LOOK BEFORE YOU LEACH: DYNAMIC SIMULATION OF HEAP LEACH FLOWSHEETS

Similar documents
Calibration and Predictive Performance of a Two Domain Empirical Metal Recovery Model

White Dam Gold Project Dump Leach

HEAP LEACHING OF LOW GRADE URANIUM ORES AT SOMAIR

Dynamic Modeling for Design of Ion Exchange Systems. Khosrow Nikkhah

FLOWSHEET CONSIDERATIONS FOR COPPER-COBALT PROJECTS

AN EFFICIENT APPROACH TO COBALT, COPPER AND NICKEL RECOVERY FROM RAFFINATES, EVAPORATION PONDS, AND OTHER LOW GRADE STREAMS

LixTRA. Novel Copper Leach Technolgy

A cobalt solvent extraction investigation in Africa s Copper Belt

Evaluation of Copper Solvent-Extraction Circuit Data and Performance

Wetar Copper Project Development and Production Update

Characterization of gold inventory and impediments to recovery at an active heap leach facility

SOLVENT EXTRACTION PROCESS DEVELOPMENT AT GIRILAMBONE COPPER COMPANY - PREDICTED vs PLANT PRACTICE

Owendale pilot plant program completed successfully

Hydraulic performance of permanent heap leach with intermediate drainage system

FLOTATION CONTROL & OPTIMISATION

IN-PIT CRUSHING AND CONVEYING MINE PLANNING AND OPERATIONS Skillings Mining Review, June 1, 1985 by: Independent Mining Consultants, Inc.

THE CESL PROCESS: SUCCESSFUL REFINING OF A COMPLEX COPPER SULPHIDE CONCENTRATE

Water balance and cost evaluation for different scenarios of impermeable covers (raincoats) in heap leach pad operations

Heap Leach Development

Versatic 10 Acid/NICKSYN Synergistic System versus D2EPHA- Cyanex 272 for the Recovery of Cobalt from Typical DRC/Zambian Copper-Cobalt Leach Liquors

NICKEL AND COBALT RECOVERY FROM MESABA CONCENTRATE

Minerals to Market. September 26 th 2011

A Framework for improving the ability to understand and predict the performance of heap leach piles

MINIMUM ENGINEERING STUDY REQUIREMENT. 128 June 2015

SAG Page 2. Page 1

EXCELLENT NICKEL LEACHING TESTWORK RESULTS

ABS Software Brochure

Closure Planning for a Tailings Storage Facility in Western Australia

#Disrupt Mining: Integrated Extraction and Recovery System for Complex. Ores and Wastes"

Industrial Solutions

CHAPTER 1 INTRODUCTION


QUARTERLY REPORT FOR THE PERIOD ENDING 31 MARCH 2017

STARVED ACID LEACH TECHNOLOGY (SALT) CONCEPTUAL STUDY. InCoR Holdings Plc MINING AND METALLURGY. April 2014 REPORT Rev. 00 > Internal ref.

Long-Hole Stope Evaluation. Operating procedures. Introduction. 1. Approach of the model. 2. Notification. 3. Worksheets

For personal use only

Outotec OreMet Optimizer

The concept of linear scheduling

Energy-Mass-Size balance model for dynamic control of a wet open circuit grinding mill: Part II Simulation tests

Commodity XL Metals and Mining

Two-stage precipitation process of iron and arsenic from acid leaching solutions

Non-Ferrous Extractive Metallurgy Prof. H. S. Ray Department of Metallurgical & Materials Engineering Indian Institute of Technology, Kharagpur

Evaluation of Grade Engineering using Enterprise Optimization. Michael Scott, Nick Redwood

IN MINING & MINERAL PROCESSING

The Use of Simulation for Bulk Cargo Terminal Planning and Design

Improved Copper/Iron Selectivity in Solvent Extraction

A Holistic Approach to Control and Optimisation of an Industrial Crushing Circuit

A PROTOCOL FOR CONDUCTING AND ANALYSING PLANT TRIALS: TESTING OF HIGH-CHROME GRINDING MEDIA FOR IMPROVED METALLURGY

Enhanced Heap Leaching: II. Applications

Arsenic: The Argument for Hydrometallurgical Processing and Stabilization at the Mine Site

Hydromet Development and Commercial Nickel Processing Plant Update

For personal use only

Duluth Metals Provides Metallurgical Update on Twin Metals Minnesota Project

A PHASED DEVELOPMENT SCHEDULE FOR A PLATINUM CONCENTRATOR UTILIZING A DYNAMIC STOCKPILE MODEL

Simulation of the BioEthnaol Process

Closure Water Balance Model to Support Closure Designs for a Mine in Laos

Increasing Net Present Value by a Third at an Operating Sublevel Cave Mine Using Draw Strategy Optimisation. Presented by Alex Campbell

Whitepaper. Water Management in Mining.

