CONNECTION TO INSPECTION CHAMBERS PRAKTO

Similar documents
SECTION UTILITY BACKFILL MATERIALS

Excavation for Natural Gas Mains and Services

Handling and Installation Instructions

SECTION FACILITY SANITARY SEWERS

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

TRENCH EXCAVATION AND BACKFILL

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS IN OPEN CUT

Technical Data Sheet NEC/GRAN/95:01

B. Borrow: Satisfactory soil imported from off-site for use as fill or backfill.

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

PD - 6 THRUST RESTRAINT DESIGN EQUATIONS AND SOIL PARAMETERS FOR DUCTILE IRON AND PVC PIPE

TABLE OF CONTENTS

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017

SECTION 500 STRUCTURES

Section SITE CLEARING. B. Description of Work: 1. The extent of site clearing is shown on the drawings.

Section 403. DRAINAGE STRUCTURES

h Installation Manual

Assembly and Installation Instructions Grease Separator KLsepa.pop

TRENCH EXCAVATION AND BACKFILL

INSTALLATION INSTALLATION

SECTION EXCAVATION, TRENCHING AND BACKFILL

APPENDIX 5: CONSTRUCTION CHECKLISTS

PRO POLYPROPYLENE MANHOLES.

Fabrication and Installation Table of Contents

SECTION FILL AND BACKFILL

Technical Documentation

Drainage structure refers to manholes, catch basins, leaching basins, inlets and drop inlets. Drainage structures are designated as follows.

SECTION TRENCHING, BACKFILLING AND COMPACTION. B. Provide necessary sheeting, shoring and bracing.

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

Special Provision No. 405F03 March 2005

July Bill No.1: Preliminaries

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING

WATER INDUSTRY SPECIFICATION

SPECIAL SPECIFICATION 4653 Polypropylene Pipe

Section 401. PIPE CULVERTS

SECTION MANHOLES AND STRUCTURES. A. Section Includes: 1. Manholes for water, storm drain and sanitary sewer systems.

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF ELECTRICAL CHAMBERS

1510 STORM DRAINAGE UTILITIES

Thi_ Qar University College of Engineering/Civil Engineering Department. Highway Lectures. Fourth Class. Part #2: - Subgrade Soil


CONTENTS INSTALLATION DETENTION SYSTEMS PHYSICAL PROPERTIES AGRICULTURE INSTALLATION GUIDE

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

SPECIAL SPECIFICATION 4425 Thermoplastic Pipe

B. Base Course: Aggregate layer placed between the subbase course and hot-mix asphalt paving.

(SIZE) MANHOLES CATCH BASINS AND DITCH INLETS -Item No. ADJUSTING AND REBUILDING MANHOLES, CATCH BASINS AND DITCH INLETS - Item No.

A. Gravity-Flow, Nonpressure, Drainage-Piping Pressure Rating: 10-foot head of water (30 kpa).

StormTech Construction Guide

Bill No.1: Preliminaries

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER

DETENTION, RETENTION AND RECHARGE STRUCTURES

h GRP Pipe Systems Transportation, Installation & Maintenance

1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK

New Fulton State Hospital Energy Control Center and Services Building (ECC/SVC) Project Number: M

StormTech Construction Guide

TYPICAL INSTALLATION INSTRUCTIONS

SECTION TRENCHING

SECTION AGGREGATES

In preparation for constructing buildings on a property, the builder. Site Preparation CHAPTER

SECTION Segmental Concrete Unit Masonry Retaining Wall Height Over 5-0 High

MagnumStone Specifications Gravity

R-TANK SPECIFICATIONS

SECTION DUCTILE IRON FITTINGS. A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller.

1.1 SECTION INCLUDES.1 Materials and installation for water mains, hydrants, valves, valve boxes, and valve chambers, including service connections.

