Open Networks Project

Similar documents
Open Networks Project 2018 Work Plan Consultation innogy renewables UK response

Open Networks Project Phase Project Initiation Document

Energy Networks Association Open Networks Project 2019 Workplan Webinar. February 13 th :30 pm

Open Networks Project Phase 2 Work Programme Webinar (15 Feb)

Electricity Network Innovation Strategy

Energy Networks Association

Energy Networks Association Open Networks Future Worlds Stakeholder Event

Energy Networks Association Open Networks Future Worlds Stakeholder Event

Energy Networks Association

Thank you for joining the Future Worlds consultation webinar. The webinar will start at 14:03.

Open Networks Workstream 3: Product 2

Energy Networks Association Open Networks Future Worlds Stakeholder Event

Energy Networks Association Open Networks Project. Delivering the Internet of Energy

Charging Delivery Body. 8 th August 2018

Driving performance through stakeholder engagement

Energy Networks Association - Response to Call for Evidence from BEIS/Ofgem

Open Networks Project Opening Markets for Network Flexibility Achievements and Future Direction

Electricity System Operator Forward Plan 2018/19

Energy Networks Association

Gas Network Innovation Strategy

25 September 2018

In responding to the consultation, we would like to draw your attention to the following points:

Energy Networks Association

DS3 System Services Project Plan Detailed Design and Implementation Phase

Energy Networks Association

Western Power Distribution Workplan to Improve Connections Performance 2014/ Quotation and Acceptance

ElectraLink s response to the Open Networks Future Worlds Consultation. To Whom It May Concern:

Introduction. Relevant IBM experience. Summary of our Response

The Energy Networks Association 4 More London Riverside LONDON SE1 2AU

Strategic Investment Options for Low Carbon Economy in the South Wales. 15th June 2016

Open Networks Workstream 1 (T-D Processes)

BUUK Infrastructure Energy House Woolpit Business Park, Woolpit, Suffolk, IP30 9UP

Energy. Association. Networks. Association. Insert presentation title here. The Voice of the Networks. Open Networks Project

Future arrangements of the System Operator. Cathy McClay Head of Commercial Operations

Facilitating Whole Electricity System Outcomes

SO incentives from February 2012

Transmission Charging Methodologies Forum. 8 th of December 2016

a) Seek clarification from the Department for Transport in respect of future core funding for the work of the Strategic Transport Forum.

Opportunities & challenges in current markets & gearing up for the future

ELEXON response to National Grid s consultation of its System Needs and Product Strategy 18 July 2017

ENA Future Worlds Consultation

1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review:

Targeted Charging Review SCR, Regulating the Future Energy System and the Charging Futures Forum. 11 October 2017

CBI Response to BEIS Call for Evidence

Energy UK response to the Electricity System Operator Forward Plan

UK Power Networks Innovation and future energy systems. Neil Madgwick & Giulia Privitera 3 March 2017

277/06 - PRELIMINARY TERRE (P344) IMPLEMENTATION IN ADVANCE OF OFGEM DECISION

The Voice of the Networks

SSEN Consultation: Unlocking Orkney s renewable potential

Response to the ENA Consultation on Future Worlds

Back to contents. Executive Summary. Flexibility Roadmap. FutureSmart. A smart grid for all: Our transition to Distribution System Operator

Consultation on DS3 System Services Contracts for Interim Arrangements. DS3 System Services Implementation Project

Stakeholder Engagement Plan for the Distribution System Security and Planning Standards Review Project

Electricity System Operator Forward Plan 2018/19: Stakeholder Engagement Report

Tenant and Customer Engagement Strategy

Open Networks Project

Energy UK response to National Grid System Needs and Product Strategy Consultation

GOVERNANCE SMART objectives / SUHFT board development programme

Wider Access to the Balancing Mechanism Roadmap

Consultation on the Electricity System Operator forward plan

Ofgem Incentive on Connections Engagement 2017/18 Key Performance Indicators

Market-wide Half-Hourly Settlement

NATIONAL GRID. NTS Shrinkage Incentive Methodology Statement Submitted for Approval

ENERGY NETWORKS ASSOCIATION RESPONSE TO RIIO-2 OPEN LETTER

NATIONAL GRID. NTS Shrinkage Incentive Methodology Statement

NIA Project Registration and PEA Document

Energy Networks Association

10 th January SPEN DSO Vision Consultation Responses

GENERAL GUIDELINES FOR REINFORCING THE COOPERATION BETWEEN TSOs AND DSOs

Power Potential webinar

Introduction to local flexibility markets What are flexibility services and how can I get involved? Jodie Giles Senior Project Manager

NPSO Limited. New Payment System Operator 2 Thomas More Square London E1W 1YN. 28 th March 2018.