It pays to talk to a specialist

Solvent Extraction versus Nano-Filtration for Upgrading Uranium and Recovery of Acid from an Ion Exchange Eluate

T S X : R M X N Y S E. M K T : R B Y

NEWS RELEASE GOLDEN QUEEN ANNOUNCES 2016 PRELIMINARY OPERATING RESULTS

IMPACT OF IN-PIT CRUSHING AND CONVEYING ON PIT SHELL OPTIMIZATION. Marc Johnson, Regional Manager - South America

Online analyser for heavy minerals grade control

DEVELOPMENT OF A NOVEL THREE-STEP SX PROCESS TO RECOVER COPPER FROM AN ACIDIC SOLUTION

Bioleaching Of Zinc Sulfide Ores And Concentrates

Impala Platinum reduces process variation by 40% with Mine Performance, from GE Predictivity

Positive Lerokis Copper Recovery Testwork

System dynamics modelling framework with specialized water management modules

For personal use only

QUADRA ANNOUNCES THIRD QUARTER 2009 PRODUCTION RESULTS

WA s MT THIRSTY COBALT-NICKEL PROJECT POTENTIALLY WORLD S FOURTH LARGEST COBALT PRODUCER

Review of ML/ARD Geochemistry & Water Quality Predictions

The Use of Computer Simulation for the Design of a Bioheap Leach for Sphalerite

THE USE OF SELECTIVE ION EXCHANGE FOR THE RECOVERY OF BASE METALS FROM EFFLUENT STREAMS

FOR IMMEDIATE RELEASE 30 August 2018 TSX-V: AZR

Kanowna Belle Pre-Oxidation Project

A phased development schedule for a platinum concentrator utilizing a dynamic stockpile model

PILOT TEST WORK TRIGGERS FINAL TRANCHE OF TREMONT FINANCING

ADVANCED MINERALOGY FACILITIES

COPPER PRECIPITATION AND CYANIDE RECOVERY PILOT TESTING FOR THE NEWMONT YANACOCHA PROJECT

HEAP LEACHING TECHNOLOGY Moving the frontier for treatment

BASE METALS REFINERY (dissolution of nickel, copper and cobalt) GE Mining

CONTRACT AWARDED FOR TESTWORK AND PURCHASE OF FIRST NATIVE COPPER SHIPMENT NATIVE COPPER IN HIGH DEMAND IN CHINA

APPENDIX 22C: CYANIDE MANAGEMENT PLAN

T S X : R M X N Y S E. M K T : R B Y. Rubicon Begins Stockpiling Mill Feed for Projected Production Commencing Mid-2015

EURARE Kvanefjeld Refinery Demo Plant Work Package 5

Grasberg Block Cave mine: cave planning and undercut sequencing

Optimizing mining operations

PYTHON UNDERGROUND PROCESSING PLANT CRITICAL DESIGN

Recent developments in spiral separator design include 3 mineral models; EP, HC and MG7S; and one coal model, the LD7C.

Study of the behavior of materials with fines content in heap leaching processes

Process optimization using real time tracking of coarse material in individual cyclone overflow streams

What is Enterprise Optimisation?

For personal use only

JULY 2015 INITIATIVES PLAN FOR REGULATED TRANSMISSION SERVICES

Feasibility studies Ulaanbaatar August 2016

Hydrometallurgical Options to Add Value to Copper Projects and Operations

DYNAMIC MODELING OF AN INDUSTRIAL COPPER SOLVENT EXTRACTION PROCESS

OXIDATIVE PRECIPITATION OF Fe AND Mn BY AIR/SO 2

Transcription:

LOOK BEFORE YOU LEACH: DYNAMIC SIMULATION OF HEAP LEACH FLOWSHEETS Brett Muller and Tim Newton Simulus Presented by Brett Muller brett.muller@simulus.com.au www.andritz.com 1 of 10