Polysewer Gravity Sewer System SPECIFICATION

SECTION STORM DRAINAGE

StormTech Construction Guide

Installation Data for Elliptical Pipes. PD 29 rev E 20/09/05

PERMANENT PAVEMENT REPAIR NO SCALE

WORKS DESCRIPTION Unit. Quantity Unit price Total USD

SECTION PIPE INSTALLATION

SECTION 39 - MANHOLES TABLE OF CONTENTS

Table of Contents. Section Trench Excavation and Backfill Section Includes Description of Work 1. 1.


CONTRACT 5E-2 APPENDIX A - TEST HOLE LOGS DYREGROV ROBINSON INC. PORTAGE AVE WINSTON DR BOURKEVALE CAVELL PARKSIDE DR ASSINIBOINE AVE

SECTION 1100 GRADING 1102 MATERIALS AND DEFINITIONS.

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

StormTech Construction Guide

SECTION STORM SEWER PIPE

Installation and maintenance instructions for PLATIN and PLATIN XL Rainwater Underground Tank

Table of Contents. Section Trench Excavation and Backfill Section Includes Description of Work 1. 1.

Retaining Wall System

Installation Overview

EUROFLO TECHNICAL BROCHURE 160MM 1200MM

Student Services & Classroom Addition

Introduction to Road Soil

CONSTRUCTION SPECIFICATION FOR EXCAVATING AND BACKFILLING - STRUCTURES

55.3 AGGREGATE PRODUCTION AND STOCKPILING

StormTech Construction Guide An company

SECTION VI SANITARY SEWERS

Anchorplex retaining wall construction guide

Underground Exhaust System

Civil Geotechnical Surveying

1. Division 01 Section General Requirements - Temporary Facilities and Controls. 2. Division 31 Section Earthwork.

SPECIAL SPECIFICATION 3504 Septic Tank System

CITY OF LETHBRIDGE SECTION INFRASTRUCTURE SERVICES Page 1 of 7 GRANULAR BASE PREP

Amendments to the January 2016 Design Criteria Manual & Supplementary Master Municipal Construction Documents

GUIDELINES FOR INSTALLATION OF ON-SITE SEWAGE SYSTEMS

Table of Contents. Section Trench Excavation and Backfill Section Includes Description of Work 1. 1.

Anchorplex retaining wall construction guide. Building. Anchorplex. Retaining Wall Systems

Rethinking Water Management Systems

Transcription:

CONNECTION TO INSPECTION CHAMBERS PRAKTO The inspection chambers PRAKTO made by Pipelife are designed and manufactured to be conveniently and securely connected to pipes and fittings of the Pragma series using an adapter! 1- PP base bottom RML 2- PP extension PRAGMA SN8 3- Telescopic part 4- Smooth-wall PVC pipe 5- Corrugated pipe PP-B PRAGMA 6- PP-B PRAGMA end cap 7- PP-B PRAGMA adapter for PVC 8- Lid Connection of Pragma pipes to PRAKTO manholes

CONNECTION TO MANHOLES PRO The manholes PRO made by Pipelife are designed and manufactured to be conveniently and securely connected to pipes and fittings of the Pragma series! Connection of Pragma pipes to PRO manholes

SETTING THE BASE AND RISER RINGS Vibrating tamper 500mm Backfill compacted layer by layer every 30 cm Bottom of excavated pit (well compacted soil or concrete bed) 1. Setting the base on the compacted sand bed - 10 cm thick 2. Fixing the rubber sealing and greasing it with Pipelife lubricant 3. Mounting the riser rings, the last one remaining without a sealing ring 4. Pouring the backfill by 30 cm thick layers and manual compacting 95-97% up to the base of the last extension ring Note: The traffic of vehicles on top of the lid should not be allowed because it has no reinforcement against horizontal dynamic stress, which may result in displacement and cause deformation of the telescopic part.

The minimum distance from the cone crown to the terrain elevation should be 30 cm Vibrating tamper MOUNTING THE CONE 100/630 Cone 1000/630 400mm Backfill compacted layer by layer every 30 cm 1. After all extension rings have been mounted proceed to the mounting of the cone on the last extension ring which was left without a sealing ring. Measure the distance from the field elevation to the cone crown and if the measured distance is shorter than 30 cm, remove the cone and shorten the extension ring below it by 10 cm or 25 cm. 2. Put the rubber sealing, lubricate and mount the cone again. Bottom of excavated pit (well compacted soil or concrete bed) Note: The traffic of vehicles on top of the lid should not be allowed because it has no reinforcement against horizontal dynamic stress, which may result in displacement and cause deformation of the telescopic part.

