STARVED ACID LEACH TECHNOLOGY (SALT) CONCEPTUAL STUDY. InCoR Holdings Plc MINING AND METALLURGY. April 2014 REPORT Rev. 00 > Internal ref.

Similar documents
THE STARVED ACID LEACHING TECHNOLOGY (SALT) FOR NI/CO RECOVERY FROM LEAN ORES AND RESIDUES ABSTRACT

For personal use only

Direct Nickel Process Breakthrough Technology. May 2015

Direct Nickel Process Breakthrough Technology

BRIEFING PAPER BHP BILLITON

AN EFFICIENT APPROACH TO COBALT, COPPER AND NICKEL RECOVERY FROM RAFFINATES, EVAPORATION PONDS, AND OTHER LOW GRADE STREAMS

Mintek 75. Using Computing Power in Process Development. Mike Dry

Two-stage precipitation process of iron and arsenic from acid leaching solutions

Teck's CESL Nickel Process: Advancing Towards a Commercial Ready Hydromet Solution for Low Grade Disseminated Nickel Sulphides

For personal use only

NICKEL AND COBALT RECOVERY FROM MESABA CONCENTRATE

Versatic 10 Acid/NICKSYN Synergistic System versus D2EPHA- Cyanex 272 for the Recovery of Cobalt from Typical DRC/Zambian Copper-Cobalt Leach Liquors

TVI Pacific Inc. Announces First Nickel Production from Pilot Plant

N E W S R E L E A S E

ENGINEERING SERVICES

Kalgoorlie Nickel Project 20ktpa Scoping Study Results Confirms Potential for Robust Long Life Project

EURARE Kvanefjeld Refinery Demo Plant Work Package 5

EXCELLENT NICKEL LEACHING TESTWORK RESULTS

THE CESL PROCESS: SUCCESSFUL REFINING OF A COMPLEX COPPER SULPHIDE CONCENTRATE

Hydromet Development and Commercial Nickel Processing Plant Update

For personal use only

Metallurgical Testwork Capability Statement

New Caledonian Nickel Conference

Syerston Nickel & Cobalt Pre-Feasibility Study Completed. Scandium by-product credits provide potential for significant economic upside

First Chalcopyrite Copper Concentrate Leaching using Albion Process TM Technology. Glenn Stieper

NICKEL AND COBALT RECOVERY FROM A BULK COPPER-NICKEL CONCENTRATE USING THE CESL PROCESS

Resource Efficient Mining Processes of Tomorrow

IRON-NICKEL SCOPING STUDY COMMENCES ON KALGOORLIE NICKEL PROJECT

CAPITAL DOWN AT TALA HAMZA

INSG Environmental & Economics Session. Bruce Wedderburn. 27 th April 2010

For personal use only

For personal use only

contents The Murrin Murrin nickelcobalt project area is located between Leonora and Laverton in the North Eastern Goldfields of Western Australia

Feasibility studies Ulaanbaatar August 2016

NOLANS REVIEW COMPLETED DELIVERING SIGNIFICANT COST AND OPERATIONAL BENEFITS

THE USE OF SELECTIVE ION EXCHANGE FOR THE RECOVERY OF BASE METALS FROM EFFLUENT STREAMS

CAPITAL COST ESTIMATE

PILOT PLANT PRODUCTION OF FERRONICKEL FROM NICKEL OXIDE ORES AND DUSTS IN A DC ARC FURNACE. Abstract

Owendale pilot plant program completed successfully

Implementing Fieldbus Technology on the Ravensthorpe Nickel Project

KATANGA MINING PROVIDES UPDATE ON MAJOR PROJECTS, ANNOUNCES 2018 FOURTH QUARTER AND YEAR END PRODUCTION RESULTS

NOLANS RARE EARTHS PROJECT: MAIDEN JORC ORE RESERVE

Industrial Solutions

FLOWSHEET CONSIDERATIONS FOR COPPER-COBALT PROJECTS

RESEARCH NEEDS IN MINERAL PROCESSING AND HYDROMETALLURGY. Geoff Senior

Outotec Hydrometallurgical Nickel Plants and Processes

For personal use only. 3 rd Annual PNG Mining & Logistics Conference 25 June 2013

