Prepared for: MeMO Reducing Mining Costs and Value Optimization

Similar documents
WHAT IS THE SMALL MINE CONCEPT AND THE MAJOR ISSUES?

Welcome to a world class operation

The Mining Industry in Canada. By: Cameron Duhn, Jeremy Etmanski and Brandon Hallam

Long-Hole Stope Evaluation. Operating procedures. Introduction. 1. Approach of the model. 2. Notification. 3. Worksheets

Cut and fill productivity. Operating procedures. Introduction. 1. Approach of the model

GUIDELINES to the MINING ACT

Discrete event simulation a tool to support the design of complex production and logistic processes; its application in underground mine design

Phase VII Underground Mine Development and Operations Plan. January Prepared by: Minto Explorations Ltd.

MAINTENANCE COST CONTROL IS YOUR SYSTEM ACTIVE OR PASSIVE?

Table of Contents. Unit 1 The Role of Mining in the World Unit 2 Non-metallic Ores Unit 3 Metallic Ores Unit 4 Ore Deposits...

T S X : R M X N Y S E. M K T : R B Y

Minto Mine QML Underground Mine Development and Operations Plan Amendment Copper Keel Ramp March Prepared by: Minto Explorations Ltd.

T S X : R M X N Y S E. M K T : R B Y. Rubicon Begins Stockpiling Mill Feed for Projected Production Commencing Mid-2015

2019 Semester Terms and Dates Summary

Chapter 26: Canada s Mineral Wealth May 8, Monday, May 12, 14

RAISE BORED SLOT RAISES: A MODERN MINING TECHNIQUE

Phase VII Expansion Waste Rock and Overburden Management Plan

MAINTENANCE COST CONTROL IS YOUR SYSTEM ACTIVE OR PASSIVE?

IDM Mining Updates Pre-Development Engineering and Optimization at Red Mountain Gold Project

Côté Gold Project. Where is the Côté Gold Project located? Who owns the Côté Gold Project? Frequently Asked Questions. May 2018.

Harte Gold Announces Positive PEA For the Sugar Zone Project

Overview. Gold Production and NCE Margin ( E) koz % Durban E. Mineral Reserves & Resources 31 Dec 2010 (Moz)

How to achieve faster drifting in mining, some aspects. SME Denver February 2007 Gunnar Nord Atlas Copco Rock Drill AB Sweden

Concrete Roof Support at Waihi Gold. Bruce Cloughley¹. Introduction

Unit 16 Mine Development

ARM COPPER. Thando Mkatshana Chief Executive: ARM Copper and ARM Coal. Vale/ARM joint venture 50% 50% Refining. Flash/ Isa smelt smelting

A conceptual study into optimizing the delivery of trackbound twin ends through trackless mechanized development

The KOIDU VERTICAL PIT & Design Implementation. Joubert, J.S.C., Freeman, L., Terbrugge, P.J. & Venter, J.

TRANS-SIBERIAN GOLD PLC

NOTES ON HAZARD IDENTIFICATION AND RISK ASSESSMENT (HIRA) PROCESSES

ASSMANG MANGANESE. Presentation 12 April 2005

Double Post Mining. A New Mining Method: Written By:

FRAGMENTATION COMMINUTION PROCESS DESIGN & MONITORING WATER MANAGEMENT. OPERATION FOCUS: Venetia Malmberget

Business Planning Group Design Guidelines & Standards

36e Session d étude sur les techniques de sautage Les 21 et 22 novembre 2013

Equipment Overview Ground Support Ore Flow Utility Vehicles

Case study: a value driver tree as a means of integrating value drivers across disciplines and activities

Bird-in-Hand Gold Project

Mining Under Fill Standards

Groundbreaking Performance Through Practical Innovation

Lessons learnt from XLP mining and ways to mitigate capital cutbacks. Presented by Charl Viljoen

