WM2013 Conference, February 24 28, 2013, Phoenix, Arizona USA. Factors Impacting Decommissioning Costs 13576

Similar documents
Remediation and Decommissioning Technology

ICFD Session 2, Cost Estimation Stockholm, Sweden - 21 September 2016 Michael Lackey P.E. Vice President - Nuclear Operations

TROJAN DECOMMISSIONING STATUS. OPUC Meeting March 8, 2005 (draft)

The Electric Power Research Institute (EPRI) is the

State of the Nuclear Industry Decontamination & Decommissioning Are We Ready. April 25, Presented by: Michael Frediani

S z5a MPC&D July 31, U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C

Decommissioning Worldwide and NEA Activities

Two Approaches to Reactor Decommissioning: 10 CFR Part 50 License Termination and License Amendment, Lessons Learned from the Regulatory Perspective

Perspective of Decommissioning Worldwide in View of Metrological Needs

WM2015 Conference, March 15 19, 2015, Phoenix, Arizona, USA

Lessons Learned from EPRI Decommissioning Program Decommissioning Pre-Planning Overview

WM2016 Conference, March 6 10, 2016, Phoenix, Arizona, USA. Preliminary Evaluation of Removing Used Nuclear Fuel from Shutdown Sites An Update 16057

U.S. NUCLEAR POWER PLANT DECOMMISSIONING

Humboldt Bay Power Plant Decommissioning Progress Update

Waste Management for Decommissioning of Nuclear Power Plants An EPRI Decommissioning Project Report

SOLUTIONS. Role of Radioactive Waste Management in D&D. Colin Austin (Senior Vice President, International Business)

San Onofre Unit 1 Decommissioning

Nuclear Energy. Nuclear Fuels Storage and Transportation Planning Project Transportation System Development Overview. Matt Feldman

S T A T E O F M I C H I G A N BEFORE THE MICHIGAN PUBLIC SERVICE COMMISSION DIRECT TESTIMONY THOMAS S. LAGUARDIA ON BEHALF OF CONSUMERS ENERGY COMPANY

Applicability of EPRI Decommissioning Pre-Planning Manual to International Decommissioning Projects

Power Reactor Decommissioning: U.S. Perspective on Regulatory Insights and Challenges

DECOMMISSIONING LESSONS LEARNED AT YANKEE ROWE. M. S. Terrell, D. McGee, Duke Engineering and Services (USA)

HOW R&D MAY HELP TO IMPROVE RP PERFORMANCE AT THE DECOMMISSIONING STAGE OF NUCLEAR POWER PLANT?

IMPACT OF LACK OF CONSISTENT FREE RELEASE STANDARDS ON DECOMMISSIONING PROJECTS AND COSTS

Current Status of Shutdown Sites Activities. San Onofre Nuclear Generating Station (SONGS) Site Visit

SYSTEMATIC APPROACH FOR DECOMMISSIONING PLANNING AND ESTIMATING

Maria Taranger Foto: Kävlinge Municipality

Zion Project Overview S. Chris Baker VP EH&S

Decommissioning Technology Update

CGoEd. June 1, U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555

2014 Decommissioning Cost Analysis of the San Onofre Nuclear Generating Station Units 2 & 3

EPRI Research and Development Projects for NPP Decommissioning

Spent Nuclear Fuel, Low Level Radioactive Waste and Decommissioning

PLANNING FOR THE EARLY RETIREMENT OF THE OYSTER CREEK NUCLEAR GENERATING STATION ENGINEERING ISSUES

Spent Fuel Storage: Defining the Problem. Commissioner Tim Echols Georgia Public Service Commission

San Onofre Nuclear Generating Station Units 2 and 3 Post-Shutdown Decommissioning Activities Report

Your Partner for Successful D&D PROVEN PROGRAMS EFFECTIVE TRANSITION WORLD-CLASS PERFORMANCE

Decommissioning of Nuclear Installations

Testimony On 2016 SONGS 1 Decommissioning Cost Estimate

Strategy for the Management and Disposal of Used Nuclear Fuel and High-Level Radioactive Waste

Spent Power Reactor Fuel:

Decommissioning of Nuclear Facilities: The Work Ahead and How to Succeed

RANCHO SECO TRANSITION TO FULL DECOMMISSIONING. Dennis E. Gardiner, Decommissioning Project Manager, SMUD John M. Newey, CHP, President, NewRad, Inc.

