Pipejacking Tunnel Boring Machines TBMs. Michael Frenke, LOVAT Inc.

Similar documents
Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Experts in tunneling with Tunnel Boring Machines

BRADSHAW CONSTRUCTION CORPORATION

CS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS

Hardrock Tunnel Boring Machines

Concrete Pipe Jacking

Tunnel Boring Machine Optimization

Ø1.8m Double Shield TBM for Mixed Ground Sewer Tunnels in Cincinnati

PIPE JACKING. An introduction to pipe jacking prepared by the Pipe Jacking Association

2 Support of the cavity and settlement Support of the face Natural support Mechanical support...

PIPE JACKING & TUNNELING SYSTEMS DRIVEN FOR CUSTOMER SUCCESS

USE OF MICROTUNNELING TO INSTALL PIPES IN AN ENVIRONMENTALLY SENSISTIVE AREA. Miranda Roman D. *, LaFaso Edward

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal

Pipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2

QUANTIFYING THE EFFECTS OF LUBRICATION ON JACKING FORCES

Developed countries require a modern infrastructure Roads Railways Power Communications Water Wastewater

TBM Selection and Specification

DIFFICULT GROUND SOLUTIONS:

Tel: Neil: Tony: Website:

From Colonia Jardín to Cuatro Vientos

IPC Company & DPI Presentation. February 2017

Concrete Pipe Jacking

2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

No-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e.

Reinforced Concrete Microtunnelling Pipe Designed for Project Conditions and MTBM Machines

Microtunnelling. Building infrastructures and power supply systems underground, while life above continues unaffected.

Tunnelling under the Fraser River at 6 bar Design and Construction of the Port Mann Main Water Supply Tunnel

Design and Implementation of the South Hartford CSO Tunnel

1.0 Micro Tunnelling An overview

2 Technology of closed-face tunnelling machines

LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL

Presented By: Brenden Tippets, Project Executive

Design Data 4. Jacking Concrete Pipe

Modeling Microtunnelling Construction Operations with WebCYCLONE

Martha Lake Gateway Sewer. An Introduction to Trenchless Methods and Evaluation for the Installation of New Pipelines

Wastewater Capital Projects Management Standard Construction Specification

Pipe Jacking. Japan Sewage Works Association

Design Data 4M. Jacking Concrete Pipe

Expert in Tunneling Systems & Trenchless Technology (HDD, Microtunneling, Pipe Jacking, Thrustboring, Sheet Piling)

Draft. Not yet Approved TABLE OF CONTENTS. Page

Pipetron Tunnel Construction Issues

Australasian Society for Trenchless Technology Standard for Microtunnelling & Pipe Jacking

PIPEJACKING AND MICR OTUNNELLIN G. James C. Thomson, C. Eng., Eur. Ing. Chairman Jasoo Consultancy Group London- Geneva- Washington DC

4th International Engineering and Construction Conference - July 28, 2006

TRANSPORTATION RESEARCH FORUM March A State-of-the-Art of Underground Construction In Urban Areas

Pipe Jacking Association An introduction to pipe jacking and microtunnelling

NO DIG BERLIN 2015 Symposium and Exhibition March. Paper 5-3. Increasing requirements move boundaries in Pipe Jacking

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

Slurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P.

Pipe Jacking. Progress is built on ideas.

Tunnels. Introduction in Shield tunnelling Pipe jacking & tunnelling Slurry & hydroshield Slurry versus EPB Principles of support pressure

COMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS

MICROTUNNELING SYSTEMS DRIVEN FOR CUSTOMER SUCCESS

The Robbins Company. Bheri Babai Diversion Multipurpose Project (BBDMP) Company Facts. Headquarters

ITEM 432 TUNNEL CONSTRUCTION

SPECIAL CONDITIONS FOR MICROTUNNELING (MT) October, 2006

TRENCHLESS SOLUTIONS FOR SEWER NETWORKS AND SEA OUTFALLS.

TBM rescue projects using shafts and ground freezing

Risk Management - TBM Manufacturer s Perspective II

Special Committee on Bay-Delta Item 3b January 24, 2017

Tunnel. Immersed Tunnels

CC1602 Microtunneling

LONGEST MULTI CURVATURE SEWER TUNNEL IN THE MIDDLE EAST

Behavior of Surrounding Soil during Construction and Its Countermeasures Using Pipe Jacking Method in Deep Strata

Exploring Critical Factors Affecting upon Micro-tunnelling Equipment Productivity

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer

Venice Pumping Plant Dual Force Main Project Draft EIR

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

Topic 3: 1 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt

FEATURES & BENEFITS OF ARMTEC TUNNEL LINER PLATE

Forensics by Freezing

Sioux City Iowa Utilizes HDD to Install Twin 36 Casings for Sanitary Sewer Siphons

NMS Table of Contents

STANDARD SPECIFICATIONS SECTION JACKED CASING

Section TUNNEL GROUT. A. Mix design requirements, testing, furnishing, and production of grout for:

Instrumentation and Data Management for the Zurich Zimmerberg Railway Tunnel Construction Daniel Naterop Solexperts Ltd.

