TPP-GIP Integration Proposal November 30, 2011

Similar documents
First Solar Proposal Integration of Transmission Planning Process and Generation Interconnection Procedures (TPP-GIP Integration)

Stakeholder Comments Template. Generator Interconnection Procedures Phase 3 ( GIP 3 ) Issue Paper, posted March 1, 2012

Resource Adequacy Deliverability for Distributed Generation DG Deliverability Assessment Results

California ISO Revised Draft Final Proposal IPE 2015

Integration of Transmission Planning and Generation Interconnection Procedures

Business Practice Manual for The Transmission Planning Process

Business Practice Manual for Distributed Generation Deliverability. Version

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

CAISO Resource Adequacy Deliverability for Distributed Generation

Advancing Renewable Alternatives

CAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes)

Appendix 1 PRELIMINARY DELIVERABILITY BASELINE ANALYSIS STUDY REPORT

A. RECOMMENDATIONS ON PROPOSED RELIABILITY PROJECTS

Business Practice Manual for the Transmission Planning Process

1. Is there a preference between MW and MWh? RPS need for San Diego Gas & Electric is based upon a percentage of retail sales, which is in MWh.

Resource Adequacy Deliverability for Distributed Generation DG Deliverability Assessment Results

Developing a Comprehensive Methodology for Valuating Transmission Impacts for New Generation Developments

What You Need to Know Before Requesting Interconnection

CAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes)

CHAPTER 6 - Load Forecast & Resource Plan

Stakeholder Comments Template

Jan Strack and Huang Lin March 14, 2017

Interconnection Specialists ensure all projects are treated in accordance with the current applicable tariff provisions

Stakeholder Comments Template

Renewable Auction Mechanism (RAM): New Procurement Tool for Distributed Renewable Generation National Summit on RPS

PJM Planning Process Strawman

DRA Comments To The CAISO On Its Proposed Generator Interconnection And Deliverability Study Methodology. Stakeholder Comments Template

Deliverability for Distributed Generation. Proposal for Complying with 11/16/12 FERC Order

Revised Transmission Planning Process. Complete Final Proposal

Is FERC s Generator Interconnection Policy really conducive to efficient generation development?

Generator Interconnection Driven Network Upgrade Cost Recovery. Draft Final Proposal

Opinion on the Integration of Transmission Planning and Generator Interconnection Procedures.

(NOT CONSOLIDATED) And Related Matters. Application Application

Recommendations on the TPP policy and economic assessment by TPP topic

PSCO QUEUE REFORM STAKEHOLDER MEETING #2 JUNE 19, 2018 LIAM NOAILLES

Photovoltaic Program Power Purchase Agreements Request for Offers 2012 Solicitation. Participants Forum. October 12, 2012

Addendum for Clusters 10 and 11

Storage as a Transmission Asset:

Re: Large Generator Interconnection Procedures (LGIP) - Generator Queuing Practices Docket No. AD

Stakeholder Comments Template

CAISO s Plan for Integration of Renewable Resources

California leads the nation in the transition to a reliable,

Roadmaps for Demand Response & Storage

Imperial County Transmission Consultation Current Resource Deliverability Capabilities from Imperial Valley

Flexible Resource Adequacy Criteria and Must Offer Obligation Phase 2. Working Group Meeting. Karl Meeusen, Ph.D. June 18, 2018

January 9, Tariff Amendment to Implement 2018 Expedited Interconnection Process Enhancements

Expanding Transmission Capacity: Options and Implications. Jennifer Curran Director Transmission Strategy April 30, 2009

Generator Interconnection Procedures Overview

Storage as a Transmission Asset:

Stakeholder Comments Template. Subject: SCE Comments on Dynamic Transfer Revised Final Draft 2/18/11

NPCC 2009 New England Interim Review of Resource Adequacy. NPCC 2009 New England Annual Interim Review of Resource Adequacy

Coordinated Planning / Deliverability Studies

Business Requirements Specification

Rice Solar Energy Project

Senate Bill 350 Study

Business Requirements Specification

Generator Interconnection Process. Wholesale Distribution Overview

TDI-NE Responses to 83D Questions December 28, b. Type of Organization (Public/Industry/Advocacy/Other)

Load Serving Entity Definition Refinement Draft Final Proposal

Renewable Market Adjusting Tariff (ReMAT) Feed-In Tariff (FIT)

Regional Resource Adequacy Draft Regional Framework Proposal. Stakeholder Meeting December 8, 2016

All Source Request for Proposals Interim Summary

ISO Transmission Planning Process. Supplemental Sensitivity Analysis: Benefits Analysis of Large Energy Storage

Nancy Rader, Executive Director Dariush Shirmohammadi, Transmission Advisor California Wind Energy Association. August 9, 2011

Comments of the California Wind Energy Association on CAISO s August 23, 2007 Draft Proposal for Remote Resource Interconnection.

