PROPOSAL EVALUATION: BWL ADVANCED DISTRIBUTION MANAGEMENT SYSTEM (ADMS)

Similar documents
The BWL has completed the evaluation for Advanced Metering Infrastructure and the work has been tentatively awarded to Leidos.

REQUEST FOR PROPOSAL. e-procurement System Implementation Project. New Development Bank

Smart Grid s ADMS Implementations: Lessons Learned

Proven Approach for Complex Technology Procurement

RFP NO A CONTRACT FOR THE PROCUREMENT AND INSTALLATION OF AN ENTERPRISE RESOURCE PLANNING SYSTEM PART V. EVALUATION CRITERIA AND PROCESS

Brief Guide to Public Sector EU Procurement Legislation. Despatch PIN not a call for competition (optional) allowing shortened timescale

REQUEST FOR PROPOSALS

Strategic Sourcing Guidelines on Requests for Proposals and Invitations for Bid

Enhancing Utility Outage Management System (OMS) Performance

ISO rule Project Procurement Compliance Monitoring Audit Process

real-time, two-way customer engagement to improve our power restoration efforts. The ACS mobile suite offers rich,

Government of Newfoundland and Labrador s. REQUEST FOR QUALIFICATIONS (RFQ) for

Support continued transparency for policy and design choices

SUMMARY Table 1 presents the proposed 2010 Smart Grid costs for Operations and Information Technology. Operations Projects 3,

Minnesota State Board Association Converging Communications, IT and OT

Smart Grid Enterprise Applications Interoperability Needs Assessment and the MultiSpeak Specification

Walk-through of long-term utility distribution plans: Part 1 - Traditional Distribution Planning

Roadmap to the Future: Integrating Substation InformationandEnterprise Level Applications

Analytics for Smart Grids. - DONG Energy Case Study on Optimization of Business Processes and Integration of IT Platforms

Procurement Presentation to the Financial Management Institute of Canada

PROCUREMENT CODE ARTICLE 5 GOODS AND SERVICES

Request For Information (RFI) For a. Spectrum Management & Monitoring System (SMMS)

INFORMATION TECHNOLOGY PROGRAM DESCRIPTIONS OPERATIONAL INVESTMENTS

Modernize your grid: Simplify smart metering with an intelligent partner.

Choosing The Right EHR For You: Best Practices In Vendor Selection & Contracting

FAIRNESS REPORT INCREMENTAL REGULATION CAPACITY REQUEST FOR PROPOSAL ISSUED: JUNE 29, 2017 INDEPENDENT ELECTRICITY SYSTEM OPERATOR PREPARED FOR THE:

Questions for MACI - RFP :

Request for Proposal: Controlled System Separation Feasibility Study

Request for Proposal. Outsourced IT & Managed Services. ISSUED DATE: April 12, 2018 SUBMISSION DATE: May 18, 2018 AT 4:00 pm EST

EXECUTIVE STEERING COMMITTEE MEETING

Selection of Contractor Step 5. June 2013

Corporate Policy and Procedure

OMS/DMS Implementation at SDG&E

All Source Request for Proposals Interim Summary

STEP 2: BID EVALUATIONS

Request for Proposals: A Vendor s Guide

Procurement Process: Architects & Professional Engineering Services. Procurement.

AMI information. for improved outage management

One System for Grid Operations Management

Industry Solution. Real-time Historian for Synchrophasor Data Management

NRECA TECHADVANTAGE 2014

Choosing The Right EHR For You: Best Practices In Vendor Selection & Contracting

Long Beach City Auditor s Office

A TECHNICAL SPECIFICATIONS LOCK BOX PAYMENTS

THE GUIDE SESSION 5 Operations, Administration & Maintenance Considerations for a A Submarine Cable Network

PURCHASING PROCEDURES: District Policies

Business Opportunities. and Insurance Board. with the Workplace Safety. Becoming a WSIB Supplier

ADDENDUM NO. 1 Kansas City Area Transportation Authority 1350 E. 17 th Street Kansas City, Missouri 64108