Spent Nuclear Fuel and Low Level Radioactive Waste: Current and Future Storage Options

Overview of US NRC Decommissioning Surveys, Surface and Subsurface, Release Criteria and Records

Post Shutdown Decommissioning Activities Report Vermont Yankee Nuclear Power Station Docket No License No. DPR-28

WM2014 Conference, March 2 6, 2014, Phoenix, Arizona, USA

Regulatory projects with Rostechnadzor and SEC-NRS Tacis/INSC Projects

Future Challenges in Decommissioning of NPPs Worldwide

WM 07 Conference, February 25 March 1, 2007, Tucson, Arizona. Reaching Site Closure For Groundwater Under Multiple Regulatory Agencies

EDF DECOMMISSIONING PROGRAMME - A PREREQUISITE FOR THE ERECTION OF NEW NUCLEAR POWER PLANTS IN FRANCE

Methodology to Manage Material and Waste from Nuclear Decommissioning. Waste Management & Decommissioning Working Group

Introduction. Status of Worldwide Nuclear Power Plants*

Radiological Environmental and Public Exposure Considerations for Existing and Future Nuclear Power Plants

RADIOACTIVE WASTE AND MANAGEMENT PROGRAMMES IN OECD/NEA MEMBER COUNTRIES SWEDEN [2010] NATIONAL NUCLEAR ENERGY CONTEXT

AN ASSESSMENT OF THE FREE RELEASE CRITERIA FOR DECOMMISSIONING PROJECTS. Jas Devgun Sargent & Lundy 55 E. Monroe St.

CONNECTICUT YANKEE ATOMIC POWER COMPANY

DECOMMISSIONING OF NUCLEAR FACILITIES IN UKRAINE

Safety Considerations in the Transition from Operation to Decommissioning of Research Reactors

RANCHO SECO DECOMMISSIONING UPDATE

RANCHO SECO PLANNING FOR LARGE COMPONENTS

Decommissioning of Nuclear Facilities. The Decommissioning Process. Lesson Objectives. Decommissioning. Decontamination. Decommissioning Objective

WM2013 Conference, February 24 28, 2013, Phoenix, Arizona USA. Progress in Decommissioning the Humboldt Bay Power Plant 13604

DESIGNING DECOMMISSIONING INTO NEW REACTOR DESIGNS 1

Decommissioning Planning

MAINE YANKEE PREFACE LICENSE TERMINATION PLAN REQUIREMENTS - A NON-TECHNICAL SUMMARY

FIG. 1. Fort St. Vrain Nuclear Generation Station.

The Question of Queue: Implications for Best Practice in Cross-country Transport of Commercial Spent Nuclear Fuel 9402

The structure of this presentation. The structure of this presentation

The Question of Queue: Implications for Best Practice in Cross-country Transport of Commercial Spent Nuclear Fuel 9402

Joint ICTP-IAEA School on Nuclear Energy Management. 15 July - 3 August, Lecture Notes. I. Mele IAEA, Vienna, Austria

Decommissioning three main strategies: Immediate dismantling, Safe enclosure (Deferred dismantling), Entombment

Draft Summary of Plant Life Management in Transition from Operation to Decommissioning for Nuclear Power Plants. Prepared by core team

Keynote Address 2007 Joint IEEE / HPRCT Conference. Jack Keenan Chief Nuclear Officer Pacific Gas and Electric Company