Modelling of Nickel Laterite Smelting to Ferronickel

Minco Plc Woodstock Manganese Property

Kanowna Belle Pre-Oxidation Project

WA s MT THIRSTY COBALT-NICKEL PROJECT POTENTIALLY WORLD S FOURTH LARGEST COBALT PRODUCER

RE: REVIEW OF THE PRAIRIE CREEK MINE SCOPING STUDY

RAW MATERIALS AND IRONMAKING. Raw materials improvement in the steel industry

THE APPLICATION OF THE CESL NICKEL PROCESS TO LATERITES

Hard Creek Nickel. Emerging Giant Turnagain Nickel Project. Ed Beswick P Eng. HNC:TSX

23 September 2010 CHL: AIM. Churchill Mining PLC

RESOURCE GOLD PTY. LTD.

CONTENTS THE MURRIN MURRIN NICKEL- COBALT PROJECT AREA IS LOCATED BETWEEN LEONORA AND LAVERTON IN THE NORTH EASTERN GOLDFIELDS OF WESTERN AUSTRALIA

Nickel Asia Corporation

MOUNT MORGAN SCOPING STUDY CONFIRMS POTENTIAL FOR A LOW COST LONG LIFE OPERATION

COPPER PRECIPITATION AND CYANIDE RECOVERY PILOT TESTING FOR THE NEWMONT YANACOCHA PROJECT

For personal use only

Unlocking Disseminated Nickel Sulphides Using the CESL Nickel Process

The Albion Process at the GPM Gold Project The success of a technology

Direct reduction of low grade nickel laterite ore to produce ferronickel using isothermal temperature gradient

19 th Zinc and its Markets Seminar May 4 th 6 th, 2015 Radisson Blu Royal Hotel, Helsinki, Finland. Welcome address. Robin Lindahl

MARILLANA MAIDEN HEMATITE ORE RESERVE OF 1.05 BILLION TONNES

INTEC ZINC TECHNOLOGY

For personal use only

PILOT TEST WORK TRIGGERS FINAL TRANCHE OF TREMONT FINANCING

The Australian treatment

Minara Resources Limited Investor Relations Presentation October Peter Johnston Managing Director and CEO

Your iron ore beneficiation solutions

MINIMUM ENGINEERING STUDY REQUIREMENT. 128 June 2015

March 2015 Quarterly Report

JUNE 2018 QUARTERLY ACTIVITIES REPORT

WATER AND CARBONATE BALANCES IN AN ALKALINE URANIUM EXTRACTION CIRCUIT

For personal use only

REGUIBAT URANIUM PROJECT SCOPING STUDY COMPLETE

Company Introduction. Management Team & Experience. Company

Integrated Pollution Prevention and Control (IPPC) Reference Document on Best Available Techniques in the Cement and Lime Manufacturing Industries

FOR IMMEDIATE RELEASE 30 August 2018 TSX-V: AZR

RENISON TAILINGS RETREATMENT PROJECT ( RENTAILS ) UPDATED DFS CONFIRMS HIGH MARGIN PROJECT

ArcelorMittal, Canada

SOLVENT EXTRACTION PROCESS DEVELOPMENT AT GIRILAMBONE COPPER COMPANY - PREDICTED vs PLANT PRACTICE

AMUR MINERALS CORPORATION (AIM: AMC)

For personal use only

PILOT PLANT CAMPAIGN CONFIRMS PRODUCTION OF COMMERCIAL GRADE FERRONICKEL AT ARAGUAIA PROJECT, BRAZIL

CIM Best Practice Guidelines for Mineral Processing

For personal use only

Solvent Extraction versus Nano-Filtration for Upgrading Uranium and Recovery of Acid from an Ion Exchange Eluate

Northern Iron. Investor Update March 2010

DEVELOPMENT OF THE KOLWEZI TAILINGS COPPER/COBALT FLOWSHEET

Ban Houayxai Project Approved operation to produce over 100,000 ounces of gold and 700,000 ounces of silver per annum

For personal use only

A CASE STUDY ON THE OPERATION OF A FLOTTWEG TRICANTER CENTRIFUGE FOR SOLVENT-EXTRACTION CRUD TREATMENT AT BWANA MKUBWA, NDOLA, ZAMBIA

