Temporary Wiring Practices And Guidelines For NECA. National Electrical Contractors Association Omaha, Nebraska

Similar documents
Temporary Wiring. Low-Voltage Electrical Safety Orders

Continuing Education Credits. Learning Objectives. Jim Dollard. OSHA Fine Structure. Reasons to get it right! 5/27/2014

2. Article (A) Delete the measurement of 6 feet 7 inches and insert: 66 inches (5 feet 6 inches).

Delaware State University

EFFECTIVE DATE: November 1, 2011, unless a later date is cited at the end of a section. [ NMAC - Rp,

Hazards. Hazards. Hazards. Effects on the Body. GA Tech Electrical Safety Presentation

MECKLENBURG COUNTY. Land Use and Environmental Service Agency Code Enforcement 5/12/10 ELECTRICAL CONSISTENCY MEETING. Code Consistency Questions

DEVICES AND LUMINAIRES

Inspection Guide for PV Systems in One- and Two- Family Dwellings (For Rooftop Photovoltaic Systems meeting the Standard Plan)

MECKLENBURG COUNTY. Land Use and Environmental Service Agency Code Enforcement 11/10/10 ELECTRICAL CONSISTENCY MEETING. Code Consistency Questions

DEVICES AND LUMINAIRES

OVERHEAD SERVICES - SECONDARY

2008 NEC Guide Lines for Home Owner Doing Electrical Work on their Property

SECTION BASIC ELECTRICAL REQUIREMENTS

Click here to get back to 2011 NEC Code Updates Part 1

MECKLENBURG COUNTY. Land Use and Environmental Service Agency Code Enforcement 7/14/10 ELECTRICAL CONSISTENCY MEETING. Code Consistency Questions

(Condensed from National Electric Code)

EFFECTIVE DATE: July 1, 2008, unless a later date is cited at the end of a section. [ NMAC - Rp,

TABLE OF CONTENTS CHAPTER 2 WIRING AND PROTECTION CHAPTER 1 GENERAL RULES... 19

WESTERN CONNECTICUT STATE UNIVERSITY ELECTRICAL SAFETY PROCEDURE S-109

DEPARTMENT OF PLANNING SERVICES BUILDING INSPECTION DIVISION 1555 N 17 TH AVENUE, GREELEY, CO (970)

NEC 2017 Code Changes Chapter 1 - General

SERVICE ENTRANCES. OPPD S Electrical Service Designer (ESD) shall designate the Point Of Entrance.

FOR ALL STAKEHOLDERS TO HAVE A SUCCESSFUL PROJECT

SERVICES - SERVICE EQUIPMENT- PANELBOARDS

The following chapters or articles of the New Jersey electrical subcode are amended as follows:

CONSISTENCY MEETING DEPARTMENTAL GOALS: % 1 DAY TURN AROUND % CONTRACTOR PASS RATE QUALITY INSPECTIONS! EXCELLENT CUSTOMER SERVICE!

The Canadian Electrical Code (Saskatchewan Amendments) Regulations, 1999

Basic Requirements for Residential Electrical Installations

Ground Fault Circuit Interrupters (GFCI) & Assured Grounding Program

PHOTOVOLTAIC (PV) SUBMITTAL REQUIREMENTS

* All equipment grounding conductors shall be tested for continuity and shall be electrically continuous.

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4.

SECTION BUSWAYS

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:

WIRING METHODS CHAPTER 38

SECTION GROUNDING

A. Provide a complete Distribution Panelboard system as indicated on the drawings, and as specified herein.

METERING INSTALLATION

Sections through of Chapter 5 of the Victoria City Code are amended to read as follows: ARTICLE IX. NATIONAL ELECTRICAL CODE

NORTHEASTERN REMC ELECTRIC STANDARDS MANUAL

DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR S OFFICE CONSTRUCTION CODE

Chapter ELECTRICAL CODE

DOWNTOWN UNDERGROUND NETWORK SECONDARY SERVICES GUIDELINES

Article 10 - ADMINISTRATIVE SECTION

INFORMATION BULLETIN

SECTION GENERAL ELECTRICAL REQUIREMENTS PART 1- GENERAL

This product specification is written according to the Construction Specifications Institute MasterFormat, 2014 Update.

