A Practical Approach using CPM/PERT: for Certain Activity Times in Construction Parking Project

Similar documents
PMP Exam Preparation Course Project Time Management

Scheduling. Adapted from John Musser

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

Program Evaluation and Review Technique (PERT)

Scheduling Resources and Costs

Chapter 3 Managing the Information Systems Project

Introduction. Project Scheduling. Morgan State University ARCH 738: REAL ESTATE PROJECT MANAGEMENT. Jason E. Charalambides, PhD, M.

Time Management PLANNING

Project Time Management

Analysis of Common Project Schedule Management Methods Wei-guo LIU *, Xue SHEN and Tian-qi WU

6 PROJECT TIME MANAGEMENT

Project Management in Practice Fifth Edition

E2-E3: MANAGEMENT. CHAPTER-3 PROJECT MANAGEMENT (Date of creation: )

Modern Systems Analysis and Design Seventh Edition

Information Technology Audit & Cyber Security

12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish

Chapter 4 Project Management

Luis R. Garcilaso March 13, Lecture #22. Service Processes & Systems Dept. of Mechanical Engineering - Engineering Mechanics

Project Management. Learning Objectives. What are Projects? Dr. Richard Jerz. Describe or Explain:

Project Management. Dr. Richard Jerz rjerz.com

Time has the least. amount of flexibility; Schedule issues are the main reason for

Introduction to Project Management

Construction Scheduling and Estimating

Week 5 Project Work Plan

Cambridge International AS & A Level Computer Science

Project Planning & Scheduling

Week 5 Project Work Plan

Network Diagram 11/10/2016 WORK BREAKDOWN STRUCTURE (WBS)

Project Time Management

Project Time Management

Project Management Professional (PMP) Exam Prep Course 6 - Project Schedule Management

IST 302 : Project Time Management

CIPRIANI COLLEGE OF LABOUR & CO-OPERATIVE STUDIES BSC IN PROJECT MANAGEMENT PRM 135: PROPOSAL DEVELOPMENT & COSTING WEEK 8

Operations Management

Lecture- 10. Project Scheduling. Dronacharya College of Engineering

Week 5 Project Work Plan

Information Technology Project Management, Seventh Edition

Project vs Operation. Project Constraints. Pankaj Sharma, Pankaj Sharma,

TEXTS IN OPERATIONAL RESEARCH

Software Project Management

MODULE 15 OPERATIONAL PLANNING TECHNIQUES (USE OF PLANNING TOOLS LIKE GANTT CHART, PERT/CPM)

Dynamic Scheduling of Aperiodic Jobs in Project Management

December 25, 2017 CHAPTER 4 SUPPORTING PLANNING AND CONTROL: A CASE EXAMPLE

Week 5 Project Work Plan

Repetitive construction processes scheduling using mixed-integer linear programming

Project Scope Management

PROJECT EFFECTIVENESS IMPROVEMENT: A CASE STUDY IN PT.X

BUTE Department of Construction Management and Technology

Topic # 12. CIS Project Management: an overview

MGT/437. Project Management. Session #2 University of Phoenix 02/12/2004 Brian Smithson. 02/12/2004 MGT/437 #2 -- Brian Smithson 1

Planning & Scheduling

EFFICIENCY OF CRITICAL PATH METHOD (CPM) AND PERT TECHNIQUE FOR YACHT CONSTRUCTION

Institute of Certified Management Accountants of Sri Lanka

Developing a Project Plan

Prepared by: Mr.M.SYED SHAHUL HAMEED CHAPTER 3 SYSTEMS PLANNING - MANAGING SYSTEMS PROJECTS

MBP1133 Project Management Framework Prepared by Dr Khairul Anuar

How to Strengthen Workers Management Relationship Using Network Techniques - A Case Study

The recommended guided learning hours for this unit are 30 hours.

CHAPTER 1. Basic Concepts on Planning and Scheduling

MBH1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar. Lecture 6b Project Time Management - II

Lecture- 11. Project Scheduling. Dronacharya College of Engineering

THE PMP EXAM PREP COURSE

Work Analysis and Design

Software Process and Management

Constructing Networks

PMP043 Project Scheduling and Budgeting

Global Project Management, LLC

International Association of Certified Practicing Engineers

The E- project manager

Chapter 5 Project Scheduling. (Source: Pressman, R. Software Engineering: A Practitioner s Approach. McGraw-Hill,

Projects can be of any size and duration. They can be simple, like planning a party, or complex like launching a space shuttle.

