Instrumentation and Data Management for the Zurich Zimmerberg Railway Tunnel Construction Daniel Naterop Solexperts Ltd.

Similar documents
Tunnelling in Squeezing Rock- Yielding Elements and Face Control

Ground Freezing for Tunnel, Shafts, and Adits

Inovatívne metódy geotechnického monitoringu na stavbách v SR a v zahraničí

HMA GROUP AUSTRALIA - NEW ZEALAND - INDONESIA - SOUTH AFRICA SINCE 1966

Design of pipeline installation D-GEO PIPELINE

Developed countries require a modern infrastructure Roads Railways Power Communications Water Wastewater

4D grouting pressure model of a bored tunnel in 3D Tunnel

4D grouting pressure model PLAXIS

rapid tunnelling thanks to efficient SePArAtion. Low-impact mechanized tunnelling: Integrated solutions.

GROUTING DURING THE DRIVING OF DRIFTS AND TUNNELS

REHABILITATION OF THE LANGETENTAL FLOOD DIVERSION TUNNEL

Introduction to Tunnel Construction

Risk Management based Ground deformation monitoring during Queens Bored Tunnels project

Performance review of a pipe jacking project in Hong Kong

Design of pipeline installation. D-Geo Pipeline

LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL

Lantz-Boggio Architects, P.C LBA Project No

Deformation monitoring and analysis of deep foundation pit of Xiaoshan rainbow Boulevard

CC1602 Microtunneling

Excellence in tunnel engineering. Consulting, planning, realisation

COMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS

ISM 2007 Toronto, Canada Horst Aschenbroich Dipl. Ing. President & CEO of Con-Tech Systems LTD. Titan Hollow Bar

VERTICAL BARRIERS SLURRY TRENCH BARRIERS: excavation equipment. prof. E. Fratalocchi Environmental Geotechnics Waste and polluted sites containment

SECTION / ENGINEERED AGGREGATE PIERS (SOIL REINFORCEMENT AND FOUNDATION SYSTEM)

Construction Technology B (CON4313)

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

Innovative and client-oriented solutions for geotechnical and hydrogeological projects

Compaction and Jet Grouting

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Civil Engineering Construction I (CBE5031)

Diaphragm wall Construction

Tunnelling and Underground. Construction Technology

Mitigation of the effects induced by shallow tunneling in urban environment: The use of compensation grouting in the underground Line B1 works in Rome

Grouting for Freezing

DIFFICULT GROUND SOLUTIONS:

DESIGN AND CONSTRUCTION OF LARGE LAINZER TUNNEL PROJECT. Josef Daller, ic consulenten, Vienna - Austria

Grouting Bilfinger Spezialtiefbau GmbH

Pipejacking Tunnel Boring Machines TBMs. Michael Frenke, LOVAT Inc.

Ching Guan Kee ABSTRACT

REAL WORLD TO THE CITIES SENSORS INTERFACE SOFTWARE

TRENCHLESS SOLUTIONS FOR SEWER NETWORKS AND SEA OUTFALLS.

03/12/2012. JSPS/CSIC international symposium on Smart Infrastructure and Construction. Business opportunities for Smart Infrastructure

Soil Improvement by Compaction Grouting

Design and Construction of Landfill Gas Monitoring Wells

Misan University - College of Engineering Civil Engineering Department

Borehole Condition Assessment

Ground Improvement Prof. G. L. Sivakumar Babu Department of Civil Engineering Indian Institute of Science, Bangalore

2 Support of the cavity and settlement Support of the face Natural support Mechanical support...

Design and development of a decline shaft through poorly consolidated Kalahari deposits at Ghaghoo Diamond Mine.

2013 ASCE Agenda. Microtunneling in Difficult Ground Craig Camp. Microtunneling Characteristics (NASTT) Akkerman MTBM Introduced 1995

Trenchless Technology

Challenges in Design and Construction of Deep Excavation With Case Studies - KVMRT in KL Limestone

Passage under Lövstavägen at Bypass Stockholm From Design to Realization

COPYRIGHTED MATERIAL. Contents PART ONE: THEORY...1. Preface to the Third Edition xiii. About the Authors xv. Acknowledgements xvii

Guide to Geotechnical Instrumentation

> GRouTING systems. The experience and expertise to deliver the right grouting solution for the job. Grouting is the most diverse

BOREHOLE CONDITION ASSESSMENT

TBM experiences from the Koralm railway tunnel (Austria) and re-use of TBM muck. Gerhard HARER

SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL

MEMORANDUM. TO: STUART OLSON DOMINION CONSTRUCTION LTD. DATE: JANUARY 31, 14 ATTENTION: MR. Dave Bauder, Construction Manager KENNY K. C.KO, P.ENG.

