15A NCAC 07H.0209 COASTAL SHORELINES (a) Description. The Coastal Shorelines category includes estuarine shorelines and public trust shorelines.

PUBLIC NOTICE. Section 404 of the Clean Water Act (33 U.S.C. 1344) Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C.

PUBLIC NOTICE. Section 404 of the Clean Water Act (33 U.S.C. 1344) Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C.

NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT

VEGETATIVE, WATER, FISH AND WILDLIFE RESOURCES POLICIES

J O I N T P U B L I C N O T I C E

PUBLIC NOTICE. US Army Corps Of Engineers Wilmington District

PUBLIC NOTICE. Section 404 of the Clean Water Act (33 U.S.C. 1344) Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C.

Ohio Power Siting Board. Staff Investigation Report and Recommendation

15A NCAC 07H.0308 SPECIFIC USE STANDARDS FOR OCEAN HAZARD AREAS (a) Ocean Shoreline Erosion Control Activities: (1) Use Standards Applicable to all

Environmental Check List Georgia Environmental Policy Act

ENVIRONMENTAL ASSESSMENT

PUBLIC NOTICE. HDC-Wendover-Greensboro Partners, LP Mr. Key Kasravi Kingsride Lane, Suite 280 Houston, Texas 77024

PUBLIC NOTICE. Mr. Jon Morris Beacon Partners, Inc 610 East Morehead Street Charlotte, North Carolina 28202

ATTACHMENT 1 GEPA CHECKLIST & Historical Archeological & Natural Heritage Preservation Documents

1.0 INTRODUCTION 1.1 SUMMARY OF SEQRA PROCESS

Public Notice ISSUED: July 13, 2018 EXPIRES: August 13, 2018

Public Notice ISSUED: December 11, 2018 EXPIRES: January 10, 2019

Public Notice ISSUED: April 5, 2019 EXPIRES: May 6, 2019

VILLAGE OF BALD HEAD ISLAND SHORELINE PROTECTION PROJECT DRAFT ENVIRONMENTAL IMPACT STATEMENT

APPENDIX N Guidance for Preparing/Reviewing CEQA Initial Studies and Environmental Impact Reports

3.0 UNAVOIDABLE ADVERSE IMPACTS. 3.1 General Mitigation Measures

List of Figures... xii. List of Tables... xiii. List of Appendices...xv. Glossary... xvii Project Summary and Facility Overview...

PUBLIC NOTICE. Section 404 of the Clean Water Act (33 U.S.C. 1344) Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C.

SUBCHAPTER 7K - ACTIVITIES IN AREAS OF ENVIRONMENTAL CONCERN WHICH DO NOT REQUIRE A COASTAL AREA MANAGEMENT ACT PERMIT

Public Notice U.S. Army Corps In Reply to Application Number of Engineers

J O I N T P U B L I C N O T I C E

Department of the Army Permit Application

BEFORE THE OHIO POWER SITING BOARD

NC DEQ Division of Energy, Mineral and Land Resources STATE STORMWATER FAST TRACK AUTHORIZATION TO CONSTRUCT PERMIT APPLICATION INSTRUCTIONS

ORD WHEREAS, the public necessity, convenience, general welfare and good zoning practice so require;

SUBCHAPTER 7B CAMA STATE GUIDELINES FOR LAND USE PLANNING. 15A NCAC 07B.0601 is amended with changes as published in 30:06 NCR 620 as follows:

J O I N T P U B L I C N O T I C E

DEPARTMENT OF THE ARMY U.S. ARMY CORPS OF ENGINEERS - MOBILE DISTRICT BIRMINGHAM FIELD OFFICE 218 SUMMIT PARKWAY, SUITE 222 HOMEWOOD, AL 35209

JOINT PUBLIC NOTICE U.S. ARMY CORPS OF ENGINEERS MISSISSIPPI DEPARTMENT OF ENVIRONMENTAL QUALITY OFFICE OF POLLUTION CONTROL

P U B L I C N O T I C E. CHARLESTON DISTRICT, CORPS OF ENGINEERS 69A Hagood Avenue Charleston, South Carolina

PUBLIC NOTICE NO. FP13-AB03-05 August 30, 2013 CESAM-PD-EC JOINT PUBLIC NOTICE

THIS IS NOT A PAID ADVERTISEMENT. Public Notice. Public Notice No. CENAP-OP-R February 13, 2019

PUBLIC NOTICE.

