SCREENING CELL DESIGNS BASED ON SYNCHRONOUS MANUFACTURING

Similar documents
SUCCESSFUL AUTOMATION OF A LINE OF G.R.C. PANELS USING SIMULATION

Simulation and Implementation Study of Robust Drum-Buffer-Rope Management System to Improve Shop Performance

JOB SEQUENCING & WIP LEVEL DETERMINATION IN A CYCLIC CONWIP FLOWSHOP WITH BLOCKING

JOB SEQUENCING & WIP LEVEL DETERMINATION IN A CYCLIC CONWIP FLOWSHOP WITH BLOCKING

PRODUCT-MIX ANALYSIS WITH DISCRETE EVENT SIMULATION. Raid Al-Aomar. Classic Advanced Development Systems, Inc. Troy, MI 48083, U.S.A.

A PRODUCTION MANAGEMENT EXPERT SYSTEM DEVELOPED IN TIRS

A STUDY OF SYSTEM BALANCE AND CYCLE OPTIMIZATION FOR MULTI-OPERATIONAL EQUIPMENT AND ITS IMPLEMENTATION

Proceedings of the 2012 Winter Simulation Conference C. Laroque, J. Himmelspach, R. Pasupathy, O. Rose, and A. M. Uhrmacher, eds.

PRODUCTIVITY IMPROVEMENT IN APPLIANCE MANUFACTURING

Ch 15 Manual Assembly Lines

Drum-Buffer-Rope in PlanetTogether Galaxy

Integrating Lean Manufacturing and the Theory of Constraints. Mandyam M. Srinivasan

PULL PRODUCTION CYCLE-TIME UNDER VARYING PRODUCT MIXES

USING THE THEORY OF CONSTRAINTS TO PRODUCTION PROCESSES IMPROVEMENT

CHAPTER 4.0 SYNCHRONOUS MANUFACTURING SYSTEM

USING SIMULATION TO SUPPORT IMPLEMENTATION OF FLEXIBLE MANUFACTURING CELL. Kambiz Farahmand

SIMUL8-PLANNER FOR COMPOSITES MANUFACTURING

THE GOAL. Dr. Eliyahu Goldratt. Theory of Constraints

A DECISION TOOL FOR ASSEMBLY LINE BREAKDOWN ACTION. Roland Menassa

Utilization vs. Throughput: Bottleneck Detection in AGV Systems

Abstract number: SUPPORTING THE BALANCED SCORECARD FROM THE MANUFACTURING SYSTEM

THE ROLE OF SIMULATION IN ADVANCED PLANNING AND SCHEDULING. Kenneth Musselman Jean O Reilly Steven Duket

SOME TYPICAL REAL BENEFITS Some benefits I have seen companies achieve with simulation modeling as part of their approach include

Stochastic Modeling and Validation of Three-Tier Supply Chains Using Multiple Tools

Process design Push-pull boundary 35C03000 Process Analysis and Management Max Finne, Assistant Professor of Information and Service management

Ch 16 Automated Production Lines

Buffer size determination for drum-buffer-rope controlled supply chain networks. Zhaleh Parsaei and Nasim Nahavandi*

PULL PRODUCTION POLICIES: COMPARATIVE STUDY THROUGH SIMULATIVE APPROACH

Justifying Simulation. Why use simulation? Accurate Depiction of Reality. Insightful system evaluations

BUSINESS PROCESS MODELING WITH SIMPROCESS. Maya Binun. CACI Products Company 3333 North Torrey Pines Court La Jolla, CA 92037, U.S.A.

CHAPTER 1 INTRODUCTION

AUTOSCHED TUTORIAL. Bill Lindler. AutoSimulations 655 E. Medical Drive Bountiful, Utah 84010, U.S.A.

