GPE engineering project management. Project Management in an Engineering Context

Similar documents
Planning & Scheduling

6 PROJECT TIME MANAGEMENT

The Project Management Cer8ficate Program. Project Time Management

Information Technology Project Management, Seventh Edition

Project Management in Practice Fifth Edition

Introduction. Project Scheduling. Morgan State University ARCH 738: REAL ESTATE PROJECT MANAGEMENT. Jason E. Charalambides, PhD, M.

Project Scheduling: Lagging, Crashing and Activity Networks

Estimating Project Schedule-Time and Cost

PROJECT TIME MANAGEMENT

Project Time Management

PMP Exam Preparation Course Project Time Management

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

Week 5 Project Work Plan

Construction Scheduling and Estimating

Project Time Management

Week 5 Project Work Plan

Developing a Project Plan

Week 5 Project Work Plan

IST 302 : Project Time Management

Scheduling. Adapted from John Musser

Project Planning & Scheduling

Software Project Management

Time has the least. amount of flexibility; Schedule issues are the main reason for

Project Management PSGLE 122. Time and Resources

Operations Management, 11e (Heizer/Render) Chapter 3 Project Management. Section 1 The Importance of Project Management

SCSD2613 System Analysis and Design. PART II: Project Planning Process

Operations Management

Week 5 Project Work Plan

The Project Planning Process Group

CIPRIANI COLLEGE OF LABOUR & CO-OPERATIVE STUDIES BSC IN PROJECT MANAGEMENT PRM 135: PROPOSAL DEVELOPMENT & COSTING WEEK 8

Cambridge International AS & A Level Computer Science

Project Time Management

Project Scope Management

Modern Systems Analysis and Design Seventh Edition

Project Management CSC 310 Spring 2017 Howard Rosenthal

Agile Project Planning

Artificial Intelligence

MBP1133 Project Management Framework Prepared by Dr Khairul Anuar

Objectives of Project Management Framework. What are the Characteristics Of Project. Activities involved Project Management

Software Process and Management

Analysis of Common Project Schedule Management Methods Wei-guo LIU *, Xue SHEN and Tian-qi WU

Project Management Professional (PMP) Exam Prep Course 6 - Project Schedule Management

Kristin Fitzgerald Director, Global Project and Alliance Management, Merck & Co, Inc.

Project ended.. Terminated or canceled.

THE PMP EXAM PREP COURSE

Lecture 7 PROJECT SCHEDULING. Ferdinand Fassa

MGT/437. Project Management. Session #2 University of Phoenix 02/12/2004 Brian Smithson. 02/12/2004 MGT/437 #2 -- Brian Smithson 1

Time Management PLANNING

Work Analysis and Design

Chapter 3 Project Management

Topic # 12. CIS Project Management: an overview

12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish

Project Management THE MANAGERIAL PROCESS

PROJECT PLANNING AND SCHEDULING

MBH1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar. Lecture 6b Project Time Management - II

Chapter 5 Project Scheduling. (Source: Pressman, R. Software Engineering: A Practitioner s Approach. McGraw-Hill,

Chapter 3 Managing the Information Systems Project

Information Technology Audit & Cyber Security

CE2353-CONSTRUCTION PLANNING & SCHEDULING

Cronfa - Swansea University Open Access Repository

PMP Course Content. Chapter 1. Introduction to PMP Objectives of PMP Requirements for PMP Exam About PMP Exam PMP Exam Syllabus.

PMP EXAMINATION PREP CHAPTER 6 SCHEDULE MANAGEMENT. PMP Exam Prep

Scheduling Concepts and MS. Project AZURITE PROJECT TRAINING AND CONSULTING PVT LTD (OPC) 2014

1.Which of the items listed below is not one of the software engineering layers?

Overview of A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition Changes

Implement. Control. Integrate. Knowledge Leverage. Course Overview

PLANNING & SCHEDULING

Introduction to Project Management

CHAPTER 1. Basic Concepts on Planning and Scheduling

Constructing Networks

The recommended guided learning hours for this unit are 30 hours.

Audi%ng and Verifica%on of an ISO Energy Management System. Ian Boylan

MODULE 15 OPERATIONAL PLANNING TECHNIQUES (USE OF PLANNING TOOLS LIKE GANTT CHART, PERT/CPM)

Network Diagram 11/10/2016 WORK BREAKDOWN STRUCTURE (WBS)

Planning Tools and Techniques Part 2

LookingGlass - Project Management Professional Exam Prep (PMP01)

Prepared by: Mr.M.SYED SHAHUL HAMEED CHAPTER 3 SYSTEMS PLANNING - MANAGING SYSTEMS PROJECTS

PMP PMBOK Guide Sixth Edition Training Course Agenda

ENGINEERING MANAGEMENT (GE

Luis R. Garcilaso March 13, Lecture #22. Service Processes & Systems Dept. of Mechanical Engineering - Engineering Mechanics