The Advanced Distribution Management System. The indispensable tool of the Smart Grid era

CONSTRUCTION MANAGEMENT SERVICES

Tendering & Purchasing

Leveraging Geography to Drive Utility Transformation and Business Value

COMMUNITY LIVING BRANT POLICY AND PROCEDURE MANUAL

PowerOn Advantage. GE Digital Energy. Integrated and Streamlined Operations. Advanced Distribution Management System (ADMS) Intuitive User Experience

Workforce. Strategic Planning. Request for Proposals

Increase Power Grid Stability and Reliability with Enterprise Historians for Synchrophasor Data Management

Request for Proposal For: 2018 American Bar Association Temporary Services

3.1 Sustainable Procurement Policy

Life Cycle Planning for Smart Grid Technologies

Substations 1 Feeders 2 Capacitors 3

Start a successful pricing project

ANNEX I - TERMS OF REFERENCE

Document Updated: 12/5/2018

2. Services. The Scope of Work is amended by adding additional work. The additional work is detailed in the attached Exhibit A.

REQUEST FOR PROPOSALS. (Safety Management Database) BID NO: Addendum 1

ELECTRIC DISTRIBUTION UTILITIES. Investigation into Grid Modernization. Order on Scope and Process O R D E R N O. 25,877.

REQUEST FOR PROPOSALS FOR STRATEGIC VISIONING AND PLANNING

Bidding and Tendering. National Occupational Standards October 2018

Request for Proposals. For Electronic Invoice and Travel Management System

Managing intelligent electronic devices

Request for Proposals Strategic Planning Facilitation

RFP IP-Based Surveillance Camera System

POSTAL STATION B ENVELOPE REHABILITATION & BASE BUILDING UPGRADE CONSTRUCTION MANAGER FAIRNESS MONITOR FINAL REPORT

Community Clean Energy Resiliency Initiative PON-ENE BESS Request for Proposals Question and Answer Log

Request for Proposal REQUEST FOR PROPOSAL. Systems Maintenance & Integration

Report No. 3 of the Environmental Services Committee Regional Council Meeting of April 18, 2013

Effective Technical RFP Development: A Guide for Jurisdictions and Other Organizations December 19, 2016

Request for Proposal Simulation-Based Learning Competition

Competitive Procurement Evaluation Process Audit

Procure to Pay (4.3) As-Is Process Flow and Narrative

North Carolina Department of Agriculture and Consumer Services Purchasing

RECOMMENDATIONS FOR THE FUTURE OF THE VERMONT HEALTH BENEFIT EXCHANGE

POLICIES AND PROCEDURES ENGINEERING SERVICES DEPARTMENT

Request for Proposal for Annual Financial Audit Services

Fault Location in a Distribution Management System (DMS).

The occurrence of severe weather events is on the rise at an

CALIFORNIA INDEPENDENT SYSTEM OPERATOR ANCILLARY SERVICES REQUIREMENTS PROTOCOL

Executive Steering Committee Meeting. Department of Revenue Building 2, Room 1250 July 27, 2016

GUIDE FOR EVALUATION PROCEDURES FOR EMPLOYMENT OF CONSULTANTS UNDER JAPANESE ODA LOANS

IT Governance Overview

Why Smart Water Networks Boost Efficiency

Procurement May 2018

Port of Whitman County Request for Proposal for Washington State Grain Train Strategic Plan

Request for Proposal Strategic Planning Consultant. Proposals will be received until: August 6, :00 PM CST

Government of Yukon. How to Guide: Doing Business with Government of Yukon

Eaton Intermediate School District REQUEST FOR PROPOSAL FOR. Proposal Due Date: Monday March 4th, 2013 at 1:00 p.m.