Grasberg Block Cave mine: cave planning and undercut sequencing

Torex Site Visit The Future at Media Luna Dawson Proudfoot

SANDVIK MINING AND ROCK TECHNOLOGY MINEXPO 2016

REGISTRATION PURSUANT TO. PART X of THE ENVIRONMENTAL PROTECTION ACT FOR THE NUGGET POND CROWN PILLAR. Newfoundland and Labrador

Certificate of competence experience logbook

National Exams May MMP-A2, Underground Mining Methods and Design. 3 hours duration

Shotcrete Equipment Choices

Nowadays, there are several methods traditionally. Raise bored slot raises: A modern mining technique RAISE BORING

REVISIONS. App Sud. App PC. App Thom AA 2014/10/28 AA 2014/11/24 AA 2015/06/24

NEWS RELEASE ROXGOLD ANNOUNCES POSITIVE FEASIBILITY STUDY FOR ITS BAGASSI SOUTH PROJECT

Review of Plans and Specs from a Constructability Perspective

CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE

Non-IFRS performance measure. Refer to the Non-IFRS Performance Measures contained in the Q Management s Discussion and Analysis.

Specialising in Ground Engineering & Slope Stabilisation

Solving Large-Scale Production Scheduling Problems in Underground Mining

Added value for mining process by production chain optimization. Harry Sandström METS2018, Madrid

Santacruz Silver Reports First Quarter 2017 Production and Financial Results

Richmont Mines Provides a Status Update on an Expansion Case Preliminary Economic Assessment for the Island Gold Mine

For personal use only

APPENDIX C MINING STUDY

Harte Gold Provides Construction and Permitting Update

SHAFT SINKING MINE DEVELOPMENT CONTRACT MINING RAISE BORING GROUND FREEZING GROUTING

Energy efficiency through optimisation of water reticulation in deep mines

CONSTRUCTION SPECIFICATION FOR TUNNELLING

Kumtor Gold Company 2018

Minerals to Market. September 26 th 2011

Ø1.8m Double Shield TBM for Mixed Ground Sewer Tunnels in Cincinnati

Sabbir Saiyed, PhD., P.Eng. Manager, Transportation System Planning

Staff Paper 12. Update on value chain analysis Introduction

Economical modelling of cement terminals as a means to reduce capital and operating costs. Ad Ligthart Cement Distribution Consultants

For personal use only

Fourth Quarter Production Report. for the three months ended 31 December 2017

NEWS RELEASE Trading Symbol: TSX: SVM

Mine optimization and its application using the Anglo Platinum Mine Optimisation Tool (APMOT)

SILVERCORP REPORTS Q3 FISCAL 2016 FINANCIAL AND OPERATING RESULTS AND FISCAL 2017 GUIDANCE ISSUED

4th International Engineering and Construction Conference - July 28, 2006

ZIMBABWE MINING DEVELOPMENT CORPORATION (ZMDC) INVESTMENT PROJECTS AVAILABLE 2014

Mine to metal: a practical balance for a large platinum producer

TEMBANG PRE-FEASIBILITY STUDY DELIVERS POSITIVE OUTCOME

Making Better haulage decisions through Discrete Event Simulation

INV METALS ANNOUNCES ROBUST PRELIMINARY FEASIBILITY STUDY AT LOMA LARGA

OTJIKOTO GOLD MINE INTRODUCTION AND PROGRESS UPDATE MAY 2014

Blast optimisation at limestone quarry operations good fragmentation, less fines

Rio Tinto is on a journey, and let me share with you just how we are travelling.