Operational Considerations for Mass Customisation

Curriculum Vitae Name Title Birth Date Gender Address Telephone Mobile Education Background Professional Experience

ISE480 Sequencing and Scheduling

Chapter 3 Assembly Systems. Screen Titles

A Roadmap Approach For Implementing Theory of Constraints In Manufacturing Organisations

A TUTORIAL ON ERGONOMIC AND PROCESS MODELING USING QUEST AND IGRIP. Deidra L. Donald

SimBa: A Simulation and Balancing System for Manual Production Lines

Jim Curry, OpStat Group Inc. January 17, OpStat

Benefits of Advanced Configuration and Simulation Study

International Journal of Technical Research (IJTR) Vol. 5, Issue 1, Mar-Apr 2016

Planning. Planning Horizon. Stages of Planning. Dr. Richard Jerz

Part 3 : 11/10/10 21:33:42. The four factors that derive from a company's distinctive competencies and which create competitive advantage are

Optimizing Inplant Supply Chain in Steel Plants by Integrating Lean Manufacturing and Theory of Constrains through Dynamic Simulation

CLASSIFICATION OF LAYOUT ( )

Manufacturing Resource Planning

Systematic Planning Layout and Line Balancing for Improvement in an Armoured Vehicle Manufacturing Plant

Methods of Solving Assembly Line Balancing Problem

Exploring simulation applications in education and research

Available online at ScienceDirect. Procedia CIRP 34 (2015 ) th International Conference on Axiomatic Design ICAD 2015

CONSTRAINT MODELING AND BUFFER MANAGEMENT WITH INTEGRATED PRODUCTION SCHEDULER

UNIT III GROUP TECHNOLOGY AND FMS

Development of Material Handling System in a Manufacturing Company

A COMPARISON OF JOHNSON S RULE AND TOC BASED SCHEDULING METHODOLOGIES

Influence of Worker Variability and Number of Workstations in. The effect on cycle time and in the work-in-process

MANUFACTURING SYSTEM BETP 3814 INTRODUCTION TO MANUFACTURING SYSTEM

Drum Buffer-Rope. Skorkovský. Based on : R. Holt, Ph.D., PE

Where to Use Automated Production Lines. Automated Production Lines. Benefits of Automated Production Lines. Automated Production Line - Defined

Risk Management User Guide

USING MODELING TECHNIQUES TO TEST THE FEASIBILITY OF SEGREGATING NON-GMO SOYBEANS AT COMMERCIAL ELEVATORS. Berruto Remigio(*) and Dirk E.

Integrating Cost, Capacity, and Simulation Analysis

Design of an Automated Transportation System in a Seaport Container Terminal for the Reliability of Operating Robots

Application of Stateflow Diagrams in Production Line Modeling

5.3 Supply Management within the MES

COMPARISON OF BOTTLENECK DETECTION METHODS FOR AGV SYSTEMS. Christoph Roser Masaru Nakano Minoru Tanaka

MODELLING AND SIMULATION OF PRODUCTION FLOW IN JOB-SHOP PRODUCTION SYSTEM WITH ENTERPRISE DYNAMICS SOFTWARE

Spatial decision support system for milk collection

Analysis of a Manual Mixed-Model Assembly Line in Food Processing Industry: A Case Study

Implementation of the Timetable Planning System STRAX/TPS in Denmark

Ch 19 Flexible Manufacturing Systems

Optimization of Cycle Time for Wire Harness Assembly Line Balancing and Kaizen Approach

Time study is not rocket science, but it is possible to get in big-time trouble with incorrect application. Briefly,

Simultaneous Perspective-Based Mixed-Model Assembly Line Balancing Problem

Simulation and Optimization of a Converging Conveyor System

Designing Guest Flow and Operations Logistics for the Dolphin Tales

Palletizers and Depalletizers

The five focusing steps of the Theory of Constraints have been successfully applied to the improvement

Set-up Reduction for Lean Cells and Multi- Machine Situations

ANALYZING PRINTED CIRCUIT BOARD ASSEMBLY LINES USING A PCB ASSEMBLY TEMPLATE. Pradip D. Jadhav Jeffrey S. Smith

Tecnomatix Plant Simulation

Introduction to Production Planning

MAINTENANCE CRITICAL ANALYSIS AND PRIORITY INDEX: A NEW MODEL FOR MAINTENANCE POLICY

Warehouse visual simulation applied to a practical layout (Brasil)

Deconstructing Bottleneck Shiftiness: The Impact of Bottleneck Position on Order Release Control in Pure Flow Shops

Proceedings of the 2010 Winter Simulation Conference B. Johansson, S. Jain, J. Montoya-Torres, J. Hugan, and E. Yücesan, eds.

