Concrete Paving Association of Minnesota CPAM Annual Workshop March 11, Gordy Bruhn- Senior Engineering Specialist

Similar documents
Minnesota Concrete Flatwork Specifications for Local Government Agencies

2. Determine Random Numbers: Determine random numbers for testing locations using the Probing, Coring, Texture and MIT-SCAN T2 Report.

< ~ -n~rtz, Concrete Engineer Office of Materials

(STRUCTURAL CONCRETE).

Concrete Office Updates Spring MEO Meeting Maria Masten April 19, 2012

Gordy Bruhn Metro State Aid 02/06/2018

SECTION RIGID PAVEMENT

Section CONCRETE SIDEWALKS. 1. Payment for concrete sidewalks is on square foot basis.

CONSTRUCTION SPECIFICATION FOR CONCRETE PAVEMENT AND CONCRETE BASE

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA.

A. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT).

A. Submittal Procedures: See Article 13 of the General Conditions.

CHAPTER 10: PAVING. Refer to page 548 of the 2016 Spec book or page 573 of the 2018 Spec book for material specifications under G.

SECTION RIGID PAVEMENT. 1. Portland Cement Concrete (PCC) pavement. 2. Section Aggregate Base Course.

SECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS

B. Reinforcing. Materials shall be as specified in Section 2000 Concrete or as indicated on the plans.

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA.

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2007 EDITION

1. Payment for concrete sidewalks is on square foot basis. a. Limits for measurement for trench excavation as follows:

SECTION CONCRETE PAVING PART 1 - GENERAL 1.1 REFERENCES

SECTION 3200 CONCRETE CURB AND GUTTER

SECTION CONCRETE PAVING

MnROAD Phase 3 Concrete Pavement Construction Update

SECTION CONCRETE PAVING FOR PEDESTRIAN AREAS. A. This Section includes exterior cement concrete pavement for the following:

Design and Construction of Concrete Overlays. By: James K. Cable, P.E. Cable Concrete Consultation

SPECIAL PROVISION Concrete Pavement

Experimental Case Study Demonstrating Advantages of Performance Specifications Karthik Obla 1 Fernando Rodriguez 2 and Soliman Ben Barka 3

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION OF 1990

9 Concrete Pavement Patching

NRMCA is working on. Experimental Case Study Demonstrates Advantages of Performance Specifications

Low 28 Day Compression Strength NOW WHAT?

WYOMING DEPARTMENT OF TRANSPORTATION SUPPLEMENTARY SPECIFICATION FOR PORTLAND CEMENT CONCRETE PAVEMENT

CONSTRUCTION SPECIFICATION FOR CONCRETE ROAD BASE

Arlington County, VA Materials Testing Specification Reference Guide (8/18/2016) MATERIAL AND TEST (REF. - VDOT TEST METHODS MANUAL )

Arlington County, VA Materials Testing Specification Reference Guide (8/18/2016) MATERIAL AND TEST (REF. VDOT TEST METHODS MANUAL )

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENT 1098 PROCEDURE FOR ESTIMATING CONCRETE STRENGTH BY THE MATURITY METHOD.

Stanford University Facilities Design Guidelines SECTION Pervious Concrete Paving

A. Section includes cast-in-place concrete, including reinforcement, concrete materials, mixture design, placement procedures, and finishes.

Evaluation of Concrete Pavement Repair Using Precast Technology in Virginia

Page 1 of 1 ADDENDUM NO. 2 PROJECT: THE SALVATION ARMY, THIFT STORE 601 N. EUCLID AVE., BAY CITY, MI WILLIAM A. KIBBE & ASSOCIATES, INC.

