Lot-Sizing in MRP. Lot Sizing in MRP IE 376 PRODUCTION INFORMATION SYSTEMS. Course Notes Lecture #3 Lot sizing in MRP Systems

Similar documents
LOT SIZING IN MRP. Week Gross requirements Scheduled receipts Projected available balance Net Requirements

Lot Sizing for Individual Items with Time-varying Demand

History IE 376 PRODUCTION INFORMATION SYSTEMS. Course Notes Lecture #2.A Material Requirements Planning

Material Requirements Planning (MRP) and ERP 14. Outline

A typical manufacturing plant

Inventory Management 101 Basic Principles SmartOps Corporation. All rights reserved Copyright 2005 TeknOkret Services. All Rights Reserved.

Al-Qadisiya Journal For Engineering Sciences Vol. 4 No. 3 Year 2011

LFL. KEYWORDS: Lot sizing techniques, Material requirements planning.

PERT 03 Manajemen Persediaan (1) Fungsi Inventory Inventory Management Inventory Model dengan Independent Demand. EOQ Model

Evaluating the Impact of the Nature of Lot-sizing Rules On MRP System Performance

Net Requirements Plan. The logic of net requirements. MRP Planning Sheet. Gross Requirements Schedule

Chapter 4. Models for Known Demand

Mechanical Engineering 101

Problem 12.2, HR7E ABC Analysis R. Saltzman

Yuji Yamamoto PPU411. Today s topic. What is MPS and MRP Developing MPS How to make MRP Enterprise Resource Planning Kanban system

MASTER PRODUCTION SCHEDULE (MPS)

Understanding inventory issues

MgtOp 340 Professor Munson Washington State University Sample Exam for Exam 2

Order Quantities - Examples

7/14/2010. Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

Inventory Segmentation and Production Planning for Chemical Manufacturing

Academy session INVENTORY MANAGEMENT

Material Requirements Planning (MRP), chap 15

Supply Chain Inventory Management Chapter 9. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall 09-01

Enterprise Resource Planning

Inventory Management

Chapter 2 Supply Chain Management

1 Introduction Importance and Objectives of Inventory Control Overview and Purpose of the Book Framework...

SLIDES BY. John Loucks. St. Edward s Univ.

مدیریت موجودی Inventory Management

INVENTORY MANAGEMENT

There are three options available for coping with variations in demand:

Inventory Models for Probabilistic Demand: Basic Concepts

Supply Chain Inventory Management. Multi-period Problems. Read: Chap Chap 11.

Stored resource used to satisfy a current or future need: Raw materials, work-in-process, finished goods.

Inventory Management [10] Outline. Inventory Models. Operations Management, 8e. Heizer/Render. ABC Analysis 2 / Prentice Hall, Inc.

International Journal of Mathematical Archive-3(7), 2012, Available online through ISSN

Sven Axsäter. Inventory Control. Third Edition. Springer

Johan Oscar Ong, ST, MT

Mechanical Engineering 101

Modern Logistics & Supply Chain Management

Note 8: Materials Requirements Planning

Measurements That Count (and Some That Don t) Hank IT DEPENDS Barr CFPIM, CSCP, CLTD, CSCM, 6σBB, C.P.M., CLA/CLT Vancouver BC November 1, 2018

MATERIAL REQUIREMENT PLANNING

INVENTORY THEORY INVENTORY PLANNING AND CONTROL SCIENTIFIC INVENTORY MANAGEMENT

Examination. Telephone: Please make your calculations on Graph paper. Max points: 100

Principles of Inventory Management

PRODUCTION SCHEDULING PART-A

Manajemen Persediaan. MRP Lot For Lot. Modul ke: Fakultas FEB. Program Studi Manajemen

A Decision-Making Process for a Single Item EOQ NLP Model with Two Constraints

The Planning Hierarchy

Chapter 6 RESOURCE PLANNING SYSTEMS. Prepared by Mark A. Jacobs, PhD

Chapter 12. Enterprise Resource Planning

Chapter 12. The Material Flow Cycle. The Material Flow Cycle ٠٣/٠٥/١٤٣٠. Inventory System Defined. Inventory Basics. Purposes of Inventory

Lecture 12. Introductory Production Control

This article appeared in a journal published by Elsevier. The attached copy is furnished to the author for internal non-commercial research and