MOUNTING THE TELESCOPE AND SAFETY RING PRAGMA DN590 Mounting the telescope very close to the terrain elevation Vibrating tamper The safety ring protects the telescope during backfill compacting Vibrating tamper 400mm 400mm 3. Mounting the telescopic ring - apply lubricant to the sealing ring which is embedded in the cone - mark the telescope 15 cm from the bottom and insert it into the cone up to the marking 4. Put the safety ring PRAGMA OD590 on the telescope to protect its shape and integrity. One side of the safety ring is cap-closed, preventing inert materials to fall inside the manhole. Note: The traffic of vehicles on top of the lid should not be allowed because it has no reinforcement against horizontal dynamic stress, which may result in displacement and cause deformation of the telescopic part.

LAYING THE BASE COURSE IN THE AREA AROUND THE TELESCOPE Gap around the telescope needed for the asphalt or concrete ring Bitumen stabilized ballast 2 x 6 cm Crushed stone 8-20 mm 400mm Backfill compacted layer by layer every 20 cm Bottom of excavated pit (well compacted soil or concrete bed) Having mounted the telescope and the safety ring on the cone, proceed to the laying of base course and bitumen stabilized ballast in accordance with the requirements for making the roadbed. Leave a gap around the telescope at 200 mm from the telescope and 160 mm under the telescope flange. The gap so created may be occupied by a 160 mm high concrete ring or may be filled with asphalt during pavement works.

LAYING THE BINDER Laying the binder and leveling the lid Binder 2 x 4 cm Bitumen stabilized ballast 2 x 6 cm Crushed stone 8-20 mm 400mm Backfill compacted layer by layer every 20 cm Bottom of excavated pit (well compacted soil or concrete bed) 1. Laying the load-bearing 80 mm high asphalt layer and preparing the base for the lid.

MOUNTING THE LID AND LAYING THE WEARING COURSE Laying the binder and leveling the lid Wearing course (compacted asphalt) Bitumen stabilized ballast 2 x 6 cm Crushed stone 8-20 mm 400mm Backfill compacted layer by layer every 20 cm Bottom of excavated pit (well compacted soil or concrete bed) 1. Laying the wearing/surface course.

TEMPORARY SOLUTION USING A CONCRETE RING AND TELESCOPE RISER DN630 Vibrating tamper Wearing course (compacted asphalt) Binder 2 x 4 cm Bitumen stabilized ballast 2 x 6 cm min 20cm Crushed stone 8-20 mm 250mm Backfill compacted layer by layer every 20 cm Bottom of excavated pit (well compacted soil or concrete bed) 1. Assembly and erection of the manhole taking care to leave at least 45 cm distance from the field elevation to the cone crown. 2. Laying the backfill by 30 cm thick layers and manual compacting 95-97% according to Proctor. 3. Mounting the telescopic ring. - mark the telescope 10 cm from the bottom and insert it into the cone up to the marking - pour the crushed stone and stamp manually taking care to distribute it evenly in order to avoid deformation of the telescope. - upon reaching the level for placement of the 16 cm high concrete ring, adjust it on the telescope by letting it rest on the flange and push it until it touches the base. 4. Fix (by anchor bolt) the lid to the concrete ring Now the base is ready for laying the asphalt pavement. Note: The traffic of vehicles on top of the lid should not be allowed because it has no reinforcement against horizontal dynamic stress, which may result in displacement and cause deformation of the telescopic part.