Aeon Metals Limited HIGHLIGHTS

Duluth Metals Provides Metallurgical Update on Twin Metals Minnesota Project

Mt Thirsty Cobalt Project - Scoping Study

The Los Bronces Development Project Brian Beamish CEO Anglo Base Metals 28th November 2007

Transcription:

STARVED ACID LEACH TECHNOLOGY (SALT) CONCEPTUAL STUDY InCoR Holdings Plc MINING AND METALLURGY April 2014 REPORT Rev. 00 > Internal ref. 140226

Document Number: 140226-0000-49ER-0001 Date: 28/04/2014 Revision: 00 Page: 7 of 208 1 EXECUTIVE SUMMARY InCoR Holdings Plc (InCoR) is currently investigating the potential of their proprietary SALT (Starved Acid Leach Technology) process to leach the low-grade saprolite ore. InCoR commissioned SNC-Lavalin to develop conceptual level engineering design and cost evaluation of the SALT process plant and supporting infrastructure aimed at producing a Mixed Hydroxide Product (MHP) for feed to the nearby PT Antam Ferronickel Smelter in Pomalaa, Indonesia. A result summary of the current study is presented in Table 1.1. Table 1.1 General Summary of Project Cost and Key Data Item Value Ore Throughput to SALT, million dry tpa 2.0 MHP Produced, wet tpa 117 000 Contained Nickel, tpa 15 000 Project Operating Cost Million US$ per annum 119 US$/lb of nickel produced 3.60 Project Capital Cost Million US$ 282 US$/lb annual nickel capacity 8.60 The current study was conducted to prepare order of magnitude capital and operating cost estimates for the project and identify key business drivers. 1.1 SCOPE OF WORK The study investigates the installation of a 2 million dry tpa processing plant producing approximately 15 000 tpa of contained nickel in MHP. The overall plant includes a processing plant incorporating InCoR s SALT process with supporting services and infrastructures such as Residue Storage Facility (RSF). 1.2 METALLURGICAL DEVELOPMENT Initial bench-scale testwork indicated 50 60% nickel extractions from Pomalaa lowgrade saprolite sample utilising the SALT process leach while restricting the total iron extraction to near 10% for an acid addition of 350 kg acid per dry tonne of ore feed. An integrated plant testwork program is recommended to obtain plant parameters required to design a full SALT plant. The testwork program should include ore preparation, settling tests of both milled ore and leached residue, mixed hydroxide precipitation and tails neutralisation.

Document Number: 140226-0000-49ER-0001 Date: 28/04/2014 Revision: 00 Page: 8 of 208 1.3 CONCEPTUAL ENGINEERING The conceptual engineering of the SALT plant is based on a process mass balance which has been developed from process design criteria and the overall process diagram (Figure 1.2). A plant availability of 70% (6 132 hours/year) has been applied for the Ore Preparation circuit and 93% (8 163 hours/year) for the rest of the plant including services and utilities. Based on projected ramp-up and an analysis of similar projects in complexity, a threeyear plant ramp-up has been applied. The key process data and assumptions are shown in Table 1.2. Item Table 1.2 Key Process Data and Assumptions Value Plant Life, years 20 Ore Throughput to SALT, million dry tpa 2.0 Ore Feed Ni, dry w/w% 1.33 Fe, dry w/w% 8.1 Mg, dry w/w% 17.2 SALT Extraction Ni, % 57.9 Fe, % 10 Mg, % 46.5 SALT Acid Demand, kg/t ore feed 350 MHP Product Analysis Ni, dry w/w% 28.2 Total S, dry w/w% 4.93 Moisture, % 55 MHP, wet tpa 117 000 Contained Ni, tpa 15 000 Overall Plant Recovery Ni, % ~55