Smart Grid Concept, Applications and Lessons Learned from Recent Deployments

Request For Proposal Procedures

Chapter 15. Competitive Negotiation: Evaluating Proposals

Seba Ismaiel. UNICEF Procurement Process and Control Oversights + Outline of Tender Document

Transcription:

November 28, 2016 PROPOSAL EVALUATION: BWL ADVANCED DISTRIBUTION MANAGEMENT SYSTEM (ADMS) The BWL has completed the evaluation for BWL Advanced Distribution Management System (ADMS) and the work has been tentatively awarded Advanced Control Systems (ACS). The BWL does not release public documents without following the proper public disclosure guidelines for information available to the public under the Michigan Freedom of Information Act. As such, should you desire any document that may be within the custody of the BWL, please direct your Freedom of Information Act request to the following email: foiarequests@lbwl.com Otherwise, requests can be sent via US mail to: Brandie F. Ekren, Esq. Freedom Of Information Act Coordinator Lansing Board of Water & Light 1201 S. Washington Ave. P.O. Box 13007 Lansing, Michigan 48901-3007 Please be specific with your request. Any responsive information will be disclosed via U.S. Mail and may involve an administrative cost. Thank you very much for your proposal. We will retain you on our bidders list for future projects. Sincerely, BOARD OF WATER AND LIGHT Jeff Schwarz Purchasing Department 517-702-6310 517-702-6042 Fax jbs@lbwl.com

January 2016 Selection Report: Lansing Board of Water & Light Advance Distribution Management System (ADMS) Util-Assist Inc. www.util-assist.com 470 Harry Walker Parkway South, Newmarket, ON, L3Y 0B3 t. 905.952.0477 f. 905.952.3479

Table of Contents Executive Summary... 3 Introduction... 3 Outage Management System RFP... 3 Timelines... 3 Scope... 4 Contents of the RFP... 4 Key Requirements... 5 Vendors... 5 Approach... 6 Phase 1: Needs Assessment... 6 Phase 2: RFP Development... 6 Evaluation Criteria... 6 Scoring... 7 Vendor Demonstrations... 8 Vendor Best and Final Bid... 8 Final Decision... 9 Conclusion... 9 Appendix A:... 10 2

Executive Summary (Lansing Board of Water & Light) BWL issued a request for proposal (RFP) to invite qualified vendors to submit proposals for the procurement of a new advanced distribution management system. The purpose of the RFP was to select a vendor to provision an advanced distribution management system. Util-Assist was engaged to work with BWL to develop the RFP and guide the procurement process. BWL is confident that the most qualified and successful vendors were given the opportunity to submit proposals in response. From the seven vendors directly invited and publication to the BWL bid notifications section of the website, BWL received proposals from three qualified firms: 1. ACS (Advanced Control Systems) 2. Schneider Electric 3. Siemens The responses were evaluated based on a number of predetermined criteria, including respondents understanding of the requirements, completeness of the proposals, technical capabilities of the systems, experience of the vendors, and pricing. An evaluation team, with representation from Customer Service, Information Technology Services, Engineering and Operations provided a wealth of both technical and operational knowledge to analyze the vendor responses. The evaluation team assessed proponents objectively, with the end goal of selecting the best-fit outage management solution vendor. With financial and operational evaluations completed, it was determined that the ACS proposal most closely matched all of the requirements, providing strong support for the system technical requirements expressed throughout the RFP. BWL is confident that the information presented here demonstrates that due diligence requirements have been completed regarding the selection of a qualified vendor. Introduction BWL pursued proposals from qualified firms to provide an ADMS solution. An ADMS provides a comprehensive solution for outage management (OMS), energy management (EMS), supervisory control (SCADA) and distribution management (DMS) that integrates the tools into one product with one common interface and one common code base to support monitoring, analysis, control, planning and optimization of the distribution and transmission network. Consequently, BWL engaged Util-Assist to develop a Request for Proposal (RFP) to select and procure a new solution. The purpose of the RFP was to solicit proposals for the procurement of an ADMS for BWL. Among the many drivers, an ADMS would ensure that BWL implements a solution that supports BWL s distribution modernization efforts and helps position BWL for future smart grid initiatives. BWL is looking to leverage newer technology to provide functionality that was not previously possible. Outage Management System RFP Timelines The RFP process followed the schedule below: Needs Assessment & RFP Development: March May 2015 RFP Issue Date: May 22, 2015 Proponent Questions Deadline ( Question Deadline ): June 12, 2015 3

