Preventing Damage to Buried Utilities Worker

Similar documents
4-0 Excavation Best Practices

Underground Utility Damage Prevention Guidelines for Contractors

SECTION GS10300 UNDERGROUND TRENCHING AND EXCAVATION CONSIDERATIONS

Risk Control Bulletin Damage Prevention Guidelines Excavation Procedures for Underground Facilities

MISSISSIPPI CODE of *** Current through the 2015 Regular Session ***

Guidelines for working

TECHNICAL PROCEDURE TABLE OF CONTENTS

Canadian Guidelines for Safe Excavation in the Vicinity of the Bell Network

The Corporation of The City of London

Notification to Super Sea Cable Networks Pte Ltd (the SEAX ) for Earthwork Procedures

Ohio Utilities Protection Service Safety Presentation

One-Call Facility Locates

The Standards referred to shall be the most recent edition.

SECTION MAINTENANCE OF EXISTING CONDITIONS

APPLICATION FOR RIGHT OF WAY PERMIT

Excavations and Blind Penetrations into Walls & Floors

Excavation Monitoring and Observation

The Essential First Step.

OHIO UNIVERSAL MARKING STANDARDS APWA COLORS or

Canadian Locator Technician Standards Table of Contents

Monitoring reinstatement and compaction of backfill materials

UNDERGROUND FACILITY LOCATOR COMPETENCY PROFILE

Contractor s Guide to Applying for Permit to Dig/Excavate

Uniform Color Code and Marking Guidelines

MISS DIG FOUNDED IN 1970 NON PROFIT CORPORATION AUBURN HILLS & GLADSTONE MDPB EDUCATION & MARKETING DEPT

GUIDELINES FOR SAFE CONSTRUCTION IN THE PROXIMITY OF THE THERMAL DISTRIBUTION PIPING SYSTEM

A GUIDE TO WORKING SAFELY AROUND VECTOR S ELECTRICITY, GAS AND COMMUNICATIONS NETWORKS.

Technical Guideline for. Section 8. Inspection and Approval of Construction

Work involving excavations

Veriforce TG CCT 607OP. Training Guide

SAFE WORK PROCEDURE 038 PIT CONSTRUCTION MARCH 2014 DOC. NO. D14/184671

Excavation Marking and Dig Safely NY Procedure

The University of Alabama General Requirements for Purchase Orders Involving Public Works

WORK DESCRIPTION AND REQUIREMENTS FOR SEMI IN-GROUND SWIMMING POOL

SECTION PROTECTION AND RESTORATION OF EXISTING FACILITIES

Corporate Policy and Procedure

Damage to Underground Infrastructure British Columbia, Ontario and Quebec

SPRINKLER SYSTEM Job Ready Checklist

Excavators Contractors Landscapers Farmers PIPELINE SAFETY. Important safety guidelines for working and digging near pipelines

Montana Excavation Safety Handbook (MESH)

Applying for a Kinder Morgan Cochin Canada / UTOPIA Canada Proximity & Crossing Permit. Design and Construction Guidelines

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

Versatile Rectangular Underground Concrete Tank. Recommended Install Guidelines

LIST OF CONDITIONS FORPROPOSED SMART CITY AT TRIANON BY HERMES PROPERTIES LTD [ENV/DOE/EIA/1695]

University of Saskatchewan Underground Utility Assessment Policy Process

Wayleave Application for Non-Queensland Rail Service

ilkti ...:- WOC LP Standards Section E005 - Excavation kj/0i DOCUMENT NO: WOC-HSE-ST-0001 & EP Department 44, 4R 11. C

CORPORATE POLICY C3.H17

DIGGING SAFELY. Damage Prevention is a Shared Responsibility. Steve Cleaver Senior Investigator Dig-in Reduction Team (DiRT)

MONTANA EXCAVATION SAFETY HANDBOOK

Know Recognize Respond PIPELINE SAFETY IN YOUR COMMUNITY PARA UNA COPIA EN ESPAÑOL POR FAVOR VISITE

Utility Locating Policy (Complying with Dig Safely NY)

Apply for Permit to Dig/Excavate

APPENDIX D DIRECTIONAL BORING GUIDELINES

APPENDIX D C DIRECTIONAL BORING GUIDELINES

Section SITE CLEARING. B. Description of Work: 1. The extent of site clearing is shown on the drawings.