CESAM-RD-N January 10, 2018 PUBLIC NOTICE NO. SAM CMS

Public Notice. Permit Application No.: SWF Date: December 20, 2012

PA Fish and Boat Commission No Known Impact No Further Review Required U.S. Fish and Wildlife Service No Known Impact No Further Review Required

APPENDIX H Guidance for Preparing/Reviewing CEQA Initial Studies and Environmental Impact Reports

NC Division of Coastal Management

THIS IS NOT A PAID ADVERTISEMENT. Public Notice. Public Notice No. CENAP-OP-R September 7, 2017

PUBLIC NOTICE. Attn: Mr. Bill Mumford 1312 Briar Chapel Parkway Chapel Hill, NC 27516

9 OTHER CONSIDERATIONS REQUIRED BY NEPA

New Jersey Statewide Stormwater, Flood Hazard and Wetlands Programs

Public Notice. Applicant: Lennar Homes Project No.: SWF Date: October 29, Name: Mr. Darvin Messer Phone Number:

Public Notice. Applicant: TXI Operating, LP Project No.: SWF Date: April 2, Name: Mr. Darvin Messer Phone Number:

15A NCAC 02B.0238 NEUSE RIVER BASIN-NUTRIENT SENSITIVE WATERS MANAGEMENT STRATEGY: AGRICULTURAL NITROGEN REDUCTION STRATEGY The following

APPLICANT: Decatur Head Beach Association 1327 Decatur Head Drive Decatur Island Anacortes, WA Telephone: (425)

PUBLIC NOTICE. Dredge, with 10-years maintenance, and placement of sand on an adjacent beach

Project Information. Pursuant to Section 404 of the Clean Water Act (33 U.S. Code 1344), notice is hereby given that

DEPARTMENT OF THE ARMY U.S. ARMY CORPS OF ENGINEERS MOBILE DISTRICT MONTGOMERY FIELD OFFICE 105 SOUTH TURNER BOULEVARD MONTGOMERY, ALABAMA 36114

CESAM-RD-N May 29, 2014 PUBLIC NOTICE NO. SAM JSC

Public Notice ISSUED: April 12, 2019 EXPIRES: May 13, 2019

Notice of Availability (NOA) of the Draft Environmental Impact Statement. (DEIS) and the Announcement of a Public Hearing for the Installation of a

Avian and Bat Studies Summary Presentation

Albemarle Resource Conservation and Development Council. Examples of Projects in Land and Water Conservation

Project Information. Pursuant to Section 404 of the Clean Water Act (33 U.S. Code 1344), notice is hereby given that

County of San Mateo Planning and Building Department

DEPARTMENT OF THE ARMY CORPS OF ENGINEERS, MOBILE DISTRICT P.O. BOX 2288 MOBILE, AL

EXECUTIVE SUMMARY. Supplemental Environmental Impact Statement Jericho Rise Wind Farm

PERMIT APPLICATION FEES Fees must be paid at time of application

Pteragen Canada Inc.

APPENDIX M CEQA Initial Study Checklist

Shrewsbury River Basin, Sea Bright, New Jersey Coastal Storm Risk Management Feasibility Study

Atlantic Coast of NY, East Rockaway Inlet to Rockaway Inlet and Jamaica Bay APPENDIX N COASTAL ZONE MANAGEMENT

PA Game Commission No Known Impact No Further Review Required

CESAM-RD-M March 16, 2018 PUBLIC NOTICE NO. SAM RCV JOINT PUBLIC NOTICE U.S. ARMY CORPS OF ENGINEERS

14. Sustainable Forestry Principals

Public Notice U.S. ARMY CORPS OF ENGINEERS, GALVESTON DISTRICT

CATEGORY a protection of the natural environment, its ecosystems and biodiversity.

