Straw Bale Barrier. - Along the face and at grade breaks of exposed and erodible slopes to shorten slope length and spread runoff as sheet flow

Similar documents
Straw Bale Barrier. Parallel to a roadway to keep sediment off paved areas

SE-6 GRAVEL BAG BERM. Objectives. Potential Alternatives

Storm Drain Inlet Protection

Common Construction-Site BMPs Quick Reference Guide

Earth Dikes and Drainage Swales

ACTIVITY: Silt Fence ES 14

Suitable Applications Where concentrated flow of surface runoff must be conveyed down a slope in order to prevent erosion.

Concrete Waste Management

PART 1 GENERAL REQUIREMENTS

Performance Standards Compliance Checklist

Outline of Presentation. Inspecting Construction Site BMPs. Inspector. Back to Basics. Erosion Control. Erosion Control

Slash Water Bar Video

Organic Filter Tubes. Fe= (Depends on soil type)

SECTION EROSION AND SEDIMENTATION CONTROLS

EROSION CONTROL REQUIREMENTS

2-16 EROSION, SEDIMENT & STORM WATER CONTROL REGULATIONS APPENDIX B1

Temporary Stream Crossing

City of Doral 8401 NW 53 rd Ter. Doral, FL 33166

Concrete Waste Management

Bowling Green, Kentucky Stormwater Best Management Practices (BMPs) Sediment Management Practices (SMPs) Activity: Temporary Inlet Protection (TIP)

Temporary Stream Crossing

Compost Socks and Berms

Rock Sock (RS) Rock Sock height.

CITY OF CHICO. Erosion and Sediment Control Plan (ESCP) Worksheet for Small Construction Projects. Project Address: Building Permit Number:

City of West Sacramento Erosion and Sediment Control Plan (ESCP) Worksheet for Small Construction Projects

City of El Centro. Erosion and Sediment Control Plan Review Checklist. Reviewer: Review Date:

Polyacrylamide. Rough graded soils that will be inactive for a period of time. Temporary haul roads prior to placement of crushed rock surfacing.

Non-Vegetative Stabilization

Block and gravel filters can be used where velocities are higher. Reduces the amount of sediment leaving the site.

Building Better Storm Water Quality

APPROVED FOR ISSUANCE REFER TO ENCROACHMENT AND/OR CONSTRUCTION PERMIT AND PLAN COVER SHEET FOR SPECIAL CONDITIONS AND PERMIT NUMBERING

Paving and Grinding Operations

Description. Installation and Implementation Requirements

Table 1: Minimum Perimeter Control Performance Requirements. Physical Property* Test Method Required Value

Figure Inlet protection (Source: Minnesota DOT)

Inlet Protection. Fe= (Depends on soil type)

IN T R A / M IN T R A M

No. 6 December, Wisconsin s Forestry Best Management Practices for Water Quality Forest Roads

Stabilized Construction Entrance/Exit TC-1

Erosion Control Blankets

Single Family Residential Construction Erosion/Sediment Control Standards

The Construction General Permit and Erosion Prevention and Sedimentation Control

Best Management Practices (BMPs) for Construction Sites & Home Remodeling Projects

Schedule A DISTRICT OF MAPLE RIDGE Watercourse Protection Bylaw

SECTION 903 EROSION CONTROL

CITY OF CAMARILLO STORMWATER POLLUTION CONTROL PLAN Demolition or Stockpile Activity Under One Acre

Flow Diversion Banks: General

Construction Entrance / Construction Road Stabilization Alturnamats & Versamats Dewatering Dandy Dewatering Bag / Dirt Bag...

EROSION CONTROL GENERAL NOTES EC JAN 2017 C.B.

Diversion Dikes. Fe=0.95

SECTION B. Prevention of sedimentation of waterways, open drainage ways, and storm and sanitary sewers due to construction activities.

METROPOLITAN UTILITIES DISTRICT No Page: 1 of 10

Construction Stormwater Best Management Practices

Sediment Control Practices

NS-5 CLEAR WATER DIVERSION. Objectives

Chapter 2: Selecting Best Management Practices (BMPs)

Installation and Maintenance of Erosion Control BMPs

Erosion and Sedimentation Pollution Control (ESPC) Plan Narrative

BMP-5. A temporary sediment barrier consisting of a synthetic filter fabric stretched across and attached to supporting posts and entrenched.