T-WALL Retaining Wall System

MN 211 INTRODUCTION TO MINING ENGINEERING 2(2/2-0/0) Pre

VALUE THROUGH GOLD BRUCEJACK PROJECT PREMIER S NATURAL RESOURCE CONFERENCE

For 100 years private mining and refining

Long Term Planning for Open Pit Mines

Ventilation and fire door coverage solution at the Chuquicamata underground mine project

TRANS-SIBERIAN GOLD PLC

301 Part A The Chemical Crusher: Drilling and Blasting. Bill Hissem & Larry Mirabelli

Development of Carbonate Hosted Uranium Mineralization in India

Blast Dynamics POWER DECK OPTIMIZATION POWER DECK COMPANY MAY, 2004 PREPARED BY: improving productivity wi th the use of efficient blast designs

For personal use only

Update on Hammer Mill 3 Commissioning

CAPABILITY STATEMENT RAISE BORE DIVISION CAPABILITIES FLEET SPECIALIST EXPERIENCE LEADERS IN UNDERGROUND MINING

CAPABILITY STATEMENT RAISE BORE DIVISION CAPABILITIES FLEET SPECIALIST EXPERIENCE LEADERS IN UNDERGROUND MINING

For personal use only

Transcription:

Prepared for: MeMO 2016 - Reducing Mining Costs and Value Optimization Prepared by: SRK Consulting (Canada) Inc. Gary Poxleitner PEng, PMP Principal Consultant (Mining) / Practice Leader

Operating Cost? Typical day to day production expenses incurred in running a business

Typical Costs Includes Staff Camp and Travel Labour Mobile Equipment Parts Services Processing Supplies

Unit Based Fuels, Lube, Gas and Power 9% Services and Supplies 38% Labour and Salary 53% Traditional Costing Unit Based Traditional cost accounting methods simply allocate costs, down onto the cost objects without considering any 'cause and effect. Breakdown by Labour costs, Materials and Supplies

Activity Based Costing ABC is an accounting method that allows mines to gather data about their operating costs. Costs are assigned to specific activities including: Drilling Engineering Truck Haulage activities are associated with the generated overall average tonnes produced per day. Activity-Based per (Unit) tonne = Total Activity (Process) Cost) Total Number of units (tonnes) Enables the mine to decide which activity may be increasing their profitability, and which are contributing to losses. able to generate data to create an improved budget and gain a greater overall understanding of the expenses that are required to keep the mine running.

Activity Based Cost Technical Overhead Management Administration Overhead G & A Direct Mining Lateral Development Shotcreting Cable Bolting Primary Ground Support Secondary Ground Support Hydraulic Fill ITH Drilling LHD Mucking Production Blasting Standard Raising Top Hammer UG Truck Haulage UG Rail Haulage Haulage and Indirect Mining Raise boring Muck Circuit Hoist and Shaft Services Training Roadway Upkeep Supplies Handling Services - Utilities Plant Security

Mine Cost breakdown Technical Overhead Management Administration Overhead Maintenance 19% G & A 13% Direct Mining 33% Lateral Development Shotcreting Cable Bolting Primary Ground Support Secondary Ground Support Hydraulic Fill ITH Drilling LHD Mucking Production Blasting Standard Raising Top Hammer UG Truck Haulage UG Rail Haulage Haulage and Crushing 7% Mine Indirects 28% Raise boring Muck Circuit Hoist and Shaft Services Training Roadway Upkeep Supplies Handling Services - Utilities Plant Security

Mine Cost breakdown Lateral Development Shotcreting Technical Overhead Management Administration Overhead G & A 13% Direct Mining 13% Cable Bolting Primary Ground Support Secondary Ground Support Hydraulic Fill Mine Indirects 11% ITH Drilling LHD Mucking Production Blasting Standard Raising Labour/Sala ry 33% Haulage and Crushing 6% Power 5% Top Hammer UG Truck Haulage UG Rail Haulage Mining Indirects Raise boring Muck Circuit Maintenanc e 19% Hoist and Shaft Services Training Roadway Upkeep Supplies Handling Services - Utilities Plant Security