A Machine Setup Model for TFT-LCD Cell Back-End Process

Chapter 1. Introduction. 1.1 Research motivation

SIMULATING BIOTECH MANUFACTURING OPERATIONS: ISSUES AND COMPLEXITIES. Prasad V. Saraph

OPERATIONS RESEARCH Code: MB0048. Section-A

Analysis of Significant Issues in Green Lean System in Small and Medium Scale Enterprises

INTERIM ADVICE NOTE 103/08. Advice Regarding the Assessment of Sites for Ramp Metering

Flexible Manufacturing Cell: development, coordination, integration and control

Balancing of hybrid assembly systems using a simulation approach

Optimize Assembly Production Line using Line Balancing

Manual Assembly Lines

USING SIMULATION TO UNDERSTAND CAPACITY CONSTRAINTS AND IMPROVE EFFICIENCY ON PROCESS TOOLS. Kishore Potti. Todd LeBaron

Operations and Supply Chain Simulation with AnyLogic

Integral Architecture for Organizational Systems Arquetipos

THE DETERMINATION OF THE OPTIMAL CONTROL LAW FOR A MANUFACTURING SYSTEM IMPLEMENTED ON FLEXIBLE LINE FMS 200

Transcription:

ASSEMBLY CELL SCREENING CELL ESIGNS BASE ON SYNCHRONOUS MANUFACTURING F. Javier Otamendi Universidad Rey Juan Carlos, Campus Vicálvaro Facultad de Ciencias Jurídicas y Sociales epartamento Economía Aplicada I Paseo Artilleros s/n 28032 Madrid, Spain E-mail: franciscojavier.otamendi@urjc.es KEYWORS iscrete Event, Capacity, Stock Management, TOC. ABSTRACT The combined analysis of an assembly cell using simulation models and theory-of-constraints is the aim of this article. The cell is a combination of a preparation and an operation phase which must keep the cycle time even under new product designs and demand mix. Simulation models are used to quantify the dynamic behaviour of the system under three configurations and theory-of-contraint concepts are used to illustrate the necessity to minimize the blockage of the input flows in order to guarantee the output flows. The chosen design synchronizes investments in equipment with the minimization of work-in-progress and the fulfilment of cycle times. INTROUCTION New product designs usually involve adjustments in the processes both in terms of layout and capacity. This is the case of an automobile assembly plant that needs to modify its layout in order to incorporate new tasks in one of the main cells of the overall process. The possibility of incorporating new different types of parts in the body puts too much stress in the assembly cell reaching the point where the throughput rate could be reduced considerably. In this particular case, part of the bodies will incorporate a new part, that need to be either manually or automatically assembled depending on the vehicle model. There exists the possibility however of preassembling parts while the vehicle body is waiting in the input buffer to the assembly cell. The main objetive is to guarantee the current cycle time both at the entrance and the exit of the pre-assembly cell, which should coincide with the cycle time of the assembly cell (Kim et al 2010). The layout of the current assembly process is depicted in Figure 1. After the bodies have gone through a series of operations, the rolling conveyor system moves the bodies to the buffer of the assembly cell. The input buffer is composed of a line buffer that may hold up to five units before it feeds three parallel lines of conveyors, in which several check operations are performed. Figure 1. Current layout PREVIOUS OPERATIONS Input Buffer Pre Assembly??? There exists then a transfer system that moves the bodies into the assembly cell. The selection of the next body is controlled by a powerful information system which is in charge of maintaining and defining the proper sequence into the assembly cell. The new product design has forced a redesign of the process, and that includes the necessity to perform preassembly operations in the buffer area, either manually, automatically or both. In fact, the aim of this study is to expand and redefine the waiting area. The reengineering task is the main topic covered in this article and includes the definition of different alternative layouts, their comparison using simulation and the selection in terms of the synchronization of cycle times as well as the minimization of the investment costs. Synchronous manufacturing (also known as Optimized Process Technology OPT, Theory of Contraints TOC or rum-buffer-rope) is a manufacturing philosophy that aims at balancing the flows of each of the stages of the process and not their capacity Proceedings 25th European Conference on Modelling and Simulation ECMS Tadeusz Burczynski, Joanna Kolodziej Aleksander Byrski, Marco Carvalho (Editors) ISBN: 978-0-9564944-2-9 / ISBN: 978-0-9564944-3-6 (C)