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

Underground works in urban environment

USE OF MICROTUNNELING TO INSTALL PIPES IN AN ENVIRONMENTALLY SENSISTIVE AREA. Miranda Roman D. *, LaFaso Edward

No-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e.

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer

The Croatian experience in the use of the interactive design method

Use of Jet Grouting in Challenging Infrastructure Renewal Situations in Hawaii


Experts in tunneling with Tunnel Boring Machines

Freezing techniques made a new tunnel possible

REPAIR OF DISPLACED SHIELD TUNNEL OF THE TAIPEI RAPID

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by

Case study of deep excavation in existing underground structure of three-story basement and diaphragm wall

4th International Engineering and Construction Conference - July 28, 2006

Foundation Innovations Ensure Successful Bridge Replacement

Prof. Eng. Daniele PEILA

A case study of twin bored tunnelling under mixed-face soil - Bendemeer MRT station project (Downtown Line 3), Singapore

STRUCTURAL HEALTH MONITORING AT THE PONT DE LA POYA, FRIBOURG

DESIGN AND INSTALLATION OF THE SHORING AND DECKING FOR TTC YONGE STATION

Dulles Corridor Metrorail Project Phase 1 NATM Tunnel Construction at Tysons Corner

Compensation grouting for TBM tunnelling beneath shallow-cover

June i TABLE OF CONTENTS

Case Study. The Challenge. Deep Micropile Installation Under Existing Multistory Building

Available online at ScienceDirect. Procedia Engineering 189 (2017 ) 11 17

Slurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P.

SECTION DUCTILE IRON PILES

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DRILLED SHAFTS

AGS(HK) Seminar - Tunnelling - Selected Topics Instrumentation for Tunnelling. Practical Aspects of Tunnelling Instrumentation

TBM Selection and Specification

SECANT PILE. Introduction:

Contents. Glossary 9. Foreword 10

Optimization of Supports in a Road Tunnel through Conglomerate during Construction

Concrete Pipe Jacking

APPLICATION NOTE AN-9920 May 1999 INSTRUMENTATION FOR MONITORING CONSOLIDATION OF SOFT SOIL 1. Introduction

Tunnel. Immersed Tunnels

Long-Term Settlement Performance Monitoring, I-15 Reconstruction Project, Salt Lake City, UT. Steven Bartlett, University of Utah

SPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006

13/05/2016. Introductions of Pipe Roof. Focuses. Application of Rectangular Shield Jacking

Steel screw settlement reduction piles for a raft foundation on soft soil

Livro: Technology Innovation in Underground Construction. 1. Introduction. 3.4 Rule base for tunnel pre-design. 1.1 Motivation

Transcription:

Instrumentation and Data Management for the Zurich Zimmerberg Railway Tunnel Construction Daniel Naterop Solexperts Ltd., Switzerland 1. Introduction The 9.4 km Zimmerberg base tunnel is an important part of the Swiss Railway system. In the southern 700 m section, from Kollerwiese to the Lochergut portal, the 12.4 m-diameter tunnel passes directly under or very close to houses and existing structures. This section of the tunnel lies in lacustrian sediments and fluvial deposits from the Sihl river coming from the Alps east of Zurich. The Herrrenknecht mixshield TBM is specially designed to drill through rock and soil and within groundwater. The groundwater level in this part of Zurich is approximately 12m below the surface. The crown of the tunnel ranges from 12m to about 5m depth. Instrumentation (mainly for monitoring settlement) located underground, on the surface and in buildings, in combination with an internet-based data management system, provides valuable, instantaneous information to all engineers involved. The system has proven to be a very powerful tool for immediate decision-making in critical situations, and for monitoring the effects of measures like grouting and jacking before and during tunnelling. Instrumentation and data management via the internet is described below, and some results are shown. Solexperts thanks the SBB, the joint venture AZT, the project engineers IG BBPS ( Basler & Hofmann, Balestra, Preisig and SNZ)and other companies involved for the fruitful cooperation in this very interesting and challenging project. 2. Project overview 2.1 The Zimmerberg Base Tunnel The Zimmerberg railway tunnel between the city of Zurich and Thalwil is part of the Swiss AlpTransit project and the Bahn2000 project. Zimmerberg base tunnel At present, all railway traffic from Zurich in the direction of Chur and Austria, from Zurich to Italy via the Gotthard tunnel and all local public transport along the left side of Zurich Lake travels over the old 2-track railway line. This results in extremely heavy traffic and a high frequency of trains. This railway line with many stations and frequent stops for local public transport is not able to meet the everincreasing demands for greater capacity. Large railway expansion projects now underway will provide a much-needed increase in capacity. Daniel Naterop, Solexperts Ltd. 1