Mine Cost Breakdown Lateral Development Technical Overhead Management Administration Overhead G & A 13% Direct Mining 13% Shotcreting Cable Bolting Primary Ground Support Secondary Ground Support Hydraulic Fill ITH Drilling Mine Indirects 11% LHD Mucking Production Blasting Standard Raising Top Hammer UG Truck Haulage Labour/Salary 33% Haulage and Crushing 6% Power 5% UG Rail Haulage Mining Indirects Raise boring Muck Circuit Hoist and Shaft Services Training Maintenance 19% Roadway Upkeep Supplies Handling Services - Utilities Plant Security

First Principals Stope Blasting Supply s Services Calculate number of Drill Holes and Number of Blasts List Supplies and Quantity Required Bulk Powder Boosters Electric Caps Slag Miscellaneous (3%) Input Unit Costs Generate Total Supply Cost per Blast ton List Services Required Emulsion Truck Service Contract Labour Other Services Input Unit Costs Generate Total Services Cost per Blast ton Based on Typical Stope Layout 18,000 tonnes Discussion with Production Crew Suppliers

Operating Cost - Basis ITH Supply Drill Costs Stope Size 24,000 tonnes Total Drill Footage 6500 metre Drill Tools (bits, steel, hammer, etc.) (total per stope or foot) - $3.00/ft Equipment Cost (based on $/hr) $4.00/ft Allowance (10%) $0.70/ft Total Drill Cost - $7.70/ft or - $2.10/ton ITH Service Costs ITH Rental - $10,000/m Drill footage per month 3,000 ft Total Drilled tonnes 10,000 tonnes Total Drill Cost - $3.33/ft or - $1.00/ton ITH Labour Costs ITH Driller - $50/hr Include: Travel time, drill time, set-up time and down time, re-drilling Total Drilled time: 20 days Total Cost - $50/hr x 20 days * 12 hrs/d hrs = $12,000/stope Total Drill Cost - $1.85/ft or - $0.50/ton But better to do a labour total requirement for the mine

Factoring and Benchmark Benchmark (Mine) New (Mine) Variable Factor Activity 2000 tpd 1500 tpd C$/t % 0 to 1 $/t Production Mucking 6.00 90 1 8.37 Backfill 5.00 85 0 0.00 LH Drilling 12.00 85 1 19.11 Cut and Fill 0.00 85 0 0.00 LH Blasting 4.00 85 1 6.37 Ore/Waste Handling Surface Crushing 4.00 90 1 5.58 Truck Haulage 4.00 90 1 5.58 Ore Sorting 2.00 85 1 3.18 Services/Ancillary UG Services 9.00 80 1 10.00 Road Maintenance 2.00 80 1 3.58 Material Handling 2.00 80 1 3.58 Maintenance UG Maintenance 5.00 50 1 14.87 UG Mobile Vehicle Maintenance 4.00 50 1 11.90

Factoring It mirrors current practice in a similar environment. Minesite operators can participate when choosing what scaling factors to use. It s a quick and easy way to consider many mine design possibilities. However It doesn t challenge current behavior. It is increasingly inaccurate as mine design is changed. It doesn t reflect how operating cost may change over life of project. It doesn t explore the relationship between operating cost and production rate.

Functions/Activities with Drivers Function/Activity Lateral Development Shotcrete Standard Raising Raise Boring Ground Support Cable Bolting Top Hammer Drilling In-the-Hole Drilling Blasting LHD Mucking Primary and Retram Driver Lateral metre Equivalent dry bags Vertical metre Vertical metre Lateral metre Bolts Drill metre Drill metre Production ore tonnes Mucked/trammed tonnes Function/Activity Driver Supplies Handling Hoisted tonnes Track Tram Rail hauled tonnes Truck Haulage Truck hauled tonnes metre Diamond Drilling Drill metre Hydraulic Backfilling Poured tonnes Muck Circuit Hoisted tonnes Hoisting and Shaft Services Hoisted tonnes Ramp, Roadway and Underground Upkeep Hoisted tonnes Level Maintenance Hoisted tonnes Surface Ore Handling Hoisted ore tonnes Hoisted waste rock Surface Rock Handling tonnes Mine Services Hoisted tonnes