THE USE OF SPREADSHEETS TO TEACH MASTER PRODUCTION SCHEDULE (MPS) AND MATERIALS REQUIREMENTS PLANNING (MRP)

INVENTORY AND PRODUCTION CONTROL

Oman College of Management and Technology

LOT-SIZING WITHIN CAPACITY-CONSTRAINED MANUFACTURING SYSTEMS USING TIME-PHASED PLANNING. S. T. Enns Pattita Suwanruji

Introduction to Principles of Production Management WS 2012/2013 Chapter 14 Aggregate sales and Operations Planning Presented by Dr. Eng.

Operations Management I Fall 2004 Odette School of Business University of Windsor

OPERATIONS RESEARCH. Inventory Theory

ISE480 Sequencing and Scheduling

EFFECTS OF DETERIORATING INVENTORY ON LOT-SIZING: A COMPARATIVE ANALYSIS OF HEURISTICS FOR MRP SYSTEMS

Inventories are important to all types of

A Single Item Non Linear Programming (NLP) Economic Order Quantity Model with Space Constraint

Exam Inventory Management (35V5A8) Part 1: Theory (1 hour)

TRUE/FALSE. 6.1 Inventory is such an expensive asset that it may account for as much as 40 percent of a firm's invested capital.

Operations Management I Fall 2004 Odette School of Business University of Windsor

Inventory Control Model

ISSN: International Journal of Innovative Research in Technology & Science(IJIRTS)

LSU Historical Dissertations and Theses

Operations Research Models and Methods Paul A. Jensen and Jonathan F. Bard. Inventory Level. Figure 4. The inventory pattern eliminating uncertainty.

THE VALUE OF DISCRETE-EVENT SIMULATION IN COMPUTER-AIDED PROCESS OPERATIONS

Introduction. Introduction. Introduction LEARNING OBJECTIVES LEARNING OBJECTIVES

FAQ: Efficiency in the Supply Chain

Planning. Dr. Richard Jerz rjerz.com

PRODUCTION EXECUTION

A Mixed Integer Programming Model Formulation for Solving the Lot-Sizing Problem

Planning. Planning Horizon. Stages of Planning. Dr. Richard Jerz

T REV A

Diploma in Management (890) Operations Management

Part IV Methods for Dependent Demand

Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras

How much money can you add to the bottom line with good inventory management?

SI403 Riset Operasi Suryo Widiantoro, MMSI, M.Com(IS)

Chapter 12 Inventory Management. Inventory Management

Yuji Yamamoto PPU411 VT Today s topic. Inventory measures The ABC system Specific situations in finding economic order quantity

MULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question.

Package SCperf. February 15, 2013

Manufacturing Information System & Review of Operation Management

Management Tool based on MRP and Lot-sizing A case study for comparing different cases

A revised and improved version of the MRP algorithm: Rev MRP Marco D Avino 1,a, Alfredo Bregni 2,b, Massimiliano Maria Schiraldi 3,c

Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras

FUNDAMENTALS OF INVENTORY MANAGEMENT AND CONTROL

Chapter 17. Inventory Control

Operations Management. Inventory management models. Stock of items kept to meet future demand Purpose of inventory management

Virtual Pull Systems. Don Guild, Synchronous Management INTRODUCTION

Time to Shipment MRP Guide DBA Software Inc.

Transcription:

PRODUCTION INFORMATION SYSTEMS Course Notes Lecture #3 Lot sizing in MRP Systems Bilkent University Lot-Sizing in MRP Lot-size is the quantity ordered/produced at one time Large lots are preferred because: Changeovers cost less and use less capacity Annual cost of purchase orders are less Price breaks and transportation breaks can be utilized Small lots are preferred because: Lower inventory carrying cost Reduced risk of obsolescence Shorter cycle time to produce customer order Lot Sizing in MRP Lot-for-lot chase demand The direct translation of net requirements into order quantities The Economic Order Quantity (EOQ) Periodic order quantity method (POQ) Leads to variable order sizes with a fixed and constant time interval between orders Uses EOQ formula to compute time between orders (TBO) Lot-size varies based upon the forecast requirements for the coverage period Doesn t allow for combining orders during periods of light demand