Proponent Bid Submission Deadline ( Submission Deadline ): July 15, 2015 Bid Evaluations & Consensus Scoring: July 30, 2015 Sept 2, 2015 Short Listed Vendor Presentations: November 9 20, 2015 Review Vendor Presentations: December 1, 2015 Best and Final Bids Documents due from Vendors: December 18, 2015 Evaluation & Recommendation: January 11, 2016 Executive Recommendation: January 19, 2016 Scope The scope of the RFP consisted of the following: 1. Monitoring functionality, for example: Situational awareness for visibility into daily operations (primary and back-up control center) Power flow and characteristics Outage and restoration information Status of assets (alarms etc.) 2. Analyzing functionality, for example: Fault identification Outage analysis and options Options to reduce system losses Outage reporting and system engineering analysis 3. Operating functionality, for example: Switching management Management of field crews during outage and restoration activities Control to reconfigure the distribution system 4. Optimizing functionality, for example: Optimizing volt/var Optimizing generation and transmission 5. Planning functionality, for example, Forecasting Simulation Asset management planning and system prioritization Contents of the RFP The RFP consisted of four separate documents, provided to vendors as a package: 1. Instructions to Proponents Introduction Timelines/Key Dates 4

Glossary of Terms Instructions for completing proposals Description of the evaluation process Legalities Project Overview ADMS Requirements Price Submission Requirements 2. Appendix A Lansing Board of Water and Light: Electric Service Territory 3. Appendix B Lansing Board of Water and Light: Water Service Territory 4. Pricing Matrix Key Requirements The following formed the minimum requirements of the RFP: 1. ADMS Functional Requirements: The ADMS must have the ability to perform network and operations monitoring specifically for outage management. Reporting and analysis functions must be available for power flow analysis, network connectivity and performance, fault location identification and energy loss analysis. Operational functionality allowing fault isolation and service restoration, Volt/Var control, crew management, schedule outage management and load shedding applications. Optimization functionality enabling load balancing and feeder reconfiguration, automatic generation control, Volt/Var optimization, and Advanced Metering (AMI) capabilities. Planning functionality for distribution load forecasting and simulation modes. 2. ADMS Non Functional Requirements: The ADMS solution must have architectural redundancy, scalability, capacity, security; meet integration point compatibility, user interfaces and informational storage and retrieval abilities. 3. Implementation and Support Services: The vendor proposed ADMS solution must have properly documented implementation plans, project management services, appropriate project staffing, quality assurance, product training services and maintenance and support. 4. Observe BWL OMS Audit Findings: The RFP process provides coverage to ensure technical factors for predicted performance reliability, structured and documented cost analysis and bid evaluation and consideration of alternatives to augment existing systems. The procurement process addresses sufficient system testing prior to operation, upgrade/replacement budgetary planning for over 6 years, ADMS roll out schedule observing connected systems and parallel period to assess system/staff readiness. Vendors The RFP was posted to the BWL internet and additionally, 7 firms were notified that a RFP was available for bidding. Proposals were received from the following three firms: Vendor 5