(Goldratt 2004). Using simulation to understand synchronous systems is a current line of research (Gonzalez et al 2010, Rhee et al 2010, Wang et al 2010). Section 2 includes a description of the three alternative designs that are going to be screened. Section 3 covers the quantitative simulation study, which includes the introduction of the available data, the definition of the decision criteria as well as the presentation of the results. Section 4 is then used to perform the comparison both quantitatively and qualitatively. Section 5 concludes. ESCRIPTION OF THE ESIGNS Option A (3+1) The first possibility is to provide room for an additional line in parallel to the current three (Figure 2). The new part will be assembled in the new line, so the bodies that need to incorporate the part will take this preassembly line composed of two stations: one manual and the other automatic. The rest of the bodies will use the original lines. In the new line some bodies will suffer a delay pre-assembly will take the second line and then the third before they reach the new buffer line. Figure 3. Layout for Option B The stress is now put on the bodies that will not go through the new operation. The feasibility of this design clearly depends on the production mix, as always, but even more so in this case. Option C The last option is to differentiate between the two types of bodies by including an additional line in which the manual assembly of parts could be performed, leaving the automatic pre-assembly for the last line (Figure 5). Figure 4. Layout for Option C Figure 2. Layout for Option A Of course, this layout releases stress out of the old lines, that have now less bodies to move. The quantitative study has to assess if the new line is able to cope with the demand for the new bodies. A capacity problem might appear also at the transfer line that is now four lines wide with the corresponding increase in movement and therefore in transfer times. The input throughput rate to the buffer system might also be in jeopardy if the new line is not able to cope with the new tasks, blocking the entrance and not allowing for the required cycle time at the assembly cell. Option B To provide flexibility and minimize the blocking probability at the entrance, the second option looks at the possibility of using the third old line also as an input buffer to the new line. This layout implies that the third line moves the bodies in the opposite direccion to the flow. If the new line is full, the bodies that require This extra investment with a higher cost will a priori allow for a higher throughput with more flexibility and less blockage at the entrance. SIMULATION OF THE ESIGNS Available data The first and most important piece of information is that of the demand. The reason for the study is the new product mix that has resulted from the possibility of including an additional part in the vehicle. This extra part might considerably vary the demand mix and therefore the capacity potential of the assembly and the pre-assembly cell. The demand in this case is not known but forecasted, and in fact, the reason for the study is to assess the demand (capacity) that each design might hold. On this screening phase, the total demand is maintained as its current level of 1 every 60 seconds (input and output cycle time) but with the mix included in Table 1 according to the new parts and resources that are needed to perform the pre-assembly.