EFSA Strategy 2020 AF meeting. Luxembourg, 8 9 December 2015

Electricity Market Reform (EMR) Contingency Products. Peter Bingham EMR Team

Electricity System Operator Forward Plan Consultation Event

Initial Modification Report No.39. Transfer of Exit Capacity between Northern Ireland Exit Points to permit Secondary Trading of Exit Capacity

Victorian AMI Program Stephen Thomson, AMI Program Director Principal Consultant Marchment Hill Consulting

C22(12) COUNCIL. GOC Business Plan KPIs and Core Activity Performance Indicators. Lead responsibility: Samantha Peters Chief Executive and Registrar

OPTIMISATIONS IN THE USE OF DIGITAL DOCUMENT MANAGEMENT FOR COLLABORATIVE ENGINEERING DESIGN. deliver projects better, faster, together

The Voice of the Networks Energy Networks Association

Operating Margins Report July 2016

PASSPORT TO PERFORMANCE Your Year-End. Empowering you to do your best work every day

NHS Improvement Agency Usage Board Diagnostic Tool

Alternative Connection Application and Offer Process Proposal

NPSO Ltd. Participant Community Event 17 th January Aldersgate, London. For internal use only

Outage Management Redesign Consultation Process (SE-109) Proposal for Process Redesign May 14, 2013

2019 Business Plan Principles and Approach Consultation Customer Feedback Report Publication Date: 16 th July 2018

Joint European Stakeholder Group. Tuesday 9 January 2018 Meeting 28 WebEx

G4 DEVELOPMENT. Document 2 of 12 Statistics: Quantitative Online Feedback. Second G4 Public Comment Period: Submissions.

REA response to Ofgem Targeted Charging Review consultation including ending grid fee double charging for storage operators

European Developments

Introduction. Background and Context. Role and Function of the PSI. Developing the Corporate Strategy

Date: 4 October 2017 Time: 10h30 15h00 Place: ENTSO-E premises, Avenue de Cortenbergh 100, conference room - AMPERE

Innovation to enable the DSO transition. Network Innovation Competition (NIC Bid) 2017 WPD/EN/NIC/03

NHS Supply Chain May SME participation figure is 28% by sales value across both transacted and nontransacted

Corporate Policy and Strategy Committee

Response to BEIS Consultation on Coal Generation in Great Britain: The pathway to a low-carbon future 08 February 2017

WELCOME TO WARWICK EMPLOYERS GUIDE

EIANZ (WA Division) Strategic Planning Session Outcomes & Action Plan (DRAFT) 11 December 2016

Asset Management Policy

Transcription:

Open Networks Project Consultation on Phase 2 Work Programme 30 January 2018 Document Ref: ON-Phase 2 Programme T +44 (0) 20 7706 5100 W www.energynetworks.org.uk E info@energynetworks.org 1

Introduction and Background to the Open Networks Project In December 2016, (ENA) members gave their commitment to the Open Networks Project, a major collaboration that will transform the way that electricity networks will operate and work for customers. Launched in January 2017, ENA s Open Networks Project has started to lay the foundations of a smart energy grid in the UK. It is a key initiative to deliver Government policy set out in the Ofgem and BEIS Smart Systems and Flexibility Plan, the Government s Industrial Strategy and the Clean Growth Plan. The Open Networks Project has introduced real momentum into the development work required to enable the UK s energy networks to: Facilitate our customers transition to a low carbon future, including the electrification of heat and transport. Address the challenges rising from the continued uptake of local generation. Evolve to be market enablers for a whole range of new smart energy technologies. Reduce costs to customers by contracting for flexibility services alongside investment in traditional and innovative network solutions. Play a key role in delivering overall lowest energy system costs for customers. Electricity is an essential service to our customers, and their reliance on it will grow, for example with the electrification of transport. Network operators must meet these challenges whilst: Continuing to deliver safe and secure operation of their Networks. Ensuring efficient and timely access to networks for customers. Continuing to provide value for money. Ensuring that our universal service continues to be available to all customers on a fair basis. The ENA Open Networks Project is intending to meet these goals by transforming the way our energy networks work and underpinning the delivery of the smart grid. It brings together transmission and distribution network operators from Great Britain, Northern Ireland and the Republic of Ireland and has included a broad range of stakeholders in its development work, including the energy regulator Ofgem, Government departments, independent Distribution Network Operators (idnos), customers, generators, suppliers, storage providers, respected academics, Citizens Advice Bureau and other NGOs amongst others. The Open Networks Project is carrying out extensive and comprehensive assessment of transmissiondistribution interactions and future Distribution System Operator functionality. We are taking a whole system approach to transmission and distribution (with consideration of gas, heat and other crossvector industries) and we will take account of other network-led and wider industry work. For example, we will continue to work closely with the Future Power System Architect (FPSA) initiative. Any changes to existing industry codes and frameworks that are proposed as a result of Open Networks work will be taken through the appropriate industry governance processes. In December 2017, we published our report Opening Markets for Network Flexibility; 2017 Achievements and Future Direction, which can be found here: http://www.energynetworks.org/electricity/futures/open-networks-project/eoy-report-2017.html In order to facilitate open debate and discussion across industry, all outputs from the Project are being published here, alongside additional information: http://www.energynetworks.org/electricity/futures/open-networks-project/open-networks-projectworkstream-products.html T +44 (0) 20 7706 5100 W www.energynetworks.org.uk E info@energynetworks.org 2