Underground Mine Cost ($/t) 1 - Direct Mining $250 $200 $150 Operating Development + Drilling + Blasting + Mucking + Backfilling $100 $50 $86 $46 $89 $52 $28 $37 $80 $40 $59 = Direct Mining Cost $0 Mine 1 Mine 2 Mine 3 Mine 4 Mine 5 Mine 6 Mine 7 Mine 8 Mine 9

Underground Mine Cost ($/t) 2 Utilities $250 $200 $150 Compressed Air + Electrical Power + Heating & Ventilation + Process Water $100 $50 $23 $17 $23 $9 $9 $13 $13 $15 $16 = Utilities Cost $0 Mine 1 Mine 2 Mine 3 Mine 4 Mine 5 Mine 6 Mine 7 Mine 8 Mine 9

Underground Mine Cost ($/t) 3 Services and Supply Handling $250 $200 $150 $100 $50 $12 $12 $9 $10 $11 $9 $10 $11 $5 Supply Handling + U/G Upkeep + Reconditioning + Drainage & Pumping = U/G Services Cost $0 Mine 1 Mine 2 Mine 3 Mine 4 Mine 5 Mine 6 Mine 7 Mine 8 Mine 9

Underground Mine Cost ($/t) 4 Haulage and Skipping $250 $200 $150 $18 $18 Track Tram + Truck Haulage + Crushing + Skipping $100 $50 $13 $5 $5 $6 $7 $5 $5 = Haulage/Crushing Cost $0 Mine 1 Mine 2 Mine 3 Mine 4 Mine 5 Mine 6 Mine 7 Mine 8 Mine 9

Underground Mine Cost ($/t) 5 Mine Processing $250 Processing $200 $35 $35 $150 $100 $35 $22 $22 $20 $19 $19 $19 $50 $0 Mine 1 Mine 2 Mine 3 Mine 4 Mine 5 Mine 6 Mine 7 Mine 8 Mine 9

Underground Mine Cost ($/t) 6 General and Administration $250 $200 $150 $100 $33 $33 $35 $26 $42 $31 $42 $31 $19 Mine Management + Administration + Water Treatment + Environment + Camp Costs = General and Administration $50 $0 Mine 1 Mine 2 Mine 3 Mine 4 Mine 5 Mine 6 Mine 7 Mine 8 Mine 9

Underground Mine Cost ($/t) Total $250 $ 207 $ 210 G & A $200 $150 $ 147 $ 130 $ 163 $ 131 $ 150 Processing Cost Ore and Waste Handling $100 $ 106 $ 100 Underground Services UG Utilities $50 In Stope Mining Cost $0 Mine 1 Mine 2 Mine 3 Mine 4 Mine 5 Mine 6 Mine 7 Mine 8 Mine 9

Fixed and Variable Costs Fixed Costs are costs that don t change based on the activity: Property taxes on site, camp costs, G & A and Labour(!) Variable Costs are costs that don t change based on the activity: Drilling, Loading, Mucking Combined Costs: Most Mine Costs are a combination of the two. Milling (50/50) Depending on production tonnes these costs can change a lot! Because of the fixed cost component!

Fixed and Variable Costs Mining Costs Cost/Tonne $250 $240 $230 $220 $210 $200 $190 $180 $170 $160 $150 $140 $130 $120 $110 $100 $90 $80 $70 $60 $50 $40 $30 $20 $10 $- 0 10,000 20,000 30,000 40,000 50,000 60,000 70,000 80,000 90,000 100,000 110,000 120,000 Monthly Production Rate

Operating Cost - Strategy Cost Profile Operating Costs MARGIN Mine General Indirect Cost METAL PRICE STRATEGIC COST Off site costs: Smelting, Refining, OH etc. Capital On site cost Milling Mining Ore & Waste Movement Development Backfill Drill & Blast Direct Cost