Table 1. emand Mix TYPE PERCENTAGE MANUAL 9. AUTOMATIC 29.5% BOTH 3.8% NONE 57.7% The second set of data is that of the sequence. ue to technology restriction, only one manual operation might be performed every three bodies. Also, and due to set-ups only two robot operations could be performed on a row. Combining all the restrictions, a repeated sequence of 30 bodies has been used as a base sequence to perform the comparisons. Process and movement rates as well as distances are also needed. Conveyor speeds, set-up and assembly times are available in the process specifications. Breakdowns and maintenance data is also available as might be critical (Patti and Watson 2010). Output Criteria The alternative designs are going to be evaluated according to the following criteria: Percent Blockage at entrance Occupation of Entry Transfer Occupation of Automatic operation Occupation of Manual operation Occupation of Ouput Transfer Average and Maximum Number at Input Buffer before Entry Transfer Average and Maximum Number of Bodies in New Area Average Cycle Time Possible Flow Improvement = Idle Percentage (Starving) for Entry to Assembly These criteria relate to the evaluation of synchronous manufacturing (TOC). Under this philosophy, the cycle time has to correspond with the demand and it should provoke a tense, lean flow at each and every stage of the process. Then, the occupation of the all the processes should be balanced and about 9 of utilization, including set-ups and downtimes (Wu et al 2010). Results The results for each of the simulated options are shown in graphical form in Figure 5, Figure 6 and Figure 7, for Options A, B, and C respectively. The graphs correspond to the MsExcel interface that was built to easily transfer data to and from the simulator. Option A shows, as foreseen a very high occupation rate in the new line, which provokes a high blockage percentage at the entrance. The output rate (cycle time) however is enough to keep the pace of the assembly cell, which is the one that cannot cope with more work due to its high downtime. Option B puts too much stress on the old system, blocking the entrance above 5 of the time. The input cycle time dictates then the output cycle time, which is too high allowing for idle time in the assembly cell (1). Option C is more balanced with cycle times similar to those of the assembly cell, but occupation rates to close to 10. COMPARISON Table 2 summarizes the behaviour of the three designs. Buffer space refers to the maximum designed capacity whereas average and maximum bodies correspond to the dynamic behaviour. The cycle time corresponds to the throuput potential and the improvement to the blockage ratio, which could be eliminated through investments or further process improvement.. Table 2. Comparison of alternatives OPTION A B C BUFFER SPACE 31.0 31.0 36.0 AVERAGE BOIES 21.8 14.8 25.3 MAXIMUM BOIES 26.0 17.0 29.0 (seconds) 66.5 75.0 67.1 FEASIBLE IMPROVEMENT (%) 0.2 11.0 0.2 The main conclusions are the following Option A and Option C show similar cycle times. The call is to disregard Option B due to subpar cycle time. The cycle time is higher than the required 60 seconds, both consistent with the assembly cell time, in both Option A and Option C due to: o o Breakdowns of the assembly process Breakdowns of the manual and the robot operations The key controlling factor is therefore the cycle time of the following assembly system. The bottleneck is at the end following the theory of constraints (Goldratt 2004) Option A shows a lower average number of bodies when comparing to Option C (spaces 31 vs 36; average approxinmately 21 vs 25), so the solution is cheaper in terms of work-inprocess. Option A gives a feasible and viable solution with a lowest conveyor investment cost. Option A might be upgraded to option C if required in the future for capacity increase or additional works.