Summary on Initiative Direction

Transmission Planning Process Phase 3 Competitive Solicitation

DRAFT Work in Progress CAISO Integration of Renewable Resources Program (IRRP) - High-Level Program Plan -

OPPORTUNITIES AND BARRIERS. EESI Briefing. June 13, 2008

Page 1

Transmission Expansion Advisory Committee

Transmission Economic Assessment Methodology (TEAM)

Cluster Study Process

BPA Comments on Appendix H. Pacific Northwest California Transfer Increase Informational Special Study

Electric Storage as a Transmission Solution in the MTEP Reliability Planning Process. Planning Advisory Committee September 26, 2018

Contents. DRAFT Capacity Deliverability Fact Finding Summary Report

PG&E s WDT Interconnection Reform Principles Document

Business Practice Manual for Reliability Requirements. Version 34

Making Sense of U.S. Energy Markets

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION TRACK 2 TESTIMONY

Storage as a Transmission Asset Stakeholder Comment Template

the most promising locations for new renewables in the Imperial CREZ.

Rule 21 Tariff / Process Overview 6/17/2015

Develop PJM Criteria/Guidelines for Assessing End of Life Transmission Facilities

Stakeholder Comments Template

Forward to the Revised Draft Transmission Plan

Maine Power Express, LLC Response to Request for Comments December 28, 2016

New York CES: Renewable Energy Standard Underlying Fundamentals

Proposal Concerning Modifications to LIPA s Tariff for Electric Service

Design Considerations for an Alberta Capacity Market

Southern California Edison Approach to Renewable Integration June 7, 2011

Resource Adequacy Compliance Overview. Candace Morey, CPUC-Legal Division Meredith Younghein, Jaime Gannon CPUC-Energy Division

Market Responsive Pricing Policy Mechanism Brief

Growing Wind. Final Report of the NYISO 2010 Wind Generation Study. John Adams Principal Electric System Planner New York Independent System Operator

Power Integrated Resource Plan PWP Presentation

Distributed Energy Resources (DER) Queue Management

Stakeholder Comments. 2012/2013 Transmission Planning Process. Presentations from December 11 and 12 meetings

Comments of Pacific Gas & Electric Company Flexible Resource Adequacy Criteria and Must Offer Obligation Phase 2 Revised Straw Proposal

2007 NYSRC RELIABILITY COMPLIANCE PROGRAM

Update on the 2015 Special Study

Transcription:

TPP-GIP Integration Proposal November 30, 2011

Major Elements of Proposal Demand-Based Planning of Network Upgrades in the TPP Synchronize GIP, TPP and the LSE Procurement Processes Allocation of Deliverability Capacity by LSEs Refundable Interconnection Financial Security (IFS) Voluntary Transition for Prior Queued Projects with Refundability of IFS Appropriate Treatment for Prior Queued Projects That Do Not Transition Integrated TPP-GIP: Step-by-Step 2

Demand-Based Planning of Network Upgrades in the TPP Plan upgrades for forecasted generation, not the whole queue Network Upgrades financed upfront by PTOs, not interconnection customers. Considerably less transmission planning work Fixes the following defects in today s TPP-GIP transmission plan: Assumes too many new generators Indicates that too many transmission upgrades are needed Interconnecting generators have to post large financial security for upgrades of dubious need, which will not be completed for 7-10 years 3

Synchronize GIP, TPP and LSE Procurement Processes LSE procurement forecasts lead to resource scenarios for the TPP The TPP produces the TRCR used in LSE resource procurement Signed PPAs provide the input assumptions for GIP Phase 2 TPP approved transmission plan includes Planned Deliverability Allocations for LSEs Greatly reduces uncertainty in demand-based transmission planning and LSE procurement decision-making 4

Allocation of Deliverability Capacity by LSEs LSEs would get a deliverability allocation to procure all new projects, whether they already have IAs or not LSEs are responsible for taking steps to gain Planned Deliverability Allocations in the TPP and procuring resources that can make use of those allocations The form of PPAs would be revised so that the sellers no longer have any responsibility for achieving Full Capacity Deliverability Status (FCDS) or for the network upgrades needed for FCDS. Scarce transmission will go to the least cost-best fit resources rather than the first in the queue. New entrants will have equal opportunity to access deliverability upgrades if they get PPAs. LSEs will know with much more certainty the timing and cost of delivery upgrades 5