2003 International Residential Code ELECTRICAL PROVISIONS ONLY October 2005 EDITORIAL CHANGES SEVENTH PRINTING

Top Changes 2014 NEC

About This Textbook... xvii About the National Electrical Code...xxi About the Author... xxv About the Illustrator... xxvi About the Team...

City of Santa Monica Building and Safety Division

DIVISION 16. Electrical Specifications

SECTION GROUNDING AND BONDING

CONTENTS. B. System Design and Performance Requirements

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4.

Please check with your local inspection authority for any additional requirements before installation.

Chapter ELECTRICAL CODE*

PORT OF SAN FRANCISCO ELECTRICAL CODE. Based on the 2016 California Electrical Code

Wyoming Division IAEI Annual Meeting/Seminar 2003 Code Panel Questions Answers in BOLD, using 2002 NEC

ELECTRICAL SAFETY Information Bulletin

A. Hazardous Areas: Hazardous areas as defined by the NEC as Class I, Division 1, Group D, or Class I, Division 2, Group D hazardous are as follows:

Permitting and Inspecting PV Systems. PV Codes and Standards 101. Photovoltaic System Basics

St. Clair County Electrical Code Regulations

Technical Specifications

OVERHEAD SERVICES - RESIDENTIAL & GENERAL SERVICE. See Chapter 3, Section 3.01 for more information about point of entrance (POE).

A. Section includes busway and fittings including plug-in units.

SECTION (Master Template Final-05) ELECTRICAL BOXES. A. Provide boxes for electrical equipment and wiring devices as follows:

(3) 1/2 INCH CONDUIT BOTTOM, (2) 3/4 INCH CONDUIT BOTTOM, (8) 1 INCH CONDUIT SIDES Box

This product specification is written according to the Construction Specifications Institute MasterFormat, 2014 Update.

Residential Rooftop PV

A. All materials shall be tested and listed by an OSHA approved Nationally Recognized Testing Laboratory (NRTL).

ELECTRIC METERING GENERAL

MANUFACTURING TECHNICAL INSTRUCTIONS SAFETY Subject: DESIGN, MAINTENANCE AND INSPECTION OF SECONDARY ELECTRICAL DISTRIBUTION SYSTEMS

Homeowner electrical wiring guide. Including the 2015 Canadian Electrical Code amendments

NEC 2014 Code Changes

8461C 4SQ, 1"RSD Rndopnw/Ers CVR

SECTION SECONDARY UNIT SUBSTATIONS

Manitoba Electrical Code

DESIGN GUIDELINES WIRING AND CONDUITS PAGE 1 of 7

Appendix C - International NEC Electric Code Amendments

UNDERGROUND SERVICES SECONDARY

Steel Square Box, Height 4 Inch; Width 4 Inch; Depth 1-1/2 Inch; Capacity 21 Cu Inch; 17 Knockout(S); Knockout Location (5) Bottom, (12) Side

Inside This Issue Temporary Wiring in Construction Update on Fall Protection Heat Stress Top 10 Construction Violations Fatalities

a) Line and load compartments must be separated by a stable barrier.

CHAPTER 29 PLUMBING SYSTEMS

MUSCO ENGINEERING ASSOCIATES Consulting Engineers

2008 Port of San Francisco Electrical Code February 2010 edition. February 2010 edition of the 2008 Port of San Francisco Building Code

NORTHEASTERN REMC ELECTRIC STANDARDS MANUAL

Replace 210.8(a)(7) with: Sinks. Where receptacles are installed within 6 feet of the outside edge of a sink. Page 1 of 5

Grounding Conductor & GFCI Employee Protection Program

CAL/OSHA ELECTRICAL HIGH VOLTAGE

1. The plan needs to show compliance with the 2013 CEC, 2013 CBC and 2013 CRC. [ CBC] RESPONSE:

SECTION A. ASTM B3 - Standard Specification for Soft or Annealed Copper Wire; 2013.