CE2353-CONSTRUCTION PLANNING & SCHEDULING

MnDOT Project Management Office Presents: Impact Schedules. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

PMP EXAMINATION PREP CHAPTER 6 SCHEDULE MANAGEMENT. PMP Exam Prep

Chapter 3 Managing Systems Projects

Estimating and Scheduling

MnDOT Project Management Office Presents: Risk Management. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

Adapting the Approach of Management by Projects in the Manufacturing Industry: A Conceptual Framework

MBP1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar

Principles of Planning for IT Projects

Seminar 6: Project Management Part 1 Semester 1, 2005

The Project Planning Process Group

Seminar 6: Project Management Part 1 Semester 1, 2005

L & L Mitigation Aid for Effective Project Management System

Introduction to IT Project Management

GE404 Engineering Management Topic1. INTRODUCTION

PMBOK Guide Fifth Edition Pre Release Version October 10, 2012

Scheduling Concepts and MS. Project AZURITE PROJECT TRAINING AND CONSULTING PVT LTD (OPC) 2014

INDIAN INSTITUTE OF MATERIALS MANAGEMENT Post Graduate Diploma in Materials Management PAPER 18 C OPERATIONS RESEARCH.

Implementing Resource Scheduling Techniques

Course Outline. Project Management Concepts Course PM12: 3 days Instructor Led

Project Management Glossary of Terms

Managing Complexity in the Face of Uncertainty

PMP Sample Questions Click here for PMP Questions. Question No : 1 Which of the following is an output of Define Scope?

Information Technology Project Management

Planning & scheduling

Artificial Intelligence

Effect of Scheduling towards increase agricultural production in Libya.

GLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155

1.Which of the items listed below is not one of the software engineering layers?

Transcription:

World Applied Sciences Journal 35 (7): 1180-1184, 2017 ISSN 1818-4952 IDOSI Publications, 2017 DOI: 10.5829/idosi.wasj.2017.1180.1184 A Practical Approach using CPM/PERT: for Certain Activity Times in Construction Parking Project 1 1 1 1 Aznida Hayati Zakaria, Norizah Haron, Wan Suryani Wan Awang, Zarina Mohamad, 1 1 1 2 Fadhilah Ahmad, Nurnadiah Zamri, Ahmad Nazari Mohd Rose and Mustafa Mat Deris 1 Faculty of Informatics and Computing, Universiti Sultan Zainal Abidin, Malaysia 2 Faculty of Computer Science and Information Technology, Universiti Tun Hussein Onn Malaysia, Malaysia Abstract: Project management technique varies and is applied based onthe domain s specifications. This research studies the applicability of a project management technique in the domain of construction project. The success of a construction project is measured based on three main factors; time, cost and project performance. The three factors must be delicately balanced and monitored in assuring the success of a project. This paper presents the parking project scheduling by using Critical Path Method/Project Evaluation and Review Techniques (CPM/PERT). CPM/PERT is used in providing the deterministic and probabilistic aspect that are used in the planning, scheduling and controlling the project s duration and cost. By doing so, the scheduling the parking project with CPM/PERT method will be more adaptable to changes during the execution of the projectby managing project delays and cost efficiently. Thus, the CPM/PERT is able to schedule the parking project and provide better schedule time. Key words: Project Management CPM/PERT Schedule Parking Project INTRODUCTION Niazi and Painting [6] identified the following reasons for the problems; 1. difficulties in financing the project by Project management is the application of knowledge, contractors, 2. changing the project requirements during skills and techniques to execute projects effectively and construction, 3. market inflation. Al-Hazim et al. [7] efficiently. It is a strategic competency for organizations found that the major top factors causing completion in ensuring that a project meets its goals, time line and delay and cost overrun in infrastructure projects in Jordan budget. However, there still exist some limits in are the terrain and weather condition. Therefore, a accomplishing the project deadlines and actual outcomes. suitable tool is needed to minimize delays and improving Sudden unexpected changes in construction technology, project delivery processes. However, to ensure suitability techniques, materials, or human resources can create stiff and applicability and thus, the success of lean tools budgetary and scheduling pressures which may increase implementation, there is a need for identification and the possibility of project failure [1]. appropriate prioritization of the lean tools [8]. The problem of delays in the construction industry is In the project planning, techniques are adopted to a global phenomenon [2]. In Saudi Arabia, Assaf and satisfy these necessities [9] whilst the techniques that are Al-Hejji [3] found that only 30% of construction projects used to schedule a project will be different according to were completed within the scheduled completion dates. In the characteristics of the project;duration, size, complexity Nigeria, Odeyinka and Yusif [4] have shown that seven and stakeholder s needs [10]. There are few techniques out of ten projects suffered delays in their execution. that have been applied known as Work Breakdown In Malaysia, about 17.3% were considered sick (more than Structure (WBS), Gantt chart, Critical Path Method (CPM) 3 months of delay or abandoned) [2]. Arditi et al. [5] and Project Evaluation and Review Techniques (PERT). showed that the major contribution on delaying in CPM and PERT are among the conventional planning construction is the effect of organizational culture. and scheduling techniques that are widely used in the Corresponding Author: Aznida Hayati Zakaria, Faculty of Informatics and Computing, Universiti Sultan Zainal Abidin, Besut Campus, 22200, Terengganu, Malaysia. 1180