VDOT s New High Performance Concrete Specifications

MnDOT s Experience With High Performance Concrete Bridge Decks & Reinforcement

National Industry Update and Strategic Directions CPAM Annual Workshop March 12, 2015

6 The Paving Operation

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION

Fundamentals of Jointing for Volume Change in Concrete

Workshop Introduction

MICHIGAN CONCRETE ASSOCIATION GUIDE FOR COLD WEATHER CONCRETING

Where WVDOH is at with Mass Concrete

CONSTRUCTION SPECIFICATION FOR FULL DEPTH REPAIR OF CONCRETE PAVEMENT OR CONCRETE BASE

PORTLAND CEMENT CONCRETE OVERLAYS. C. Unbonded Concrete Overlays Over Concrete (with separation layer)

SECTION PORTLAND CEMENT CONCRETE

INDOT/ACPA Technical Committee 2009 Specification Revisions 2009 Test Method Revisions Studies

Concrete Pavement Preservation Partial Depth Repairs

Integrated Pavement Solutions

Construction Specification for Concrete Bus Pad

Minnesota Concrete Flatwork Specifications for Local Government Agencies

Section 603. CONCRETE PAVEMENT RESTORATION

Pre-Construction Conference for Concrete Construction

BOCA Project Suitability, Design and Construction

Division 03 Concrete Section includes various guidelines for general concrete use, curing, forming, reinforcing, finishing and concrete accessories.

High Strength Epoxy tested in accordance to ICC-ES AC308

Michael Nelson, P.E. Concrete Engineer INDOT Office of Materials Management. February 19, 2019

SPECIAL PROVISIONS - SP2014 BOOK Page 1 October 8, 2013

SPECIAL SPECIFICATION 4491 Type CAC Concrete

FOR PROJECTS INITIATED Page -1- AFTER FEBRUARY 1, 2010 REVISION 13 ITEM 360 CONCRETE PAVEMENT

MATERIAL SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS

Performance of Ultra-Thin Whitetopping District 58. Neal West, P.E.

DIVISION II CONSTRUCTION AND MATERIAL SPECIFICATIONS SECTION 2700 STRUCTURES

ITEM Drainage Structure Inlet Protection

PCC Pavement Mix Proportioning and Strength

LTC Implementation of LADOTD Mass Concrete & Maturity Testing Specifications. Presented by. Mark A. Cheek, PE, FACI Vice-President

National Open House Two-Lift Concrete Paving October 15 16, 2008 Salina/Abilene, KS Interstate 70

Long-Life. Life Concrete Pavements. Virginia Concrete Conference March 10, 2006 Richmond, VA. Kurt D. Smith, P.E. Applied Pavement Technology, Inc.

SECTION CONCRETE PAVING

Mix Design & Construction -1-

2. Exterior Concrete Exposed to Freeze/Thaw: 4500 psi minimum. i. Water Cement Ratio < 0.45 for exterior concrete exposed to freeze/thaw

PCC Pavement Rideability

Section 602. CONCRETE PAVEMENT CONSTRUCTION

Public Works Manual. Revised September Concrete & Asphalt

The Latest Technologies For Concrete Pavements

Whitetopping: The Overlay Choice

Section 708. PRESTRESSED CONCRETE

Non-destructive Testing of Installed Soil Nails Using Sonic Echo Test Method

(D) Surface Slope Bituminous patch in front of the truncated domes must not exceed 5% measured perpendicular to the flow line or edge of roadway.

Long Life Concrete Pavements Wisconsin s Experiences. Kevin W. McMullen, P.E. President

B. W/C Ratio: The ratio by weight of water to cementitious materials.

1. Cast-in place structural concrete including footers, foundations, and other non-slab applications. 2. Formwork 3. Reinforcement

50-Year Concrete Pavements

500 Rigid Pavement. 502 Portland Cement Concrete Pavement (Non-QC/QA) Concrete Pavement (**)(**)(**) 501-1

SECTION 12 INDEX CONCRETE CURBS AND GUTTERS

MNDOT PAVEMENT DESIGN MANUAL

21 PAVEMENTS General Administrative Requirements Standards Personnel Certification

Federal Highway Administration Concrete Overlays Program. Sam Tyson, Office of Pavement Technology AASHTO Subcommittee on Construction August 2009