ICEM A STEP-BY-STEP DEVELOPMENT OF RADIOACTIVE WASTE MANAGEMENT STRATEGY

DECOMMISSIONING LICENSING PROCESS OF NUCLEAR INSTALLATIONS IN SPAIN

TABLE OF ACRONYMS / ABBREVIATIONS

The Social and Economic Impacts of Nuclear Power Plant Closures Jonathan Cooper & Jen Stromsten Institute for Nuclear Host Communities

LOW-LEVEL LIQUID WASTE PROCESSING PILOT STUDIES USING A VIBRATORY SHEAR ENHANCED PROCESS (VSEP) FOR FILTRATION

June 28, 2013 TM CFR CFR 50.82

Page 1. WM2011 Conference, February 27- March 3, 2011, Phoenix, AZ. A Standardised Listing of Cost Items for Decommissioning Costing 11483

Status of Decommissioning Preparation for Kori #1

US Ecology Update & Case Studies. Chad Hyslop Director of Sales & Marketing (208)

WM2010 Conference, March 7-11, 2010, Phoenix, AZ MODULAR CONSTRUCTION FOR EVENTUAL DECONSTRUCTION AND DECOMMISSIONING

Vermont Yankee Nuclear Decommissioning Citizens Advisory Panel June 22, 2017

Interim Storage of Used Nuclear Fuel. The Nuclear Energy Institute

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C SAFETY EVALUATION REPORT

STATUS OF NRC EFFORTS ON REGULATORY APPROACHES FOR CONTROL OF SOLID MATERIALS

Long Term Operation of Nuclear Power Plants in Spain: Preparing for the Future

W R I T T E N S T A T E M E N T O F R U S S E L L A

Nuclear Energy. Consolidated Interim Storage Facility Design Concepts In the United States. Nuclear Fuels Storage and Transportation Planning Project

Safety Research for the Disposal of Radioactive Waste Generated by Decommissioning of of Nuclear Power Facilities

IAEA Activities Related to Clearance and Exemption

Low-Level Waste and Radiation Management

Activities of the OECD/NEA/CSNI Working Group on Fuel Cycle Safety in Spent Fuel and High-Level Waste Management

The relevance for the nuclear industry decommissioning programmes

Regulatory Standard Format and Content of License Termination Plans for Nuclear Power Reactors

Activities of the NRC s Division of Spent Fuel Management: An Overview

Decommissioning (technical knowledge/experience; national strategies / policies; main issues; future trends)

RESUME of SCOTT ATWATER

Transcription:

Factors Impacting Decommissioning Costs 13576 Karen Kim*, Richard McGrath* *Electric Power Research Institute, 342 Hillview Ave., Palo Alto, California. USA. kkim@epri.com, rmcgrath@epri.com ABSTRACT The Electric Power Research Institute (EPRI) studied United States experience with decommissioning cost estimates and the factors that impact the actual cost of decommissioning projects. This study gathered available estimated and actual decommissioning costs from eight nuclear power plants in the United States to understand the major components of decommissioning costs. Major costs categories for decommissioning a nuclear power plant are removal costs, radioactive waste costs, staffing costs, and other costs. The technical factors that impact the costs were analyzed based on the plants decommissioning experiences. Detailed cost breakdowns by major projects and other cost categories from actual power plant decommissioning experiences will be presented. Such information will be useful in planning future decommissioning and designing new plants. INTRODUCTION Several nuclear power plants in the United States have decommissioned to reach license termination. Cost information from these completed decommissioning projects is available in license termination reports that have been submitted to the United States Regulatory Commission (U.S. NRC). There are also plants that have not yet reached license termination but are in various states of decommissioning. These plants must provide the U.S. NRC with updates to their decommissioning cost estimates biennially. The cost estimates from the completed and ongoing decommissioning projects provide insights into technical factors that impact cost estimates. The Electric Power Research Institute (EPRI) studied the cost estimates from seven completed decommissioning projects and one ongoing decommissioning project. The results of this study are documented in the EPRI Report: Decommissioning Experiences and Lessons Learned: Decommissioning Cost. [1] The completed decommissioning projects that EPRI studied are Trojan [6, 7, 8], Big Rock Point [9, 1], Maine Yankee [2, 11, 12], Connecticut Yankee [3, 13], Yankee Rowe [14, 15], San Onofre Unit 1 [4], Rancho Seco [5, 16]. The ongoing decommissioning project studied is the Humboldt Bay power plant [17]. The plants studied and their attributes are summarized in Table 1 below. These plants are 6 Pressurized Water Reactors (PWRs) and 2 Boiling Water Reactors (BWRs) ranging from 65 to 113 MWe. 1