Construction Site Inspections

Construction Site Erosion Control and Phase II of the Stormwater Permit Program

Material Delivery and Storage

2.1 MINIMUM WATER QUALITY PROTECTION REQUIREMENTS FOR DEVELOPMENT CONSTRUCTION PROJECTS

Erosion Control Inspection Form

Stormwater Management Permit Application LESS Than One Acre. Public Works Department st Ave East Kalispell, Montana (406)

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL

CONSTRUCTION SPECIFICATION FOR TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

Kristin Kerr EOA, Inc. Construction Inspection Workshop February 1, 2017

The Good, The Bad, and The Ugly

ITEM 750 ROCK FILTER DAMS

Construction Site Erosion Control and Phase II of the Stormwater Permit Program

EROSION AND SEDIMENT CONTROL

Construction Site Erosion Control and Phase II of the Stormwater Permit Program

Post Construction Erosion Controls

Kristin Kerr and Peter Schultze-Allen EOA, Inc. March 20, 2018

INDEX BMP SUMMARY FOR CONSTRUCTION SITES

This silt fence system is composed of geotextile filter fabric and steel posts.

This silt fence system is composed of geotextile filter fabric and steel posts.

Slide Presentation. Exercise (if there s time) Field Demonstration. Various Pollutants of Concern: Why Use BMPs? 10/02/2013

Best Management Practice (BMP) Guidance Manual

Attachment 7.3 APPENDIX F SEDIMENT CONTROL BMPS

Material Delivery and Storage

WQ-08 ENHANCED DRY SWALE

Typical Local Erosion Control Requirements (Storm Water Management Authority, Inc.)

CONSTRUCTION SPECIFICATION FOR TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES

PHASE 1 UPDATES TO DESIGN AND CONSTRUCTION STANDARDS INITIAL DRAFT FOR. Chapter 6 EROSION PREVENTION AND SEDIMENT CONTROL

Fabric Drop Inlet Protection

Manual for Erosion and Sediment Control Updates

LAND DISTURBANCE PERMIT

SC-01 Surface Outlet and Baffle Sediment Basin

City of Bozeman. Construction Site Management Program

York County STORMWATER LUNCH & LEARN

Concrete Waste Management WM-8

EROSION CONTROL AND GRADING PERMIT APPLICATION

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent

Erosion and Sediment Control (ESC) Bylaw: Best Management Practices November 2014

CONSTRUCTION SPECIFICATION FOR TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES

Project Information. Check all that are applicable to the construction project site: RIPDES CGP (construction) RIPDES RGP (dewatering)

Transcription:

Straw Bale Barrier SE-9 Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective Secondary Objective Description and Purpose A straw bale barrier is a series of straw bales placed on a level contour to intercept sheet flows. Straw bale barriers pond sheet- flow runoff, allowing sediment to settle out. Suitable Applications Straw bale barriers may be suitable: As a linear sediment control measure: - Below the toe of slopes and erodible slopes - As sediment traps at culvert/pipe outlets - Below other small cleared areas - Along the perimeter of a site Targeted Constituents Sediment Nutrients Trash Metals Bacteria Oil and Grease Organics Potential Alternatives SE-1 Silt Fence SE-5 Fiber Rolls SE-6 Gravel Bag Berm SE-8 Sandbag Barrier - Down slope of exposed soil areas - Around temporary stockpiles and spoil areas - Parallel to a roadway to keep sediment off paved areas - Along streams and channels As linear erosion control measure: - Along the face and at grade breaks of exposed and erodible slopes to shorten slope length and spread runoff as sheet flow January 2003 California Stormwater BMP Handbook 1 of 6