ABSTRACT A projectlevel dynamic model has been developed to simulate heap leach operations from ore handling through to final product. The model deals with the longterm effects of leach recovery rates, solution management, inventory buildup, complex reaction chemistry, and the limitations of the downstream process plant. It is applied as a decision tool for both process design and production planning functions. The model is developed on a flexible simulation platform, allowing for ready manipulation to meet any sitespecific configuration. It can accommodate single or multilift stacking, and multistage irrigation schemes. Any type of extraction rate model may be incorporated into the simulation for a comprehensive and rigorous dynamic mass balance. INTRODUCTION The difficulty of scaling up metallurgical test data to industrial scale heap leach practice is well known. This paper addresses the broader problem of creating a model for the entire process, considering the interactions of multiple operating heaps, solution storage, and the downstream processing plant. The Simulus models described here are dynamic, flowsheetlevel models that consider the unsteadystate process mass balance over a period of several years. The power of these models lies in their ability to rapidly and reliably show the effect of alternative configurations and leaching conditions. Developing the model forces a rigorous examination of the process design. Simulation results are often counterintuitive, and reveal issues that were not previously apparent. In an uncertain project environment, process models are used to evaluate a wide range of operating situations, highlight the key risks, and provide a means of testing alternative solutions. THE HEAP LEACH PROBLEM Heap leaching is a conceptually simple process but has several characteristics that make modelling the flowsheet quite complicated. Fundamentally, it is a slow process. There is a substantial time lag between stacking ore and producing the final product. During this time the soluble inventory builds up and impacts the recovery and solution tenor. An insufficient stacking rate may not be apparent until 6 months later, when the plant is struggling with low solution grades. Furthermore, the process is never at steady state. Any leach operation has a range of ore under leach, from freshly stacked to neardepleted material. There is usually a combination of ore types with different leaching characteristics. Seasonal variations such as rainfall or cold weather can also have a significant impact on production. The irrigation scheme introduces a new level of complexity. Leaching may be single stage or multistage, with intermediate solution recycled to the heaps to build up solution grades. The new nickel laterite projects are devising more elaborate schemes than normally used in the copper industry. Multilift heaps further complicate the inventory estimate as high grade PLS may be held up in lower lifts. Interactions between the heaps, solution storage and downstream plant add a further dimension. Plant flow capacity is always limited and metal recovery is dependent on solution composition, which is variable. 2 www.andritz.com 2 of 10

The combination of all these factors means that applying simplistic recovery data to process design is risky. As is normally the case with process fluctuations, the downs hurt more than the ups help. It is not valid to assume the variations cancel each other out and give steady production over time. Heap leaching, possibly more than any other metallurgical process, requires dynamic rather than steady state models to reliably forecast behaviour. All of these problems are on top of the basic difficulty of scaling up metallurgical test results to industrial scale heaps. The best scaleup techniques still have a fairly wide margin of error due mainly to uneven flow patterns through a heap. A simulation model can be used to assess the impact of changes in final extraction or leach cycle time on solution grades and production rate over time. There are several reviews of heap leach simulation techniques available in the literature. Taylor and Jansen (Ref. 1) gave an overview of existing models and presented a new approach. The Simulus model seeks to address many of the limitations noted in this approach. ALTERNATIVE MODELS There have been substantial advances in mathematical modelling of the chemical and physical processes involved in heap leaching. In particular, the work by David Dixon and coworkers (Ref. 2) represents the current state of the art in developing models of the process. The essence of these models is to relate metal extraction under real heap conditions to fundamental factors such as ore particle size, mineral particle size, diffusion rates, and reagent concentration. The Simulus models take heap extraction forecasts as direct input data, and apply these to the flowsheetlevel model. Several different approaches have been applied to this problem. The following discussion refers mainly to copper heapleaching, but the same approach applies to gold or nickel processes. SPREADSHEET MODEL An Excelbased model was developed for two Australian copper heap leach operations. The model was primarily used for production planning, in particular to ensure that the heap stacking plan would maintain consistent cathode production in future months. Key input data used: Monthly mine plan; tonnes and grade by ore type Recovery data; up to 16 separate extraction curves based on ore type and leach conditions Heap stacking & irrigation plan; physical dimensions and flow rates SXEW plant capacity flow and extraction The monthly mass balance required an iterative calculation due to the interaction between solution inventory and recovery. A macro was used to perform the iterations on a month by month basis, with inventory carried forward each month. Figure 1 shows the model structure and interaction with metallurgical accounting functions. The spreadsheet model was successful in forecasting PLS grade and cathode production. It was able to highlight production shortfalls well before they occurred. The forecasts were reviewed 6 months later and found to be in close agreement with actual plant performance. 3 www.andritz.com 3 of 10