Table 1 Decommissioning Nuclear Power Plants Included in EPRI Study Plant Type Power Rating (Mwe) Operating Period Trojan PWR 113 1975-1995 26 Big Rock Point BWR 67 1963-1977 26 Maine Yankee PWR 86 1973-1996 25 Decommissioning Completed (Expected) Connecticut PWR 619 1968-1966 27 Yankee Yankee Rowe PWR 167 1963-1991 27 San Onofre Unit PWR 41 1968-1992 28 1 Rancho Seco PWR 913 1975-1989 28 Humboldt Bay BWR 65 1962-1976 215 (Expected) Studying the cost estimates of these plants, it was clear that there is not a standard methodology for categorizing the costs of decommissioning. Also, publically available decommissioning cost information for some plants do not include a breakdown of the costs or the breakdown of costs is considered confidential. As such, this study makes some assumptions related to categorization of costs from the different publically available cost information to allow for common categorization and analysis. If the breakdowns for the costs are not available, the costs were allocated to the categories that were identified during earlier phases of decommissioning. The EPRI study categorized the decommissioning costs into the following major categories: Dismantling and Removals of Systems, Structures, and Components (includes decontamination if identified) Radioactive Wastes (includes disposal of wastes and includes preparation/transportation of wastes if indentified) Staffing (if identified) Other costs (includes Final Status Survey and Site Restoration if identified) Spent Fuel (includes costs to construct the Independent Spent Fuel Storage Installation (ISFSI), Storage Canister/Cask fabrication, and ISFSI operating cost) Of these eight plants, three plants did not provide a separate line item for staffing costs the staffing costs for these three plants were included in other cost categories. This difference is accounted for in further analysis of the costs. In order to allow for comparative analysis, the costs from the different plant decommissioning projects were escalated to 28 costs. 2

The rest of this paper summarizes the results of the study for each of the major categories listed above including some narratives on the technical factors, experiences, and lessons learned associated with each category. DECOMMISSIONING COST The total final and estimated decommissioning costs of the eight plants are graphed in Figure 1. Several initial decommissioning cost estimate methodologies use the generating capacity or size of the plant as a metric for estimating decommissioning costs. However, it is apparent from experiences that there is not necessarily a trend between size of the plant and decommissioning costs. There are many other variables that impact the final decommissioning costs including final state of the site, waste disposal site access, waste transportation mode and distance, plant duty factor, and failed fuel history. For example, the highest rated plants, Rancho Seco and Trojan, have the lowest total decommissioning costs. This may be due to the fact that both of these plants operated for less than 1 effective full power year (EFPY) and left many of their buildings standing at the time of license termination. Total Decommissioning Costs (28$) 1 Total Decommissioning Costs ($M) 9 8 7 6 5 4 3 2 1 65 67 167 41 619 86 913 113 Figure 1 Total Decommissioning Costs Dismantling and Removals of Systems, Structures, and Components The first major cost category discussed is the dismantling and removal of systems, structures, and components. Figure 2 provides a depiction of the removal costs versus plant power rating. Figure 3 provides the same information but excludes the three plants that did not provide staffing as a separate line item. This is done because the staffing costs for these three plants would be included in the other cost categories. 3