Kaf-Tech Product Specification

UNDERGROUND SERVICES - GENERAL SERVICE AND MULTI-UNIT RESIDENTIAL

SECTION GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY

HOMEOWNER PERMITS AND ELECTRICAL WIRING GUIDE

New Jersey Chapters July NEC updates. The Association of Electrical and Medical Imaging Equipment Manufacturers

PENNSAFE BUILDING INSPECTION SERVICES LLC PERMIT APPLICATION

Transcription:

Temporary Wiring Practices And Guidelines For NECA National Electrical Contractors Association Omaha, Nebraska

Table of Contents I. Planning II. Lighting and Power III. Maintenance IV. Inspections V. Routing and Moving VI. Removal A) Application of National Electrical Code Rules 2 B) Temporary Wiring Articles NEC Handbook 3 C) Overhead/Underground-Services Installation Diagrams 3-5 D) Jobsite Trailers 6 E) Panel board Covers 6 F) Temporary Feeders and Branch Circuits 7 G) Splices 8 H) Terminations at Cabinets and Boxes 8 I) Ground-Fault Protection for Personnel 8-9 J) Branch Circuits for Receptacles and Lighting 9 K) Weatherproof Covers 8 L) Temporary Lighting Fixtures & Support 10 M) Example Installation Pictures 10-20 N) Quiz Temporary Wiring Practices and Guidelines 21 O) Acknowledgement Form 22 Temporary Wiring Practices and Guidelines for NECA Omaha, Nebraska have not been processed in accordance with NFPA regulations governing committee projects. The text and commentary is not the official position of the NFPA or any of its committees and shall not be considered to be a formal interpretation of the meaning or intent of any specific provision or provisions of the 2008 edition of the NFPA National Electrical Code.

I. Planning Plan your work. Failing to plan is essentially planning to fail. Temporary wiring requires planning. There are serious responsibilities associated with installing and maintaining temporary electrical wiring on construction sites. Temporary wiring must meet the requirements of the National Electrical Code (NEC) and Occupational Safety and Health Administration (OSHA). NEC Article 590 provides minimum requirements for installing temporary electrical power and lighting. Overcurrent protection and conductor sizing must meet the NEC requirements in Article 240 and 310 respectively and grounding and bonding must comply with Article 250. The wiring should be adequately supported and secured and protected from physical damage as practical. NFPA 70E provides the requirements for electrical workplace safety, this is the standard used by OSHA. II. Lighting and Power We utilize GFCI protection as our Temporary Power Grounding Program. Use GFCI protection for all temporary lighting. o If temporary lighting is plugged in, use a single outlet, protected by GFI Breaker. o Do not hang temp lighting by the conductors. Support stringers by screw shell. o Replace missing or broken bulbs and bulb guards. Must use junction boxes for splices. o Provide physical protection for wiring where it is subject to abuse or where it enters a box; use connectors. III. Maintenance Temporary wiring tends to get abused, sometimes severely during the course of construction. The temporary wiring should be maintained in a safe, code-compliant condition throughout the duration of the project. This aspect of temporary wiring is usually overlooked until something happens. Damaged circuits should be repaired or replaced. IV. Inspections: Maintain a log of weekly GFCI testing. Maintain a log of weekly temporary lighting inspections. Maintain a log of weekly ladder inspections. Make sure breakers are identified in the temporary panels. Label breakers not in use as spare. Make sure all openings in temp panels are closed, breaker blanks, KO seals. If a City or County Electrical Inspection is required, we, (the electrical contractor), must request a wiring permit to install the temporary service. This wiring permit is usually separate from the building wiring permit. The local electrical City or State inspector authorizes the electric utility to connect power to the temporary service when the installation is found to comply with the provisions of the NEC. Electrical inspectors tend to focus on the service and rarely look at temporary branch circuits for lighting and power even during rough-in inspections on the building wiring. 1