FOR HIGHWAY TUNNEL GALLERIA SPARVO.

ASCE PIPELINES 2015 CONFERENCE. Recap/Highlights by Bill Chavez, PUG Vice-Chairman Baltimore, MD August 23-26, 2015

Direct Pipe Installations underneath USACE Levees Keeping Permitted Minimum Hydraulic Fracture Factor of Safety

Prof. Eng. Daniele PEILA

HYDRAULIC CYLINDERS. Custom made in Germany

WARNING DO NOT BID ON THIS PROJECT

MICRO-TUNNELING LARGE DIAMETER SEWER MAY BE THE BEST OPTION FOR YOU

An introduction to. pipe jacking

SPECIFICATION : BORING AND JACKING

Total Automatic Excavation System for TBMs Takayoshi Nakayama, Satoshi Inoue, Yasuhide Seno Kansai Branch, Okumura Corporation ABSTRACT

Remote Monitoring of Gauge Cutter Wear in Pressurized Face Tunneling

Project report on a deep well construction

Dahlia Ponds Tunnel Project. Presented By: Nathan Soule, PE, PG Brierley Associates & Brenden Tippets, Project Executive, BTrenchless

Solutions for tunneling and mining TBM. Expanding Horizons Underground

Logistics of Limited Space Urban Tunnelling at Singapore s Mega Metro

The new Standard DWA-A 125E. Pipe jacking and related techniques. published in German and English by

Short Drive Microtunnelling (MTBM) TRENCHLESS TECHNOLOGY ROADSHOW May 28-29, 2014 Scotiabank Convention Centre, Niagara Falls, ON

Analysis of Design When You Should Consider Pipe Ram Over Traditional Auger/Jack & Bore

Design of pipeline installation. D-Geo Pipeline

Cutting-Edge Trenchless Technology Proposed for Challenging CSO Project

13/05/2016. Introductions of Pipe Roof. Focuses. Application of Rectangular Shield Jacking

Transcription:

Pipejacking Tunnel Boring Machines TBMs Michael Frenke, LOVAT Inc.

Pipejacking Tunnel Boring Machines (TBMs( TBMs) Introduction Pipejacking Sequence TBM Design Features Types of Jacking Pipe Pipejacking Considerations LOVAT Pipejacking TBMs

Introduction Pipejacking is a technique for installing underground pipelines via the use of a boring machine ahead of a pipe string, advanced through the ground by a jacking station in the main shaft. Pipejacking is a one pass lining method, where the pipes form and act as the finished tunnel liner. Pipes may be constructed of various materials (concrete, steel, fiberglass, clay, plastic). Pipejacking is used as an alternative to open-cut excavation, especially in smaller diameters and in deep or difficult ground conditions.

Introduction Pipejacking can be performed with: Tunnel Boring Machines (TBMs) Earth Pressure Balance and Slurry type Piloted from with TBM Micro Tunnel Boring Machines (MTBMs) Slurry type Controlled remotely from surface Auger Borers Hand Mining Shields

Pipejacking Sequence 1. Pipe lowered into shaft, onto main jacking station cradle 2. TBM advances using propulsion cylinders, muck cars filled with excavated earth and removed from shaft 3. Main jacking station thrusts pipe forward until TBM propulsion cylinders have retracted

Pipejacking Sequence 4. TBM advances using propulsion cylinders, muck cars filled with excavated earth and removed from shaft 5. Main jacking station stroked out completely, retracting TBM propulsion cylinders and burying pipe 6. New pipe is lowered in shaft and cycle restarted

TBM Design Features Overview Propulsion Cylinders Telescopic Leading Can Arch Ring Supports Main Jacking Station Intermediate Jacking Stations Tunnel Eye Seal Bentonite Injection System Ground Conditioning System Pipe Lock (Hyperbaric Airlock)

TBM Design Features

TBM Design Features

TBM Design Features Propulsion Cylinders

TBM Design Features Telescopic Leading Can

Support of TBM Ancilliary Equipment (Ventilation, Transformer, Power- Packs, Conveyors, etc.) TBM Design Features Arch Ring Supports Arch ring is expanded within the pipe sections

TBM Design Features Arch Ring Supports

TBM Design Features Installed at bottom of main shaft Main Jacking Station Provides forward thrust to advance the TBM and/or pipe string Integral Rail System

TBM Design Features Main Jacking Station

TBM Design Features Installed in-between pipes Intermediate Jacking Station Assists in forward movement of pipe string (inch-worm motion

TBM Design Features Bentonite Injection System Bentonite is used to reduce friction between the outside diameter of the pipe string and the surrounding ground. The system pumps the bentonite through ports in the TBM and the pipe into the surrounding excavation annulus. The system is usually automatic and interlocked with the advance of the TBM.