Natural & Cultural Resources

CESAM-RD-N January 21, 2016 PUBLIC NOTICE NO. SAM JSC

Public Notice ISSUED: March 18, 2016 EXPIRES: April 18, 2016

SECONDARY WETLAND IMPACTS ANALYSIS

CESAM-RD- N April 2, 2013 PUBLIC NOTICE NO. SAM CHE

Public Notice No Metropolitan Avenue Charlotte, North Carolina 27204

DEPARTMENT OF THE ARMY CORPS OF ENGINEERS, MOBILE DISTRICT P.O. BOX 2288 MOBILE, ALABAMA CESAM-RD-A-S August 21, 2018

PUBLIC NOTICE. Specific plans are shown at the following website:

City of Bishop. Environmental Checklist Form

DEPARTMENT OF THE ARMY CORPS OF ENGINEERS, MOBILE DISTRICT P.O. BOX 2288 MOBILE, AL

PUBLIC NOTICE. Village of Bald Head Island Mr. Chris McCall, Village Manager Post Office Box 3009 Bald Head Island, North Carolina

PUBLIC NOTICE. Attn: Mr. John Koenig 235 Green Street Fayetteville, North Carolina 28301

JOINT PUBLIC NOTICE August 4, 2014

Maryland s s Critical Area Program

U.S. Army Corps of Engineers, Alaska District PRECONSTRUCTION NOTIFICATION FORM

APPENDIX H: SFEIS FLOODPLAIN IMPACT ANALYSIS SECTION

THIS IS NOT A PAID ADVERTISEMENT. Public Notice. Public Notice No. CENAP-OP-R November 21, 2017

Issuing Office: CELRB-PM-EA Published: 22 FEB 2019 Notice No: SANDUSKY-19 Expires: 25 MAR 2019

DEPARTMENT OF THE ARMY U.S. ARMY ENGINEER DISTRICT, MOBILE DISTRICT CORPS OF ENGINEERS P.O. BOX 2288 MOBILE, ALABAMA

CESAM-RD- N April 2, 2013 PUBLIC NOTICE NO. SAM CHE

Bureau of Land Management. Public Scoping Meeting

Regulatory Programs Administered by Indiana DNR, Division of Water presented by George Bowman

J O I N T P U B L I C N O T I C E

Public Notice.

Applicant: Glenwood Springs, LLC Mr. Kevin Hochstedler. Joint Public Notice. Iowa Department of Natural Resources

Coastal Management ENVIRONMENTAL QUALITY

Transcription:

N.C. DIVISION OF COASTAL MANAGEMENT FEDERAL COASTAL ZONE MANAGEMENT ACT CONSISTENCY CERTIFICATION SUPPORTING DOCUMENTATION Desert Wind Project Pasquotank and Perquimans Counties, North Carolina Prepared for: Atlantic Wind, LLC c/o Iberdrola Renewables, Inc. 201 King of Prussia Road, Suite 500 Radnor, PA 19087 Prepared By: Kimley-Horn and Associates, Inc. Post Office Box 33068 Raleigh, NC 27636-3068 September 2011 Kimley-Horn and Associates, Inc. 2011

