Piling & Contaminated Land. Dr Derek Egan Technical Director Keller Ltd

Similar documents
Ground Improvement Techniques

Lesson 2 Substructure. Dr S.Sreenath BSc Engg, MSc Engg, MSc (ICM), MBA, PhD

11 HYDROLOGY, HYDROGEOLOGY AND DRAINAGE

Advantages / Disadvantages of Piling Methods. Continuous Flight Auger (CFA)

Ground Improvement Piling Piled Retaining Walls Enlarged Head Piles Innovations.

Unit title: Construction Technology: Substructure (SCQF level 7)

BRE Seminar Ground treatment - Getting the best from difficult sites A Reality Check What Does the Designer Need to Know?

Advantages / Disadvantages of Piling Methods. Continuous Flight Auger (CFA)

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5. Turbine Foundation Construction Method Statement

An Introduction to Keller in the UK COLCRETE EURODRILL GETEC PHI GROUP. Piling and Ground Improvement. Grouting, Soil Nails and Anchors

Comparison of Liquefaction Mitigation Options: A Christchurch Case Study

Foundation Works for a Sewage Treatment Plant using Ground Improvement Methods in Malaysia Y.W. Yee, C.G. Chua and

Geotechnical Engineering

Piling Risk Assessment Towcester Moat Lane Re-Development Community Building

APPENDIX F GEOTECHNICAL INVESTIGATION UPDATE CITY OF SANTA CRUZ D RAFT EIR L A B AHIA H OTEL JANUARY 2014

1. Introduction Selection of Pile Type Soil Report / Boreholes Obstructions Design and Installation of Piling Mat 3

Sabah Shawkat Cabinet of Structural Engineering 2017

Contents. Glossary 9. Foreword 10

Desktop guide to aggregate pier ground improvement

Golder Associates Innovative Applications (GAIA) Inc.

Can sustainability win you more work? 10th April 2013

Civil Engineering Construction I (CBE5031)

* The use of these areas can vary from car park space, where little waterproofing is required through to store rooms or plant rooms where a high

Design and Construction of Drilled Full Displacement Piles using the Penetration Resistance Method

Compaction and Jet Grouting

A Case Study: Foundation Design in Liquefiable Site

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

RIGID INCLUSIONS. Rigid Inclusions offer an economical approach for building on sites underlain by soft soil.

PIANC UK Seminar Design Developments and Specification for Steel. Duncan Nicholson Arup Fellow 9/3/17 ICE London

Chapter 1. Introduction to Engineering Ground Modification. The Need for Engineered Ground Improvement

LOAD CAPACITY OF AUGER DISPLACEMENT PILES

SITE INVESTIGATION. Foundation Engineering

Assalamualaikum & Good Morning (May All Of You Gain A Better Understanding)

Basement Construction in Ho Chi Minh Pitfalls and Collected Stories

PILE CAPACITY REDUCTION OF JACK-IN PILES WITH EMPTY PREBORED HOLE AT META-SEDIMENTARY FORMATION IN PENINSULAR MALAYSIA

Construction Technology B (CON4313)

Steel screw settlement reduction piles for a raft foundation on soft soil

Combined Pile Foundation System for a Residential Complex

FURTHER TECHNICAL INFORMATION IN RELATION TO THE OPERATIONS OF OUR GROUP

VERTICAL BARRIERS SLURRY TRENCH BARRIERS: excavation equipment. prof. E. Fratalocchi Environmental Geotechnics Waste and polluted sites containment

SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL

On-site determination of pile capacity Distribution of pile load between the shaft and tip, and Detection of possible pile.

The use of micropiles as a form of underpinning of existing commercial buildings development of IKEA hall in Gdańsk

Basement & Waterproofing

1 Introduction. 2 Site Description. Auckland Transport Private Bag Auckland 1142 New Zealand. 2 March Attention: Sunil Kariyawasam

A brilliantly simple Foundation Method

Ground Improvement. Martin G. Taube, P.E., P.G. February 4, 2003

CONTINUOUS FLIGHT AUGER (CFA) PILES QC/QA PROCEDURES. Preferred QC/QA Procedures

Thermal Pile Installation

An Introduction to. By Michael L. Schumaker, P.E. An Introduction to Shaner Industries Metal Foundation System

INTRODUCTION TO INNOVATIVE PILING SOLUTIONS

Analysis of Design When You Should Consider Pipe Ram Over Traditional Auger/Jack & Bore

Geotechnical & Materials Testing Specialists

Site Investigation MUHAMMAD AZRIL HEZMI

The Technical and Contractual Matters of Bored Piling Works. By Wallace Yeung Vibro (H.K.) Ltd.