Vendor Advanced Control Systems (ACS) Schneider Electric Siemens Approach BWL and Util-Assist followed a three-phased approach to develop the RFP and evaluate and select a vendor: 1. Needs Assessment Phase 2. RFP Development Phase 3. RFP Evaluation and Selection Phase Phase 1: Needs Assessment Util-Assist engaged BWL stakeholders to gather the ADMS requirements through working group sessions. Meetings were held with the following departments: Customer Service Information Technology Engineering Operations The ADMS requirements procured through the RFP process were considered to be exclusive to BWL based upon the information gathered through the consultation process with Util-Assist. Phase 2: RFP Development Util-Assist worked with the BWL departments above to ensure that the gathered requirements were clearly expressed and documented within the RFP. Supplementary to the RFP, Util-Assist developed the following documents as part of the scoring package: Best Response Document Weightings Sheet Evaluator Score Sheet Final Pricing and Evaluation Model To ensure that there was no bias in the operational evaluation of vendors, the Best Response document provided RFP evaluators with scoring guidelines. In addition, weighting spreadsheets were used to properly assign BWL s priorities to the RFP requirements. By finalizing these documents prior to receipt of RFP responses, the Best Response documentation and weighting model formed the foundation for a fair and unbiased evaluation process. Phase 3: Evaluat ion and Selection Evaluation Criteria Vendor submissions were evaluated on two fronts: operational strength, as described by the vendor documentation and evaluated using the Best Response Document, and pricing as submitted by the vendors and evaluated on an apples-toapples basis using the pricing functionality matrix. The criteria used by BWL in evaluating and weighting proposals 6

consisted of the following: Criteria Criteria Description Weight Factor (%) Operations Proponent Company Information and References 6.4% ADMS Functionality 65% Implementation and Support Services 8.6% Pricing Pricing Proposal 20% Total 100% Pre-determined evaluation criteria ensured a consistent and fair approach in the evaluation of the bids. Scoring The evaluation team consisted of the following BWL stakeholders: Department Engineering/Business Process Operations Project Coordinator Operations Operations and Reliability Compliance Information Technology Services Engineering Stakeholders Kellee Christensen Lynn McKinstry Brian Sebolt Robert Lalonde Greg Hess Wayne Lynn Individually, these evaluators compared each vendor s response for a given requirement against the ideal response as outlined in the pre-determined Best Response document. Operational scores were awarded based on the information contained within the bid response documents, eliminating any consideration of BWL s past experience with the bidding companies. This process was consistent with best practices and preserved an unbiased procurement process. Util-Assist averaged the operational scores across departments and factored in weightings to determine a Total Operational Weighting for each vendor. The ADMS financial analysis is attached as Appendix A. These scores were combined with the pricing analysis, resulting in the following rankings: ADMS RFP (10 Years) ACS Evaluation Score Schneider Evaluation Score Siemens Evaluation Score ADMS Pricing Capital & O&M Base Functionality (10 Yrs.) $7,569,086.53 $7,845,189.42 $8,240,103.28 Price Ranking 1 2 3 Total Operational Weighting 53.38% 52.91% 34.53% Operational Ranking 1 2 3 Operationally, the scores for two of the three vendors (ACS and Schneider Electric) were quite close; in fact, both vendors 7

can meet BWL s mandatory requirements. However, the analysis revealed that ACS scored the highest on operational scores (Out of a total 80% Total Operational Weighting, ACS scored 53.38% compared to 52.91% for Schneider Electric and 34.53% for Siemens). In addition, ACS s pricing is the lower of the two vendors shortlisted for vendor presentations. File a request with the BWL Purchasing department to obtain copies of the scoring sheets. Overall, ACS was positioned first and Schneider Electric placed second in the weighted rankings. Vendor Demonstrations To ensure that the written responses and functionality descriptions in the RFP matched the state of the actual technology released, vendor demonstrations with the two finalists were held which gave BWL the opportunity to see the actual product. Based on the operational and pricing scores, the two top vendors were invited to deliver on-site demonstrations of their products: ACS Schneider Electric Util-Assist worked with BWL to develop standard demo scripts to ensure that all vendors presented the same functionality. The demo scripts were organized by time blocks, for example, 20 minutes on company history and 25 minutes on technology roadmaps. This evaluation process was considered critical in satisfying the due diligence requirements of the team, as it provided the opportunity for the group to see the products, and to satisfy any outstanding concerns before making a final decision, and initiating the contract negotiation process. Vendors were asked to perform demonstrations of the proposed solution at a utility site with a similar population coverage, commodities and services to that of BWL. The vendor demonstrations confirmed that both vendors could provide the core functionality required by BWL. Schneider brought the evaluation team to Austin Power to demonstrate the deployed AMDS solution November 10 th, 2015. Schneider presented some additional add-in features and a polished user interface. Although these features proved compelling to the stakeholders, they are not a necessity for BWL s ADMS procurement. Schneider s product support is based out of Serbia, potentially resulting in extended resolution periods. ACS brought the evaluation team to the City of Anaheim and Cobb EMC to demonstrate the deployed AMDS solution November 17 th and 19 th, 2015 respectively. It is important to note that ACS s proposed approach consisted of localized product support. BWL felt this would be a significant benefit to their organization. Ultimately, the stakeholders agreed that the vendor demonstrations served to reinforce their original operational scores and that ACS remained the top vendor. Vendor Best and Final Bid Vendors were instructed to provide Best and Final bids during the on-site demonstrations for the purpose of providing an accurate pricing matrix after having the opportunity to fully understand BWL s requirements. Util-Assist performed a second pricing analysis on the Best and Final vendor bid submissions, resulting in the following rankings: 8