Refundable Interconnection Financial Security If deliverability upgrades will no longer be assigned to the queue, there is no need to make IFS non-refundable to reduce the queue (or have the second posting of IFS) Decreased resource development costs Developers could market the same queue position indefinitely, as long as they pay for ongoing study costs 6

Voluntary Transition for Prior Queued Projects with Refundability of IFS Existing queued projects, even those with signed IAs, could volunteer to give up their claims to assigned delivery upgrades and let LSEs assign the associated deliverability in return for their IFS becoming fully refundable PPAs for those resources would be amended, without reopening negotiations or modifying other terms, to relieve sellers who transition from any responsibility for achieving FCDS or for the network upgrades necessary for FCDS Volunteers can shed expensive long-term upgrades, potentially get delivery on planned near-term upgrades, and get fully refundable IFS. LSEs do not have to wait for expensive, long term upgrades to be built, or for queue attrition to demonstrate that upgrades are not needed, to make the resources they procure deliverable. 7

Appropriate Treatment for Prior Queued Projects that Do Not Transition An LSE may not count an existing queued project with FCDS toward its Resource Adequacy requirement unless it has included that resource in its forecast submitted for the TPP assumptions and has received sufficient Planned Deliverability Allocation and Actual Deliverability Allocation to accommodate that resource. Appropriately recognizes that the ultimate purpose of FCDS is for an LSE to satisfy its RAR and that a generator s achievement of FCDS is of no use or meaning if the generator does not have a PPA. Prevents LSEs from gaming the new TPP-GIP rules by counting a resource for Resource Adequacy that it has not included in its resource forecast for the TPP. 8

Integrated TPP-GIP Proposal Step by Step ISO: Previous year s TPP results & TRCR LSEs: Forecasted resources Ceilings and Floors for each area i TPP Resource Scenarios ii Consolidated Procurement Ceiling/Floor forecast for each area PTOs & CAISO: Transmission Planning Studies - TTP Preliminary Transmission Plan includes network upgrades for each scenario Least Regrets Category 1 Second Tier Category 2 - GIP Phase 1 Results Interconnection Facilities Costs Plan of Service Network Upgrades Costs DFAX for Delivery Network Upgrades CAISO & PTOs: Revised TRCR with LSE preliminary Planned Deliverability Allocations iii CAISO & PTOs: Transmission Planning Studies GIP Phase 2 Study Results Final TPP Transmission Plan Revised TRCR Final LSE Planned Deliverability Allocations Regulatory Authorities: Approve PPAs LSEs: Resource Procurement Sign PPAs CAISO & PTOs: Update TPP Preliminary Transmission Plan (update Category 1 and Category 2) project lists, TRCR and LSE preliminary Planned Deliverability Allocations LSEs: Resource Procurement Select Short List - Identify gen projects not previously anticipated - Revise resource forecast floors and ceilings for each area CAISO, PTOs & ICs: Sign GIAs CAISO Board approves major Category 1 Network Upgrades TOs design, procure and construct approved transmission projects LSEs designate NDRs from their operational QNDRs/CNDRs as completed upgrades enable Actual Deliverability Allocations iv TPP protects Actual Deliverability Allocations 9

Integrated TPP-GIP Proposal Step by Step: Footnotes i Forecasts will include all new generators, with or without PPAs or GIAs, except those under active construction, which are automatically included in the TPP. ii The TPP resource scenarios will be derived from LSE resource forecasts (i.e. the area floors and ceilings) with input from the states (e.g. CEC and PUCN). The sum of the LSE resource ceilings assumed for each area will need to represent more than 33% RPS (e.g. 50% RPS), to reflect uncertainty in the outcome of LSE procurement activities, including bid pricing and project viability. The scenarios will include LSE preliminary Planned Deliverability Allocations for each area. iii Consistent with the TPP resource scenarios, the TRCR would state the LSE Planned Deliverability Allocation ceilings for each area. The allocations would apply to both previously signed PPAs and projects not yet signed. Actual allocations of deliverability capacity to LSEs occur as the required Delivery Network Upgrades and planned resources reach commercial operation. iv To the extent that an LSE signs PPAs with QNDRs (Queue-conditional Network Delivery Resources) and CNDRs (Conditional Network Delivery Resources) in an area that total more than the LSEs Planned Deliverability Allocation, the LSE will not be able to designate the excess amount of those resources as NDRs (Network Delivery Resources) or count them toward meeting its Resource Adequacy Requirement. This applies even for a resource that has Full Capacity Deliverability Status under the existing GIP. 10

Clean. Affordable. Sustainable. Global. Copyright 2010, First Solar, Inc. First Solar Confidential & Proprietary 11