Ground Improvement Techniques: Dynamic Compaction Martin Larisch & Tim Pervan

Piling and Archaeology

Wet Speed-Mixing WSM - Soil Mixing Procedure in Twinmix Design

In-ground cellular structure as a foundation system

ADVANCED GEOSOLUTIONS INC AGI FOUNDATION CONTRACTORS, ULC (Canada Subsidiary) The premier design-build ground improvement contractor TM

Ground Modification Applications for Bio-Fuel Plants Raymond J. Franz, P.E. Roselle, IL

Exploration, Sampling, and In Situ Soil Measurements. Dr. Omar Al-Hattamleh

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

Grouting Bilfinger Spezialtiefbau GmbH

Development in Geotechnical Engineering. Concrete for wet processed bored piles

Design of Temporary Excavation and Lateral Support System for the DSD Sheung Wan Stormwater Pumping Station

DBM Contractors, Inc. Donald B. Murphy Contractors, Inc. 60 Years of Innovation and Customer Satisfaction

#47 CASE STUDY INSTALLATION OF A SOIL-BENTONITE CUTOFF WALL THROUGH AN ABANDONED COAL MINE (GROVE CITY, PA)

Challenges of Offshore Geotechnical Engineering

Modular Course on Foundations and Earth retaining Structures for Building and Infrastructure Projects 9th March 2000

NPTEL. e-book on Concepts and Techniques in Geotechnical and Foundation Engineering - Web course. Civil Engineering.

SECTION XXXXX STONE COLUMNS PART 1 - GENERAL

Possible solution to past CM exam question. Question 2 July New city centre office block. by Rajavel Inbarajan

Ductile Iron Systems trm.at

Concrete in aggressive ground

Geo-E2010 Advanced Soil Mechanics L Wojciech Sołowski. 19 March 2017

Earth Retaining System

SEMINAR. Introduction to Continuous Flight Auger (CFA) piling Thursday 21/8/2013. Facilitator: Martin Larisch

Ground Improvement Techniques

SECANT PILE. Introduction:

This method significantly reduces the over-consumption of concrete and eliminates any risk of over-augering.

Earth Mechanics, Inc. Geotechnical & Earthquake Engineering

SCG INTERNATIONAL TRINIDAD AND TOBAGO LIMITED COUVA CHILDREN S HOSPITAL

A Comparison of Static Axial Capacity Between Drilled and Driven Piles. Outline

Modular Course on Foundations and Earth retaining Structures for Building and Infrastructure Projects 9th March 2000

Performance of high capacity jack-in pile for high-rise building with preboring in weathered sedimentary rock formation

Expert Solution in BUILD ON US GEOTECHNICAL AND CIVIL ENGINEERING CONTRACTORS

Geotechnical Investigation Reports and Foundation Recommendations -Present status in India -Examples

UNDERPINNING A CRANE FOUNDATION

Aveng Ground Engineering Profile

Foundation improvement system. system overview

A.Zh.Zhussupbekov Department of Civil Engineering and Engineering Mechanics, Columbia University, New York, USA

A. Section includes temporary excavation support and protection systems.

Earth Retaining Walls CIVL455 CHAPTER I: INTRODUCTION

JERSEY FUTURE HOSPITAL CO004 SITE OPTION REPORT. APPENDIX 6 Technical Site Appraisal TN-STR TECHNICAL NOTE STRUCTURAL CONSIDERATIONS

Partial Factors of Safety

penetrometer test (CPT) soundings were done to supplement the SPT data. Construction recommendations were made for most of the new buildings.

Construction of Access Shafts for Tunnels and Deep Pipelines in Urban New Zealand

Construction Technology B (CON4313)

Transcription:

Piling & Contaminated Land Dr Derek Egan Technical Director Keller Ltd

FEDERATION OF PILING SPECIALISTS The FPS began in 1963 with 5 companies. Now we have 18 members accounting for circa 500M of specialist geotechnical contracting per annum. Membership by rigorous registration. Three sub committees Health, Safety & Training Plant Commercial Technical

The FPS... Promoting Best Practice in safety, innovation, technical excellence, value engineering & quality management; Independently audited membership. Past initiatives include:- safety of temporary working platforms, working adjacent to railway lines, ICE Piling & Embedded Retaining Wall Specification, publication of a range of guidance notes relevant to piling www.fps.org.uk Aims

What governs the choice of foundation solution? Structure Size/weight Form Geology & Groundwater Performance Load-settlement Durability Environment Noise Vibration Economy Time, Cost Sustainability Logistics Access Weight Limits

Considerations when encountering contaminated land Transport Pushing contaminated Soil down/sideways Durability Ground & Ground water Health Chemical Particulate Flow Paths Temporary Permanent

Considerations when encountering contaminated land

Piling Replacement Continuous Flight Auger (CFA) Rotary Bored Displacement Driven PC Piles Driven Cast In-situ Steel Tubes Sheet piles High capacity Low noise & vib. In-situ concrete Creates spoil Moderate capacity No spoil Noise & vib. (but less so these days)

Cast In-situ Displacement Piling Driven cast in-situ piling Olympic Stadium Old car plant Daganham