construction, IT, manufacturing and defence Earliest Start (ES) Time = the maximum of the earliest finish organizations [9]. They can be applied to solve many times of all activities immediately preceding activity i. problems in project management and can be used in the (This is 0 for an activity with no predecessors). programming of large-scale projects. Thus, this paper focuses on the construction parking Earliest Finish (EF) Time = (ES Time) + (Time to complete project which aims to identify the critical path using activity i). CPM/PERT. The rest of this paper is organized as follows; Next section discusses on the literature review of where the project completion time is the maximum of the CPM/PERT. Then follows by the construction of EF Times and the Finish node. CPM/PERT based on the real case of parkingto demonstrate the feasibility and applicability of the Phase 2: Latest Start (LS) and Latest Finish [12] Times: proposed method. The last section concludes this paper. Make a backwards pass through the network as follows: Move sequentially backwards from the Finish node to the Literature Review: This section is divided into two Start node. At a given node, j, consider all activities subsections. Subsection CPM/PERT focuses on the ending at node j. For each of these activities, i, compute: CPM/PERT method and the next subsection, reviews on the construction project using CPM/PERT. Latest Finish [12] Time = the minimum of the latest start times beginning at node j. (For node N, this is the project CPM/PERT: Critical Path Method (CPM) was completion time). developed by Du Pont and Remington Rand in the late 1950s for industrial projects (chemical plant shutdown) Latest Start (LS) Time = (LF Time) (Time to complete [11]. Project Evaluation and Review Techniques (PERT) activity i). was developed by U.S. Navy for Polaris missile project in the year 1958 to handle uncertain activity times. Phase 3: Determining the Critical Path: Calculate the Nowadays, CPM and PERT have been used to plan, slack time for each activity by: schedule and control a wide variety of projects such as research and development of new products and Slack = (LS) (ES), or processes, construction of buildings and highways, = [12] (EF) maintenance of large and complex equipment, design and installation of new systems and many more. In project where a critical path is a path of activities, from Start node scheduling, projects may have as many as several to the Finish node, with 0 slack times. thousand activities. A complicating factor in carrying out the activities is that some activities depend on the The Uncertain Activity Times: Besides the three steps, completion of other activities before they can be started. the uncertain activity times are also a main keys in the CPM/PERT assists the project managers in the CPM/PERT methodology. In the three-time estimate following aspects: 1. The total time to complete a approach, the time to complete an activity is assumed to project. 2. The start and finish dates for each specific follow a Beta distribution. activity. 3. The critical activity that must be completed as scheduled. 4. The duration of noncritical activities that An activity s mean completion time is: t = (a+4m+b)/6 can be delayed to avoid exceeding time in project 2 2 An activity s completion time variance is: = ((b-a)/6) completion. Thus all these aspects can be depicted in the form of networks diagram to help a manager to have a where a is the optimistic completion time estimate, b is the better view in project implementation. Additionally, critical pessimistic completion time estimate and m is the most path can be determined on the network by identifying the likely completion time estimate activity with zero slacks. The process in CPM/PERT can be described by the Phase 4: Determining the PERT/ Cost: PERT/ Cost is a following phases: technique for monitoring cost during a project. Work packages (groups of related activities) with estimated Phase 1: Earliest Start and Finish Times: Make a budgets and completion times are evaluated. A cost forward pass through the network as follows: For each status report may be calculated by determining the cost activity i beginning at the Start node, compute: overrun or underrun for each work package. Cost overrun 1181