Contents 1.0 Project Background... 1 2.0 Project Description... 1 3.0 Existing Site Conditions... 2 4.0 Proposed Impacts... 3 5.0 Areas of Environmental Concern... 3 5.1 Estuarine and Ocean Systems (15A NCAC 07H.0200)... 4 5.1.1 Coastal Wetlands (15A NCAC 07H.0205)... 4 5.1.2 Estuarine Waters (15A NCAC 07H.0206)... 4 5.1.3 Public Trust Areas (15A NCAC 07H.0207)... 4 5.1.4 Coastal Shorelines (15A NCAC 07H.0209)... 5 5.2 Ocean Hazard Areas (15A NCAC 07H.0300)... 5 5.3 Public Water Supplies (15A NCAC 07H.0400)... 5 5.4 Natural and Cultural Resource Areas (15A NCAC 07H.0500)... 5 5.4.1 Coastal Areas that Sustain Remnant Species (15A NCAC 07H.0505)... 5 5.4.2 Coastal Complex Natural Areas (15A NCAC 07H.0506)... 6 5.4.3 Unique Coastal Geological Formations (15A NCAC 07H.0507)... 6 5.4.4 Significant Coastal Archaeological Resources (15A NCAC 07H.0509)... 7 5.4.5 Significant Coastal Historical Architectural Resources(15A NCAC 07H.0510) 7 5.5 Outstanding Resource Waters (15A NCAC 02B.0225)... 7 5.6 High Quality Waters (15A NCAC 02B.0224)... 8 5.7 Conclusion... 8 6.0 General Policy Guidelines... 8 6.1 Conclusion... 9 7.0 Land Use Plan Review... 9 7.1 Conclusion... 9 8.0 Other State Permits... 10 8.1 State Water Quality (401) Certification... 10 8.2 State Stormwater Permit... 10 8.3 Sedimentation and Erosion Control Permit... 10 8.4 North Carolina Utilities Commission Certificate... 10 8.5 Driveway Permit... 10 9.0 Project Consistency Conclusion... 10 Appendices Appendix A NCDCM and NCDWQ project review letters i

1.0 Project Background Atlantic Wind, LLC (Atlantic Wind) is proposing the development of the Desert Wind Power Project in Perquimans and Pasquotank Counties in eastern North Carolina, approximately 7.5 miles west of Elizabeth City and approximately 2.5 miles north of the Town of Winfall. The proposed project area has been situated on 24,242 acres of privately-owned land within Pasquotank and Perquimans counties in an area known locally as the Desert. The project area is located between Highway 158 to the north, Highway 17 to the east and south and County Road 1002 to the west. (See Figure 1-Vicinity Map in the Individual permit support document). For the purposes of this report, the following terminology is used to define the limits of the Desert Wind project. Project area Approximately 24,242 acres of privately owned land within Pasquotank and Perquimans counties in which Atlantic Wind, LLC has secured lease option agreements for the development of the Desert Wind project. Project corridor (Site) Approximately 2,513 acres of land located within the Project area where the specific project construction will occur. The Site consists primarily of agricultural fields (~ 71%) with areas of both jurisdictional and non-jurisdictional managed timberlands (~25%) and natural forested wetlands (~4%). While various technical studies referenced throughout this report were conducted for the larger Project area, the delineation of jurisdictional areas and the impact quantities presented as part of the Section 404/401 permit application are specifically for the Project corridor/site. The Site area was established based on the layout of the turbine locations, crane paths, access roads, transmission lines, and facilities. The corridor generally was defined by a 200-ft radius from each turbine location, 150-ft width for crane paths, 100-ft width for access roads, and 50-ft width for transmission lines. Permanent impacts to jurisdictional areas within the ~2,513 acre Site include 27.76 acres of managed jurisdictional timberlands and 1.47 acres of impact to hardwood flat wetlands. 2.0 Project Description The project will consist of 150 modern wind turbines, each with a projected capacity of 2.0 MW, for a total installed capacity of 300 MW. The construction-related facilities will consist of the following: 150/ 2.0 MW Gamesa G97 wind turbine generators on 90 meter towers; Permanent and temporary access roads to each turbine; Temporary crane paths; Underground and overhead 34.5 kilovolt ( kv ) electrical collector lines connecting the turbines to the Collection Substation; A 34.5 kv to 115 kv Collection Substation facility; 1