Operational challange 27of XX

Operational challenge 28of XX

Mine Cost vs Gold Price

Operating Cost Breakdown Indirect Cost Direct Cost Mine General Ore & Waste Movement Development Backfill Drill & Blast Crushing & Hoisting Underground Services Utilities Surface Services Mine Management Transport to Mill Diamond Drilling Operating Development Cable bolting ITH Drilling Solo Drilling Blasting Raising Mucking Secondary Mucking Backfill Supply handling By grouping the costs you can then look at opportunities for savings and determine the Ground Zero Costs (The lowest reasonable costs) You may also benchmark those costs against your mine s costs Utilizing: Benchmark Data and First Principals

Benchmark Sources Cost Mine World Mine Cost Data Exchange Inc CRU International Brook-Hunt Associates Annual reports Sedar (technical reports) SNL * Best info is from operating mines

Development - Cost $14,000 Development Cost/m Benchmarked Single Heading $12,000 $10,000 Very Por Ground $8,000 Rapid Development $6,000 Poor Ground $4,000 5.0m x 5.0m Development Cost $2,000 4.5m x4.5m Development Cost $- 32of XX

Ground Zero Cost Fixed rate component will bottom out your costs. Direct Mining (ITH, Blasting, mucking) is variable and difficult to reduce costs on supplies and parts. Mining is material handling and rock breakage exercise only streamline processes to reduce ore and waste handling. Labour cost is difficult to change. Service contracts should be reviewed, there is often opportunity there. Trim out the fat accumulated by the high price years and from mining lower grades. Mines often run in silos so have a 3 rd party look through your costs with someone on site familiar with the mine.

Reclaiming efficiency and lowering costs Common Approaches that don t work: Top-Down: Simply slash costs without addressing the downside risk and sacrificing opportunities. the single solution mind-set Slash and burn (cut 10%) Arbitrary targets, Reactive and survival focused negatively effects morale and risk loosing your strongest people. Focus on short term cost cutting and one-off savings Pushing contractors to the wall for steep concessions that may not be sustainable, instead build a partnership model, look for opportunities-what is it you really need Bottom-up: analysis across all departments to identify opportunity Departments personally invested in their own budgets, negative impact on morale, produces lists, greater investment, lacks urgency 34of XX

Reclaiming efficiency and lowering costs To be successful focus: Operational improvement Minimize waste Increase volume Focus on outputs (not inputs) 35of XX

Reclaiming efficiency and lowering costs Mine Planning: Focus on high quality ore with higher Cut-off grade (low cutoff isn t always good) Ramp up production e.g. mining methods, better fill, increasing stope cycle time ( carefull of implications of increasing mining fronts and sequencing) Attract and retain experienced mine planners (out-of box thinkers and interested in improving operational performance and tracking performance) Monitor that the priority headings are being realized (development drives production) Streamline material and ore/waste handling in your mine (mining is a material movement exercise) New low-cost stream-lined technology 36of XX

Reclaiming efficiency and lowering costs Costs: Understand and be clear on your unit costs of your operation. Compare current costs with ground-zero costs and benchmark data. Set realistic targets of KPIs Share metrics with everyone in your group and have everyone track them. Post it Ramp up production e.g. mining methods, better fill, increasing stope cycle time ( careful of implications of increasing mining fronts and sequencing) 37of XX

Reclaiming efficiency and lowering costs Operation Analysis: Access all costs items to uncover your actual cost base and identify outliers Meet with operations and discuss targets and mine plan. Look for ideas 38of XX

Ground Zero Cost Fixed rate component will bottom out your costs Direct Mining (ITH, Blasting, mucking) is variable and difficult to reduce costs on supplies and parts Mining is material handling and rock breakage exercise only streamline processes to reduce ore and waste handling Labour cost is difficult to change Service contracts should be reviewed, there is often opportunity there. Trim out the fat accumulated by the high price years and from mining lower grades Mines often run in silos so have a 3 rd party look through your costs with someone on site familiar with the mine. 39of XX

Questions