Wes Yeomans Vice President Operations Management Committee May 31, 2017 COPYRIGHT NYISO ALL RIGHTS RESERVED

Similar documents
Ramapo Phase Angle Regulator Cost Recovery Discussion

Con Ed/PSEG Wheel Replacement Protocol - Update

Operational Aspects of PJM/NYISO Wheel Replacement Protocol

Broader Regional Markets Report

Broader Regional Markets Report

Broader Regional Markets Report

Con Ed/PSEG Wheel Replacement Proposal A joint white paper from the New York Independent System Operator and PJM Interconnection

PSE&G/ConEd Wheel Modeling

Broader Regional Markets Report

Less than 20 MW Constraint Reliability Margin Values

Summer 2017 Capacity Assessment

Summer 2018 Capacity Assessment

Securing 100+kV Transmission Facilities in the Market Model Market Design Complete Presentation

Broader Regional Markets Report

Broader Regional Markets Report

Locational Export Capacity Proposal

Broader Regional Markets Report

New York Independent System Operator, Inc. NYISO Tariffs. OATT Schedules

PJM/NYISO Wheel Replacement

Broader Regional Markets Report

Congestion Assessment and Resource Integration Study (CARIS)

CRIS for External-to-ROS Transmission Investment External-to-ROS Deliverability Rights (EDR)

NYISO / PJM - Focused Study Reliability Analysis. Northeast Coordinated System Plan IPSAC09 November 06, 2009

Proposed ICAP Manual Revisions Regarding Deliverability Requirements for Capacity Imports from PJM

Coordination with PJM

PJM Manual 27: Open Access Transmission Tariff Accounting Revision: 88 Effective Date: November 16, 2017

Lake Erie Loop Flow Modifications

PJM Manual 29: Billing Revision: 28 Effective Date: April 1, Prepared by Market Settlements Department

PJM Manual 29: Billing Revision: 28 Effective Date: April 1, Prepared by Market Settlements Department

Large Scale Solar Integration

Small Generator Interconnection Procedures

PJM Business Practices for Hudson Transmission Service

PJM Manual 29: Billing. Revision: 26 Effective Date: 11/20/2014. Prepared by Market Settlements Department

PJM Business Practices for Neptune Transmission Service

2017 Project Prioritization & Budgeting Process

Solar Integration Study

PJM Manual 29: Billing. Revision: 23 Effective Date: January 1, Prepared by Strategic Market Services Department

Consumer Impact Analysis: Proposed Assumption Framework

Constraint Specific Transmission Shortage Pricing. Study Approach

Carbon Pricing Straw Proposal Overview

JCM Drill Down Report -- Draft. March 21, 2014

Gas-Electric Coordination A NYISO Perspective

Alternative Methods for Determining LCRs

Carbon Pricing Import/Export Transaction Examples

OPEN ACCESS TRANSMISSION SERVICE TARIFF OF THE

JCM Drill Down Report. February 19, 2015

SCHEDULE 12 Transmission Enhancement Charges

Deliverability Requirements for Capacity Imports

Carbon Pricing: Treatment of Existing REC Contracts. Michael DeSocio Senior Manager, Market Design IPPTF. October 11, 2018, Rensselaer, NY

ISO/RTO Metrics Initiative

NYISO Pilot Program Update

Energy Uplift (Operating Reserves)

Distributed Energy Resources Roadmap

Shared Governance at the New York Independent System Operator

Wholesale Markets for the Grid of the Future Whitney Lesnicki Manager, Energy Market Design DRAFT FOR DISCUSSION PURPOSES ONLY

SCHEDULE 6A Black Start Service

Sustaining & Enhancing Reliability in NY

Applicable New York Wholesale Electricity Supplier Emissions

/s/ Henry Chao Henry Chao Vice President, System Resource Planning. December 9, 2013

NYISO/PJM Market-to-Market Coordination

Consumer Impact Analysis: Transmission Constraint Pricing

Attachment M3 and Sub-Regional RTEP Process Improvements. TRPSTF September, 27, 2017