A 115 to 230 kv Transmission Voltage Step-up Substation facility (the Step-up Substation ); An approximately 5.5 mile long, 115 kv overhead Sub-Transmission Line connecting the Collection Substation to the Step-up Substation; A 230 kv Interconnection Switching Station facility (the Switching Station ); An Operations and Maintenance ( O&M ) facility; One permanent meteorological tower; A temporary batch plant; and A temporary lay down and contractor staging area. The Facility will be interconnected with VEPCO s 230 kv Winfall to Suffolk line, which intersects the southwest portion of the Project Area in Perquimans County. Based upon current assessments, the 300 MW project is predicted to have a net production between 750,000 and 950,000 megawatt hours (MWhs) of electricity per year. The output from the Facility is estimated to power between 55,000 to 70,000 homes in North Carolina per year. In order to transmit the output of the Project to the location where it will be connected to the regional transmission system, Atlantic Wind will construct an overhead, 115 kv Sub- Transmission Line. The Transmission Voltage Step-up Substation will consist of a main transformer, circuit breakers, switching devices, auxiliary equipment, and a control enclosure containing equipment for the proper control, protection, monitoring, and communications. The principal function of the step-up substation is to increase the voltage from the sub-transmission line to that of the transmission line, by which the Project will interconnect with the regional transmission system. There will also be a VEPCO-owned and operated Interconnection Switching Station. The Switching Station will serve as the electrical interconnection between the Project and the regional transmission system. The Switching Station will consist of 230kV circuit breakers, disconnect switches, bus conductors, auxiliary equipment, and a control enclosure containing equipment for the proper control, protection, monitoring, and communications. The proposed site layout is shown in Figure 8 in the Individual permit support document. 3.0 Existing Site Conditions The proposed ~2,513 acre Site is located within the ~24,242 acre project area and is situated in an area that historically was the lower portion of the Great Dismal Swamp. However, most of the area has since been converted to active agricultural crop land and silvicultural uses through decades of land clearing, extensive drainage and intensive land management. The Site is currently managed for agriculture (wheat, corn, and soybean) and silviculture. The Site 2

contains extensive lateral ditches within the fields and forested areas, as well as larger collector and roadside ditches. The lateral and collector/roadside ditches ultimately discharge into the Perquimans, Pasquotank, and Little Rivers, and are therefore hydrologically connected to navigable waters of the U.S. and are considered jurisdictional waters under the Clean Water Act. Forested portions of the site, either under timber management or in more of a natural forested state, were determined by the USACE to be predominantly wetland as part of a preliminary determination performed for the project area. Although drainage ditches are present in most of these areas altering hydrology, portions of these areas still posses sufficient hydrology to meet wetland hydrology criteria and are therefore considered jurisdictional. A more detailed discussion of the existing site conditions and jurisdictional features is included in the Individual Permit Support Document. 4.0 Proposed Impacts Impacts to jurisdictional wetlands and waters will be avoided and minimized to the extent practical. However, the preferred alternative will result in 45.67 acres of temporary impacts to jurisdictional waters (roadside canals and agricultural/silvicultural ditches) and 1.37 acres of permanent impacts to jurisdictional waters (roadside canals and agricultural/silvicultural ditches). The preferred alternative will also result in 227.09 acres of temporary impact to managed jurisdictional wetlands (timber lands), 22.12 acres of temporary impact to hardwood flat wetlands, and 27.76 acres of permanent impact to managed jurisdictional wetlands (timber lands) and 1.47 acres of permanent impacts to hardwood flat wetlands. The temporary impacts associated with the project in the managed wetlands are similar in nature to the current timber clearing practices that are incurred in these areas as part of the forestry management plans. A more detailed discussion of the proposed project impacts is included in the Individual Permit Support Document. 5.0 Areas of Environmental Concern The project is located within Perquimans and Pasquotank counties, both of which are under the jurisdiction of the Coastal Area Management Act (CAMA). In order to assess whether the project required a CAMA Major Development Permit, it was necessary to determine if the project impacted Areas of Environmental Concern (AECs) as defined in the North Carolina Administrative Code 15A NCAC 07H. Based upon a field evaluation of the Site by N.C. Division of Coastal Management, (letter dated February 10, 2011 by Kelly Russell, NCDCM) it was determined that the project Site is not located within any NCDCM regulated AECs. A letter from NCDCM confirming their findings is included as Appendix A. The following information documents that the proposed project will be consistent with the State s coastal management program and that the consistency process is the appropriate form of DCM review of this project. 3

