Grizzly Oil Sands ULC

Similar documents
Pengrowth Energy Corporation

Nexen Inc. OPTI Canada Inc.

Harvest Operations Corp.

Decision MEG Energy Corp. Amend Christina Lake Industrial System Designation. December 15, 2011

Seven Generations Energy Ltd.

Connacher Oil and Gas Limited

Suncor Energy Inc. Errata to Decision Firebag Substations and Power Plant Expansion and Industrial System Designation Amendment

Nexen Inc. and CNOOC Canada Inc.

The City of Red Deer

Canadian Natural Resources Limited

Decision Cenovus FCCL Ltd.

Decision B. St. Pierre kW Photovoltaic Micro-Generation System. May 15, 2013

NOVA Chemicals Corporation

Pembina NGL Corporation

Decision GTE Solar Inc. Brooks Solar Power Plant. January 31, 2013

NaturEner Wild Rose 1 Energy Inc.

Signalta Resources Limited

Grande Prairie Generation, Inc.

Aquatera Utilities Inc.

ENMAX Power Corporation

SunEEarth Alberta Solar Development Inc.

Burdett Solar GP Corp.

Decision D The City of Calgary. Bonnybrook Cogeneration Expansion Project. May 17, 2018

Pteragen Canada Inc.

Alberta Electric System Operator Yeo 2015S Substation Needs Identification Document

EPCOR Distribution & Transmission Inc.

C&B Alberta Solar Development ULC

Alberta Electric System Operator Needs Identification Document Application

EDF EN Canada Development Inc.

Decision D ATCO Electric Ltd. Swan Hills F.P.L. 744S Substation Decommission and Salvage. November 8, 2018

C&B Alberta Solar Development ULC

Alberta Power (2000) Ltd.

C&B Alberta Solar Development ULC

Decision FortisAlberta Inc. Micro-Generation Determination. December 16, 2008

TransAlta Corporation

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments

Oldman 2 Wind Farm Limited

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments

Meadow Creek West. Project overview:

Greengate Power Corporation

Oldman 2 Wind Farm Limited

AltaGas Utilities Inc.

Solar Krafte Utilities Inc.

HYDRO AND ELECTRIC ENERGY REGULATION

C&B Alberta Solar Development ULC

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments

Section 1 - Introduction

Decision Syncrude Canada Ltd. Mildred Lake Power Plant. July 17, 2014

AltaGas Utilities Inc.

RULE 302 Permit Fee Schedules - Adopted 04/18/72; Amended 06/20/78; 12/15/80; 06/29/81; 04/25/83; 06/29/87; 03/01/88; 06/01/93; 03/13/08, 11/13/08.

Renewable Energy Services Ltd.

Notice of Technical Meeting

ALBERTA ENVIRONMENT ENVIRONMENTAL PROTECTION AND ENHANCEMENT ACT APPLICATIONS NO AND ENVIRONMENTAL IMPACT ASSESSMENT

Alberta Electric System Operator

JAPAN CANADA OIL SANDS HANGINGSTONE SAGD PROJECT

Telephone Lake project

SUNDANCE 7 January 2014

October 2, 2015 EAB File #: Transaction #:

Understanding Bill 50

ATCO HEARTLAND GENERATING STATION PHASE 2

Jackfish 2 Project. Public Disclosure Document. August 2005

OPEN HOUSE PROJECT OVERVIEW OPEN HOUSE NOVEMBER 16, :00-8:00 PM FALL 2017

Alberta Electric System Operator

ATCO Gas and Pipelines Ltd.

Cold Lake expansion project

LARICINA ENERGY LTD. STONY MOUNTAIN PIPELINE PROJECT DESCRIPTION DOCUMENT FEBRUARY 2012

GROUSE GROUSE IN SITU OIL SANDS PROJECT. Proposed Development Plan. Plain Language Project Summary

Alberta Electric System Operator AltaLink Management Ltd. Alberta-Pacific Forest Industries Inc.

Project Location. The CEC is a 320 MW combined-cycle power generation

[] Brochure, picture, drawing, etc., of the use to be conducted (if applicable).

Grand Valley Wind Farms Phase 3 Wind Project Wind Turbine Specification Report

ATCO Gas and Pipelines Ltd. (South)

Decision D Alberta Ltd. (BluEarth) Bull Creek Wind Power Project Noise Complaints

Welcome to our Open House!