As seen in Figure 2, there does not seem to be a trend between plant size and removal costs. Rancho Seco, has very low removal costs. This low removal cost could be due to the fact that Rancho Seco left several buildings standing, had a shorter operating period, and extended SAFSTOR period, and implemented aggressive cost control measures. Figure 4 provides the percentage of removal costs to the total decommissioning costs. Removal costs for the five plants ranged between 19-26% of total decommissioning costs. Total Removal Cost 6 Total Removals Cost ($M) 5 4 3 2 1 65 67 167 41 619 86 913 113 Figure 2 Total Removal Costs 4

Removal Cost (Plants with Detailed Breakdown) 25 Total Removals Cost ($M) 2 15 1 5 65 67 41 86 913 Figure 3 Total Removal Costs for Five Plants Removals as % of Total Decommissioning Cost 45 4 Removals % of Total Cost 35 3 25 2 15 1 5 65 67 41 86 913 Figure 4 Removal Costs as Percent of Total Decommissioning Cost 5

Radioactive Waste Figure 5 provides the total waste costs for each of the eight plants studied. As discussed in the introduction, this category includes the preparation, transportation, and disposal costs for the waste. Plants that disposed of all above grade concrete (Maine Yankee, Connecticut Yankee, and Humboldt Bay) have the higher waste costs. San Onofre Unit 1 s low waste cost is partially influenced by the fact that they have not yet disposed of its reactor vessel. Connecticut Yankee s high waste cost is also due to the large soil remediation project they had to undertake to meet site release criteria for soil and groundwater. Figure 6 shows the percentage of waste costs to the total decommissioning costs of each plant. Waste disposal costs ranges from between 17-27% for the plants studied. Total Decommissioning Waste Costs 3 Total Waste Costs ($M) 25 2 15 1 5 65 67 167 41 619 86 913 113 Figure 5 Total Decommissioning Waste Costs 6

Waste Cost as % of Decommissioning Cost 35 Waste % of Total Costs 3 25 2 15 1 5 65 67 167 41 619 86 913 113 Figure 6 Waste Costs as Percent of Decommissioning Cost The costs of radioactive waste management can be impacted by the location of the plant (i.e. access to disposal sites and distance to disposal sites) and the discounts negotiated with waste disposal sites for large volumes of waste. Also, lower radioactive wastes (e.g. very low level waste or Class A waste) costs less to dispose of than higher activity wastes. Figure 7 shows the total volumes of radioactive waste shipped (or two be shipped) from each decommissioning plant. Figure 8 provides the waste disposal cost per unit volume (cubic meter) per the total volume shipped. As can be seen from Figure 8, the more waste shipped, the lower the unit volume costs. If the total volume of waste shipped is very low, the higher cost of the disposal of the reactor vessel and internals leads to higher per unit waste costs. With respect to transportation, the availability of rail transportation (via a rail spur that extends to the plant) led to costs savings over truck transportation. 7

Radioactive Waste Volumes vrs Plant Size Radwaste Volume (m3 X ) 12 1 8 6 4 2 65 41 619 86 913 113 Figure 7 Radioactive Waste Volumes versus Plant Size Unit Cost vrs Decommissioning Waste Volume Average Waste Unit Cost ($/m3) 14, 12, 1, 8, 6, 4, 2, 2 4 6 8 1 12 Radwaste Volume per Plant (m3 x ) Staffing Figure 8 Average Waste Unit Cost versus Decommissioning Waste Volume Figures 9 and 1 provide the staffing cost information for the five plants that provided staffing costs as a separate line item in their decommissioning cost estimates. Figure 9 provides the total staffing costs and Figure 1 provides the percentage of staffing costs to the total decommissioning costs. The noteworthy observation from this data is that staffing costs for these five plants were 29-52% of the total decommissioning costs and is the highest percentage of total decommissioning costs. Staffing costs are tied to the duration of decommissioning. As such, strategies that shorten decommissioning time may reduce staffing costs. This is further discussed in the analysis section below. 8