Document Number: 140226-0000-49ER-0001 Date: 28/04/2014 Revision: 00 Page: 9 of 208 1.4 PROCESS DESCRIPTION Refer to Figure 1.2 for the overall process flow illustration. The ore for leaching is crushed, milled and thickened to produce a high solids density saprolite ore slurry. In the SALT circuit, concentrated sulphuric acid (98.5%) is added to leach nickel from saprolite ore at atmospheric conditions. The acid addition is restricted to a minimum with the aim to recover the maximum amount of nickel while keeping the impurities extraction low. The leached slurry from the SALT process is neutralised with limestone to reduce the levels of free acid and impurities. This neutralised slurry is washed in a seven-stage counter-current decantation (CCD) circuit. The wash liquor is then neutralised with magnesia and lime to precipitate the nickel as an impure Mixed Hydroxide Precipitate (MHP). The MHP is filtered, washed and treated with soda ash solution to reduce impurities prior to being sent to the ferronickel smelter. The nickel barren solution is further neutralised with lime to reduce the manganese content to a suitable level for ocean outfall. This stream is mixed with the washed residue slurry and sent to the residue storage facility. The modular residue storage facility is developed in stages and includes provision for decant liquor return to the plant and to ocean outfall for disposal. Although the proposed site is within the complex of an existing ferronickel smelter, the SALT plant also requires some specific infrastructure and the upgrade of existing infrastructure to support the overall plant operation. These are identified as follows: Temporary construction facilities to accommodate the construction workforce. Site works for the process plant and other facilities. Berth and ship unloading facilities upgrade at the port for reagents such as limestone, MgO and coal. Process plant roads, haul roads, and upgrade of the existing roads. Utilities and services including water supply (630 m 3 /h), power supply (11.3 MW), waste treatment and disposal. Site and process buildings. Plant loading and unloading facilities for limestone, coal and ore stockpiles. Communication facilities to provide telecommunications and computer data. Residue Storage Facility to contain the treated plant residue. Mobile equipment

Document Number: 140226-0000-49ER-0001 Date: 28/04/2014 Revision: 00 Page: 10 of 208 Figure 1.2 SALT Process Plant Block Flow Diagram

Document Number: 140226-0000-49ER-0001 Date: 28/04/2014 Revision: 00 Page: 11 of 208 1.5 CAPITAL COST ESTIMATE The conceptual capital cost estimate for the project has been prepared in accordance with SNC-Lavalin estimating guidelines for a Class 5 estimate (order of magnitude estimate). The capital cost estimate has a +40% / -30% accuracy. The capital cost estimate is developed using the factored estimating technique. The summary of the SALT plant capital cost is presented in Table 1.3 in January 2014 United States dollar (US$) values. Table 1.3 Capital Cost Summary Area Description Cost, US$ Ore Preparation 20,400,000 Starved Acid Leach Technology (SALT) 5,740,000 Primary Neutralisation (PN) 1,810,000 Counter Current Decantation (CCD) 20,000,000 Mixed Hydroxide Precipitation (MHP) 9,470,000 Tailings Neutralisation Manganese Removal 1,260,000 Final Neutralisation 14,600,000 Tailings Disposal 7,260,000 Sulphuric Acid Storage and Supply 4,890,000 Other Reagents Preparation and Distribution 4,420,000 Lime Calcining and Slaking Plant 49,710,000 Water and Air Supply and Distribution 14,750,000 Piperacks 1,750,000 Residue Storage Facility (Phase 1) 28,580,000 Mobile Equipment 7,510,000 TOTAL DIRECT COST 192,100,000 EPCM 48,250,000 Other Indirects 2,980,000 Contingency 38,600,000 TOTAL INDIRECT COST 89,830,000 TOTAL PROJECT COST 282,000,000

Document Number: 140226-0000-49ER-0001 Date: 28/04/2014 Revision: 00 Page: 12 of 208 1.5.1 Scope of the Capital Estimate The scope of the current SALT Project direct costs estimate includes the direct cost for the process plant and supporting services, utilities and RSF cells. The indirect cost includes EPCM, capital and commissioning spares, vendor representatives and contingency. 1.5.2 Basis of the Capital Estimate Process plant estimates are developed from process plant equipment of similar sized nickel projects, and adjusted for flow or equipment capacity and currency movements. Bulk material costs have been factored based on the ex-works cost of mechanical equipment by facility. The capital costs relate to a project based in Indonesia. The cost for RSF is developed from preliminary material take off estimates, with costs based on a nickel project in Northern Philippines, where a similar RSF model is quoted. The indirect costs were prepared on the basis of a project management team being retained to perform the services of engineering, procurement of major equipment and management of construction. This is estimated as 25% of the project direct cost. A contingency of 20% has been applied to direct costs. The contingency reflects the state of development of the project, and allows a margin for changes to the process and equipment selection and sizing where specific design criteria are not yet available. 1.5.3 Exclusions A number of costs had been excluded from the capital cost estimate for the current conceptual study as follows: Owner s costs; Mining and ore delivery related capital costs ; Technology fees, permits and licenses; Off-site infrastructure (except RSF); Existing port upgrade. 1.6 OPERATING COST ESTIMATE The project operating cost has been developed for 20 years of plant operation based on the projected ramp-up. Year 3 is considered to represent the full nameplate production. The operating cost estimate has a +40% / -30% accuracy. Table 1.4 presents the summary of the project operating cost at Year 3 onwards in January 2014 US dollar (US$) values.