V. Rerouting and Moving Where circuits for power and lighting have to be extended or re-routed to accommodate the various crafts or phases of construction, it should be done with the power disconnected and locked out. Circuit directories are a challenge to create and maintain on construction projects, but are essential and a requirement for OSHA. Always follow the applicable electrical safety rules when working with temporary wiring or permanent wiring installations. The hazards are essentially the same. VI. Removal The NEC requires temporary wiring to be removed when the project is completed. Notice that this requirement apples to all temporary wiring and does not distinguish between accessible and inaccessible wiring. See NEC 590.3(D) for installation removal requirements. A. Application of National Electrical Code Rules Temporary wiring and installations are covered in article 590 of the 2008 National Electrical Code or NEC. Chapters 1 through 4 generally apply to all electrical installations. Chapters 5, 6, and 7 either supplement or modify Chapters 1 through 4. In some cases, the rules in Temporary Wiring modify the requirements of Chapters 1 through 4. The appropriate location for Temporary Wiring is outside Chapters 1 through 4 Article 590. 2

The most important single thing to keep in mind about all of this is that if it isn t specifically modified by Article 590, the rules in Chapters 1 through 4 have full force and effect. For example there is nothing in Article 590 that modifies any of the grounding rules in Article 250, so all of Article 250 applies to temporary wiring. We see this statement in Section 590.2(A): See Below B. Temporary Wiring Articles - NEC Handbook Article 590.2(A) Other Articles. Except as specifically modified in this article, all other requirements of this Code for permanent wiring shall apply to temporary wiring installation. Article 590.2(B) Approval. Temporary wiring methods shall be acceptable only if approved based on the conditions of use and any special requirements of the temporary installation. Article 590.3(A) During the Period of Construction. Temporary electric power and installations shall be permitted during the period of construction, remodeling, maintenance, repair, or demolition of buildings, structures, equipment, or similar activities. Article 590.3(B) 90 Days. Temporary electric power and lighting installations shall be permitted for a period not to exceed 90 days for Holiday decorative lighting and similar. Article 590.3(C) Emergencies and Tests. Temporary electric power and lighting installations shall be permitted during emergencies and for tests, experiments, and development work. Article 590.3(D) Removal. Temporary wiring shall be removed immediately upon completion of construction or purpose for which the wiring was installed. Article 590.4(A) General. Services shall be installed in conformance with Parts 1 through VIII of article 230, as applicable. Article 240 Overcurrent Protection Article 250 Grounding and Bonding Article 310 Conductors for General Wiring C. Services Services shall be installed in conformance with Article 230. This is the statement made in Section 590.4A. No exceptions or modifications allowed. A service is a service is a service. The same hazards exist on a temporary electrical service as a permanent electrical service. Overhead conductor clearances, equipment ratings, grounding electrodes, location, and protection from physical damage are some of the service installation concerns. 3

Typical Overhead Temporary Service Typical Underground Temporary Service Panelboard enclosure must be suitable for the environment. If installed outdoors, either a NEMA 3 or 3R must be used, unless a weather resistant structure is utilized. 4

Typical Underground Temporary Service Temporary Wiring Practices and Guidelines Panelboard enclosure must be suitable for the environment. If installed outdoors, either a NEMA 3 or 3R must be used, unless a weather resistant structure is utilized. Note: Some inspectors and utilities will not permit connection of the grounding electrode conductor in the metering equipment. It is individual company policy that the connection shall be made at any accessible point from the load end of the service drop or service lateral to and including the terminal or bus to which the grounded service conductor is connected at the service disconnecting means. An additional benefit of this method is that it is more readily accessible for the inspector. 250.24(A) (1) General. The grounding electrode conductor connection shall be made at any accessible point from the load end of the service drop or service lateral to and including the terminal or bus to which the grounded service is connected at the service disconnecting means. Despite the language of 250.24(A) (1), you must follow local rulings. 5