Construction of the new Zimmerberg base tunnel began in 1997 and will be completed in the year 2003. The link to the Gotthard line will be completed by the year 2008 together with the Gotthard base tunnel. From one of the two shafts at Brunau, the 12.3m diameter mixshield TBM is being used to construct the most difficult 2.7km-long section to the Lochergut portal. The first 2 km from Brunau was drilled through intact rock. After 2 km, the TBM was switched to closed-face mode. It will drill the last 700m under very shallow cover and will pass near existing structures. In this section, excavation will take place in lacustrian sediments of sand and silt and in coarse-grained fluvial sediments. The groundwater level in this section is at about 12m depth from the surface, practically at the level of the crown of the tunnel. The sand and especially the gravel are highly permeable with groundwater flow velocities of 10 to 30m per day. It is also anticipated that remains of structural elements (steel piles and parts of sheet piles) will be encountered within the excavation cross section. Cross section of the 700 m section from Kollerwies to the Lochergut Portal From a 3.5 m diameter pilot tunnel, which is parallel to the main tunnel and above the groundwater level, extensive grouting above the tunnel took place. This grouting was almost entirely completed by the end of the year 2000, before the excavation of the main tunnel began at this particular section. The grouting created a covering layer about 3m thick. Additionally, below foundations of some of the houses above and very close to the new tunnel, and at certain pre-selected locations, grouting was performed over the whole tunnel cross section as well as above the tunnel. The purpose of grouting at pre-selected locations was to allow service of the TBM and long-term TBM-excavation stops (e.g. over Christmas). These measures are intended to prevent settlement (a maximum of about 20mm of settlements is allowed) and reduce the risk of blowout of the bentonite water slurry. Schematic cross section of tunnel and pilot tunnel Drilling for grouting from the 3.5 m diameter pilot tunnel Daniel Naterop, Solexperts Ltd. 2

During drilling for grouting, some of the steel drill pipes (diameter 150m, length 1m) broke off and remained in the soil. These pipes as well as some large blocks (one as big as 60m 3 ) affected progress and required special measures. A section of the three-story underground garage of the SSF-building lies directly in the axis of the tunnel. With a series of micro-piles and a frame of pre-stressed concrete beams, the foundation of this office building was reinforced and a part of the garage was dismantled to prepare for TBM penetration trough the old location of the structure. In the last 150m of the southern part of the tunnel, until the Lochergut portal, grouting from the pilot tunnel was not possible. There the tunnel is excavated under a pipejacked umbrella. Each of the pipes has a diameter of 1.2m and is jacked over 130m to 150m practically horizontally at a vertical distance from the tunnel of about 1.5m. Underground garage of the SSF building Location of the pipejacked umbrella Schematic cross section of the pipejacked umbrella Instrumentation includes various elements which are manually, semi-automatically, and automatically read and processed. All data and information from the instruments, together with the position of the TBM has to be available to all engineers in charge with the following criteria: Data are available around the clock and can be obtained quickly Processed data must be provided The data management system must be easy to operate All engineers in charge must have the same information and a complete overview Automatic alarms must provide immediate alerts in critical situations 3. Instrumentation 3.1 Settlement measurement from the pilot-tunnel The pilot tunnel provided a good opportunity for instrumentation. To measure subsurface settlement and heave during tunnel construction (including all preparatory work and TBM excavation) an automatic system which combined hydraulic and geodetic levelling was installed. This system had to monitor a section approximately 50m ahead and 50m behind the TBM. In the end, the monitored section was about twice as long as originally specified by the client. Daniel Naterop, Solexperts Ltd. 3

