Insights into Mining. Project risk and the role of the board. How can a mining company come to grips with capital cost overrun?

Similar documents
KPMG s Major Projects Advisory Project Leadership Series: Stakeholder Management and Communication

Let s talk: governance

IT Governance and the Audit Committee Recognizing the Importance of Reliable and Timely Information

Enterprise Performance Management in the Pharmaceutical Industry. kpmg.co.uk

Future of finance: Finance disrupted. How should the CFO respond to a business environment in turmoil? kpmg.com/us/futurefinance

Internal controls over financial reporting

Short, engaging headline

Internal controls over financial reporting

Finance disrupted. Future of finance in healthcare: As the industry adjusts to continuous disruption, the finance function has an opportunity to lead

Short, engaging headline

Powered by technology, our experts are unlocking the value of your audit. Dynamic Audit

Source-to-pay: Delivering value beyond savings

Strategy Group kpmg.ca

Working better by working together

Managing compliance in a complex world

2017 Internal Controls Survey

Continuously improve your chances for project success

Working better by working together

Corporate governance for banks

Insights into Mining Issue 12: Unlocking the value of D&A

EY Center for Board Matters. Leading practices for audit committees

Leveraging a Dynamic Management Model for Success in Upstream

Working better by working together

Internal controls over financial reporting Uncovering the full picture of control costs

Driving improved supply chain results Adapting to a changing global marketplace. The COO perspective

The Project Confidence Book. Eight best practices for driving project confidence

Beyond Compliance. Leveraging Internal Control to Build a Better Business: A Response to Sarbanes-Oxley Sections 302 and 404

Canadian Insurance Accountants Association

REALOGY HOLDINGS CORP. CHARTER OF THE COMPENSATION COMMITTEE OF THE BOARD OF DIRECTORS. As Amended on January 25, 2017

KPMG International. kpmg.com

David Lucas: Cost Management in a Complex Contracting Environment

Infrastructure and Capital Projects

Driving healthy growth

September 9, 2016 kpmg.ca

Managing Compliance in a Complex World. kpmg.com.cy

IIROC 2015 Financial Administrators Section Conference

CIRCOR International, Inc. Principles of Corporate Governance

Evaluating alternative operating models for government-wide shared services. Taking the back office out of mission-focused agencies

Getting more from your Legal Spend - the emerging trends and best practices

Operational Transaction Services

Audit Committee Charter

The Value- Driven CFO. kpmg.com

GRI s G4 Guidelines: the impact on reporting

Source-to-pay: Delivering value beyond savings

Top 35 Reasons You Need Contact Center Performance Management

Audit Committee Charter for XL Group Ltd

BOARD OF DIRECTORS HUMAN RESOURCES AND COMPENSATION COMMITTEE MANDATE

BOARD OF DIRECTORS HUMAN RESOURCES AND COMPENSATION COMMITTEE MANDATE

Introduction to our brand

EY Center for Board Matters

Giving you clarity on your change programmes

Services to Local Government

Shared Services in the Financial Services Industry: An Operating Model to Reach Strategic Goals

Oversight of external auditors by the audit committee

KPMG s Audit Committee Institute

Audit quality. a director s guide. November This handbook offers guidance for. entities about how to improve audit quality

SOLUTION BRIEF RSA ARCHER AUDIT MANAGEMENT

Your Workday Operating Model The Build Versus Buy Decision

KPMG s financial management practice

Executives Beware: White Paper. Senior Vice President

IFC Corporate Governance Progression Matrix for Listed Companies. (Integrating Environmental, Social, and Governance Issues)

Unlocking the potential of pricing

Room for improvement. The KPMG Survey of Business Reporting. UK Findings. kpmg.com/betterbusinessreporting

Your global work force is your business. Helping you effectively manage your mobility programs across borders is ours.