Slab Replacement in Urban Areas

ST. TAMMANY PARISH PATRICIA P. BRISTER PARISH PRESIDENT

ST. TAMMANY PARISH PATRICIA P. BRISTER PARISH PRESIDENT

SECTION CEMENT CONCRETE PAVEMENT PART 1 GENERAL 1.01 RELATED DOCUMENTS

Webinar on: Concrete Overlay Design Details and Joints. Dale S. Harrington P.E. March 5, 2015

The work required for this project includes, but is not limited to, the following items, not listed in order of execution.

Transcription:

Concrete Paving Association of Minnesota CPAM Annual Workshop March 11, 2016 Gordy Bruhn- Senior Engineering Specialist

FDR Removals I-94 Monticello, MN FDR Removals TH 2 Erskine, MN

Revised Reinforcing Steel Sizing from metric back to standard numbering of 1/8 th inch increments. For example: #13 mm bar is now a #4 bar. Type BE Repair

Allow either water or grout to bond the old and new concrete Continue to require grout to seal outside perimeter of the partial depth repair

Increased Drill and Grout Dowel Bar Size, From 1- inch to 1.25-inch Dowel Bar Diam. Full Depth Repair 12 wide (typical) Low Volume Full Depth Repair will Remain 1 Diameter Dowel Bars

1.25 Dowel requires a drill bit diameter of 1.375 (1 3/8 min.)

Increased Minimum Number of Dowel Bars as Roadway Width Wider Required Start Dowels 1foot in from both ends Roadway Lane Width Dowel Bars Required Need to add an additional dowel bar per side for each 1 increase in lane width 12 feet 11 Dowels 13 feet 12 Dowels 14 feet 13 Dowels

Dowel Bars Supplied in Dowel Bar Assemblies will Remain 1-inch Diameter Dowel Bars

Projects with both Paving & CPR will separately tabulate dowel bars. Will include 2301 and 2302 Dowel Bar Pay Items

Transverse No.4 epoxy coated rebar length = Repair Width minus 2 feet

Concrete Mixes previously designed by MnDOT now Contractor/Producer designed New mix numbers for all concrete mixes

Concrete Grade R Pavement Rehab OLD Mix Number 3A32 3B42 NEW Mix Number 3R52 Intended Use CPR - Full depth concrete repairs, concrete base Maximum w/c ratio Maximum Cementitio us Content (lbs/cy) Maximum %SCM (Fly Ash/ Slag/ Ternary) Slump Range Minimu m Compres sive Strength, f c (28-day) 3137 Spec. 0.45 750 30/35/40 2-5 4000 psi 2.D.3

Opened at a minimum of 48 hours of age and strength of 3000 psi HE concrete requires approval of the Engineer prior to incorporation into the work HE concrete requires control cylinders OLD Mix Number NEW Mix Number Table 2461-7 High-Early (HE) Concrete Requirements (Not applicable to Mass Concrete) Concrete Grades Allowed Minimum Time to Opening Maximu m w/c ratio Maximum Cementitio us Content (lbs/yd 3 ) * 3A22HE 3HE32 F 48 hrs 0.42 750 3A32HE 3Y43HE 3Y33HE 3Y46HE 3Y37HE 3A32HE Slump Range 1 3 Minimum Strength to Opening Minimum 28-day Compress ive Strength, f c 3137 Spec. 3000 psi 4500 psi 2.D.1 3HE52 B, F, G 48 hrs 0.42 750 2 5 3000 psi 4500 psi 2.D.1 3YHE52 3RHE52 Y (Repairs Only) R (Repairs Only) 48 hrs 0.42 750 2 5 3000 psi 4000 psi 2.D.2 48 hrs 0.42 750 2 5 3000 psi 4000 psi 2.D.3 * Supplementary Cementitious Materials allowed. Adjust slump in accordance with 2461.3.G.7.a for slipform concrete placement.