Section 1 Project Introduction

October 30, 2012 Our File:

Form B GENERATION INTERCONNECTION APPLICATION (Non-Inverter Based Generation and Inverter Based Generation > 25 kw)

Cogeneration & Carbon Management Key Issues in the Design of Carbon Management Policies and Regulations in Alberta

Canadian Natural Resources Limited

SUNCOR ENERGY CEDAR POINT WIND POWER PROJECT DESIGN AND OPERATIONS REPORT. Attachment D. Property Line Setback Assessment

THE LEGISLATIVE FRAMEWORK FOR MUNICIPAL PLANNING, SUBDIVISION, AND DEVELOPMENT CONTROL

MICRO-GENERATION NOTICE SUBMISSION GUIDELINE

ATCO Electric Ltd. ATCO Gas (a division of ATCO Gas and Pipelines Ltd.) ENMAX Power Corp. EPCOR Distribution and Transmission Inc. FortisAlberta Inc.

ADMINISTRATION RECOMMENDATION(S) 2017 May 04. That Calgary Planning Commission recommends APPROVAL of the proposed Land Use Amendment.

The current note, approved by the County Commission on August 11, 2015 (INSTR # ) reads as follows:

Suspension Requirements for Wells

The Standards referred to shall be the most recent edition.

Capital Power Generation Services Inc.

May 8, 2017 EASB File #: Transaction #:

ALBERTA QUEEN ELIZABETH II HIGHWAY (HWY 2) STONEY TRAIL. To Edmonton. Calgary International Airport EDMONTON CALGARY. To the U.S.

Ellerslie Substation Expansion

Garvagh Glebe Wind Energy Project County Leitrim

Your guide to the. SOUTHERN ALBERTA Transmission Reinforcement

Order. -AI1ta. Energy Regulator. MADE at the City of Fort McMurray, in the Province of Alberta, on

GARKANE ENERGY COOPERATIVE SMALL GENERATOR QUALIFIED FACILITY INTERCONNECTION APPLICATION

Decision (Errata) Alberta Ltd. Errata to Decision Bull Creek Wind Project. March 10, 2014

nine (9) pad-mounted tranformers each approximately 75 kilovolt-ampere (kva), designated as sound sources ID: BC-63 to BC-71;

State Environmental Quality Review NEGATIVE DECLARATION Notice of Determination of Non-Significance

EPCOR Distribution & Transmission Inc.

Tullynahaw Wind Energy Project County Roscommon ENVIRONMENTAL IMPACT STATEMENT

Transcription:

Decision 2013-124 Algar Lake Project Distribution System Exemption March 28, 2013

The Alberta Utilities Commission Decision 2013-124: Algar Lake Project Distribution System Exemption Application No. 1609370 Proceeding ID No. 2484 March 28, 2013 Published by The Alberta Utilities Commission Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary, Alberta T2P 3L8 Telephone: 403-592-8845 Fax: 403-592-4406 Website: www.auc.ab.ca

The Alberta Utilities Commission Calgary, Alberta Decision 2013-124 Application No. 1609370 Algar Lake Project Distribution System Exemption Proceeding ID No. 2484 1 Application 1. (GOS), by Application No. 1609370, registered on March 8, 2013, filed a letter of enquiry with the Alberta Utilities Commission (AUC or the Commission) under Section 11 of the Hydro and Electric Energy Regulation. GOS requested that the previously granted exemption, pursuant to Section 24 the Hydro And Electric Energy Act, for its Algar Lake Steam Assisted Gravity Drainage (SAGD) Project site in the Fort McMurray area, be extended in scope to include the following: Extension and construction of a 4,160-volt (V) cable along the north perimeter of the main production facility (MPF). Relocation of a 4,160/600-V, 500-kilovolt-ampere (kva) transformer to the northeast corner of the MPF. 2 Background 2. GOS is in the process of developing the Algar Lake SAGD Project (the Algar project), located approximately 40 kilometres southwest of Fort McMurray. GOS has approval, by Approval No. U2012-415, 1 to construct and operate a 15-megawatt power cogeneration facility. The power will be used solely for the Algar project and an exemption was granted to GOS, in Decision 2012-228, 2 to operate the associated 600-V distribution lines that will serve the electrical requirements both on-site and at four nearby well pads. 3. The decision specified the following details: The proposed power plant and the nearby off-site load are located on lands which GOS has been granted surface rights, under Miscellaneous Lease, thus showing tenancy within the lease area where distribution facilities will be located. 3 There are no dwellings within 2,500 metres of the proposed development. 4 The noise impact assessment was completed for the entire Algar project which included the proposed power plant and two backup diesel generators. Results indicated that the 1 2 3 4 Power Plant Approval No. U2012-415, Application No. 1608422, Proceeding ID No. 1870, August 31, 2012. Decision 2012-228: Algar Lake 15-MW Cogeneration Power Plant, Application No. 1608422, Proceeding ID No. 1870, August 31, 2012. Decision 2012-228, paragraphs 10 and 26. Decision 2012-228, paragraph 11. AUC Decision 2013-124 (March 28, 2013) 1