Document Number: 140226-0000-49ER-0001 Date: 28/04/2014 Revision: 00 Page: 13 of 208 Table 1.4 Operating Cost Summary (Year 3+) Cost, US$ US$/lb Ni Items Year 3+ Year 3+ Reagents and Consumables Sulphuric Acid, 98.5% 58,800,000 1.80 MgO 10,300,000 0.31 Limestone 6,950,000 0.21 Sub-bituminous Coal 4,850,000 0.15 Other Plant Reagents 2,320,000 0.07 Process Plant Consumables 2,720,000 0.08 Power Consumption 8,150,000 0.25 Utilities and Services Reagents & Consumables 1,300,000 0.04 Labour 4,240,000 0.13 General Expenses 5,000,000 0.15 Maintenance Materials 3,740,000 0.11 Contract Services 3,770,000 0.12 RSF Sustaining Capital 6,530,000 0.20 PROJECT OPERATING COST 119,000,000 3.62 1.6.1 Basis of the Operating Cost Estimate The operating cost estimates are based on the process design criteria, flowsheet and mass balance. Key inputs to operating cost are as follows: Manning levels are evaluated for each project area according to similar plant operation. Labour rates at different salary levels, including on-costs, are sourced from a database of Indonesian projects. Reagent and consumables quantities are based on the process mass balances and unit pricing is sourced from either budget pricing or from data for recent projects. The costs of maintenance consumables, which are replacement parts necessary to maintain equipment, are estimated using historical ratios for similar scale plants based on the installed equipment costs Contract expenses were estimated for a range of services provided to the project on a contract basis, including:, contract maintenance, periodic metallurgical testing and consultants fees in areas such as safety and training

Document Number: 140226-0000-49ER-0001 Date: 28/04/2014 Revision: 00 Page: 14 of 208 Administration and general expenses are estimated for a range of miscellaneous expenses associated with providing services to the project, including: safety equipment and training, medical costs, community relations, environmental costs, human relations costs, telecommunications costs, and business travel. The RSF sustaining capital of the project is the deferred cost of progressively building and decommissioning RSF cells 2-5 necessary to store the plant residue. The cost also includes the decommissioning of Phase 1. The total cost is annualised from Year 3 through to the life of the plant at Year 20. No contingency has been applied to the operating cost estimate as it is assumed that inputs to the operating costs have been comprehensively covered. 1.6.2 Exclusions The exclusions to the operating cost are: Mining and ore delivery; Replacement cost (e.g. mobile equipment); Some government charges; Royalties Marketing costs; Duties, customs and other imposts. 1.7 TECHNICAL DISCUSSION 1.7.1 Technical Drivers The following are key technical drivers that have been identified for the success of the SALT Project. Acid Consumption at 350 kg/t demand, it contributes to about 50% of the operating cost and is consumed by the MgO uptake. The current evaluation is based on 13-20% Mg content in the ore, but will require further testwork to evaluate the capacity of SALT to treat different ore profiles. Solids Settling Properties Good settling properties produce higher U/F solids in thickeners, which is required to optimise the downstream processing equipment. Lower solids concentration and poor settling conditions will result in bigger ore and CCD thickener requirements and larger RSF surface area, which increases the capital cost. Nickel Recovery Higher nickel recovery would mean lower ore throughput, smaller plant equipment and thus lower capital cost. Ocean Outfall Limits - The manganese concentration limitation on outfall composition drives the lime usage, requiring significant additional capital and/or operating costs.