For hydraulic levelling, a specially designed system for borehole installation was used. This system includes a borehole probe (length 250mm, diameter 50mm) with a very precise pressure transducer. The probe is pushed into the borehole with fibreglass rods. Outside the borehole a small hydraulic reservoir is installed. The reservoir connects to the borehole probe with a hydraulic line and a pneumatic line to compensate for changes in atmospheric pressure. The sensor line connects to the interface outside of the boreholes. These sensors measure changes in level between the reservoir located at the borehole top and the sensor located at about 1.5 m above the crown of the tunnel. The distance between the sensor and the top of the borehole ranges from 6.5 to 8 m. The pilot gallery is very close to the tunnel and will also be affected by excavation. To measure total settlement, the readings of the hydraulic levels were combined with settlement readings at the top of the borehole (reservoir). For this purpose, two automatic Total Stations (theodolites with electronic distance meters) are employed. At every reservoir, an optical prism is installed as a measurement target for the Total Stations. At the opposite end from these instruments, reference points are installed and measured which are outside the influence of tunnel construction. 3.2 Automatic measurements of settlement in basements of houses In the basement of two buildings, one of them being the SSF office building described above, settlement and heave had to be measured automatically over several months. This period covered the preparations before excavation and the period when the TBM passed under or near each building. A series of motion-controlled digital levels with bar-coded staffs was installed on the ceiling and walls in these basements. Reference points outside the influence of tunnelling activities compensate for settlements of the instruments (levels) themselves. Often the best location for installing a level is in Daniel Naterop, Solexperts Ltd. 4

the centre of the influenced zone. This way visibility of the staffs (measuring points) is optimal. The levels are motorized to move and focus the optical axis on the bar code staffs, and include a spotlight for illuminating staffs. Vertical deformations were observed which were mainly due to grouting activities (heave of up to 15 mm by the end of October, 2000). When the TBM passed beneath the basements of the instrumented buildings, settlements in the range of 2 to 4 mm were observed (beginning of January 2001). 3.3 Deformation measurements in vertical Boreholes A total of 20 boreholes along the tunnel line have been instrumented to enable linewise deformation readings with the Sliding Deformeter (a high-precision probe extensometer) and with the borehole inclinometer. The boreholes above the tunnel crown reach to a depth of about 12m and the boreholes alongside the tunnel reach to a depth of about 30m. Combination measurement casing which enables readings with both instruments within the same borehole is installed and grouted to the soil. The soft grout (a mixture of cement, water and bentonite) and telescopic couplings every 1m guarantee that the measurement casing also moves in very soft soil without acting as a pile. Daniel Naterop, Solexperts Ltd. 5

The readings from the Sliding Deformeter and borehole inclinometer are stored on a portable palmtop PC, and are processed using calibration readings to provide deformation profiles. To present, only very small settlements have been observed due to tunnel excavation. These results show clearly that the quality of the grouting is good, and that the selected tunnel excavation method is optimal, since no or only slight settlement has occurred. 3.4 Deformation measurements in the horizontal pipejacked umbrella Two of the approximately 150 m-long pipejacked horizontal piles have been equipped with inclinometer casing. This casing was installed within 120 mm diameter steel protective casing and firmly cemented inside the piles with grout. Readings are taken with a standard horizontal borehole inclinometer probe. The probe is pushed into the casing to the end, and retracting the probe meter by meter, inclinometer readings are taken in two directions. These readings are stored on a portable palmtop PC, and are processed using calibration readings to provide deformation profiles 3.5 Automatic and manual settlement measurements on the surface Four automatic Total Stations are used to automatically measure settlement on buildings and on the pavement. They are operated similarly to the ones used in the pilot tunnel. The Total Stations are moved with the progressing tunnel excavation, so that the zone of influence is always covered by measuring points. For long-term settlement monitoring and to supplement automatic settlement readings, especially for measuring points which are not easily accessible, classical manual levelling is performed. 4. Data Management 4.1 Data Sources Diverse instrumentation, data from various sources and a large number of measuring points necessitated a powerful tool for data handling. DAVIS Data Visualisation Software combined with data management over the internet offered an optimal solution for the needs of the various engineers and companies involved: Daniel Naterop, Solexperts Ltd. 6