Algar Lake Project Distribution System Exemption projected noise levels will comply with the requirements of AUC Rule 012: Noise Control (AUC Rule 012). 5 The Commission accepted that the proposed development is expected to have minimal environmental impacts (as the gas turbines would be installed within the MPF buildings at the Algar project site) and will meet Alberta Ambient Air Quality Objectives. 6 The Commission found that GOS had provided information to indicate there is no public highway on the lands over which the electric energy will be distributed. 7 Exemption, pursuant to Section 24 of the Hydro and Electric Energy Act, was granted to GOS to own and operate the proposed 600-V distribution system. 8 3 Discussion 4. GOS stated that during the detailed engineering phase it was recognized that, by extending the MPF internal 4,160-V distribution system to a location immediately adjacent to the MPF and close to the well site loads, an improvement to the distribution system could be achieved. The improvement areas would be as follows: Reduced voltage drop on the system to the well pad sites. Reduced operating losses on the system to the well pad sites. Reduced voltage sag during motor start. 5. GOS submitted that the construction of the 4,160-V cable and the relocation of the transformer (the alterations) would occur within the originally approved site boundaries and would be installed in accordance with standard industry practice. Specifically, the proposed 4,160-V cable would be installed in a common tray with the already approved 600-V cable system and the 500-kVA transformer would be relocated adjacent to the MPF. 6. GOS also submitted that no incremental environmental impact will result from the proposed alterations as no new lands would be impacted. 7. The 500-kVA transformer which was originally proposed to be located within the MPF, was not identified as a major noise source in the noise impact assessment in the original application 9 and thus it is not considered a significant noise source within the approved project. The relocation of the transformer to its proposed location is therefore not expected to alter the predicted noise levels. 8. There is no change to the site location or the ownership of the land over which the electric energy will be distributed. 5 6 7 8 9 Decision 2012-228, paragraph 17. Decision 2012-228, paragraph 19. Decision 2012-228, paragraph 27. Decision 2012-228, paragraphs 28 and 30. Proceeding ID 1870, Exhibit 002. 2 AUC Decision 2013-124 (March 28, 2013)

Algar Lake Project Distribution System Exemption 4 Findings 9. Based on the information submitted by GOS, the Commission finds: No other persons would be directly affected by the proposed alterations as there are no dwellings within 2,500 metres of the Algar project site. The proposed alterations do not include additional sources of emissions and, therefore, will not alter the air quality assessment. The proposed alterations will not alter the predicted noise levels and, thus, the project remains in compliance with the requirements set out in AUC Rule 012. No adverse environmental impacts will be caused by the proposed alterations. 10. As there is no change to the site location or the ownership of the land over which the electric energy will be distributed, the exemption, pursuant to Section 24 of the Hydro and Electric Energy Act, granted to GOS in Decision 2012-228, remains valid. 5 Decision 11. The Commission approves the application and grants the exemption, pursuant to Section 24 the Hydro And Electric Energy Act, which is extended in scope to include the 4,160-V electric distribution system. 12. The Commission may cancel or suspend this exemption, in whole or in part, in accordance with Section 41 of the Hydro and Electric Energy Act or may review this exemption, in whole or in part, upon its own motion or upon an application by an interested party, in accordance with Section 10 of the Alberta Utilities Commission Act. Dated on March 28, 2013. The Alberta Utilities Commission (original signed by) Tudor Beattie, Q.C. Commission Member AUC Decision 2013-124 (March 28, 2013) 3