Although quite effective, the spreadsheet model suffered several drawbacks. It became cumbersome and unwieldy as more heaps were added. The formulas and macros were complicated and difficult to trace. The model was inflexible with regard to alternative heap configurations and irrigation schemes and could not readily be used to investigate alternative designs. The spreadsheet method could not effectively deal with complex chemical reactions. Met Accounting Production Forecast Solution inventory Cu (t) Monthly stripped Cu (t) Leach parameters 4 Leach curves Leach feed Cu g/l PLS Cu g/l Irrigation m 3 /h (cell by cell) Production forecast Irrigation schedule m 3 /h Stacking schedule t & Cu% Solution inventory Cu (t) Monthly stripped Cu (t) Leach extraction Cu (%) (each cell) Acid consumed (t) Acid consumed (t) Extraction Cu (t) Extraction Cu (t) (each cell) Stacking record t & Cu% www.andritz.com 4 of 10 Legend Data input Calculation Data output

Figure 1 Spreadsheet Model Structure SYSCAD MODEL SysCAD is a specialised process simulation software package, widely used in the minerals industry for flowsheet modelling. A dynamic model was initially developed for evaluation of a nickel laterite heapleach in conjunction with an existing pressure leach operation. The model was further developed and refined for a standalone nickel heap leach project, incorporating multistage irrigation and downstream processing. The SysCAD approach successfully enabled a rigorous dynamic mass balance model, taking into account detailed reaction chemistry, stacking and irrigation sequences, solution management, inventory buildup and the downstream process plant. Figure 2 shows the model overview flowsheet. The drawbacks of this approach were slow simulation time, and lack of flexibility. The model structure can be modified to match any plant configuration, but significant effort is required for each site application. IDEAS MODEL IDEAS is a generalpurpose process modelling software focussed on pulp & paper, oil sands and mining industries. It is based on the Extend simulation platform, giving the model structure a strong visual component. Rather than lines of code, the logic associated with sequencing of stacking and irrigation operations is created with model objects such as timers, switches and calculation blocks, directly connected to flow streams on the flowsheet. IDEAS has only recently been applied to hydrometallurgical flowsheets, and is still undergoing development to meet industryspecific requirements. Figure 3 shows the model overview flowsheet, with subsequent diagrams showing the underlying structure. The great advantage of the IDEAS model is ready duplication and rearranging of model components. It is also easily traceable and transparent, with no requirement for programming code. It is very fast to run; a 3 year simulation with 10 minute step size is complete within about 10 minutes. Table 1 Model Method Comparison Model platform: Excel SysCAD IDEAS Method / structure Spreadsheet pgm code HBlocks No. leach curves 16 unlimited unlimited Chemistry basic detailed detailed Flexibility low medium high Solve time medium slow fast 5 www.andritz.com 5 of 10

Figure 2 SysCAD Model Overview 6 www.andritz.com 6 of 10

Figure 3 IDEAS Model Overview 7 www.andritz.com 7 of 10

The model input data includes: Table 2 IDEAS Model Input Data Area Ore Stacking Heap Leach Downstream Plant Input Data Ore grade & mineralogy over time Crusher / agglomerator / stacker capacity Delay times due to conveyor relocation Reclaimer capacity (for onoff pads) Heap dimensions Bulk density Irrigation capacity / specific rates / rest cycles (if applicable) Delay time due to irrigation pipe laying Multistage leach data irrigation rate and time under leach independently specified for each stage Pond volumes Extraction curve as a function of time or flux, or any other relationship (by ore type if required) Other chemical reactions Heap moisture; operating and drained Rates of precipitation and evaporation Flow capacity Metal recovery (as a function of PLS composition, e.g. SX extraction isotherms) Reliability data duration & frequency of stoppages The model is a collection of hierarchical blocks that perform particular functions, as listed in the table below. The sequencing and control scheme is designed to mimic realistic plant operation as closely as possible. Each block can be cut and pasted to duplicate the function in another part of the flowsheet. This modular nature makes the model easily modifiable to different sites. Table 2 IDEAS Model Blocks Block SubBlock Function Heapleach Stacker Receive ready signal Feed ore at the t/h rate (global setting) Totalise ore mass stacked Totalise contained metal stacked Compare total mass with heap ore capacity, stop stacking when reached OnFlow Control Heap Heap Reactions Wait for specified delay time (for stacker movement) Transmit ready signal to OnFlow Control block and to Stacker block in next heap Receive ready signal Wait for specified delay time (irrigation pipe laying) Calculate irrigation rate from specific L/m 2 /h rate (global setting) and heap area for each leach stage Inflow solution from each pond in sequence for the duration specified for each leach stage Totalise volumetric flow Record days under leach Signal current leach stage to offflow control Volume storage, representing heap size Determine extraction based on days or m 3 /t cumulative flow (selectable) Perform chemical reactions to the required extent Track metal remaining in heap and calculate extraction Separate reaction products into solution and solids at the specified % moisture Transmit finished signal after draindown to final moisture 8 www.andritz.com 8 of 10