SE-9 Straw Bale Barrier - At the top of slopes to divert runoff away from disturbed slopes - As check dams across mildly sloped construction roads Limitations Straw bale barriers: Are not to be used for extended periods of time because they tend to rot and fall apart Are suitable only for sheet flow on slopes of 10 % or flatter Are not appropriate for large drainage areas, limit to one acre or less May require constant maintenance due to rotting Are not recommended for concentrated flow, inlet protection, channel flow, and live streams Cannot be made of bale bindings of jute or cotton Require labor-intensive installation and maintenance Cannot be used on paved surfaces Should not to be used for drain inlet protection Should not be used on lined ditches May introduce undesirable non-native plants to the area Implementation General A straw bale barrier consists of a row of straw bales placed on a level contour. When appropriately placed, a straw bale barrier intercepts and slows sheet flow runoff, causing temporary ponding. The temporary ponding provides quiescent conditions allowing sediment to settle. Straw bale barriers also interrupt the slope length and thereby reduce erosion by reducing the tendency of sheet flows to concentrate into rivulets, which erode rills, and ultimately gullies, into disturbed, sloped soils. Straw bale barriers have not been as effective as expected due to improper use. These barriers have been placed in streams and drainage ways where runoff volumes and velocities have caused the barriers to wash out. In addition, failure to stake and entrench the straw bale has allowed undercutting and end flow. Use of straw bale barriers in accordance with this BMP should produce acceptable results. Design and Layout Locate straw bale barriers on a level contour. - Slopes up to 10:1 (H:V): Straw bales should be placed at a maximum interval of 50 ft (a closer spacing is more effective), with the first row near the toe of slope. - Slopes greater than 10:1 (H:V): Not recommended. 2 of 6 California Stormwater BMP Handbook January 2003

Straw Bale Barrier SE-9 Turn the ends of the straw bale barrier up slope to prevent runoff from going around the barrier. Allow sufficient space up slope from the barrier to allow ponding, and to provide room for sediment storage. For installation near the toe of the slope, consider moving the barrier away from the slope toe to facilitate cleaning. To prevent flow behind the barrier, sand bags can be placed perpendicular to the barrier to serve as cross barriers. Drainage area should not exceed 1 acre, or 0.25 acre per 100 ft of barrier. Maximum flow path to the barrier should be limited to 100 ft. Straw bale barriers should consist of two parallel rows. - Butt ends of bales tightly - Stagger butt joints between front and back row - Each row of bales must be trenched in and firmly staked Straw bale barriers are limited in height to one bale laid on its side. Anchor bales with either two wood stakes or four bars driven through the bale and into the soil. Drive the first stake towards the butt joint with the adjacent bale to force the bales together. See attached figure for installation details. Materials Straw Bale Size: Each straw bale should be a minimum of 14 in. wide, 18 in. in height, 36 in. in length and should have a minimum mass of 50 lbs. The straw bale should be composed entirely of vegetative matter, except for the binding material. Bale Bindings: Bales should be bound by steel wire, nylon or polypropylene string placed horizontally. Jute and cotton binding should not be used. Baling wire should be a minimum diameter of 14 gauge. Nylon or polypropylene string should be approximately 12 gauge in diameter with a breaking strength of 80 lbs force. Stakes: Wood stakes should be commercial quality lumber of the size and shape shown on the plans. Each stake should be free from decay, splits or cracks longer than the thickness of the stake, or other defects that would weaken the stakes and cause the stakes to be structurally unsuitable. Steel bar reinforcement should be equal to a #4 designation or greater. End protection should be provided for any exposed bar reinforcement. Costs Straw bales cost $5 - $7 each. Adequate labor should be budgeted for installation and maintenance. January 2003 California Stormwater BMP Handbook 3 of 6

SE-9 Straw Bale Barrier Inspection and Maintenance Maintenance Inspect BMPs prior to forecast rain, daily during extended rain events, after rain events, weekly during the rainy season, and at two-week intervals during the non-rainy season. Straw bales degrade, especially when exposed to moisture. Rotting bales will need to be replaced on a regular basis. Replace or repair damaged bales as needed. Repair washouts or other damages as needed. Sediment that accumulates in the BMP must be periodically removed in order to maintain BMP effectiveness. Sediment should be removed when the sediment accumulation reaches one-third of the barrier height. Sediment removed during maintenance may be incorporated into earthwork on the site or disposed at an appropriate location. Remove straw bales when no longer needed. Remove sediment accumulation, and clean, regrade, and stabilize the area. Removed sediment should be incorporated in the project or disposed of. References Stormwater Quality Handbooks - Site Best Management Practices (BMPs) Manual, State of California Department of Transportation (Caltrans), November 2000. 4 of 6 California Stormwater BMP Handbook January 2003

Straw Bale Barrier SE-9 January 2003 California Stormwater BMP Handbook 5 of 6

SE-9 Straw Bale Barrier 6 of 6 California Stormwater BMP Handbook January 2003