BA /14/2010. PSU Problem Solving Process. The Last Step 5. The Last Step 8. Project Management Questions PLAN IMPLEMENT EVALUATE

Seminar 6: Project Management Part 1 Semester 1, 2005

Index. Symbols. 80/20 Rule, /15 Rule, 306

Seminar 6: Project Management Part 1 Semester 1, 2005

Project Scheduling Public Works Projects. E- Contractor Academy, Level II

Geog 469 GIS Workshop. Project Management

Index. Backup plans for presentations, Backward pass, 55 59, 72 73, 102. Saleh Mubarak

Project Management Framework

Project Management. Time and Resources DPLE 157

FIGURE 8-8 Computer Printout of Sewer Line Activities Only (Sort of Activities List by Code Digit #I Equal to One).

Chapter 4 Project Management

A system is a group of elements organized and arranged so that the. elements can act as a whole toward achieving a common goal; is a collection of

2. What is a phase? A phase is a collection of related activities or tasks that produce a deliverable or work product.

LECTURE 8: Planning & Control Functions & Tools (Part II) Project Management BACA

GLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155

: SOFTWARE PROJECT MANAGEMENT UNIT I PROJECT EVALUATION AND PROJECT PLANNING PART A

Project Management Concepts, Tools & Techniques

TEXTS IN OPERATIONAL RESEARCH

Lecture- 10. Project Scheduling. Dronacharya College of Engineering

PROJECT TIME PLANNING. Process and Bar Chart Technique

Transcription:

GPE engineering project management Project Management in an Engineering Context

PM Network diagrams in context SOW CHARTER SCOPE DEFINITION WBS circulation, negotiation, translation WBS WP à activities ----- estimation Time Cost GANTT PERT AOA AON - - - - - - - - - - - planning, resource alloca7on, cost alloca7on, control - - - - - - - - - - Mainly PMBOK chapter 6

Network diagrams WBS

PERT, what does it state for? They are like WBS?

PERT Program Evalua/on & Review Technique

WBS GANTT PERT

Network Analysis (PERT Program Evalua/on & Review Technique; CPM Cri/cal Path Method) Network modula7on approach used in planning, scheduling and controlling projects. Beyond the analysis they facilitate, they represent a common ground to discuss op7ons so they are excellent communica7on tools. They facilitate thema7c brain- storming analysis Network diagrams are en7ty/rela7onship models (interrela7ons among instances of resources) usually used in project planning, namely on scheduling and 7me management Using these models we need to take into account: interrela7on of ac7vi7es (sequencing rela7ons) and rela7ons among ac7vi7es and resources (alloca7on) There are more complex models, using sta7s7cs but we will eventually address them later

Cri7cal Path Method (CPM) (determinis7c) A schedule network analysis technique used to determine the amount of scheduling flexibility (the amount of float) on various logical network paths in the project schedule network, and to determine the minimum total project dura7on. Early dates are calculated by means of a forward pass, using a specified start date. Late dates are calculated by means of a backward pass, star7ng from a specified comple7on date, which some7mes is the project early finish date calculated during the forward pass calcula7on. Program Evalua7on and Review Technique (PERT) (probabilis7c) A technique used to improve the accuracy of the cost or dura7on es7mates of project components when there is uncertainty. PERT uses weighted averages of op7mis7c, pessimis7c, and most likely es7mates (the well- known three- point es7mates) of the components' cost or dura7on. Different weigh7ng schemes represent different probability distribu7ons of the possible cost or dura7on of a component. For instance, the typical formula is [(op/mis/c + 4 /mes the most likely + pessimis/c) divided by 6], approximates a beta distribu7on.

CPM/PERT Cri7cal Path Method (CPM) DuPont & Remington- Rand (1956) Determinis7c task 7mes Ac7vity- on- node network construc7on Project Evalua7on and Review Technique (PERT) US Navy, Booz, Allen & Hamilton Mul7ple task 7me es7mates (probabilis7c) Ac7vity- on- arrow network construc7on

PERT elements Events (states), ac7vi7es (nature and 7me), preceding, alloca7on, context (context must always be defined and clarified) Some examples of PERT representa7on - AOA ac7vity on arrow, or ADM - arrow diagramming method; and AON ac7vity on node A,3 B,5 C,7 D,2 E,6 F,3 G,10

PERT elements Events (states), ac7vi7es (nature and 7me), preceding, alloca7on, context (context must always be defined and clarified) Some examples of PERT representa7on - AOA ac7vity on arrow, or ADM - arrow diagramming method; and AON ac7vity on node A,3 E,6 B,5 C,7 F,3 G,10 D,2 17 19

Examples of different nota/ons

Parallel ac/vi/es signaled as we exemplify are not allowed A B A A,B B dummy If you fail this notation in the exam you will have 0 in the entire question

Task B can only be started acer ac7vity A is completed. The same with D and C A,3 B,7 C,4 D,6 10 10

Network Analysis example AOA A,3 B,7 C,4 D,6 There is a dummy ac7vity dura7on 0 (only a logical dependency)

Network Analysis example AOA A,3 B,7 C,4 D,6 10 10 Are all paths iden7fied?