TEMPORARY SOLUTION USING A CONCRETE RING AND TELESCOPE RISER DN630 Wearing course (compacted asphalt) Binder 2 x 4 cm Bitumen stabilized ballast 2 x 6 cm min 20cm Crushed stone 8-20 mm 250mm Backfill compacted layer by layer every 20 cm Bottom of excavated pit (well compacted soil or concrete bed)

MOUNTING THE LID USING A CONCRETE RING AND TELESCOPE RISER DN630 Wearing course (compacted asphalt) Binder 2 x 4 cm Bitumen stabilized ballast 2 x 6 cm min 20cm 500 Crushed stone 8-20 mm 250mm Backfill compacted layer by layer every 20 cm Bottom of excavated pit (well compacted soil or concrete bed) Laying the asphalt pavement: Note: Check the lid elevation and the position in case there was an instance of vehicles traffic from the time of mounting the lid to the time of laying the road pavement.

Note: The depth and composition of the road pavement should correspond to the client's design specifications. The backfill may consists of the most types and classes of natural granular materials with maximum grain size not bigger than 10% of the pipe nominal diameter or maximum size 30 mm. The backfill material should not contain foreign objects (mixtures) such as snow, ice or frozen earth masses. Characteristics of materials used for backfilling: material gravel, crushed stone gravel sand, moraine pebbles grain size [mm] 8-22, 4-16 8-22, 4-16 2-20 0.2-20 Remarks this is the most suitable soil material, containing from 5 to maximum 20% particles with grain size 2 mm this is a suitable soil material, containing from 5 to maximum 20% particles with grain size 0.2 mm this is an acceptable soil material, containing maximum 5% particles with grain size 0.2 mm The sand cushion should be compacted very well up to 95% according to Proctor. The bottom of excavated pit should be made of well compacted soil or concrete bed. The areas around the inlets and the outlet should be compacted manually. The compacting density should be 95% according to Proctor. Observe the direction of compacting shown in the design drawing.

Compacting Non-Compacted backfill layer Compacted backfill layer Compacted backfill layer Maximum depth of the compacted backfill layer Lower compacted backfill layer Soil type Gravel type (Non-Cohesive) Soil group acc. to ATV127 Soil group popular name symbol* distinguishing features examples G1 Single grain size gravel [GE] [GU] Gravel with different size grains, gravel-sand Gravel with uniform size grains, gravel-sand Single grain size sand Sand with different size grains, sand-gravel [GW] [GI] [GP] [SE] [SU] [SW] Steep granular line with prevalence of large size grains Uninterrupted granular line with several granulometric groups Steep granular line with one or more missing granulometric groups Steep granular line with one dominating granulometric group Uninterrupted granular line with several granulometric groups Crushed stone, river and coastal pebbles, moraine sand, cinders, volcanic ashes Sand from dunes and basin beds, river sand Moraine sand, coastal sand, beach sand Backfill compacting tools Manual or foot-operated stamping - min 15 kg Vibrating Tamper - min 70 kg No of compacting tool courses to achieve 95% compacting acc. to Proctor Maximum depth of the backfill layer after compacting depending on the soil group G1 G2 G3 G4 Minimum depth of the backfill layer remaining above the pipe crown before compacting m m m m m 3 0.15 0.1 0.1 0.1 0.2 3 0.3 0.25 0.2 0.15 0.3 Sand with uniform size grains, sand-gravel [SI] [SP] Steep granular line with one or more missing granulometric groups G2 & G3 Debris gravels, gravel-debris-sand with uniform size grains [GU] [GM] Wide/interrupted granular line with fine debris particles Crushed gravel, rock debris, clay gravel Clay gravel, gravel-sand-clay with uniform size grains [GT] [GC] Wide/interrupted granular line with fine debris particles Debris sand, sand-debris with uniform size grains [SU] [SM] Wide/interrupted granular line with fine debris particles Quicksand, earth, sand loess Clay sand, sand-debris with uniform size grains [ST] [SC] Wide/interrupted granular line with fine debris particles Sandy soil, alluvial clay, alluvial chalky clay Cohesive G4 Inorganic debris, fine sand, rock particles, debris or clay fine sand Inorganic clay, distinctly plastic clay [UL] [ML] [TA] [TL] Low stability, shortly reactive, zero to low plasticity Medium to high stability, slowly reactive, low to medium plasticity Loess, clay Alluvial clay, clay [TM] [CL]