THE DAMAGE PREVENTION PROCESS IN ALBERTA

Construction Specification for General Excavation

OSH INFORMATION MEMORANDUM: 90-X-84. Inspection Procedures for Enforcing the Excavation Standard, Subarticle 7, 1926, Subpart C

BLUETEL NETWORKS PTE LTD 180 Paya Lebar Road #06-03 Yi Guang Building Singapore Tel Fax

The Damage Prevention Process in Alberta

Public Works and Utilities Department RIGHT-OF-WAY USE PERMIT APPLICATION

THE DAMAGE PREVENTION PROCESS IN ALBERTA

HOLDING TANK PLANNING & INSTALLATION GUIDELINES

THE DAMAGE PREVENTION PROCESS IN ALBERTA

Worksite Safety Update Promoting safety in road construction

ARTICLE 10: INSPECTIONS

THE ANTICIPATED SEQUENCE OF EVENTS ARE AS FOLLOWS, BUT THE CONTRACTOR IS RESPONSIBLE FOR ALL MEANS AND METHODS

SUP 02 Avoiding danger from underground services during ground works Unified procedures for use within NHSScotland

B. The purpose of the meeting shall be to establish the conditions of all existing trees upon receipt of the Project site by the Contractor. Failure t

PUBLIC WORKS COMMISSION 2018 STREET EXCAVATION PERMIT PROCEDURE

C. Foundation stabilization for pipe and utility structures.

MetroLink Operations 700 South Ewing Street Saint Louis, Missouri

Contents. Before you begin. Introduction: Installing trench support 1. Element 1: Planning and preparing 3

DIG SAFELY NEW YORK OVERVIEW

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

API & AOPL Provisions of a Model State One Call Law

Application For Graywater Irrigation System Permit

Guidance on Avoiding Danger from Underground Electricity Cables based on HSE Document HS(G)47

SECTION SANITARY SEWER SYSTEM

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER

CITY OF WILSON. Public Services Engineering. Backfilling, Compaction, & Patching Policy on Existing Pavements

Guide to Moving Your Electricity Service

UNDERGROUND INFRASTRUCTURE SAFETY IS A SHARED RESPONSIBILITY

REQUIREMENTS TO BE COMPLIED WITH BY EARTHWORKS CONTRACTORS FOR THE PREVENTION OF DAMAGE TO TELECOMMUNICATION CABLES

Field Instruction. All Horizon Power workers who work in and around excavations.

MONOLITHIC CONCRETE IRRIGATION PIPE INTRODUCTION CIPCP FOR IRRIGATION

INTER PLANT STANDARD - STEEL INDUSTRY SAFETY PROCEDURE FOR WORKING AT HEIGHT BY REGULAR EMPLOYEES OF PLANTS / MINES

BILL AS INTRODUCED H Page 1 of 8. Subject: Utilities; underground; damage prevention system; hot water and

GENERAL NOTES REQUIRED NOTES ON ALL PLANS

LENAWEE COUNTY HEALTH DEPARTMENT Environmental Health Division Well and/or Sewage Disposal Construction Permit Application

Excavation in the highway

WORK IN THE VICINITY OF UNDERGROUND ASSETS

GROUND DISTURBANCE 201 STANDARD (BRITISH COLUMBIA)

To Loughborough University Facilities Management (FM) Health and Safety Policy

December NULCA Standard. Professional Competency Standards for NULCA Member Locators

APPLICATION FOR GRAYWATER IRRIGATION SYSTEM PERMIT SIMPLE RESIDENTIAL GRAVITY SYSTEMS, NO STORAGE

Installation Guide BLUE904 PEX MUNICIPAL WATER SERVICE TUBING. We Build Tough Products for Tough Environments

ROBOTIC ROADWORKS & EXCAVATION SYSTEM

Call OR EXCAVATOR MANUAL

Transcription:

Preventing Damage to Buried Utilities Worker Excavation Checklist

Damage prevention concerns us all! Are you an excavation worker on an excavation site? If so, this checklist applies to you! Following these effective damage prevention practices will ensure employee and public safety as well as maintaining the integrity of our buried utilities. Based on Quebec s APISQ Buried Utility Damage Prevention Guide, more specifically in Chapter 4 Excavation, this checklist gives you the outlines for safe digging from start to finish.

