P Temporary piezometer. MW Piezometer to remain in place. P Temporary piezometer

Similar documents
Sump Pump Feasibility Review Summerside West Residential Development - Phases 4, 5 and 6 Tenth Line Road - Ottawa, Ontario

Sampling Plan Supplement PG&E Topock Interim Measures Drilling Program

3. FIELD INVESTIGATION PROGRAM

BROWARD COUNTY ENVIRONMENTAL PROTECTION DEPARTMENT (EPD) MINIMUM CRITERIA FOR MONITORING WELL INSTALLATION AND SAMPLING

May 3, Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street NE, Room 1A Washington, D.C

INVESTIGATION RESULTS

Influence of purging the surrounding monitoring wells for groundwater sampling during a hydraulic conductivity test in a monitoring well.

Monitoring Well Installation Report

Soil Improvement by Compaction Grouting

GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO

Multilevel Systems, Remediation & Drive-Points.

July 23, Mr. Richard Miller, Vice President Lake Arrowhead Property Owners Association 7065 Arrowroot Trail Gaylord, Michigan 49735

Groundwater level fluctuations caused by surface hydrologic pulsing of a wetland

Exploring Dynamic Interactions Between Surface Water and Groundwater at a Point Bar System in the Muskegon River Watershed

Design Checklist for EWB-USA Chapters Working on Drilled Well

APPENDIX E SOIL VAPOR PROBE AND PIEZOMETER INSTALLATION AND MONITORING PROCEDURES Central Los Angeles High School#11 and Vista Hermosa Park

Interim Source Removal Summary Groundwater Extraction System Former American Beryllium Company Site Tallevast, Florida

Subject: Aquifer Test Observation Well Installation Work Plan Hilmar Cheese Company, Hilmar, Merced County, CA

Environmental Management Chapter

SECTION GEOTECHNICAL INSTRUMENTATION

Date: March 23, 2018 Reference No.: VAN A0 To: cc: Mike Dolman Assistant Project Manager

April 7, Webster Street Sub-Surface Stormwater Storage System Bid No Bid Date: 4/13/17 ADDENDUM NO 1

ABSTRACT & POWERPOINT PRESENTATION

Squaw Valley Creek/Aquifer Interaction Study Final Report

NGWA s Water Well Construction Standard: ANSI/NGWA 01-14

September 3, 2013 Via

June i TABLE OF CONTENTS

PHASE I ERNEST MINE COMPLEX. The objective of the project was to develop an economically feasible, safe

Appendix I-2.4 Sub-cell 3 Monitoring Well Details

Performance and Analysis of Aquifer Slug Tests and Pumping Tests Policy

Water Well Drilling Agreements

14.0 MONITORING AND CONTINGENCY 14.1 Effects Monitoring

5.0 - WATER SUPPLY WELLS

This work will be completed in support of the corrective measures evaluation. The objectives of this study are as follows:

patersongroup Consulting Engineers October 7, 2010 File: PE2100-LET.01 Springcress Properties Inc. 6 Gurdwara Road, Suite 200 Ottawa, Ontario K2E 8A3

ONTARIO MUNICIPAL BOARD

This report presents the findings of the subsurface exploration concerning the design of the taxiway rehabilitation. Description

Stormwater Standards. Clackamas County Service District No. 1. Infiltration Testing Guide

SECTION SUBSURFACE INVESTIGATION. 1. Protection of the environment; Section

SUPPLEMENTAL PHASE II INVESTIGATION REPORT

SECTION IRRIGATION WATER WELL

SECTION IRRIGATION WATER WELL

Westbay System. Multilevel Technology for Subsurface Characterization and Monitoring

Misan University - College of Engineering Civil Engineering Department

Lab 6 - Pumping Test. Pumping Test. Laboratory 6 HWR 431/

Preliminary Geotechnical Investigation

Wastewater Capital Projects Management Standard Construction Specification

An Inexpensive Device for Multiple Depth Sampling of Groundwater Quality in Cohesionless Aquifers 1

Attachment B: Field Forms and Notes

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

British Columbia s New Guidance for Groundwater Site Characterization

APPENDIX B Line 3A Pond Proposed Leach Pond Drawing

Monitoring Well Installation Report

APPENDIX A Standard Operating Procedures

SECTION GRAVEL PACKED WATER WELL

CONDUCTED FOR: PREPARED FOR: 5 May 2016 YPC Project No. 16GY146

TEST PLAN. Constant Head Saturated Hydraulic Conductivity Measurements on Repacked Core Samples

Date: 05/25/2006. Bob Hare/ENCORE. From: Tony Perfetto/CRA. Gavin O Neill/CRA John McKenna/BBL

CONDUCTED FOR: PREPARED FOR: 18 October 2010 YPC Project No. 10GY133

CMYK. Pantone. Westbay System. Greyscale. Black on White. White on Black. Multi-level Technology for Subsurface Characterization and Monitoring

The following sections provide the approved standard infiltration testing specifications.