Style Definition: PJM_Normal. PJM Manual 29: Billing. Revision: 267 Effective Date: 11/20/2014. Prepared by Market Settlements Department PJM 20162

2017 CARIS Phase 1 Report

Broader Regional Markets

PJM Transmission Replacement Processes Senior Task Force COST ALLOCATION & COST RECOVERY Educational Session. June 3, 2016

Midwest ISO EIM Start-up and Exiting Issues Todd Ramey, Executive Director Market Administration. March 7-8, 2011

5.1 Transmission Congestion Charge Calculation Calculation by Office of the Interconnection.

Public Policy Transmission Planning Process Manual

Ethan D. Avallone Senior Market Design Specialist, Energy Market Design ICAPWG/TPAS February 21, 2018 Rensselaer, NY

2018 DRAFT Annual Incentive Goals

SCHEDULE 12 Transmission Enhancement Charges. Establishment of Transmission Enhancement Charges.

LOAD SERVING ENTITIES PJM REGION

Western New York Public Policy Transmission Planning Report. A Report by the New York Independent System Operator. Final Report

Constraint Specific Transmission Demand Curves

Update on Northeast Seams Issues. February 20, 2008 NYISO Business Issues Committee Meeting

2020/2021 RPM Base Residual Auction Planning Period Parameters

Issue Track 5: Customer Impacts

Témoignage de Mme Judy W. Chang de The Brattle Group sur la politique d'ajouts au réseau de transport

Price Correction Deadlines: Proposed Tariff Changes

the Real-Time Market will be based on the system marginal costs produced by the Real-Time

Section 3 Characteristics of Credits Types of units. Economic Noneconomic Generation.

Mothball Outages in Capacity Markets

Linden VFT Scheduled Line Market Integration Update Initial Tariff Review

2019 Project Prioritization and Budgeting Process

Illinois State Institute for Regulatory Policy Studies Conference

2018 Project Schedule Milestone Update

MC Legal Report Summary of Significant Filings And Federal Energy Regulatory Commission ( Commission ) Orders (April 18, 2016 May 8, 2016)

Expanding Capacity Eligibility

the Real-Time Market will be based on the system marginal costs produced by the Real-Time

PJM s Implementation of Order 845

New York Independent System Operator System Reliability Impact Study Criteria and Procedures

MISO-PJM Joint and Common Market Drill Down Report

PJM Wholesale Markets. Hisham Choueiki, Ph.D., P.E. Ohio PUC Staff October 20-24, 2014 Tbilisi, Georgia

Carbon Pricing Carbon Residual Allocation

MISO-PJM Joint and Common Market Drill Down Report

MISO-PJM Joint and Common Market Drill Down Report

CUSTOMER GUIDE TO PJM BILLING

Written Statement of Thomas Rumsey Vice President External Affairs New York Independent System Operator

Schedule 9 and 10 PJM /23/2017

Transcription:

Ramapo Phase Angle Regulator Cost Recovery Wes Yeomans Vice President Operations Management Committee May 31, 2017

Agenda Background Benefits of Two Ramapo Phase Angle Regulators Annual Cost Projections Proposal Motion Next Steps 2

Background In 1993, members of the New York Power Pool (NYPP) and the PJM group p( (i.e.,, certain PJM transmission owners) executed an agreement requiring Con Edison to purchase, install, own, and maintain two Phase Angle Regulators (PARs) at the Con Edison Ramapo Substation for the purposes of controlling power flows on the 500 kv Branchburg-Ramapo 5018 transmission line between the NYPP and PJM. The 1993 Ramapo PAR Agreement defines the monthly cost allocation terms associated with the two Ramapo PARs. The agreement requires its signatories to each pay for a portion of the Ramapo PAR costs. 50% of the costs are allocated to members of the NYPP and 50% are allocated to the PJM group. 3

Background On June 24, 2016, a fire at the Ramapo Substation resulted in the catastrophic failure of the Ramapo PAR #3500. There is currently only one PAR in operation at the Ramapo Substation Con Edison is waiting for certainty on cost allocation prior to installing a replacement PAR at Ramapo. 4