Purpose of this Consultation Following our successful delivery in 2017, we have scoped and planned our development work for 2018 and it is this plan of work, set out in the attached Phase 2 Project Initiation Document, which we are inviting responses to in this consultation. It is very important for the success of the project that we focus on the right topics and that we are informed by the widest possible stakeholder perspective. This Phase 2 workplan has been built up with stakeholder input through our Advisory Group, but this consultation is an opportunity for all stakeholders to consider the full workplan and feedback on priorities, scope, time-scales and those areas where detailed consultation is proposed through 2018. The paper outlines the 2018 workplan and asks a short set of questions. We have established the project to be adaptable and feedback will be used to: Prioritise the work to be carried out in Phase 2. Add further products to the Phase 2 programme if needed or defer proposed products from the Phase 2 programme if these do not address priority areas of work. Adjust the detailed scope and timing of products. Adjust the proposed stakeholder engagement, communication and consultation plans. This consultation is being processed quickly so that feedback can be used to adjust the Phase 2 workplan. The consultation is not holding up progress on the project, as we have begun Phase 2 on the basis of what is set out in the Phase 2 Project Initiation Document. How to Engage and Respond We will be hosting an open webinar/webex on this consultation on 15 th February and further details will be provided on the ENA website and to people on our stakeholder distribution list. You can sign up for this distribution list or ask any questions by emailing the Open Networks project at the address below. The consultation closes on 23 rd February 2018. Please send your responses electronically to opennetworks@energynetworks.org. We intend to publish all responses on the ENA website, therefore if your response is confidential and not for publication, please clearly notify us or if elements are confidential, please provide us with a full version for consideration and a non-confidential version for publication. All are welcome to respond: Feedback on this paper is welcomed from all stakeholders, including (but not exclusively): network users, energy market participants; network operators, independent distribution network operators, aggregators, suppliers, DER, consumers, community energy schemes, new and existing business models and technologies. Phase 2 2018 Programme Overview The Phase 2 work in 2018 will build on and add to the work carried out in Phase 1. The project will continue to be managed through 5 workstreams considering: 1) T-D Processes, 2) Customer Experience, 3) DNO to DSO Transition, 4) Network Charging and 5) Communications. T +44 (0) 20 7706 5100 W www.energynetworks.org.uk E info@energynetworks.org 3

Much of the work will be delivered through workstream products with well-defined outputs. The Phase 2 programme develops and adds to the work started in Phase 1. New products have been developed through the gap analysis and stakeholder reviews carried out during Phase 1. Figure 1 Short/Medium/Long-Term Open Networks Programme Phases Overall, the Phase 2 programme is significantly larger than Phase 1. Around twice as many network operator resources are planned to be directly engaged across the different workstreams and products. Given the number of products, there will also be interactions and dependencies between workstreams and products such that project management will be even more important, and we are working on clarifying the interactions between workstreams. Work carried out in Phase 2 will continue to draw on innovation projects and other case studies including those summarised in Figure 2. In addition, 3 projects approved as part of the 2017 Network Innovation Competition (Fusion, Electricity Flexibility and Forecasting System and Transition) will be used to trial aspects of the work. Figure 2 Case Study Timelines T +44 (0) 20 7706 5100 W www.energynetworks.org.uk E info@energynetworks.org 4