Standard Mixes UNCHANGED FROM PAST PRACTICES Store in same condition as structure Allowed to cure HE control cylinders in temperature monitored coolers Both the structure and storage/curing vessel need to be temperature monitored Must maintain temperature within storage / curing vessel at 5ºF of the poured concrete structure

The Contractor may choose to make additional control cylinders (beyond MnDOT s 3) to determine strength at any time other than 28-days. The Contractor may request the use of concrete maturity to determine opening to traffic, removal of forms, or loading.

MnDOT uses as part of acceptance Based on an average of 3 cylinders Cured under controlled conditions MnDOT Defined Curing Periods Moist Curing Environment Provided, By Contract

Initial Cure up to 48 hours Use of ventilation, Use of ice, Use of thermostatically controlled heating or cooling devices, or Use heating methods such as stoves or light bulbs. Other suitable methods are allowed provided the requirements limiting specimen storage temperature and moisture loss requirements are met.

The Contract requires providing moist curing environments of adequate size and number for initial and intermediate curing (first 7 days) of concrete cylinders Part of Field Office Spec (2031.3.C) If no Field Office, still required by Standard Specification (2461)

2016 Spec Book Requirement Walks(2521) and Curb and Gutter (2531) Concrete Contractor or Subcontractor required to have the following: 2 - ACI Certified Flatwork Finisher or Technicians 1 required to be on site at all times

Questions?

Concrete Paving Association of Minnesota CPAM Annual Workshop March 11, 2016 Maria Masten, Concrete Engineer

Concrete Paving Updates Specification 2301

MnDOT has allowed two methods to achieve texture in concrete Astroturf Drag Broom Drag Beyond those requirements, we do not specify how to achieve the required texture.

Broom Drag (Combined Texture and Cure Cart)

Broom Drag (Separate Texture Cart)

In 2015, lateral wandering with certain types of vehicles felt on some roadways Seems attributed to some broom texturing options Met with Industry to discuss options

Beginning November 2015 Astroturf drag only for mainline paving Broom drag allowed for lower speeds, edge of pavements and hand placed concrete Looking for volunteer project to install some different broom drag test sections in 2016

Used for locating dowel baskets and centerline tie bars Original use ~ concrete pavement thickness Five (5) pilot projects using the MIT-SCAN T2 to determine the thickness of the concrete were conducted in 2015.

Evaluated the concrete thickness with the following: (1) Contractor Probing (1 per 1,000 lineal ft) (2) Probe Verification Scan (1 per 4 probes) (3) Quality Acceptance Core (1 per 4,000 lineal ft)

What we learned?? Probe vs. Scan Location Correlation was acceptable but not great Variation was likely caused by the probe measurements which are typically measured to the nearest 1/8 to 1/4 inch depending on the Contractor. Core vs. Scan Location Difference was typically a few hundredths of an inch.

What we are going to do different. Not require the Contractor to probe at specified locations they can probe at their discretion Instead, the Contractor will scan the concrete at the former probe locations (1 per 1,000 lineal ft) Required to core some of the scan locations for verification and a better comparison Reduce overall coring Scan Verification Core (1 per 8 scans) Quality Acceptance Core (1 per 8,000 lineal ft)

The MIT-SCAN T2 is currently being used to determine thickness by several state DOT s and is accepted by the FHWA. MnDOT s goal is for full implementation in 2017 or 2018.

In 2015, MnDOT reviewed approximately 10 projects with unsealed joint test sections installed between 1994 1999 Cored 5 projects In all cases where the seal was breached, the face of concrete cores looked worse than unsealed Well sealed joints looked the best

Seal the following: All Roadways: Speed limit 45 mph or less Whitetopping < 6 thick CPR projects: Speed limit 45 mph or less Bridge Approach Panels MnDOT Standard Plans updated to reflect unsealed joint recommendations

Questions?