall support all conduits, sewers, structures, piping, wiring and cables that are exposed due to trenching and excavations. Support system shall be designed by an engineer licensed in the State of Wisconsin. Provide by-pass pumps, piping and structures needed to keep the existing service on line while allowing work to progress. Provide all temporary piping as needed. Existing storm and sanitary sewer piping may have joints that leak. Provide temporary joint wraps and clamps to keep storm and sanitary sewer piping from leaking into excavation or provide temporary storm and sanitary sewer piping to keep excavation dry and clean. All open cut excavations shall have mil plastic sheeting installed to cover and protect slope of excavation. INSULATION FOR EXISTING UTILITIES Contractor shall provide temporary insulation over exposed utilities to keep them from freezing. BEDDING AND UTILITY COVER If unstable native soils are adjacent to bedding and utility cover in trench wrap bedding and utility cover in geotextile fabric. Where sheet piling/shoring is abandoned between unstable soil and trench wall geotextile fabric may be omitted. Bed pipes and place utility cover material in accordance with detail drawings and the requirements of specifications for the utility and pipe type being installed (minimum depth of bedding). Establish excavation subgrade in accordance with proposed utility lines and grades, allowing for required amount of bedding material. Excavation shall be reasonably free of water prior to placement of bedding material. Place bedding material to required depth, and compact as specified in table 1.-. Shape bedding material to conform to bell of pipe, fittings and structures. After placing pipe, support during placement and compaction of initial utility cover material. Place utility cover to required depth and compact to 1 above utility piping, as specified in table 1.-. Compaction of initial cover material for pipe and fittings shall be accomplished using hand tools and vibratory plate or tamping type walk behind compactors. BACKFILL AND COMPACTION Backfilling shall not begin until construction below finish grade has been approved, underground utilities systems have been inspected, tested and approved, forms removed and the excavation cleaned of trash and debris. Backfill trenches from elevations 1 above utility cover material to subgrade below pavements, base course, and topsoil as required by the plans and other Contract Documents. Where final restoration will be delayed, backfill trench to existing grade to provide a safe, free-draining surface. Ramp around structures left above surface. Moisture condition backfill material as necessary to achieve density required for given use. Do not place material on frozen surfaces or use frozen material. 1. -

1 0 1 0 1 Compact material to minimize settlement and avoid damage to structures, pipes, utility lines and other features. Place backfill simultaneously on both sides of structures. It is the responsibility of the Contractor to provide all necessary compaction equipment and other grading equipment that may be required to obtain the specified density. Vibratory plate or tamping type walk behind compactors will be required whenever backfill is placed adjacent to structures, pipes, utility lines and other features. Flooding or jetting of backfill material for compaction purposes is not allowed. Location Bedding Materials Beneath Footings, Slabs, or Structures Bedding Materials Beneath Utilities Utility Cover Areas Over Bedding Materials to 1 Over Utilities Areas Between Top Soil and Utility Cover Areas Between Utility Cover and Crushed Aggregate Basecourse Beneath Exsting or Proposed Pavement (Roads, Drives, Walks) Areas with of an Existing or Proposed Building or Structure Footing or Slab Turf Areas Required Material Maximum Compacted Lift Thickness Minimum Proctor Compaction Controlled Backfill 1 % Modified 0% Utility Bedding and Cover Utility Bedding and Cover 1 % Modified 0% 1 % Modified 0% Earth Backfill 1 0% Modified 0% Controlled Backfill 1 Controlled Backfill 1 % Modified 0% % Modified 0% Minimum Relative Density (a) Earth Backfill 1 % Modified 0% (a) Minimum relative density as determined by ASTM D--00 for coarse-grained soils with less than % by mass passing the No. 0 sieve. Applicable only when minimum proctor compaction cannot be achieved. Table 1.- FLOWABLE FILL Where a new or existing utility pipeline, structure, box conduit or signal/power conduit requires support, or where existing utility lines are required to be abandoned in place, provide one of the flowable fill materials approved by the engineer and/or construction representative. GRADING Grading shall include areas necessary to establish new grades as required, additional areas disturbed by construction activities, storage, equipment including all trenching, where excess fill is deposited and where cutting is required. New grades are designed to produce desired configuration of site and do not represent a balance between cut and fill. Excavated materials shall be disposed of by contractor at a suitable off-site location. Contractor shall be responsible for securing suitable disposal site(s) and for all off site disposal costs. Place grade stakes at not more than foot intervals both ways. Grades not indicated shall be uniform levels or slopes between point elevations as shown. Adjust all grades as necessary to provide positive drainage away from structures. Contractor may utilize GPS controlled grading equipment. Contractor shall be responsible for Owner s cost to provide design files and for the accuracy of the files used. Grades for earthwork shall not deviate from established elevations, as shown in excess of 1 inch unless otherwise directed by Owner's Project Representative. 1. -

1 Do all cutting, filling, compacting fill, rough grading required to bring entire project to within respective base course elevations or inches below finished topsoil elevations. GRADING AROUND TREES Limit excavation, fill or grading near trees or other vegetation to the extent possible. When tree roots are encountered, cut roots cleanly and squarely. No excavation, trenching or backfilling within the fenced drip-edge of exsiting trees shall occur without authorization from DFD Construction Representative. TEMPORARY BERMS AND STORM SEWERS Contractor shall provide temporary asphalt or concrete berms to direct storm water away from excavations. Contractor shallprovide temporary storm sewer piping to cross trenches and excavations to keep storm water out of the excavations. RESTORATION Restore trenches to proposed grades and surfaces as soon as practicable after backfilling. Remove excess bedding, backfill and spoil material from the site as soon as possible after backfilling is complete, but no later than 1 calendar dates after backfilling is complete. Thoroughly clean all drainage ways, roads, parking lots sidewalks and paved surfaces and remove and dispose all debris and mud. END OF SECTION 1. -