English Translation (For Information Purposes Only) CODE OF BEST CORPORATE PRACTICES. Introduction

KPMG International. kpmg.com

Japan desk. Supporting your success in the Middle East. August kpmg.com/ae kpmg.com/om

GRI s G4 Guidelines: the impact on reporting

KING III COMPLIANCE ANALYSIS

Your incentive compensation plans have no borders. Why should your compliance processes?

Audit Report. Audit of Contracting and Procurement Activities

The Case for the SIO. A guide to navigate the new challenges of Service Management. kpmg.ca

The Concept: Moving from Data Analysis to Data Analytics

E-Guide to the Enterprise Agreement Program

Effective and pro-active audit committee reporting

STRATEGIC PLAN. Responsible Regulation in a Dynamic Environment

Making a fast start for your capital projects. Power and Utilities Maturity Model and Architecture

GOVERNANCE POLICY. Adopted January 4, 2018

COMPENSATION, NOMINATING AND GOVERNANCE COMMITTEE CHARTER

10 Signs That Your Business is Ready for Managed IT Services. Find out when your business will truly benefit from a Managed Service Provider

Internal Audit and Robotic Process Automation

U.S. Department of Energy Office of Inspector General Office of Audits and Inspections

Audit of Travel and Hospitality

The journey to procurement excellence

2017 KPMG N.V., a Dutch limited liability company, is a member firm of the KPMG network of independent member firms affiliated with KPMG

Deal Advisory / Australia WORKING BETTER BY WORKING TOGETHER. We can help you Partner.

Audit quality a director s guide

Pillars of Success for Your Family Business

Scenario planning and uncertainty

CB&I SUPERVISORY BOARD CORPORATE GOVERNANCE GUIDELINES

Boards and internal audit: Working together to strengthen risk management

PRODUCT BROCHURE COMPLIANCE MANAGER

Seeking value through Internal Audit

How to best position your construction company to a surety in 2013

Global Entity Management Global coverage, local expertise

Digital Labor Analytics

Corporate Governance Policy

APOGEE ENTERPRISES, INC. CORPORATE GOVERNANCE GUIDELINES

Workplace Safety and Insurance Board Workwell Program 2011 Value for Money Audit. Executive Summary March 2012

Accelerating your automation journey through outsourcing

Transcription:

Insights into Mining Issue #4 kpmg.ca/mining Welcome to Insights into Mining, a periodic e-newsletter focused on current topics relevant to the Mining Industry. KPMG s mining practice is committed to the industry and will periodically publish a series of insightful articles authored by leading KPMG Mining professionals and advisors. The articles are designed to inform and stimulate debate amongst those involved in the industry. If you have any questions, please contact your local KPMG representative or click here for a list of KPMG s Mining leaders across the country. Augusto R. Patmore Partner, Advisory Global Infrastructure & Mining Project risk and the role of the board How can a mining company come to grips with capital cost overrun? For the mining industry, controlling costs on capital projects has become a very challenging issue. In fact, it ranks among the top three most challenging issues for mining executives, according to a KPMG survey conducted in September 2014. Mining projects are increasingly complex to plan and execute, partly because they are built in remote areas of the world that must often be supplied with costly infrastructure for transportation and energy. In the coming years, nearly $160 billion in mining projects has been proposed for Canada alone. 1 The average cost of a greenfield project today can run from hundreds of millions of dollars into the billions. Looking at a sample of seventeen recent greenfield projects, the average cost overrun was ninety-five percent above original estimate. Canadian mining companies have also written down assets by US$17 billion since the beginning of 2012. 2 1 Source: Mining Association of Canada, Facts and Figures, 2014 2 Source: Various company disclosures, Bloomberg, as of July 1, 2013