D. Jobsite Trailers Jobsite trailers aren t mentioned in Article 590; they re discussed in Mobile Homes, Manufactured Homes, and Mobile Home Parks Article 550. Section 550.4(A). Mobile Home not intended as a Dwelling Unit for example, contractor s onsite offices, etc. shall not be required to meet all of the provisions of Article 550 pertaining to the number and capacity of circuits. But if supplied from a 120-volt or 120/240-volt ac power supply, they are required to meet all of the other applicable requirements of Article 550. Section550.32 (A). Mobile Home Service Equipment. The service equipment for the mobile home (job-site trailer) must be located adjacent to the mobile home and not mounted on the mobile home (job-site trailer). It must be located in sight from and not more than 30 feet (9.0 m) from the exterior wall of the mobile home. Service equipment is permitted to be located elsewhere on the premises provided a disconnecting means suitable for use as service equipment is located in sight from and not more than 30 feet from the mobile home. Section 550.10(1) The feeder to the job-site trailer is required to consist of four continuous, insulated color-coded conductors, one of which is required to be an equipment-grounding conductor. E. Panelboard Covers It isn t hard to keep the cover on a temporary power panelboard. The real challenge is keeping covers on permanent panelboards during construction. Branch circuits are continuously being pulled in and terminated, and permanent panels inevitably supply temporary lighting and receptacle outlet circuits. Cardboard or Wood isn t the solution! 312.10(C) Nonmetallic Cabinets. Nonmetallic cabinets shall be UL listed. 110.3(B) Installation and Use. Listed or labeled equipment shall be installed and used in accordance with any instructions included in the listing or labeling. When utilizing permanent panelboards, the permanent dead front and permanent panel cover must be used. 6

F. Temporary Feeders and Branch Circuits Use of individual conductors for temporary lighting was banned after a case where a fatal accident occurred in Harrisburg, Pennsylvania when a worker on a scaffold was killed when one of the metal studs he was removing cut into a single conductor which energized the metal stud. Temporary feeders are permitted to be cable assemblies, (including Type NM and NMC cables) multiconductor cords, or single-conductor cords Section 590.4(B). 590.4(B) Feeders. Overcurrent protection shall be provided in accordance with 240.4, 240.5, 240.100, and 240.101. For the purpose of this section, Type NM and Type NMC cables shall be permitted to be used in any dwelling, building, or structure without any height limitation or limitation by building construction type and without concealment within, floors, or ceilings. Flexible cords used as feeders must be identified for hard or extra-hard usage according to Table 400.4. Individual conductors, as described in Table 310.13, are not permitted as open conductors but must be part of a cable assembly or used in a raceway system. 590.4(C) Branch Circuits. All branch circuits shall originate in an approved power outlet or panelboard. Conductors shall be permitted within cable assemblies or within multiconductor cord or cable of a type identified in Table 400.4 for hard usage or extrahard usage. 590.4(J) Support. Cable assembles and flexible cords and cables shall be supported in place at intervals that ensure that they will be protected from physical damage. Support shall be in the form of staples, cable ties, straps, or similar type fittings installed so as not to cause damage. Romex is not permitted to be in direct contact with building steel. When necessary, PVC sleeves or tie wrap cradles are to be used to prevent direct contact between the Romex and the building steel. 1926.405(g) (1) (iii) Prohibited Uses. Unless necessary for a use permitted in paragraph (g) (1)(i) of this section, flexible cords and cables shall not be used: 1926.405(g)(1)(iii)(D) Where attached to building surfaces; 7