The project manager for the client, the Swiss Federal Railway Company (SBB) The project engineers: Ingenieurgemeinschaft BBPS, Zürich (Basler & Hofmann AG, Balestra, F. Preisig and SNZ) The contractor (joint venture AZT) Solexperts AG, the company responsible for operating the system The following table gives an overview of the various data sources. Manually read instruments have an interval between readings of.5 days to 45 days. This interval is determined by the position of each point in relation to tunnel excavation and other construction work. Automatically read instruments are measured at intervals of about 0.5 to 1 hour. Type of Instrument number of locations type of reading total number of measurement points Hydraulic levelling 4 automatic 98 Total Station subsurface 4 automatic 98 Total Station above surface 16 automatic 640 Manual levelling manual 380 Motion-controlled levels 3 automatic 37 Sliding Deformeter 20 manual 390 Vert. Inclinometer 15 manual 430 Horiz. Inclinometer 2 manual 290 TBM-Position 1 automatic 1 Data from all automatically-read instruments are processed at the remote computers. Processing basically involves comparison of processed data with predefined alarm values, sending alarms via fax and SMS and: Hydraulic levelling Calculation of settlement of the sensor in relation to the reservoir at the borehole top and in relation to the reference (from Total Station reading). Total Station subsurface and above surface: Transformation (Helmert transformation) in relation to reference points, even if some of the reference points are not visible, settlement of each individual measuring point in relation to reference points is calculated. Motion-controlled levels Calculation of settlement of the individual measuring points in relation to reference points. TBM Position processed into a table and plotted to a graph which can be viewed on the internet at www.los201.ch by anyone (try it out). This website also contains interesting information about the project. After these automatic measurements are made and processed, data from these sources are sent to an FTP server. All data are also stored in a backup file on a server. Operation of the data visualization is done on the DAVIS server where all the data files from the different sources are combined into one database. The graphics are automatically updated with new data. Daniel Naterop, Solexperts Ltd. 7

Sensor positions and all graphs of data can be viewed over the internet. An overview of this part of the project includes symbols for the various instrumentation. Some of the typical instrumentation layouts and graphs generated from measurement data which are available over the internet are shown below. Locations and results from linewise deformation measurements with the Sliding Micrometer and the borehole inclinometer. Daniel Naterop, Solexperts Ltd. 8

25 20 15 10 5 Heave from grouting recorded at the surface 0-5 -10-15 3725 3726-20 3727 3728-25 3729 3730-30 12-Mär 13-Mär 14-Mär 15-Mär 16-Mär 17-Mär 18-Mär 19-Mär 20-Mär 21-Mär 22-Mä Measurement points at the surface and measurement results as displayed in DAVIS 30 25 20 15 10 5 0-5 -10-15 -20-25 H-DN3302 H-DN3303 H-DN34 H-DN3401 H-DN35 H-DN3501 Nivellement Pilotstollen (TCA) Heave from grouting recorded subsurface -30 12-Mär 13-Mär 14-Mär 15-Mär 16-Mär 17-Mär 18-Mär 19-Mär 20-Mär 21-Mär 22-Mär DAVIS screen and measurement results of hydraulic levelling in the pilot tunnel Settlement measured with hydrostatic levelling from the pilot tunnel as the TBM was passing directly below instruments: 5 4 mm Heave Hydrostat. Nivellement 4 mm Heave 3 3 2 2 1 0-1 N1401 N15-2 N1303 N1304 N1304 N14 N1303-3 N1501 N1401 N15 N14-4 N1501 mm Settlements -5 2-Okt 8-Okt 14-Okt 20-Okt 26-Okt 1-Nov 7-Nov 13-Nov 19-Nov 25-Nov 1-Dez Plotted against time dh (mm) 1 0-1 -2-3 -4 mm Settlements etzung-5 N1303 2070 2080 2090 2100 2110 2120 2130 2140 2150 2160 2170 V t i b (T ) Plotted against TBM advancement N1401 N15 N1304 N1501 N14 Daniel Naterop, Solexperts Ltd. 9