Joint NYISO/PJM Initiative The NYISO and PJM have commenced a joint stakeholder initiative to consider modifying the NYISO- PJM Joint Operating Agreement (JOA). This will address cost recovery and cost allocation for the expenses Con Edison incurs to maintain two Phase Angle Regulators at the Ramapo Substation The joint PJM-NYISO stakeholder initiative began March 9, 2017 5

Providing Cost Recovery will Accelerate Installation of the Second PAR NYISO believes there are significant benefits to both New York and PJM of maintaining two PARs at Ramapo. Delay in reaching agreement on interregional cost allocation should not be permitted to indefinitely delay the installation of a second PAR at Ramapo. Assuring Con Edison that it will be able to recover its costs after Con Edison installs and places in-service a second PAR at Ramapo is expected to accelerate the installation of a second PAR at the Ramapo Substation. 6

Benefits of Two Ramapo PARs Reliability Reliability benefits in event of extreme contingencies or restoration Economic Increased total energy import capability from PJM into NYISO with 2 PARs Increased capability to direct PJM AC import schedules into eastern NY with 2 PARs Increased real-time Market-to-Market capability Minimum i Installed Capacity Requirements Reduced Installed Reserve Margins & Locational Capacity Requirements 7

Reliability Benefits Beyond Criteria Events: Actual contingencies beyond minimum NERC Planning Criteria can and do occur. Both PJM and NYISO recognize higher levels of reliability during periods of extreme contingencies with two Ramapo PARs in-service. Two Ramapo PARs reduce the risk of sustained, customer outages during extreme contingencies (severe thunder storms, ice storms, hurricanes, extreme conditions). Flexibility: The control capability provided by the two Ramapo PARs increases operational flexibility for NYISO. Power injections can be directed where needed for reliability. Restoration Resource: The Hopatcong-Ramapo 5018 line with two PARs in-service can provide tremendous support during a restoration event in either eastern NY or eastern PJM; as was the case in 2003. 8

Economic Benefits Summer Import Scheduling Limits from PJM to NYISO Two Ramapo PARs 1,750 MW One Ramapo PAR 1,400 MW Zero Ramapo PARs 1,000 MW (#5018 in-service, PARs bypassed) Ramapo Target Flows Post May 2017 Two Ramapo PARs 32% of PJM-NY AC schedule plus 80% of RECO One Ramapo PAR 16% of PJM-NY AC schedule plus 80% of RECO 9

Economic Benefits Production Cost Simulation NYISO considered a No Ramapo PARs scenario to determine the production cost benefits NY realizes from two Ramapo PARs on the 500 kv Hopatcong Ramapo 5018 interconnection

Economic Benefits Production Cost Simulation Base Case Two Ramapo PARs Started with 2016 CARIS 2 Base Case Assumed two Ramapo PARs in-service Assumed Energy Import Scheduling Limit of 1750 MW Only Evaluated Year 2018 Assumed ABC-JK 1000 MW wheel expired Western ties carry 32% of PJM-NYISO AC Interchange 5018 Line carry 32% of PJM-NYISO AC Interchange plus 80% RECO PAR ABC to carry 21% of PJM-NYISO AC Interchange plus 400 MW OBF PAR JK to carry 15% of PJM-NYISO AC Interchange minus 400 MW OBF

Economic Benefits Production Cost Simulation Sensitivity Case No Ramapo PARs (Line 5018 in-service, PARS bypassed) Started with 2016 CARIS 2 Base Case Assumed no Ramapo PARs in-service Assumed Energy Import Scheduling Limit of 1000 MW Only Evaluated Year 2018 Assumed ABC-JK 1000 MW wheel expired Western & Line 5018 carry 64% of PJM-NYISO AC Interchange PAR ABC to carry 21% of PJM-NYISO AC Interchange plus 400 MW OBF PAR JK to carry 15% of PJM-NYISO AC Interchange minus 400 MW OBF