Stakeholder Engagement & Products Proposed for Consultation Given the increased size and scope of the programme, effective engagement with stakeholders will continue to be crucial. We will continue to use the Stakeholder Advisory Group 1 to provide input to our development work as we progress and we will engage other groups (e.g. DER Connections Group) for input to particular products. There are some key products that we wish to go beyond our project stakeholder groups and put out to public consultation to gather the widest possible set of stakeholder views. Stakeholders have asked us for a schedule of when to expect these consultation papers and our latest view of public consultations and when these would be issued is given below. Product Description Timing Overall Project WS1 T-D Processes Future Workplan & Prioritisation for 2018. Jan 18 1 Investment Processes Dec 18 Whole system investment models and proposed extension to NOA framework to include DER solutions. 10 Current good practice document for flexibility connections. Potential formal consultation. Apr 18 WS2 Customer Experience 2 Position paper for capacity recycling. A formal Sep 18 consultation is likely to be linked to Ofgem s review of Network Access and Forward Looking Charges. 5 Improve customer information and improve network operator processes including queue management. Potential formal consultation. Oct 18 WS3 DSO Transition 5 Seek input on DSO modelling, leading DSO models and key criteria on which to base cost benefit assessment. Jun 18 Figure 3 Plan for Public Consultations on Open Networks Products We expect that any consultation associated with Workstream 4 will carried out through the Ofgem-led work of the Charging Futures Forum and Charging Delivery Body. Workstream Overview Workstream 1 (WS1) will continue to focus on transmission-distribution (T-D) investment and operational planning processes and on how to improve these in the shorter term to enable greater DER access to networks and services, introduce whole system investment planning, provide further information to customers and ensure continued network reliability. This will build on work carried out in Phase 1 including the commercial principles and models for accessing DER services that were consulted on in August 2017. 1 The Stakeholder Advisory Group is a representative group containing approximately 40 experts from across the GB energy industry including Suppliers, Aggregators, idnos, industry groups, academia, Generators, consumer groups, the gas industry, Government, Ofgem and other industry parties. The group works closely with the Open Networks project team to shape and review workstream products. Membership of the Stakeholder Advisory Group is detailed at the following link Stakeholder Advisory Group. T +44 (0) 20 7706 5100 W www.energynetworks.org.uk E info@energynetworks.org 5

Tangible customer benefits from the 2018 work should include new opportunities for DER to provide services to support transmission and distribution network operators and to participate in whole system investment solutions. A broader range of information will be made available to distribution customers and service providers through 2018. Network operators will also take forward actions to ensure that the wider benefits of DER are not undermined by unintended impacts on network reliability. 13 separate WS1 products are included in Phase 2. These are more fully described in the Phase 2 Project Initiation Document. WS1 Products Description Timescale 1 Investment Processes 2 DER Services Procurement 3 Industry Framework Interactions 4 Reliability Standards & Emergency Requirements Enable a whole system approach utilising a range of investment and operability options across T&D. Build on 2017 Product 3 to extend the Networks Options Assessment (NOA) process for transmission network reinforcement to include distribution sourced options. This product would include public consultation late in 2018. Put in place the framework for providing contract visibility, conflict resolution and service optimisation across T&D networks. (Build on 2017 Product 4.) Consider the operational exchanges to schedule and despatch services. Ensure that Open Networks outputs are reflected into code & framework development including European Network Code adoption and BSC modifications. Ensure that emerging Whole System investment & operational processes maintain security of supply across T&D and cover requirements under emergency conditions. 5 Whole System FES Establish a whole system approach to Future Energy Scenarios. 6 Regional Service Define and publish regional service requirements and Requirements constraint heat maps. Ongoing to Dec 2018 Ongoing to Dec 2018 Jan to Sep 2018 July 2018 onwards 7 ANM Information Establish processes to capture ANM system status and performance for investment planning purposes. 8 System Wide Review the feasibility of putting in place a system-wide Resource Register resource register for GB generation, storage and flexible 9 TSO-DSO Transmission Impacts 10 Facilitating Connections Current Practice for Flexible Resources 11 Facilitating Connections Action Plan and Report 12 TSO/DSO & DER Data Requirements 13 Operational Data & Control Architectures demand (T&D). Complete work to replace Statement of Works and embed updated TSO-DSO processes across GB. Review current DNO approaches to flexibility queue management and publish a document to stakeholders to clarify DNO practice at present on handling flexibility. This product is expected to include a public consultation in April 2018 to seek customer views on good practice. Develop gap analysis and action plan for flexible resources in connection queues (including storage as per action 1.6 from the Smart Systems and Flexibility Plan) and publish to stakeholders. In light of DSO-TSO changes (Statement of works), consider revisions to existing data exchange processes. Also, update the data requirements to be provided from DER customers when they apply for a connection and after they agree a connection from the DNO. Further develop the architectures and mechanisms for operational data exchange. This will support other products. May to Dec 2018 Jan to Sep 2018 Jan to Jun 2018 Ongoing to May 2018 Feb to Dec 2018 Workstream 2 (WS2) will continue to focus on improving customer experience. It will look to improve the information available to customers to support network connection and service provision, review and recommend ways to better manage ongoing network connections and provide greater clarity on the use of industry terminology. T +44 (0) 20 7706 5100 W www.energynetworks.org.uk E info@energynetworks.org 6