Cast In-situ Displacement Piling Vibro concrete columns Olympic Stadium

Other Cast Insitu Piling Continuous Flight Auger Rotary Displacement

Pre-formed Displacement Piles

Piling Ground Treatment Replacement Continuous Flight Auger (CFA) Rotary Bored Displacement Driven PC Piles Driven Cast In-situ Steel Tubes Sheet piles Soil Mixing In-situ/ex-situ Dynamic Compaction Vibro Stone Columns Vibro Compaction High capacity Low noise & vib. In-situ concrete Creates spoil Cast in-situ Moderate capacity No spoil Noise & vib. (but less so these days) Pre-formed Lower capacity No spoil Potential for pathways

Ground Improvement Techniques include vibro stone columns, vibro compaction, dynamic compaction, deep soil mixing (wet & dry), grouting (jet grouting, compaction grouting, in-fill grouting etc)

Process Decide if site/groundwater is contaminated EC7 Desk study & GI No No more action required Yes Consider potential adverse impacts using Source-Pathway-Receptor approach Mitigate risk Consider 6 Scenarios (Westcott et al) Consider the need/do a Foundation Works Risk Assessment Report

The 6 Scenarios

The Six Scenarios Pollution Scenario 1 Creation of preferential Pathways through an aquitard to allow potential contamination of an aquifer. Driven pile, VCC, Stone Column Driven piles no open void - cast in-situ enhanced sealing with the ground CFA OK but opportunity for temporary pathway VSC open pores unless special measures taken Source Contaminated Layer Pathway Receptor Contamination of Aquifer Aquitard Aquifer

Use of QC/QA to ensure installation is correctly recorded

Pollution Scenario 2 Creation of preferential Pathways through a low permeability surface layer, allowing migration of landfill gas, soil gas or contaminant vapours to the surface. Pile, VCC, Stone Column Receptor Driven piles no open void - cast in-situ enhanced sealing with the ground CFA OK but opportunity for temporary pathway Gas VSC open pores unless special measures taken Pathway Low Permeability Cap Source Gassing material/soil Founding stratum

Innovation - ESCs The dilemma:- VSCs need to be flexible to interact with the ground upon loading VSCs may need sealing to prevent a pathway Cementitious grout/concrete does not fulfil the flexibility criterion Source Pathway Receptor Contamination of Aquifer Contaminated Layer Aquitard Aquifer

Settlement (mm Innovation - ESCs The solution - development of a flexible non-setting grout:- low permeability (k = 10-8 m/s) does not set leading to hard spot allows standard column construction Dartford, Powdermill Road Strip Footing qw=125kpa Bearing Pressure (kpa) 0 20 40 60 80 100 120 140 160 180 200 0.0 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0

Pollution Scenario 3 Direct contact of site workers and others with contaminated soil arisings that have been brought to the surface. Replacement Pile Receptor (Poisoned worker) Contaminated Spoil Rotating replacement piles CFA, rotary bored (lesser extend rotary displacement) Displacement systems no spoil Pathway Isolation Layer/Cap Source Waste/contaminated material Founding stratum

Pollution Scenario 4 Direct contact with contaminated soil or leachate causing degradation of materials - durability Mainly concerns concrete Use BRE SD1 (2005) Pile, VCC, Stone Column Source Pathway Receptor Attack Attack Contaminated/aggressive Soil Founding stratum

Pollution Scenario 5 The pushing of solid contaminants down into an aquifer during pile driving. Pile, VCC, Stone Column Effects displacement piles only - but not that critical. Contaminated Layer Contaminated Soil Aquitard Aquifer

Solid piles drag down max. 3d pointed shoes help but not really necessary? H piles trapped soil risk Tubular piles soil plugging

Pollution Scenario 6 Contamination of groundwater and subsequently, surface waters by wet concrete, cement paste or grout Pile/VCC Natural soil + very open structure & flowing water Services/drainage/voids greater risk? Only affects cast in-situ Groundwater contamination Fractured/permeable soil

Foundation Works Risk Assessment Report To be undertaken by the scheme designer. 1. Geology/SI 2. Selection of preferred piling method considering geology, structural, noise, vibration etc. 3. Adverse impacts due to preferred method 4. Site specific assessment of magnitude & consequence of risk 5. Changes/special measures required 6. QA/QC measures 7. Final selected method considering geotechnical, financial, environmental considerations.

A Note on Ground Investigation Poor quality geotechnical investigations still rife. FPS Survey 2006 ~20% of all contracts in the UK in a 3 month period (of all sizes) 30% of projects had Poor SI 55% thought between geotechnical & environmental elements wrong NHBC Survey 2010 60% of respondents insufficient SI undertaken for low rise developments; most strongly felt by foundation designers compared to house builders and developers (but are they at the front line of taking the risk?).

Some common failings On 16% of projects no BH location plan On 73% of projects BHs not levelled (83% not coordinated) In 59% of cases inadequate topographical information Boreholes too shallow (at least 5m below pile toe, may need to be more for large rafts)?; Insufficient insitu and/or laboratory geotechnical testing (e.g. SPTs every 1m to 2m).

Summary Contaminated land:- presents an added, but surmountable, additional complexity; the 6 scenario approach provides a systematic assessment framework; knowledge of different piling & ground improvement options informs the choice; mitigation don t be afraid to demand high levels of QA/QC from contractors.

Thank you for listening.