35 3 Total Staffing Cost Staffing Cost ($M) 25 2 15 1 5 65 67 41 86 913 Figure 9 Total Staffing Cost Staffing as a Percentage of Total Cost Staffing % of Total Cost 6 5 4 3 2 1 65 67 41 86 913 Figure 1 Staffing Cost as a Percent of Total Decommissioning Cost Final Status Survey and Spent Fuel Management Figures 11 and 12 show the Final Status Survey (FSS) and spent fuel management costs for the eight plants studied. Both of these cost categories show an increasing trend with increasing plant size. FSS costs are expected to increase with larger plant sizes (as for newer plant designs) with more building areas to survey. Connecticut Yankee had relatively high FSS costs because of the soil and groundwater monitoring and remediation they needed to conduct to meet site release criteria. 9

The spent fuel management costs also increase with plant size and generating capacity. Spent fuel management costs include includes costs to construct the Independent Spent Fuel Storage Installation (ISFSI), Storage Canister/Cask fabrication, and ISFSI operating cost. Larger capacity plants would have generated more spent fuel and therefore require a larger ISFSI. Spent fuel management costs also depend on the length of operation of the plant. For example, Yankee Rowe and Connecticut Yankee operated longer than the other plants, leading to a higher generation of spent fuel and higher spent fuel management costs. Trojan and Rancho Seco have relatively low spent fuel management costs because, as discussed before, they operated for less than 1 EFPY. Final Status Survey Costs FSS Costs ($M) 2 18 16 14 12 1 8 6 4 2 65 167 619 86 913 113 Figure 11 Final Status Survey Cost Spent Fuel Storage Cost Vs Plant Size Spent Fuel Storage Cost ($M) 45 4 35 3 25 2 15 1 5 65 67 167 41 619 86 913 113 Figure 12 Spent Fuel Storage Cost 1

ANALYSIS OF TOTAL DECOMMISSIONING COSTS AND COST CATEGORIES Figure 11 provides the average percentages of each cost category with respect to the total decommissioning costs. Cost Categories as a % of Total Cost 13.9% Staffing 19.% 43.5% Removals Waste Other 23.6% Figure 13 Cost Categories as a Percent of Total Decommissioning Cost Staffing cost is the highest fraction of total costs when compared to the other cost categories. Staffing is tied to the length of the decommissioning project. As such, strategies that reduce the length of the decommissioning would reduce the staffing costs. For example, the low staffing cost associated with the Rancho Seco plant might be associated with the fact that they left their buildings standing instead of demolishing them. Other time saving (and staff cost saving) strategies implemented by plants include disposing of systems, structures, and components (SSCs) known to be contaminated instead of surveying them for free release, disposing of the concrete inside of the containment liner as radioactive waste, etc. However, the staff costs savings that are gained from such strategies must be balanced against the radioactive wastes costs in consideration of the total decommissioning cost. Removal costs are the second highest percentage of decommissioning costs. These costs are impacted by the parameters such as the size of the buildings within the radiation controlled areas (RCA), contamination levels, and building radiological release strategies (e.g. whether above ground structures are left standing or demolished). Such parameters may be less amenable to optimization during the decommissioning project, careful management and planning can help control removal costs. The third highest percentage of decommissioning costs is waste costs. The costs related to generation and disposal of radioactive waste should be balanced with costs related to surveying and releasing structures. The latter are associated with staffing costs as surveying structures can 11