OPTION A: ORIGINAL - 3+1 NEW BLOCKAGE BUFFER AVG 2.64 9.70 BUFFER MAX 5.00 4.61 52.63 OL 0.60 3.00 NEW 5% 42.76 3.61 4 ROBOT 100.00 0.00 90.2% 0.92 ENTRY 100.00 17.74 10.92 5.85 77.57 OL NEW 3.78 4 52% Avg. Bodies 6.17 3.92 0.84 5.85 Capacity 7 6 6 6 MANUAL 100.00 Occupation 88. 65. 13.9% 97.5% 1.39 33.19 62.49 2.92 OL 0.99 0.43 NEW 1.42 2 Max. Bodies 0.21 70.9% 21.80 26.00 90.22 WHOLE 31 0.00 70. 83.9% 9 9.57 1 13.76 hours 1.91 shifts of 7.2 hours 95.57% of 2 shifts 66.50 seconds 4% 18% 77% 6 3 Figure 5. Results for OptionA OPTION B: SNAKE - 1+3 NEW BLOCKAGE BUFFER AVG 4.44 19.88 BUFFER MAX 5.00 0.08 46.69 OL 0.79 0.47 NEW 53.22 1.27 4 ROBOT 100.00 0.00 31.7% 66.88 ENTRY 100.00 15.74 47% 6.89 5.03 13.99 OL NEW 3.39 Avg. Bodies 6.89 0.92 0.51 3.61 5 Capacity 7 6 6 6 MANUAL 100.00 Occupation 98.4% 15. 8.5% 60. 44.23 29.45 23.36 2.95 OL 0.92 0.69 NEW 1.61 2 Max. Bodies 11.05 80. 14.80 17.00 1 80.05 WHOLE 31 0.00 47.7% 54.8% 8.91 9% 8 15.51 hours 2.15 shifts of 7.2 hours 107.72% of 2 shifts 74.95 seconds 14% 16% 67% 2 45% 29% Figure 6. Results for Option B OPTION C: EXTRA LINE - 2+3 NEW BLOCKAGE BUFFER AVG 2.98 10.46 BUFFER MAX 5.00 0.95 52.16 OL 0.79 2.17 NEW 46.89 2.96 5 ROBOT 100.00 0.00 59. 0.53 ENTRY 100.00 17.58 12.81 8.01 78.01 52% OL NEW 3.88 47% Avg. Bodies 6.91 5.90 2.12 5.89 Capacity 7 6 10 6 MANUAL 100.00 Occupation 98.8% 98. 21.2% 98.2% 0.98 32.90 63.43 2.69 OL 1.18 0.36 NEW 1.54 2 Max. Bodies 0.20 77. 25.32 29.00 89.43 WHOLE 36 0.00 70. 80.6% 10.37 9 13.88 hours 1 1.93 shifts of 7.2 hours 96.42% of 2 shifts 67.09 seconds 4% 18% 77% 3 6 Figure 7. Results for Option C

CONCLUSIONS The simulation study shows the weak points of the assembly process, pinpointing the necessity to address a quality assurance, balancing and improvement process. The applicability of theory-of-constraints concepts in which there has to be a synchronization between input and output flows is also highlighted. Both Options A and C also follow TOC principles by making the bottleneck be the last stage, that of the final assembly process. Work-in-process is optimum also as a by-product. REFERENCES Goldratt, E.M. 2004. The Goal. North River Press. Gonzalez-R PL, Framinan JM, Ruiz-Usano R. 2010. A Multi-Objective Comparison Of ispatching Rules In A rum-buffer-rope Production Control System. International Journal Of Computer Integrated Manufacturing 23(2), 155-167. Kim S, Cox JF, Mabin VJ. 2010. An Exploratory Study Of Protective Inventory In A Re-Entrant Line With Protective Capacity. International Journal Of Production Research 48(14), 4153-4178. Patti AL, Watson KJ. 2010. owntime variability: the impact of duration-frequency on the performance of serial production systems, International Journal Of Production Research 48(19), 5831-5841. Rhee SH, Cho NW, Bae H. 2010. Increasing The Efficiency Of Business Processes Using A Theory Of Constraints, Information Systems Frontiers 12(4), 443-455. Wang YH, Cao J, Kong LX. 2009. Hybrid Kanban/Conwip Control System Simulation and Optimization Based on Theory of Constraints, 2009 IEEE International Conference On Intelligent Computing And Intelligent Systems, Proceedings, VOL 2, 666-670. Wu HH, Chen CP, Tsai CH, Yang, CJ. 2010. Simulation And Scheduling Implementation Study Of TFT-LC Cell Plants Using rum-buffer-rope System. Expert Systems With Applications 37(12), 8127-8133. AUTHOR BIOGRAPHIES JAVIER OTAMENI received the B.S. and M.S. degrees in Industrial Engineering at Oklahoma State University, where he developed his interests in Simulation and Total Quality Management. Back in his home country of Spain, he received a B.S. in Business Administration and a Ph.. in Industrial Engineering. He is currently a simulation and statistics consultant and university professor at the Rey Juan Carlos University in Madrid.