The Economic Order Quantity (EOQ) Method Assumptions 1. Demand rate is known and stable (D -units/time) 2. No shortages allowed 3. Costs include setup/order cost (K -$/per order) and inventory holding cost (h - $/unit/time) 4. Production is instantaneous (the entire batch is produced & delivered simultaneously) 5. Delivery is instantaneous (no lead time) Inventory Build-Up Diagram D: Annual demand rate, Q: Lot size Number of orders per year = D/Q. Time b/w orders (T o)= Q/D Average inventory = Q/2 Inventory Q D = Demand rate Total Average Cost TC(Q) - ignoring the purchasing cost (C*D): Time t D Q TC ( Q) = K + h Q 2 EOQ: Thereis a trade-off between lot size and inventory D Q TC( Q) = K + h Q 2 D h TC'( Q) = K + = 0 Q* 2 Q 2 Q* = 2KD h D Q* K = h = Q* 2 TC( Q*) = 2KDh KDh 2 EOQ Total annual costs h Q/2: Annual holding cost K D /Q:Annual setup cost Q

Criticisms of EOQ Successfully applied to many environments (where the underlying assumptions reasonably hold) E.g. used in setting lot sizes in batch manufacturing environments, MRP type systems, managing input buffers, etc. Simple system illustrating the economic trade-off between setups, inventory, demand. Too simplified? Stable and known demand Independent products (ignores resource constraints) Setup costs are hard to estimate (True cost of a setup depends on the capacity utilization) Example: Lot-Sizing Decision The net requirements for a material from an MRP schedule are: Week 1 2 3 4 5 6 7 8 Net Requirements 1000 0 1300 800 1200 1300 0 800 It costs $400 to change over the machines for this material in the affected work center. It costs $0.40 per unit when one unit of this material must be carried in inventory from one week to the next. Identify the lot-sizing method that results in the least carrying and changeover costs for the 8-week schedule. Example: Lot-Sizing Decision Lot-for-Lot Method Carrying Cost = 0($.40) = $0 Changeover Cost = 6($400) = $2,400 Total = $2,400 Week 1 2 3 4 5 6 7 8 Net Requirements 1000 0 1300 800 1200 1300 0 800 Beginning Inventory 0 0 0 0 0 0 0 0 Production Lots 1000 0 1300 800 1200 1300 0 800 Ending Inventory 0 0 0 0 0 0 0 0

Example: Lot-Sizing Decision Economic Order Quantity (EOQ) Method K = $400.00 D = [(Net Req. for 8 wks)/8 weeks)](50 weeks/year) = (6400/8)(50) = 40,000 h = ($0.40 per week)(50 weeks/year) = $20.00 EOQ= 2KD h = 2(40,000)(400) 20 = 1265 Example: Lot-Sizing Decision Economic Order Quantity (EOQ) Method Carrying Cost = 4855($.40) = $1,942 Changeover Cost = 6($400) = $2,400 Total = $4,342 Week 1 2 3 4 5 6 7 8 Net Requirements 1000 0 1300 800 1200 1300 0 800 Beginning Inventory 0 265 265 230 695 760 725 725 Production Lots 1265 0 1265 1265 1265 1265 0 1265 Ending Inventory 265 265 230 695 760 725 725 1190 Example: Lot-Sizing Decision Periodic Order Quantity (POQ) Method POQ = (# Weeks/year)/(# Orders/year) = 50/(D/EOQ) = 50/(40,000/1,265) = 1.58 or 2 weeks

Example: Lot-Sizing Decision Periodic Order Quantity (POQ) Method Week 1 2 3 4 5 6 7 8 Net Requirements 1000 0 1300 800 1200 1300 0 800 Beginning Inventory 0 0 0 800 0 1300 0 800 Production Lots 1000 0 2100 0 2500 0 800 0 Ending Inventory 0 0 800 0 1300 0 800 0 Carrying Cost = 2900($.40) = $1,160 Changeover Cost = 4($400) = $1,600 Total = $2,760 Lot Sizing in MRP Part period balancing try to make setup/ordering cost equal to holding cost Wagner-Whitin optimal method The Silver-Meal Heuristic Objective is to select T to minimize the total relevant costs per unit time, TRCUT(T), for the duration of the replenishment quantity, where T is constrained to integer values. The Least Unit Cost method Lot Sizing Example t 1 2 3 4 5 6 7 8 9 10 D t 20 50 10 50 50 10 20 40 20 30 WW 80 130 90 LL 20 50 10 50 50 10 20 40 20 30 300 K = 100 h= 1 D = = 30 10 Note: WW is optimal given this objective. Wagner-Whitin: $580 Lot-for-Lot: $1000