TITLE 252. DEPARTMENT OF ENVIRONMENTAL QUALITY CHAPTER 652. UNDERGROUND INJECTION CONTROL

SITE INVESTIGATION. Foundation Engineering

the former Honeywell plant building (3 Hamilton Avenue) a single-storey brick industrial/commercial building (233 Armstrong Street)

N60234.AR NAS SAUFLEY FIELD a

A Site Location Map, Site and Surrounding Properties Map, and Site Plan are attached as Figure 1, Figure 2, and Figure 3, respectively.

TOWNSHIP OF NORTH GLENGARRY MAXVILLE COMMUNAL SEWAGE LAGOONS 2011 GROUNDWATER AND SURFACE WATER MONITORING PROGRAM REF.: FINAL REPORT

Identification. Module 4 Water Well Drilling Agreements

Sepetember 27, Florida Department of Environmental Protection Attn: Dawn Templin 160 Governmental Center Pensacola, FL

APPENDIX K. Groundwater Monitoring Results

1.0 PROJECT INFORMATION. 1.1 Site Location and Description. October 31, 2017

Borehole Data Package for Calendar Year RCRA Wells at Single-Shell Tank Waste Management Area TX-TY

PROPOSED CONDOS 1129 Victoria Drive, Dunedin Parcel: , Pinellas County Geotechnical Services June Report No.

Appendix VIII. Guidelines for groundwater bores and wells

Advancements in ASR Well Design and Operations- City of Phoenix Case Study

Nye County Comptroller Accounting Contracts Finance Grants Purchasing

City Policy & Procedure

Geoprobe SDT45 Sonic Dual Tube Sampling System

DESIGN PARAMETERS FOR MULTI-PHASE EXTRACTION SYSTEMS USING UNSATURATED AND SATURATED SOIL PROPERTIES

June 28, Test Well Flow Rate Report MSD Underground Injection Control Wells City of Richlawn Louisville, Kentucky 40207

SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL

Technical Bulletin No. MK3176. PREPARED: July, 2010

PO7: Preston New Road Groundwater Monitoring Borehole Installation Report. Date: September Page 1 of 24

2.6 Methods of Soil Sampling

Water Well Decommissioning Guidelines

Borehole Condition Assessment

VOCs, including fuel oxygenates, via EPA Analytical Method The second soil sample from MW-24 (MW ) was analyzed for Total Organic Carbon.

The artesian well hydrology of Big Bertha has been logically divided into 5 phases of monitoring, analysis, and investigation as outlined below:

CCR Groundwater Monitoring System

MITIGATION PLAN SEAWATER INTRUSION

Earth Mechanics, Inc. Geotechnical & Earthquake Engineering

Site Investigation MUHAMMAD AZRIL HEZMI

Hydrogeologic. Valley Waste Disposal Company Cymric Field. Characterization Workplan Easton Drive. t ý4k. Prepared for.

Bi-Directional Static Load Testing of Drilled Shafts

Bi-Directional Static Load Testing of Drilled Shafts

Electrical Conductivity & Hydraulic Profiling. The Combining of Two Subsurface Investigation Methods (With More to Come)

2.0 HEALTH AND SAFETY

PROVINCE OF BRITISH COLUMBIA ORDER OF THE LIEUTENANT GOVERNOR IN COUNCIL

APPENDIX F NON-ROUTINE SERVICES

SECTION DUCTILE IRON PILES

Transcription:

2. Field Program 2.1 Health and Safety Plan Prior to beginning the field program, CH2M HILL developed a health and safety plan (H&SP). The H&SP provided a summary of potential physical hazards that could be encountered by field staff during fieldwork. The plan included the following components: Tasks permitted (regulated tasks) Hazard controls Listing of CH2M HILL personnel performing site work Personal protective equipment to be used at the site Emergency response plan The plan was communicated to CH2M HILL s subcontractors via pre-job on-site safety meetings. Subcontractors were required to sign the H&SP docket following the safety meeting, indicating that they fully understood the H&SP. 2.2 Drilling Program Six boreholes were advanced during the hydrogeologic portion of the investigation. Soil samples were collected with a split-spoon sampler that measured 0.6 m in length. Soil samples were collected continuously to a depth of 3 m below ground surface after which point they were collected at 1.5 m intervals. Piezometers were installed within four of the boreholes. Table 2.1 below summarizes the drilling program. The new piezometers provide water table elevations to assess local groundwater flow conditions. TABLE 2.1 BOREHOLE SUMMARY Location ID Depth (m bgs) Diameter Screen Details (mm) Length (m) P-06-8 9.9 51 1.7 Temporary piezometer MW-06-5 9.1 51 3.15 Piezometer to remain in place P-06-6 16.4 51 1.66 Temporary piezometer MW-06-7S 12.5 25 3.0 Shallow piezometer to remain in place MW-06-7D 23.6 51 1.5 Deep piezometer to remain in place BH-06-13 25 No installation BH-06-14 22.8 No installation The hydrogeologic drilling was conducted between July 7 and July 12, 2006, under the supervision of CH2M HILL personnel. CH2M HILL retained Atcost Soil Drilling (Atcost) of Concord, Ontario, to drill the boreholes and install the piezometers. An additional deep 34633606RP_ES082006004KWO 2-1