2 Insights into Mining Projects then and now Since the early 2000s and through other periods of higher commodity prices, the most important consideration for project development was fast-track delivery. Mines needed to go into production as quickly as possible, because commodity sale revenues would soon outweigh execution cost overruns. The need for fast delivery arguably made the on time side of a project more important than the on budget side. It pulled attention away from cost estimate accuracy, and gave mining executives incentive to start projects early and drive to completion. Fast forward to 2015, and the picture looks very different. In a commodity price environment where mines struggle to be profitable, unexplained capital cost overruns are galling to institutional and private investors. Now these investors are asking tough questions, and expecting the board of directors to be accountable. In turn, the board is looking inside the organization for solid information that will satisfy investors, and help preserve the company s equity. Mining s design/build function Project design/build is seldom a core function within today s mining organizations. The industry has often relied on engineering firms to manage the design and build of its capital projects as an alternative to developing in-house project management capability. This leaves project development at mining companies to become a subset of the operations function, staffed primarily by operations people. At many companies, a Senior VP leads the projects area and reports to the Chief Operating Officer. The projects team on the ground may or may not have in-house access to the skill sets of civil engineers with design/build or construction management experience. Project reports for the board would follow normal upward channels, from the ranks of the regional projects area to the Senior VP to the COO to the CEO and the board. The operations (mining) function may have also engaged the services of an engineering, procurement and construction management (EPCM) firm to assist with managing this wide range of project-related needs. A certain amount of reporting would flow from this relationship, depending on the nature of the arrangement. In our opinion, however, it is not uncommon for these project reports to be heavier on technical details and lighter on commercial and strategic considerations such as strategic planning, financial controls, risk management, and construction cost variance analysis.

3 Insights into Mining Is status quo adequate for the board? At a time when capital cost overruns are among the worst problems for mining companies, traditional reporting systems to the board for projects are not meeting contemporary needs. First of all, reports of serious cost overruns must be able to reach the board quickly; within hours or days instead of the weeks or months it can take to pass a report up through the organizational hierarchy, from site to regional offices, then on to corporate head office. Second, those reports must reflect the plain unvarnished truth, even if the news is very bad. In most corporate organizations of any kind, bad news with a high price tag can attract the wrong kind of attention. When reports hit several desks on their way to the board, the message has an opportunity to be repositioned for any number of reasons. Third, the board must receive project reporting in a concise and direct form that directors can easily digest and understand. This is true of reports about cost overruns through execution, but it is also true of reports generated through the stage-gate planning process. Another problem related to those above is the expectations mining companies often have for EPCM providers. These excellent firms have strengths and weaknesses that need to be understood as part of the risk assessment for the overall project. Without a doubt, the main strengths of EPCM firms are design engineering and feasibility studies, which make them particularly effective partners for the upfront planning stage of a project. But at the execution stage, EPCM firms have not traditionally accepted transfer of construction risk. The mine owner retains all risk for construction costs usually the largest spend (and risk) in a greenfield project. Furthermore, some EPCM contracts do not contain enough disincentives to help ensure that construction cost management remains the priority. Project reports to the board from this source must be viewed accordingly.

4 Insights into Mining 1 What needs to change? What needs to change at mining companies to improve their approach to project risk at the board level; and specifically, to reduce capital cost overruns? Develop in-house construction specialization that can be applied through the upfront planning stage to increase the accuracy of cost estimates. Fundamentally, mining companies need to recognize mine building as a core activity of the organization. Owners can play a much more visible role in the management of construction contractors, while leaving EPCM firms to focus on engineering, design and procurement of long lead items. Companies should use their in-house construction knowledge to help drive effective upfront project planning and definition, helping to reduce the risk and cost of changes at the execution stage. Other risk-reducing tasks that are well suited to an in-house approach include producing and validating cost estimates, performing valueengineering workshops, challenging scope assumptions, and defining the contracting strategy. 2 Companies also need to build teams of execution-side project experts that mainly include engineers with construction experience, but also include other professionals with construction experience such as accountants and contract lawyers. Such a team can include a blend of employees and professional advisors, because the mix of relevant delivery skill sets is paramount. Create a capital projects sub-committee of the board to oversee and manage capital project assurance reviews. To keep the board right up to date on projects matters, mining companies should consider creating a capital projects sub-committee of the board in charge of independent project assurance programs on major capital projects. On a regular basis, this sub-committee would meet with management s projects team together with the independent project management advisors mentioned above to review progress, cost performance, and risks. Bad news would be delivered upfront, and solutions proposed that would give the board actionable information to mitigate risk proactively. The board will potentially benefit from an independent assessment of the business case presented by the project management team before advancing each project to its next stage of development. Once projects have moved through to execution stage, independent monitoring of cost and schedule performance will help give added assurance to the Board about project performance and risk management.