Before Excavating

Was a locate request made to Info-Excavation? If so, is it still valid? The locate request is valid for a 30 day period from the date which the ticket number has been received. If work is extended beyond the 30 day period, a new locate request must be made. Attention! A locate request must be made to Info-Excavation a minimum of four working days before undertaking any excavation work. The ticket number given by Info-Excavation confirms that your request has been processed. A locate request prevents damage to buried utilities, ensures worker safety and lowers the risk of unforeseen costs.

Do you have all necessary documents? Regardless of whether your excavation work is taking place near one or many buried utilities, you must at all times have a copy of every report received (locate report, clearance and utility supporting methods). Attention! All documents must be in your possession and remain onsite throughout the excavation. An additional copy should be kept with the mechanical equipment operator. In the event of an emergency, these documents will be required by emergency services.

Was the future worksite verified before excavating? The worksite must conform with the locate reports received. Verify if the location of buried utilities (markings, stakes, flags or other methods) and worksite correspond with the excavation to be executed. Attention! If the worksite and locate reports do not conform, DO NOT start work! Contact the worksite or project manager.

Did you attend a pre-excavation / tailgate meeting? A tailgate meeting gives you an opportunity to share information and coordinate the location of buried utilities and excavation work. Attention! A tailgate meeting is equally beneficial to discuss and plan for special excavation work, such as major or specialized excavation work. Are emergency numbers readily available? Emergency numbers must be kept onsite. In the event of an emergency, these numbers must be immediately accessible.

During Excavation Work

Were the markings protected? Buried utilities must be marked in accordance with the Universal Colour Code for Underground Utilities (paint, stakes, flags or other methods). Offset, GPS coordinates or survey methods may be used to protect the marks. Attention! Despite using all necessary precautions, markings are no longer visible? Call Info-Excavation, as well as owners / operators of buried utilities who are non-members so that they may remark the work zone. Check the Universal Colour Code printed at the back of this document as reference. Are two workers present during excavation? In an effort to detect potential hazards, a minimum of two workers (including the machine equipment operator) must be present while excavating.

Was the buffer zone on each side of the markings respected? Certain precautions, such as soft excavation (hand-digging) must be followed within the 1 metre buffer zone on either side of the utility markings.

If you discover a previously unidentified buried utility... STOP WORK IMMEDIATELY and advise Info-Excavation of the situation. Info-Excavation, as well as buried utility owners or operators who are non members, must also be advised in the event of an inaccurate locate. The owners or operators locator will be dispatched to the worksite to assess the situation.

Are buried utilities supported and protected? Supporting exposed buried utilities during excavation is critical to maintaining their integrity and to worksite safety. Supporting methods certified by an engineer must be used. Attention! Line break or damages? STOP excavation work. Harmful breaks? Call 911 or advise emergency services, then secure worksite. Other types of damage? (leakage, breakage, gap, cut-out or dent) Immediately call Info-Excavation, the owner or operator of buried utilities.

After Excavation Work

Ensure that the backfilling complies will all buried utility owner/operator requirements Care must be taken when backfilling a worksite. Do not use sharp objects, compacted or frozen soil. Do not bury trash or pipe ends.

The ministère des Transports du Québec is a proud partner of the APISQ and Info-Excavation. Thank you to our GOLD partners.

Useful Information Info-Excavation www.info-ex.com 1 800 663-9228 APISQ www.apisq-qcga.ca Montreal area: 514 339 APISQ (339-2747) Elsewhere in Quebec: 1 877 71APISQ (712-7477) info@apisq-qcga.ca The Buried Utility Damage Prevention Best Practice Guide can be downloaded on the APISQ s Website. Colour Codes ELECTRICITY TELECOMMUNICATIONS CABLES OPTICAL FIBER SURVEY SEWERS WATER WORKS NATURAL GAS HYDROCARBONS STORM SEWER NON DRINKING WATER IRRIGATION PRE-MARKING This document was produced by the Alliance pour la protection des infrastructures souterraines du Québec (APISQ), with the collaboration of its members.