be time consuming. If waste costs are low, then it may be more cost effective to dispose of much of the structures as radwaste instead of surveying and decontaminating these structures for release. SUMMARY AND CONCLUSIONS Each nuclear power plant must prepare and update cost estimates for the decommissioning throughout operation, SAFSTOR (if a SAFSTOR period is taken), and active decommissioning. Cost information and the associated technical experiences from the completed and ongoing decommissioning projects can provide insights for planning and optimizing future decommissioning projects. Experiences from the eight plants analyzed in this study reveal that decommissioning costs do not generally trend with plant generating capacity and size. This applies to most of the cost categories except Final Status Survey and spent fuel management costs which do increase with plant generating capacity and size. Of the various decommissioning cost categories staffing costs is the highest fraction of costs, with removal costs and waste costs following as the second and third highest fractions. Staffing cost is tied with decommissioning project duration, so strategies for optimizing decommissioning duration could also reduce staffing costs. However, such strategies must be balanced with removal and waste costs, as some strategies for reducing project duration could increase removal and waste disposal costs. REFERENCES The following references were used in the EPRI study summarized in this paper. The full EPRI study is documented in the EPRI Report Decommissioning Experiences and Lessons Learned: Decommissioning Cost (211). [1] Decommissioning Experiences and Lessons Learned: Decommissioning Cost: EPRI, Palo Alto, CA: 211. 12325. [2] Maine Yankee Decommissioning Experience Report: Detailed Experiences 1997-24: EPRI, Palo Alto, CA: 25. 111734. [3] Connecticut Yankee Decommissioning Experience Report: EPRI, Palo Alto, CA: 26. 113511. [4] San Onofre Nuclear Generating Station Unit 1 Decommissioning Experience Report: EPRI, Palo Alto, CA: 28. 116773. [5] Rancho Seco Nuclear Generating Station Decommissioning Experience Report: EPRI, Palo Alto, CA: 27. 115121. [6] Trojan PWR Decommissioning: Large Component Removal Project: EPRI, Palo Alto, CA: 1997. TR-17916. [7] Portland Gas and Electric, Trojan Defueled Safety Analysis Report and License Termination Plan (LTP), Revision 21, March 31, 25. [8] Trojan Nuclear Power Plant Reactor Vessel and Internals Removal: Trojan Nuclear Plant Decommissioning Experience: EPRI, Palo Alto, CA: 2. 192. 12

[9] Big Rock Point License Termination Plan (LTP), Revision, April 1, 23 [1] Case No, U-15611, Before the Michigan Public Services Commission, Application of Consumers Energy Company for Reconciliation of Nuclear Power Plant Decommissioning Revenues and Expenses for the Big Rock Point Nuclear Plant. February 8, 21. [11] Maine Yankee License Termination Plan (LTP), Revision 2, August 13, 21. [12] Maine Yankee website, www.maineyankee.com [13] Connecticut Yankee website, www.connyankee.com [14] Yankee Rowe License Termination Plan (LTP), Revision 1, November 19, 24. [15] Yankee Rowe website, www.yankeerowe.com [16] Sacramento Municipal Utilities District (SMUD), Rancho Seco Letter to the U.S. NRC: DPG-11-155 Rancho Seco Report on Decommissioning Funding Status. March 29, 211. [17] Pacific, Gas, & Electric (PG&E) Letter to the U.S. NRC: HBL-11-3 Decommissioning Funding Report for Humboldt Bay Power Plant Unit 3. March 31, 211. ADDITIONAL SOURCES OF INFORMATION IAEA, Nuclear Energy Agency of the Organisation for Economic Co-Operation and Development, European Commission; A Proposed Standardized List of Items for Costing Purposes in the Decommissioning of Nuclear Installations, Interim Technical Document issued jointly by the IAEA, OECD/NEA and EC, Paris 1999. Nuclear Energy Agency of the Organisation for Economic Co-Operation and Development, Publication No. 6831, Cost Estimate for Decommissioning An International Overview of Cost Elements, Estimation Practices and Reporting Requirements. 21. United States Nuclear Regulatory Commission NUREG-137, Report on Waste Burial Charges: Changes in Decommissioning Waste Disposal Costs at Low-Level Waste Burial Facilities, Revision 14. November 21. 13