5 Insights into Mining 3 Develop dashboard reporting for the board focused on 5 4 detailed cost performance metrics. Miners can work with professional advisors to develop executive dashboard reports for the board that are informative, easily understood by the broader team, and more consistent through time for comparison purposes. When a reporting format focuses on the root causes and locations of cost variances, it can lead to more efficient discussions as well as proactive executive and project team decision-making. Consider alternative delivery models such as engaging individual firms for E, P and CM support If an EPCM provider is not satisfying the company on the execution side, there is an option to hire different companies that exhibit core competencies in each area. Although it may first appear that fees and administrative requirements may be higher, this is not necessarily the case. The quality of oversight and reporting could be higher, and cost reductions may be easier to identify and achieve with the right team composition. Build more effective risk transfer mechanisms into EPCM and construction contracts. Striking the right balance between incentives and disincentives in EPCM and construction contracts will help promote a collaborative owner/contractor relationship, and strengthen the contractor s focus on cost management. Many large infrastructure developers are moving away from the reimbursable time and materials contract strategy and moving toward a lump sum strategy for certain elements of the scope.

6 Insights into Mining Conclusions As mining companies continue to seek to create long-term value for shareholders, capital cost overruns have been working in the opposite direction draining value from companies and driving away investors. Promising projects are being suspended, closed or even divested because of past failures. In a business environment of low commodity prices and high investor scrutiny, capital projects can no longer afford to fail. Companies can get a handle on capital costs from the board level on down by changing their mine-building mindset. This does not necessarily mean foregoing relationships with EPCM firms, but it does mean evaluating alternative delivery models where: More upfront planning investment of time and money is accommodated before projects are approved More risk is transferred to contractors as a result of increased planning efforts and improved scope definition More direct involvement is reserved for mine owners when managing the construction stage. This formula can be partly achieved by enhancing in-house engineering/construction expertise (at both management and board levels) as well as empowering the project assurance team to carry out independent project oversight from early planning right through execution. When the right team and reporting mechanisms are in place, the board will gain the confidence to delegate detailed oversight of development projects. A capital projects subcommittee of the board should be asking some key questions: 1. Is our projects delivery team led by design/build professionals? Do we have a strong design/build management professional leading delivery on the ground? 2. Do we understand how much upfront investment is required through the definition stage of the stage-gate process? Have we allowed sufficient time for the cost estimate to evolve and gain maturity through the stage gate process? 3. Have the key elements of our business case (cost estimate, risk, contingency, management reserves) been vetted by external experts (independent project advisors) prior to board approval? 4. Does our monthly executive/board reporting satisfy our needs? 5. Are we able to effectively ensure that executive management decisions are quickly deployed at site level? Are we able to delegate project management and budget accountability to project directors on the ground?

Contact us Augusto R. Patmore Partner, Advisory Global Infrastructure & Mining T: 416-777-3277 E: apatmore@kpmg.ca kpmg.ca/mining The information contained herein is of a general nature and is not intended to address the circumstances of any particular individual or entity. Although we endeavor to provide accurate and timely information, there can be no guarantee that such information is accurate as of the date it is received or that it will continue to be accurate in the future. No one should act on such information without appropriate professional advice after a thorough examination of the particular situation. firms affiliated with KPMG International Cooperative ( KPMG International ), a Swiss entity. All rights reserved. 9819 The KPMG name, logo and cutting through complexity are registered trademarks or trademarks of KPMG International.