At present, WS2 s scope and products are clearer for the first half of 2018. Much of this early work is focussed on agreeing and promoting existing good practice across network operators. In doing this, WS2 product teams will work closely with WS1 and WS3 product teams where scope is closely related. Later in 2018, as T-D processes are updated through WS1 and as DSO functionality is agreed through WS3, it is likely that WS2 products will be further developed. Tangible customer benefits from the 2018 work should include enhanced information to support network connections and service provision. Approaches across distribution networks should also be more consistent. The work could also provide opportunities to better use existing network capacity. 8 separate WS2 products are included in Phase 2. Again, these are more fully described in the Phase 2 Project Initiation Document. WS2 Products Description Timescale 1 Good Practice ahead of Connection Applications Review network operator approaches for handling prospective connection applications and publish good practice for supporting customers pre-application. Jan to Jul 2018 2 Management of Capacity 3 Explanation of Terms & Definitions 4 Information on Flexibility Services 5 Good Practice Following Connection Applications 6 Guidance on Post Connection Changes 7 Provision of Constraint Information Identify and review options for managing and planning capacity that may be contracted for but may not be being used by customers. Options and principles would be laid out in a position paper and recommendations would be provided to Ofgem & BEIS. This product is expected to include a public consultation around September to help establish recommendations. Produce a document that explains commonly used terms such as 'firm and unfirm'. This would be published and used by network operators going forward to provide greater clarity for customers. Review how information should be provided to customers on potential DNO requirements for flexibility services. Agree good practice. Review approaches for handling customer connections in the post-application phase and agree good practice around areas including connection queue management. This product is expected to include a public consultation late in the year to seek feedback on proposals. Provide guidance to customers on the impacts of changes to DER operational regimes. Agree when and how changes should be notified to DNOs. Review what information on constraints and curtailment would be useful to customers, what can be provided and establish good practice for network operators. 8 2017 Product Updates Review the changes to connection arrangements agreed through WS1 s 2017 Product 6 and update WS2 2017 products (including journey maps) if required. Jan to Oct 2018 Jan to Jun 2018 Apr to Dec 2018 Jan to Sep 2018 Apr to Dec 2018 Jan to Apr 2018 Workstream 3 (WS3) will continue to determine the functionality that DSOs will require going forward. Specific Phase 2 objectives include the completion of ongoing SGAM (Smart Grid Architecture Model) modelling to fully describe and scope the models for DER services procurement. This builds on 2017 work to establish commercial principles and a range of potential models for accessing DER services. The modelling will also be extended to cover whole system planning of the electricity system. Phase 2 will also develop a cost benefit analysis to compare the costs and benefits of the different potential DSO models. It would look to agree those elements of consolidated DSO models that can be prioritised for action and identify any gaps in ongoing industry work to firm up technological requirements for DSOs and the wider industry. By the end of Phase 2, we would look to put in place an implementation plan to take forward those elements of DSO where functionality has been agreed by network operators and stakeholders and to show what steps might be needed to transition to a GB market model for DSO. The tangible customer benefits from the 2018 programme include a clear articulation of DSO functionality, an articulation of DSO value, and a proposed plan for implementing elements of DSO T +44 (0) 20 7706 5100 W www.energynetworks.org.uk E info@energynetworks.org 7