G. Splices 590.4(G) Splices. On construction sites, a box shall not be required for splices or junction connections when the circuit conductors are multiconductor cord or cable assemblies, provided that the equipment grounding continuity is maintained with or without the box. Best Practice is to utilize a junction box with proper connectors and box support. 110.14(B) Splices. Conductors shall be spliced or joined with splicing devices identified for the use. All splices and joints and the free ends of conductors shall be covered with an insulation equivalent to that of the conductors or with an insulating device identified for the purpose. Wire connectors or splicing means installed on conductors or direct burial shall be listed for such use. Splices must be made in such a way as to prevent any strain on wire connectors. Best Practices will use boxes with box connectors to prevent the strain on wiring. H. Terminations at Cabinets and Boxes 590.4(I) Termination(s) at Devices. Flexible cords and cables entering enclosures containing devices for termination must be secured to the box with fittings designed for the purpose. Entering an enclosure with flexible cord or cable through an open knockout without a connector is a sure invitation for a citation. I. Ground-Fault Protection 590.6 Ground-Fault Protection for Personnel. Ground fault protection for personnel for all temporary wiring installations shall be provided to comply with 590.6(A) and (B). (A) Receptacle Outlets. Temporary receptacle installations used to supply temporary power to equipment used by personnel during construction, remodeling, maintenance, repair, or demolition of buildings, shall comply with requirements of 590.6(A)(1) through (A)(3). OSHA Construction Standard 1926.404 Wiring design and protection, also provides some important guidelines to temporary power. 1926.404(b)(1)(ii) Ground-fault circuit interrupters All 120-volt, singlephase 15- and 20-ampere receptacle outlets on construction sites, which are not a part of the permanent wiring of the building or structure and which are in use by employees, shall have approved ground-fault circuit interrupters for personnel protection. 8

(B) Use of Other Outlets. For Temporary wiring installations, receptacles other used to supply temporary power to equipment used by personnel during construction shall have ground-fault circuit-interrupter protection or assured equipment grounding program. Outlets that are 220-volt are to be GFCI protected and are generally not provided unless specified in the contract. J. Branch Circuits for Receptacles and Lighting 590.4(D)(1) All Receptacles. -- Receptacles on construction sites shall not be installed on branch circuits that supply temporary lighting. 590.4(F) Lamp Protection. All lamps for general illumination shall be protected from accidental contact or breakage by suitable luminaire or lamp holder with a guard. 590.4(J) Support. Cable assembles and flexible cords and cables shall be supported in place at intervals that ensure that they will be protected from physical damage. Support shall be in the form of staples, cable ties, straps, or similar type fittings installed so as not to cause damage. The intent is to require separate circuits for lighting and receptacle loads to prevent the activation of a fuse, circuit breaker, or ground-fault circuit interrupter, due to fault or equipment overload, from de-energizing the lighting circuit. K. Weatherproof Covers This style of weatherproof cover is now required in outdoor wet locations. 406.9(B) Wet Locations. 15 and 20 ampere receptacles installed in a wet location shall have an enclosure that is weatherproof whether or not the attachment plug cap is inserted. Generally this style of cover will not stand much abuse it won t survive intact on construction sites. There are metal covers, in this style, that are considerably more durable, but they are more expensive. 406.9(B) Exception: 15 and 20 ampere receptacles installed in a wet location and subject to routine high-pressure spray washing shall be permitted to have an enclosure that is weatherproof when the attachment plug is removed. This style of cover is permitted in damp locations and other indoor wet locations where the product plugged in will be attended while in use, and where wash down with high pressure spray washer is done. 9

L. Temporary Lighting (Fixtures) 1926.505(a)(2)(ii)(E) All lamps for general illumination shall be protected from accidental contact or breakage. Metal-cage sockets shall be grounded. Temporary lighting must be a factory assembly. Support 1926.505(a)(2)(ii)(F) Temporary lights shall not be suspended by their electric cords unless cords and lights are designed for this means of suspension. Unsupported fixtures are an open invitation for a citation. J Nail Tie Wire 10

Pull String 11

Hooked through Sprinkler brace Plugged into GFI receptacle mounted on ceiling 12

Stapled loose so doesn t contact steel beam Stapled around steel beam; a little to close 13

Transformer attached to temp power skid. 14

Light Switch Light Switch for temp lighting. GFI breaker protected 15

Labeled Panel: Danger High Voltage, Do Not Enter. English and Spanish as may be required. 16

Strain Relief for additional temp power cord. PVC sleeved wiring for temp wiring in exposed areas. 17

Temp power attached to building steel. Not Good. Small movable temp power 18

Temp power secured and marked along the exterior of building. Caution Warning Tape 19

Temp wiring secured up out of the way. Temp wiring secured up out of the way. 20