borehole (BH-06-14) was completed on August 25, 2006 to provide supplementary stratigraphic data. Drilling for the geotechnical portion of the investigation took place on July 13, 2006. Naylor Engineering Ltd. was subcontracted by CH2M HILL to conduct the geotechnical portion of the investigation. Details of the geotechnical investigation are presented under a separate report included in Appendix A. Naylor borehole designations differed from those of CH2M HILL and are outlined in Table 2.2 below. TABLE 2.2 GEOTECHNICAL BOREHOLE IDENTIFICATION CH2M HILL Borehole Designation P-06-1 P-06-2 P-06-3 P-06-4 BH-06-9 BH-06-10 BH-06-11 BH-06-12 Naylor Designation BH108 BH107 BH106 BH104 BH105 BH103 BH102 BH101 Borehole and piezometer locations are shown in Figure 2-1. All boreholes were advanced in the overburden. Piezometer construction details are shown on the well logs, included in Appendix B. Piezometers were constructed with threaded PVC pipes and machine slotted well screens. No. 3 silica sand was placed around the annulus of each well screen and extended above the top of the screen. A bentonite seal was placed around the piezometer above the sand pack and the remainder of the annulus was filled with bentonite grout to surface to prevent surface water from entering the well bore. All installations were completed with stick-up pipes and steel protective casings that were approximately 0.6 m high and equipped with locks. Boreholes BH-06-13 and BH-06-14, where no piezometers were installed, were backfilled with bentonite grout to surface. Atcost, a licensed water well driller, installed all piezometers in accordance with R.R.O. 1990, Reg.903. A water well record was completed for permanent piezometer MW-06-7 and copies were retained by Owen, CH2M HILL, and the Ontario Ministry of Environment (MOE). A copy of the well record is included in Appendix E. 2.2.1 Surveying The elevation of the ground surface was surveyed by PEIL and the piezometer stick-ups measured to provide vertical elevations and relate them to existing on-site monitoring wells (MW1, MW2, MW3). 2-2 34633606RP_ES082006004KWO

2.3 Groundwater Measurement All permanent on-site piezometers were developed on July 13 and 14, 2006 to remove fine grained sediments that may have accumulated along the well screens. Each piezometer was equipped with polyethylene tubing and a Waterra foot valve and was developed until dry or until at least three well volumes had been removed (volume of water in stand pipe screen plus sand pack). Following this water levels were measured at all onsite wells on July 19, 2006, to determine groundwater flow direction and magnitude of horizontal hydraulic gradients. Groundwater sampling was not conducted at this time. CH2M HILL understands that PEIL will be conducting all future groundwater monitoring activities. 2.4 Hydraulic Testing Single well response tests were carried out on selected piezometers to estimate the hydraulic conductivity of the geologic formation. Falling head tests were conducted in MW1, MW3, P-06-8, and MW-06-7D. Piezometer MW-06-5 had an insufficient water level to conduct a single well response test. A static water level was taken at the well using a water level meter prior to commencing the single well response test. Solinst Level Loggers were programmed to measure groundwater changes at a one-second time interval before the testing began. The Level Logger was placed in the well before the test commenced and was allowed to record for approximately 3 to 5 minutes to provide baseline water level measurements. Depending on the piezometer diameter, a 1.5-inch or 3/4-inch diameter slug of known volume was quickly introduced into the well to raise the water level. The rate of groundwater recovery (falling head) to static groundwater levels was measured using a Level Logger. Water levels were measured until they recovered to static conditions (or at least two-thirds of static conditions).upon recovery to static conditions (or at least two-thirds of static conditions), the Level Logger was removed from the well and the single well response test was concluded. Data was downloaded from the Level Logger using the optical reader (supplied by Solinst) and a laptop computer installed with the Level Logger software. This process was completed for each location. Tests were repeated on two different occasions in MW-06-7D and MW3 to confirm that the results were consistent and reproducible. 2.5 Piezometer Abandonment Once hydrogeologic measurements were completed, the temporary piezometers were abandoned in accordance with R.R.O. 1990, Reg. 903, s.21. Under the supervision of CH2M HILL, Atcost abandonded the piezometers on August 25, 2006. 2-4 34633606RP_ES082006004KWO

2.6 Private Water Well Survey Well records were obtained from the Region of Waterloo for two private wells found within the area of investigation. These wells were identified as the McNally well and well TR2-64-91. Four additional well logs were obtained from the Ontario Ministry of Environment (MOE) Water Well Information System database. Copies of the well logs are provided in Appendix E. Data from the private well logs were used to prepare geologic cross-sections that transect the site. The private well logs provided additional information about deeper stratigraphic units within 500 m of the site. The private wells in the vicinity of the site range in depth from 12.5 to 64.92 m. To supplement the private well data, CH2M HILL conducted a review of historical reports and compiled data from borehole logs on adjacent properties which were included in the cross-sections. 34633606RP_ES082006004KWO 2-5