level Offflow selector Reclaim Direct solution to a pond depending on stage of leaching Receive finished signal Inflow heap residue at the specified rate (global setting) Totalise mass of solids reclaimed Pond Volume storage Inflow water to required level Inflow reagent to required concentration Overflow excess solution Rainfall Outflow water at the specified rate (variable function over time) Process Draw solution at the specified rate Plant Chemical reactions for product The extraction may be described as a function of time under leach, irrigation flux, or any combination of relevant process parameters. Any mathematical function can be readily inserted to the model to control chemical reaction extents within the heap. Model outputs are setup to mirror the information seen in a production report. Critical numbers such as PLS grade over time are plotted for each heap, and for the combined stream. Inventory buildup is plotted against metal tonnes stacked and produced for a quick picture of the overall balance. DESIGN DECISIONS Dynamic interactions between the heaps and plant need to be understood to arrive at the optimum process design. As with all process design, there are a series of tradeoffs between capital cost, operating cost and recovery or production rates. Process options can normally be tested with the model, provided there is some basis to relate the variables in question. Increasing the heap height saves on both operating and capital cost of the heap, but carries a penalty in terms of recovery. The higher solution grades mean the downstream plant can be smaller. Higher irrigation rates may shorten the leach time but also give a more dilute PLS and may exacerbate shortcircuiting in the heap. A key question is how many lifts are to be used, are the spent heaps to be removed (on/off pads), are they to be sealed after each lift, or are new lifts built directly on top. The low capital option is multilift on unsealed residual heaps. The penalty is the increased inventory from high grade solution being held up in lower lifts. The model is ideally suited to determine this side of the equation, and enable an assessment of the impact on cash flow. Solution ponds should be large enough to manage plant downtime, rainfall events, and general operability. In particular they should be large enough to bring new, dry heaps on line without interrupting production. They also help smooth out the solution composition fed to the plant. Sizing is often based on experience and guesswork. The model takes into account heap moisture levels (stacked, operating and drained), equipment reliability, rainfall, evaporation, and the solution management scheme. The pond levels are tracked over time to indicate if they are ever the cause of restricted production rates. Heap chemistry can be a complex set of dissolution and precipitation reactions. Over time, impurity elements build up in the heaps and reach saturation levels. This impacts acid consumption in the heaps, and also has effects on the downstream plant. The model can readily deal with complex mineralogy and chemistry and show the expected composition of solution in a mature operation. Operating mines need to know that the tonnes and grade being stacked today will give sufficient production rate several months into the future. The stacked ore may be a blend of various rock 9 www.andritz.com 9 of 10

types, with different extraction and acid consumption characteristics. The model can readily handle multiple ore types and leach curves, and take the guesswork out of production planning. MODEL VALIDATION The model is fundamentally a dynamic mass balance, performed repeatedly over a period of several years. The model output data is presented to show that the overall balance is sound in terms of total tonnes, solution tonnes, and metal tonnes. The calculations and control logic are completely transparent and traceable, and it is easy to drill down to extract specific data for validation purposes. Both the spreadsheet model and the SysCAD model have been validated against real plant operating data. Forecast production rates and solution grades were compared, 6 12 months later, with actual process outcomes. In all cases the models results compared favourably with plant data. CONCLUSIONS Heap leaching is a fundamentally dynamic process and requires a plantwide dynamic model to effectively simulate process behaviour. The Simulus model combines comprehensive reaction chemistry, inventory management and downstream plant limitations to mimic real plant operation over a period of years. Any scaleup or extraction rate model can be readily integrated into the flowsheet model. The model can be applied to design optimisation and verification, and production planning. Used in conjunction with mine plans and economic models, it can take much of the guesswork out of heap leach design and operation. REFERENCES 1. A New Approach to Heap Leach Modeling and ScaleUp, M. Jansen and A. Taylor, ALTA 2002 Copper Proceedings 2. HeapSim Unravelling the Mathematics of Heap Bioleaching, N. Ogbonna, J. Petersen, D. Dixon, Computational Analysis in Hydrometallurgy, 2005 10 www.andritz.com 10 of 10