functionality to address key areas for customers and consumers relating to DER services procurement and whole system investment. This will draw heavily from the work being carried out in Workstream 1 under Products 1 and 2. Whilst Workstream 3 is focussed on agreeing enduring DSO arrangements, the Phase 2 work plan is designed to enable early delivery of DSO functionality through progressing no regrets actions to enable DSO, by surfacing key regulatory enablers and by utilising ongoing industry work as far as practicable. For example, if elements of DSO functionality are common to different models, these market agnostic elements could be taken forward ahead of wider industry agreement on a preferred market model. 8 separate WS3 products are included in Phase 2. Again, these are more fully described in the Phase 2 Project Initiation Document. WS3 Products Description Timescale 1 SGAM Modelling of DSOs and DER Procurement Future DSO Model SGAM Frameworks & Analysis (Started in Phase 1). Jan to Apr 2018 2 Further SGAM Modelling of DSO Functionality 3 Market Agnostic DSO Elements 4 Independent Review of DSO Models including CBA 5 DSO Model Validation & Review Including Public Consultation Further modelling to address stakeholder feedback on Commercial Principles and to cover further areas of DSO functionality. Complete Assessment of Market Agnostic elements of DSO functionality such that no regrets DSO implementation actions can be brought forward. Commission and support an independent assessment of the transition to different DSO models. As well as cost benefit analysis (CBA), this should include dimensions such as UK/EU regulatory compliance, sustainability, customer satisfaction, complexity, Smart Network indicators and impacts on vulnerable consumers. The assessment is intended to compare models and underpin regulatory impact assessments. Detailed review of SGAM outputs to ensure these provide a sound basis for DSO direction setting and implementation. Public consultation on market models and next steps is planned for June 2018. 6 Key Enablers for DSO Identify and document key enablers to implement DSO functionality (e.g. IT systems, comm s infrastructure, organisational changes, contract requirements, regulatory changes, funding). These would support comparisons and feed into the implementation plan. 7 Further Trials to Address Gaps in DSO Functionality 8 Preferred DSO Models & Proposed Implementation Plan Identify and initiate further trials to address any gaps. This will look to utilise ongoing projects including those approved as part of the 2017 NIC competition that will be aligned through the ON project - Fusion, Electricity Flexibility and Forecasting System and Transition. If necessary, further projects would also be considered. Draw on earlier work to determine elements of DSO Models that have been agreed by NO s & Stakeholders and develop and propose an Implementation Plan. Mar to Dec 2018 Mar to Dec 2018 Apr to Nov 2018 May to Sep 2018 Apr to Nov 2018 Mar to Dec 2018 Nov to Dec 2018 Workstream 4 (WS4) will continue to focus on network charging. Its main areas of work will be to support Ofgem s CFF (Charging Futures Forum) and related Task Forces to help provide development resource and network operator input to existing and future industry charging reviews. WS4 will also support Ofgem s CDB (Charging Delivery Body) in translating the results from the CFF into manageable actions and ensuring their delivery. It will provide continued input and support to inform the CFF on reforms required for network residual charges and provide support on charging to the wider Open Networks project. Finally, WS4 will develop recommendations to remove inefficient signals in charging and remuneration of TSO/DSO services such that customers and flexibility providers are presented with a level playing field whilst ensuring whole system cost reflectivity (rather than focusing on individual licensed parties) to deliver the best value for customers. T +44 (0) 20 7706 5100 W www.energynetworks.org.uk E info@energynetworks.org 8

Workstream 5 (WS5) will use a combination of public affairs, press, social media and direct engagement to raise stakeholder awareness around the need to think holistically across the transmission-distribution boundary, the DSO transition and its importance, the opportunities for stakeholders to engage with the Open Networks Project and the role network operators are playing in laying the foundations for the UK s smart electricity grid. WS5 will look to use a wide range of engagement techniques. These will include social media, webinars, industry events and Westminster panel events alongside the other approaches used in Phase 1. Key Questions on Phase 2 Programme Please consider and respond to the following questions, referring to the Phase 2 Project Initiation Document where possible: Q1. Which specific areas of 2018 work or Products are most important to you and why? Q2. Are there any other areas of work or Products you would like to see included in the Open Networks Phase 2 workplan and if yes, why and how should they be prioritised compared with other work? Q3. Should any areas of work or Products be removed or deferred and if yes, why? Q4. Do you agree with the proposed Products for wider consultation and what other work should be consulted on and why? Q5. Have you any feedback on the proposed timescales for delivery and consultation through Phase 2? Q6. How would you like to provide input to the Open Networks Project and be kept informed of developments? Next steps The consultation closes on 23 rd February 2018. Please send your responses to opennetworks@energynetworks.org. T +44 (0) 20 7706 5100 W www.energynetworks.org.uk E info@energynetworks.org 9