Document Number: 140226-0000-49ER-0001 Date: 28/04/2014 Revision: 00 Page: 15 of 208 1.7.2 Risk and Opportunities Product Quality Several ferronickel plants which trialled MHP feed highlighted the following product quality issues as: o Sulphur content is recommended to be limited to <1% as it adds to the total SO x emission of the plant. o Low nickel and high impurity content will potentially displace high grade saprolite feed. o There is no cobalt credit gained from MHP as it is an impurity in ferronickel. Project Scale Bigger scale favours a more economical project due to the high cost of off-site infrastructure requirement such as RSF and port. Project Location and RSF Area Previous studies on Pomalaa had highlighted the limited availability of area for large surface area RSF cells. Project location should be within the proximity of the port, RSF and existing infrastructure to minimise cost and logistics. Size and Location of Resources Due to lack of information, it is assumed that there is sufficient resource to feed the SALT plant for 20 years. Ore Beneficiation Rejecting larger size fractions to increase the ore feed grade and thus reduce downstream equipment size. Mn Limits on Ocean Outfall Determining the likely environmental constraints to provide possibly a lower lime requirement reducing the capital and/or operating costs. Alternative Liquor Disposal Examine alternative to ocean outfall to improve the water balance and lime requirement of the tailings neutralisation. High Mg Leaching An option to reduce the amount of liquor to be disposed of by recycling it to ore preparation, while also possibly providing leach advantages. Sulphuric Acid The volatility of sulphuric acid price and unstable long term supply will expose the project to a significant commercial risk. Opportunities are identified in the current study to mitigate this risk: o o o Locally sourced sulphuric acid securing a long term contract with locally sourced sulphuric acid from major operating and/or emerging copper concentrators in the country. Acid pipeline from the port acid transport via overland piping to minimise the cost of acid transport and risk of handling. Acid plant installation consideration to install a Chinese acid plant (with integrated power and demineralised water plant) utilising Western technology license. Cost reductions of up to 50% have been quoted and the waste heat can be converted to supply the power for the plant. Limestone The cost of limestone represents around 6% of the overall project cost which is based on crushed imported supply. Locally sourced limestone within the area can potentially reduced the overall cost.

Document Number: 140226-0000-49ER-0001 Date: 28/04/2014 Revision: 00 Page: 16 of 208 MgO The cost of magnesia represents around 9% of the overall project cost which is based on the highest reactive product. Potentially cheaper and lower chemical grade MgO sources should be tested to determine if operating cost reductions are possible. Power supply Power contributes to about 7% of the project operating cost based on national grid supply. The lack of major power grid infrastructures in Sulawesi Island and current national power crisis can prove risky for the project. The following options are suggested to address this issue: o Enter a negotiation to purchase power from PT Antam which has an existing 102 MW and is currently constructing 2 x 30 MW coal-fired power plants in Pomalaa. o Power to be provided from the sulphuric acid plant waste heat conversion. Preliminary calculations estimated a surplus of 13 MW (net of the steam and power required for the process plant and sulphuric acid/power plant), which can be sold to the grid and potentially improve the project operating costs. Opportunities for Cost Reductions such as optimisation of CCD washing stages and use of cheaper type of kiln and slaker for the lime plant. Port Upgrade a major infrastructure requirement of the project. Bathymetric data and a berthing schedule are required in order to evaluate the extent of port upgrade cost. 1.7.3 Recommendations The preliminary engineering evaluation of SALT suggests that the technology has the potential to process low-grade saprolite ore. The overall operation incorporates simple and proven atmospheric leaching and precipitation processes. This will enable the plant to have fast ramp-up and achieve high availabilities. The order of magnitude project costs of $282 million capital cost and $3.60 /lb nickel produced indicate that the SALT process has potential to be economically attractive in comparison to other nickel laterite processes such as PAL and AL. Numerous risks and opportunities were identified that should be pursued in future work to mitigate risk and maximise returns. These were summarised into seven major recommendations; 1. Testing of the integrated plant and investigation of the flowsheet modification opportunities. 2. Trade-off study for sulphuric acid and power sources for optimum project costing. 3. Locating and testing lower cost limestone sources. 4. Locating and testing lower cost MgO sources. 5. Determination of ore resource available.

Document Number: 140226-0000-49ER-0001 Date: 28/04/2014 Revision: 00 Page: 17 of 208 6. Full assessment of the infrastructure required for the project for a complete assessment of the capital cost. 7. Assessment of environmental and community requirements.