TBM Design Features Tunnel Eye Seal

TBM Design Features Ground Conditioning System Foam agent injection system used to control the earth pressure and consistency of the excavated muck Integral component of an Earth Pressure Balance (EPB) TBM

TBM Design Features Pipe Lock Airlock installed directly in pipe section Allows for hyperbaric interventions in high pressure environments and poor ground conditions

Types of Jacking Pipe Pipejacking TBMs can be configured to mine with all types of Jacking Pipe. The trailing edge of the Telescopic Leading Can is machined to fit the leading edge of the first pipe in the string, creating a seal against earth and water ingress. Type of Jacking Pipe Reinforced Concrete Pipe Steel Pipe Welded Joint of Permalok type Glass Fiber Reinforced Pipe HOBAS Plastic Pipe High Density Polyethylene (HDPE) Clay Pipe - Meyer

Types of Jacking Pipe Reinforced Concrete Pipe

Type of Jacking Pipe Steel Pipe Permalok Joints

Types of Jacking Pipe Glass Fiber Reinforced Pipe - HOBAS

Pipejacking Considerations Considerations for a successful pipejacking TBM tunnel: 1. Proper Geotechnical Investigation Extensive boreholes to determine what type of geology lies along the intended alignment 2. Tunnel Length Shaft to Shaft distances should be short (200m to 1,000m) Longer drives are possible using intermediate jacking stations 3. Lubrication Bentonite lubrication reduces friction on the outside of the pipe string ( float pipe if possible) Ensures pipe string will not bind-up between shifts or during long stoppages

Pipejacking Considerations 4. Ground Treatment Uses of conditioning agents mechanically alters the characteristics and behavior of the earth and reduces wear on the cutting tools and cuttinghead 5. Alignment Keep it straight for best results Wide curves are possible, but need to consider many other factors (pipe joints, specialized guidance systems, etc.) 6. Water-Proofing Reduce water and ground inflows into tunnel by utilizing tunnel eye seals and proper pipe joint seals

LOVAT Pipejacking TBMs RME106PJ Series 17800 Bern, Switzerland

LOVAT Pipejacking TBMs RME104PJ Series 22501 Milwaukee, USA

LOVAT Pipejacking TBMs Micro Tunnel Boring Machine (MTBM)

LOVAT Pipejacking TBMs DELIVERY MACHINE SERIES CURRENT DRIVE GROUND YEAR OPERATING CITY Meters 2006 MP90PJ 22500 Appelton, USA 1,800 1,2,3,4 2008 MP104PJ 22501 Milwuakee 4,201 1,2,3,4 2000 RMPS121PJ 19400 Pusan, Korea 750 7 2006 RMP101PJ 19303 Milwaukee, USA 1,500 2002 RME101PJ 19301 Florida, USA 65 2004 RME106PJ 17802 Kraznoyarsk, Russia 2000 RME106PJ 17801 Zurich, Switzerland 1,200 1, 2, 3, 4, 6 1998 ME106PJ 17800 Bern, Switzerland 1,586 1, 2, 3, 4, 6 1997 MP101SE/PJ 17700 Southport, U.K. 2,400 2,3,4 1996 MP79PJ 12700 London, U.K. 4,700 5 1996 RMP121PJ 16800 Seoul, South Korea 480 4, 7 1994 RMP101PJ 14500 Brighton, U.K. 3,200 2, 3, 6 1994 MP112PJ 14400 Alexandria, Egypt 3,600 2 1993 RMP113PJ/SE 13400 Glasgow, Scotland 2,300 1, 2, 3, 5 1991 MP134PJ 11900 Alexandria, Egypt 2,500 2, 4 1991 MP83/90PJ/RL 11800 Dallas, USA 4,270 2, 3, 4 1991 M104PJ 11200 Kenosha, USA 6,096 1, 3, 4

LOVAT Pipejacking TBMs DELIVERY MACHINE SERIES CURRENT DRIVE GROUND YEAR OPERATING CITY Meters 1990 MP117RL/PJ 10600 St. Louis, U.S.A. 6,401 2, 4 1988 MP86SE/PJ 9500 Cleethorpes, U.K 3,048 2 1988 MP133SE/PJ 9300 Fort Worth, USA 4,572 1, 2, 3, 4 1988 MP77PJ 7700 Milwaukee, USA 4,572 1, 3, 4 1987 MP121/137RL/PJ 8600 San Diego, USA 4,572 2, 4 1987 MP118PJ 8200 Chieti, Italy 2,743 3, 4 1987 MP86PJ 8100 Deal, U.K 3,353 2, 3 1986 MP100PJ 7800 Blackpool, U.K. 2,743 2, 3 1986 MP90RL/SE/PJ 7600 Dallas, USA 5,791 1, 3 1986 MP77PJ 7200 Manchester, U.K 5,738 2, 3, 4 1985 M60PJ 3500 Cairo, Egypt 915 3, 4 1984 M77RL/PJ 6200 USA 4,572 4, 5 1983 M100/116SERL/PJ 6300 Glasgow, Scotland 3,500 2, 3, 4 1983 RM79/85SE/PJ 4900 Cleethorpes U.K. 8,600 2, 3, 4 1975 M100RL/PJ 1600 Toronto, Canada 9,144 3, 4 1975 M110/112PJ 2000 Detroit, USA 12,192 3, 4 1974 M96PJ 900 Toronto, Canada 2,743 2, 3