Economic Benefits Production Cost Simulation Using the 2016 CARIS 2 database with the assumption on slides 15-16 resulted in; $25 million in production cost benefits of two Ramapo PARs versus no Ramapo PARs $100 million in NY Load Payment benefit of two Ramapo PARs versus no Ramapo PARs

Economic Benefits Installed Capacity Based on 2017 IRM Study Report, the minimum Installed Reserve Margin (IRM) and Locational Capacity Requirements (LCRs) would increase with one Ramapo PARs assumed out-of-service: Ramapo PARs In- Service IRM Zone J NYC Zone K Long Island 2 118.1% 81.6% 103.5% 1 118.4% 81.8% 103.8% Potential capacity market impact of a reduction from two Ramapo PARs to one Ramapo PAR would result in approximately a $75 million impact across Rest of State, Zone J, and Zone K 14

Annual Cost Projection The preliminary, annual cost projection from the asset owner to install, maintain, and operate two PARs at the Con Edison Ramapo substation is approximately $5.5 5 million per year. 15

Commitment to Install Replacement PAR The asset owner will proceed with replacing the Ramapo PAR #3500 (the one destroyed in the June 2016 Ramapo fire) after an affirmative 58% vote at the NYISO Management Committee 16

NYISO Proposal NYISO proposes to make modifications to Rate Schedule 1 of its OATT whereby NY Transmission Customers would, on a going-forward basis (commencing on the effective date of the Tariff revisions), pay up to 100% of the charges associated with installing a second PAR at Ramapo and Con Edison s s cost of owning, maintaining and operating the two Ramapo PARs Tariff revisions also provide for: Transparency of the Ramapo PARs Charge Potential partial refund of the Ramapo PARs Charge to NY Transmission Customers if PJM pays for part of the cost of the PARs 17

Con Edison s Ramapo PARs Charge Con Edison will calculate the Ramapo PARs Charge in accordance with the 1993 PARs Facilities Agreement Filed in FERC Docket No. ER93-640 on May 10, 1993 NY Transmission Customers will commence reimbursing Con Edison on a going-forward basis, for Up to 100% of the costs to acquire and install a replacement for the 3500 PAR, and Up to 100% of the going-forward costs to own, operate and maintain both Ramapo PARs If PJM assumes an obligation to pay a portion of the Ramapo PARs Charge, the NY Transmission Customers obligation will be reduced by that amount Con Edison will not submit a charge that would cause NY Transmission Customers to pay more than 50% of the cost of replacing the 4500 PAR or more than 50% of the charges Con Edison issued for the 4500 PAR prior to the effective date of these proposed tariff revisions 18

Transparency of the Ramapo PARs Charge NYISO will post on its website the itemized monthly bill (for the preceding month) it receives from Con Edison that t determines the Ramapo PARs Charge By August 1 of each year, Con Edison will prepare and NYISO will post on its website an estimate of the monthly costs and expenses associated with the Ramapo PARs for the next calendar year and for each of the four subsequent years Con Edison will maintain books and records related to its calculation of the Ramapo PARs Charge, including costs incurred Such books and records will be subject to review by the NYISO s Transmission Customers NYISO will not audit the monthly bills, books or records prepared by Con Edison for the Ramapo PARs Charge 19

Potential Refund of the Ramapo PARs Charge If NYISO receives a refund from Con Edison, or a payment from PJM or PJM TOs related to the Ramapo PARs Charge, the NYISO will refund the amount received to its Transmission Customers Any refunds will be allocated to Transmission Customers based on their market participation during the Billing Period in which the refund is paid using the same load ratio share basis used to allocate the NonISOFacilitiesCosts charges to Transmission Customers 20

Next Steps May 31 MC July NYISO Board of Directors July FERC filing The replacement for the 3500 PAR is expected to be in service in September 2017 Continued joint NYISO-PJM stakeholder discussions on regional benefits and regional cost allocation 21

The Mission of the New York Independent System Operator is to: Serve the public interest and Provide benefit to stakeholders by Maintaining and enhancing regional reliability Operating open, fair and competitive wholesale electricity markets Planning the power system for the future Providing factual information to policy makers, stakeholders and investors in the power system www.nyiso.com 22