Network Analysis example AOA A,3 B,7 C,4 D,6 10 10 11 No, there are three paths, not two! And that makes quite a difference!!

Network Analysis example AOA A,3 B,7 C,4 D,6 10 10 11 (A,B) (C,B) (C,D) Instant time - 5 Time interval - 6

Network Analysis example AOA A,3 B,7 C,4 D,6 10 10 11 Activity Duration Early St Early Fi Latest St Lat. Fi. Float A B C D Dummy

Network Analysis example AOA A,3 B,7 C,4 D,6 10 10 11 Activity Duration Early St Early Fi Latest St Lat. Fi. Float A 3 0 3 1 4 1 B 7 4 11 4 11 0 C 4 0 4 0 4 0 D 6 4 10 5 11 1 Dummy 0 4 4 4 4 0 Instant times

PERTS, and projects 1. Define the project and all its ac7vi7es. The project is made of tasks and all tasks should have a single start and a single finish 2. Develop the rela7onships among the ac7vi7es. Decide which ac7vi7es must precede, which must follow others, and the ones that can be executed in parallel. If you are short in 7me try to put in parallel as much ac7vi7es as you can 3. Draw the network diagram connec7ng all the ac7vi7es. Each ac7vity is unique. Dummy ac7vi7es are immaterial in 7me but relevant in sequence, they impose logical dependences 4. You can assign 7me and cost to each ac7vity Preceded by a planning effort by the project management team. This planning effort is part of the Develop Project Management Plan process 5. Compute the longest 7me path through the network. This path is called the Cri/cal Path 6. Use the network to help plan, schedule, monitor and control the project and also as a communica7on tool documented in the schedule management plan

PERTS, and projects

PERTS, and projects

WBS GANTT PERT

Late start and backward path backward pass Early dates are calculated forwards, using the forward path. Late dates are calculated in reverse direc7on, star7ng at the date of the finishing of the project this is the backward path In this example one backward path leads us to event 3 through ac7vity B. So we have: Total project 7me (cri7cal path) = 11 11-7 = 4. This means that the late start for ac7vity B is 4 Rela7ng to event 2 we have to evaluate two paths, Dummy and D. Through Dummy we have 4-0 = 4, this means that Dummy late start is 4 and through D we have 11-6 = 5, so ac7vity D late start is 5 Activ ity Dura tion Early St Early Fi Lates t St Lat. Fi. Float A,3 3 B,7 A 3 0 3 1 4 1 B 7 4 11 4 11 0 C 4 0 4 0 4 0 D 6 4 10 5 11 1 Dum my 0 4 4 4 4 0 DUMMY,0 C,4 D,6 2 4

So you already have the rule to compute early starts and late starts. Early starts are computed in the forward path from the beginning to the end, adding dura7on and late starts are computed in the backwards path, subtrac7ng dura7on from the end Project management tools compute this for you, you just have to manage according to situated condi7ons (environment, resources, risk, )

Your project is to design and develop an electric motor. Ac7vity dura7ons and predecessors are iden7fied at the following table. A) construct a PERT AOA; B) Which is the dura7on of every path? Which path is the cri7cal one? C) What happens if ac/vity E dura/on becomes 8? Ac7vity dura7on predecessor A 10 - B 20 - C 4 - D 2 A E 10 B,C F 8 B,C G 4 B,C H 2 C I 6 G,H J 2 D,E

Network Analysis example AOA Ac7vity dura7on predecessor A 10 - B 20 - C 4 - D 2 A E 10 B,C F 8 B,C G 4 B,C H 2 C I 6 G,H J 2 D,E

Network Analysis example AOA Ac7vity dura7on predecessor A 10 - B 20 - C 4 - D 2 A E 10 B,C F 8 B,C G 4 B,C H 2 C I 6 G,H J 2 D,E 8 paths CP

Network Analysis example AOA Ac7vity dura7on predecessor A 10 - B 20 - C 4 - D 2 A E 10 B,C F 8 B,C G 4 B,C H 2 C I 6 G,H J 2 D,E 8 paths E from 10 to 8: 30 CP CP 14

Network Analysis example AOA à AON AOA A,3 B,7 C,4 D,6 AON BEGIN A,3 B,7 END C,4 D,6 With AON you don t have dummies

Network Analysis example AON A,10 D,2 Ac7vity dura7on predecessor A 10 - B 20 - C 4 - D 2 A E 10 B,C F 8 B,C G 4 B,C H 2 C I 6 G,H J 2 D,E B B,20 C,4 E,10 F,8 G,4 H,2 J,2 I,6 END ADJ 14 BEJ 32 BF 28 BGI 30 CEJ 16 CF 12 CGI 14 CHI 12