Lot Sizing Example (cont.) EOQ: 2KD 2 100 30 Q= = = 77 h 1

First Lot Example Tentative lot size Extra Inv Weeks Held Total Cost Cost/Unit 124 0 0 100 0.81 184 60 1 112.6 0.61 500* 316 2 245.32 0.49 683 183 3 360.61 0.53 Second Lot Tentative lot size Extra Inv Weeks Held Total Cost Cost/Unit 183 0 0 100 0.55 183 0 1 100 0.55 238* 55 2 123.1 0.52 281 43 3 150.19 0.53 Third Lot Example Tentative lot size Extra Inv Weeks Held Total Cost Cost/Unit 43 0 100 2.33 197 154 1 132.34 0.67 197 0 2 132.34 0.67 197* 0 3 132.34 0.67 311 114 4 228.1 0.73 Fourth Lot Tentative lot size Extra Inv Weeks Held Total Cost Cost/Unit 114 0 0 100 0.88 285* 171 1 135.91 0.48

Example Resulting order plan 1 2 3 4 5 6 7 8 9 10 11 12 NR 124 60 316 183 0 55 43 154 0 0 114 171 POR 500 238 197 285 End Inv. 376 316 0 55 55 0 154 0 0 0 171 0 Total Cost= 4*100+1127*.21=636.67 Lot sizing in SAP MRP How to choose the Lot Sizing policy Two sets of criteria for comparing lot sizing techniques: How easy to use in practice, and how efficient in terms of computing time Its performance in terms of the total cost Most commonly used ones Lot-for-lot method Least unit cost (or Silver-Meal heuristic) Periodic order quantity

When to use the Silver-Meal heuristic? EOQ method works well when there is not much variability in demand The variability of the demand pattern should exceed a certain threshold before it make sense to use the Silver-Meal heuristic A useful measure of the variability in a demand pattern is the Variability Coefficient, VC Variance of a demand per period VC= Square of average demand per period N VC= [ N 2 [ D( j)] 1 1 2 D( j)] j= N j= 1 where N is the number of periods demand forecasts readily available Computational studies have shown that If VC<0.2, use EOQ of POQ, take the average of D as your demand If VC>0.2, use the Silver Meal Heuristic (or Least Unit Cost Method) Nervousness Nervousness occurs when even small changes to higher-level MRP records or the master production schedule leads to significant changes in the MRP plans Nervousness is most damaging in MRP systems with many levels in the product structure Some lot-sizing techniques (such as POQ) can amplify the nervousness Nervousness Item A (Leadtime = 2 weeks, Order Interval = 5 weeks) Week 1 2 3 4 5 6 7 8 Gross Requirements 2 24 3 5 1 3 4 50 Scheduled Receipts Planned available balance 28 26 2 13 8 7 4 0 0 Planned order receipts 14 50 Planned order releases 14 50 Component B (Leadtime = 5 weeks, Order Interval = 4 weeks) Week 1 2 3 4 5 6 7 8 Gross Requirements 14 50 Scheduled Receipts 14 Planned available balance 2 2 2 2 2 2 0 0 0 Planned order receipts 48 Planned order releases 48 Note: we are using POQ lot-sizing rule.

Nervousness Example (cont.) Item A (Leadtime = 2 weeks, Order Interval = 5 weeks) Week 1 2 3 4 5 6 7 8 Gross Requirements 2 23 3 5 1 3 4 50 Scheduled Receipts Planned available balance 28 26 3 0 58 57 54 50 0 Planned order receipts 63 Planned order releases 63 Component B (Leadtime = 5 weeks, Order Interval = 4 weeks) Week 1 2 3 4 5 6 7 8 Gross Requirements 63 Scheduled Receipts 14 Planned available balance 2 16-47 Planned order receipts Planned order releases 47* * Past Due Note: Small reduction in requirements caused large change in orders and made schedule infeasible.