or underrun is calculated by subtracting the budgeted cost from the actual cost of the work package. For work in progress, overrun or underrun may be determined by subtracting the prorated budget cost from the actual cost to date. Thus, the whole phases of PERT/CPM method can be summarized as follows: Break project into operations necessary for completion Determining sequential relationship of operations Event to mark commencement Overlapping possibility Phase 1 Creating time estimates for each operation Determining earliest possible start date and earliest possible finish date Phase 2 Determining LS date and LF date Phase 3 Determining the slack time for each activity Phase 4 Revised after completion of Phase 3 Establish time-cost relationship Establish scheduling variations Determine most favourable balance between time-cost Normal Start normal time, least cost All-Crash Start least time, higher cost Figure 1 Phases in CPM/PERT Figure 1 summarizesthe four main phases involved in CPM/PERT. Each phase produces output that can be used in project planning. As illustrated, this technique complies the work done towards the completion of a project. The start and finish dates andtheactivities involve represented as grid visual information. The duration of activity in deterministic method such ascpm is assumed to be constant [13]. This paper will only focuses on Phase 1, Phase 2 and certain activity times in Phase 3 to manage the scheduling of the parking project. The previous studies on the methodology of CPM/PERT are been discussed in the next subsection. Overview on Construction Project using CPM/PERT: CPM/PERT has been actively used in many area such of construction, IT, manufacturing and defence organizations [9]. For example, Lee et al. [14]constructed a Program Evaluation and Review Technique (PERT) to find the critical activities when constructing the plant and to calculate the total project cost and total duration time for the project under normal condition. Gladysz et al. [15]modified the PERT method with mixed linear programming to illustrate the construction project. Dolabi and Abbasnia [12] proposed a methodology of Heuristic Line of Balance (HLOB) from CPM/Line of Balance (LOB) for scheduling projects with serial activities. This proposed method was successfully tested on large-scale highway project. Boushaala [16] proposed a PERT/CPM and Petri Net (PNs) Tools for project scheduling. Aziz [10] developed Repetitive-Project Evaluation and Review Technique (RPERT), which is a simplified software and generated the expected project completion probability of a specified/ certain duration (contract duration). Thus this paper proposed a CPM/PERT method for a real case of parking project. Calculation for Certain Activity Times in Construction Parking Project: In this research, we have chosen randomly a contractor among the small and medium enterprise (SME) contractors who involved in the construction of parking lots at University Sultan Zainal Abidin (UniSZA), Besut Campus. Specifically, this parking project is developed at students hostel. Once the contractor has been awarded a tender to develop the project, he has to fulfil the predefined requirements. The contractor needs to submit a project scheduling and planning to the committee. It is important that the project must be completed on time otherwise the contractor will face penalty. Therefore, the contractor needs to comply with the scheduling activities. For that reason, CPM/PERT 1182

is highly recommended to assist the contractor and the stakeholders to have a clear picture of a timeline on each activities. CPM/ PERT analysis have the capability to be adopted in a scheduling system which involves the activities of the project, times and critical paths. For example, in certain circumstances, contractors may face conflict decisions such as which parallel activities that need to be prioritized. Besides, another issue is the earliest time to start the prioritized activities. Generally, many SME contractors used their intuitions or discretion to plan and schedule the construction activities. However, one of the drawbacks of this traditional method is the susceptibility to errors. Therefore, we propose a practical approach to develop an application to assist SME contractor in scheduling their construction project activities. In this paper we test the feasibility of the CPM/PERT approach in scheduling the activities for parking lot construction. There are four (4) variables were used in this system, activities, start times, end times and the duration. The developed scheduling system provides a decision output based on the input criteria from the contractor. Each of the four parameters was assigned as shown in Table 1. Table 1: Time Estimation for Project A by ABC Enterprise Activity ES time EF time Duration A Formwork 0 5 5 B Reinforcing steel 0 6 6 C Cast in place concrete 5 9 4 D Brick Masonry 5 8 3 E Waterproofing 5 6 1 F Glazing 6 10 4 G Plastering and Pointing 10 24 14 H Cement Mortar Coating 9 21 12 Table 2: Activity Schedule for Project A Slack Time Critical Activity ES EF LS LF ( LS ES ) Path A 0 5 0 5 0 / B 0 6 6 12 6 C 5 9 8 12 3 D 5 8 7 10 2 E 5 6 5 6 0 / F 6 10 6 10 0 / G 10 24 10 24 0 / H 9 21 12 24 3 I 24 26 24 26 0 / Start A 0 5 5 0 5 E 5 6 1 5 6 F 6 10 4 6 10 A 0 5 5 0 5 B 0 6 6 6 12 C 5 9 4 8 12 D 5 8 3 7 10 Fig. 2: Project a Network Diagram Start B 0 6 6 6 12 E 5 6 1 5 6 F 6 10 4 6 10 C 5 9 4 8 12 D 5 8 3 7 10 H 9 21 12 12 24 G 10 24 14 10 24 H 9 21 12 12 24 G 10 24 14 10 24 I 24 26 2 24 26 Finish I 24 26 2 24 26 Finish Fig. 3: Network Diagram for Project A with Critical Path There are eight (8) activities stated by ABC Enterprise, starting from the Formwork until the Cement Mortar Coating. Each activity defines the earliest start (ES) time and earliest finish (EF) time. The duration of each activity is calculated based on the formula of EF-ES. Based on the information provided in Table 1, the network activities will be constructed which will include the activity, event and network itself. In order to determinethe critical path,the values of LS and LF must be determine prior to calculating the backward pass. The following Figure 2 presents the complete network diagram. The Slack Time and Critical Path will be calculated in order to find the best schedule time. Activity with zero (0) slack time is considered as the Critical Path. The following Table 2 indicates the resulted activities identified with critical path. Based on the Table 2, a complete network diagram is derived as in Figure 3. In Figure 3 the shaded box indicates critical path of the project where A E-F-G-I = 26 weeks. Based on the calculated critical path, the project completion time equals to the maximum of the activities earliest finish times. 1183