ADMS RFP (10 Years) ACS Evaluation Score Siemens Evaluation Score ADMS Pricing Capital & O&M Base Functionality (10 Yrs.) $6,881,015.13 $12,144,906.29 Price Ranking 1 2 ACS provided more competitive pricing which is common after detailed discussion has occurred with the vendor outlining the requirement specifications not available in the RFP document. Schneider provided significantly higher pricing, approximately double the initial bid. Final Decision Having completed the due diligence to support the RFP process, the evaluation team recommends ACS as the winning proponent. ACS s strong functional components would be provided at a highly competitive price, which in combination, results in the best solution for BWL s requirements. Conclusion Util-Assist and BWL are confident that a comprehensive and consistent process has been undertaken and successfully completed, and that the due diligence requirements for a decision of this magnitude have been satisfied. It is recommended that BWL enter into contract negotiations with the top ranking vendor, ACS for the Advanced Distribution Management System solution to satisfy the requirements in BWL s ADMS RFP. Upon executive approval of PO, funds be allocated to advanced discovery during the contract negotiation process with the selected vendor. Budgeting and scheduling will be revised throughout the discovery process. 9

Appendix A: Total Meter Volume 130,000 Base Functionality (10 Years) ACS Evaluation Score Schneider Evaluation Score Financing ADMS Pricing - Capital Base Functionality $3,224,986.96 $7,867,303.03 Interest Rate 4.5 ADMS Pricing - O&M Base Functionality (10 Yrs) $4,960,492.71 $6,041,589.97 Years 10 ADMS Total Pricing - Base Functionality (10 Yrs) $8,185,479.67 $13,908,893.00 NPV Total Pricing - 10 Yrs (NPV with a 5% discount) $6,881,015.13 $12,144,906.29 Travel Costs Vendor Amount % of Integration Price Ranking on NPV 1 2 ACS $ 155,479.75 10.00% Difference Compared to Lowest Individual Price $0.00 $5,263,891.16 Schneider $ 1,089,950.00 20.50% Total Operational Weighting 53.38% 52.91% Average $ 622,714.87 15.25% Total Pricing Weighting Based on Gross 20.00% 11.77% Total Pricing Weighting Based on NPV 20.00% 11.33% Total Weighting Based on Gross 73.38% 64.68% Total Weighting Based on NPV 73.38% 64.24% Total Weighting Ranking 1 2 $16,000,000.00 ADMS Total Pricing - Base Functionality (10 Yrs) $14,000,000.00 $12,000,000.00 $10,000,000.00 $8,000,000.00 $6,000,000.00 ADMS Total Pricing - Base Functionality (10 Yrs) $4,000,000.00 $2,000,000.00 $0.00 ACS Evaluation Score Schneider Evaluation Score LBWL_AMDS_RFP_E valuation_best & Fin 10