CONCLUSIONS 6. Niazi, G.A. and N. Painting, Significant factors causing cost overruns in the construction industry in In this paper, we have presented a method that Afghanistan. Procedia Engineering, 182: 510-517. combines CPM/PERT. CPM/PERT is an efficient method 7. Al-Hazim, N., Z.A. Salem and H. Ahmad, 2017. Delay to be used in scheduling the construction project and cost overrun in infrastructure projects in Jordan. planning as it helps in answering main questions such as Procedia Engineering, 182: 18-24. total time to complete the project, scheduled start and 8. Ansah, R.H. and S. Sorooshian, 2017. Effect of lean completion time for each activity, the activities are critical tools to control external environment risks of and the time taken for non-critical activities that can be construction projects. Sustainable Cities and Society, delayed during the project execution. In this project, an 32: 348-356. expert was interviewed and nine activities starting from 9. Mazlum, M. and A.F. Güneri, 2015. CPM, PERT and Formwork activity until Cement Mortar Coating had been Project Management with Fuzzy Logic Technique identified. In addition, this project calculated the Slack and Implementation on a Business. Procedia-Social Time and Critical Path. In future, a software tool can be and Behavioral Sciences, 210: 348-357. developed to assist SME contractors in scheduling their 10. Aziz, R.F., 2014. RPERT: Repetitive-projects construction project activities. evaluation and review technique. Alexandria Engineering Journal, 53(1): 81-93. REFERENCES 11. Acuña, R., 2010. Analysis of Project Planning Using CPM and PERT. Partial Fulfillment of Math, 1. Zeng, J., M. An and N.J. Smith, Application of a fuzzy 12. Dolabi, H.R.Z., A. Afshar and R. Abbasnia, 2014. based decision making methodology to construction CPM/LOB scheduling method for project deadline project risk assessment. International Journal of constraint satisfaction. Automation in Construction, Project Management, 25(6): 589-600. 48: 107-118. 2. Sambasivan, M. and Y.W. Soon, Causes and effects 13. De Meyer, A., C.H. Loch and M.T. Pich, 2002. of delays in Malaysian construction industry. A framework for project management under International Journal of Project Management, uncertainty. Sloan Management Review, 43(2): 60-67. 25(5): 517-526. 14. Lee, A.H., H.Y. Kang and T.T. Huang, 2017. Project 3. Assaf, S.A. and S. Al-Hejji, Causes of delay in large Management Model for Constructing a Renewable construction projects. International journal of project Energy Plant. Procedia Engineering, 174: 145-154. management, 24(4): 349-357. 15. Gladysz, B., et al., 2015. Project risk time 4. Odeyinka, H.A. and A. Yusif, The causes and effects management a proposed model and a case study in of construction delays on completion cost of the construction industry. Procedia Computer housing projects in Nigeria. Journal of Financial Science, 64: 24-31. Management of Property and Construction, 2: 31-44. 16. Boushaala, A., 2014. An approach for project 5. Arditi, D., D.E. Lee and G. Polat, Fatal accidents in scheduling using PERT/CPM and Petri Nets (PNs) nighttime vs. daytime highway construction work Tools. Industrial engineering and operations zones. Journal of Safety Research, 38(4): 399-405. management, 5(85): 939-947. 1184