5.1 Estuarine and Ocean Systems (15A NCAC 07H.0200) This category of AECs includes those areas that are either geographically within an estuary or, because of its location and nature, may significantly affect the estuarine and ocean system. AECs included in estuarine and ocean system include: coastal wetlands, estuarine waters, public trust areas, and coastal shorelines. 5.1.1 Coastal Wetlands (15A NCAC 07H.0205) Coastal wetlands are defined as any salt marsh or other marsh subject to regular or occasional flooding by tides, including wind tides. Coastal wetlands include some if not all of the 10 identified marsh plant species. Kimley-Horn and Associates, Inc. delineated the wetlands at the site U.S. Army Corps of Engineers Wetland Delineation Manual, Atlantic and Gulf Coast Regional Supplement (Version 2.0, December 27, 2010). Field verification meetings with the USACE staff (Tracey Wheeler and Kyle Barnes) were conducted on April 26, May 25 and June 7, 2011. A Preliminary Jurisdictional Determination request of these jurisdictional features has been submitted to the USACE in conjunction with the Section 404 permit application package. Based upon the NC Wetland Assessment Methodology (NCWAM), the on-site wetlands are classified as pine flats and hardwood flats and are not flooded by ties and do not contained the coastal wetland marsh species. A detailed discussion of the delineated wetland features is included in the in the Individual Permit Support Document. Therefore, this project will not impact coastal wetland areas of environmental concern. 5.1.2 Estuarine Waters (15A NCAC 07H.0206) Estuarine waters include all of the waters of the Atlantic Ocean within the boundary of North Carolina and all of the waters of the bays, sounds, rivers, and tributaries thereto seaward of the dividing line between coastal fishing waters and inland fishing waters. No estuarine waters are located in the proposed project area; therefore, this project will not result in impacts to estuarine waters. 5.1.3 Public Trust Areas (15A NCAC 07H.0207) Public trust areas are all waters of the Atlantic Ocean and lands thereunder from the mean high water mark to the seaward limit of the State jurisdiction, including all natural bodies of water subject to measurable lunar tides and lands thereunder to the mean high water mark. These public trust areas include all navigable water bodies and lands thereunder to the mean high water level or mean water level as the case may be. The proposed project will not directly impact waters of the State of North Carolina and therefore not impact public trust areas. 4

5.1.4 Coastal Shorelines (15A NCAC 07H.0209) Coastal shorelines include estuarine shorelines and public trust shorelines. Estuarine shoreline areas of environmental concern are those non-ocean shorelines extending from the normal high water level or normal water level along the estuarine waters, estuary sounds, bays, fresh and brackish waters, and public trust areas for a distance 75 feet landward. No estuarine or public trust shorelines are located within the project area; therefore, the proposed project is outside of the estuarine shoreline area of environmental concern. 5.2 Ocean Hazard Areas (15A NCAC 07H.0300) This category is composed of AECs that are considered natural hazard areas along the Atlantic Ocean shoreline, where, because of their special vulnerability to erosion or other adverse effects of sand, wind, and water, uncontrolled or incompatible development could unreasonably endanger life or property. Ocean hazard areas include beaches, frontal dunes, inlet lands, and other areas in which geologic, vegetation and soil conditions indicate a substantial possibility of excessive erosion or flood damage. The project is not located along the Atlantic Ocean shoreline and contains no ocean hazard areas. Therefore, the proposed project is outside of the ocean hazard area of environmental concern. 5.3 Public Water Supplies (15A NCAC 07H.0400) This category of AECs includes valuable small surface water supply watersheds and public water supply fields. The project Site is located in the Pasquotank River Basin, North Carolina Division of Water Quality (NCDWQ) sub-basins 03-01-50 and 03-01-52, and U.S. Geological Survey (USGS) Hydrologic Unit Code (HUC) 03010205. The Perquimans River is the nearest stream reach to be classified by NCDWQ (Classification: C, Sw ) and the same classification applies to tributaries and modified natural channel that connect to this segment. The project is not located within a small surface water supply watershed or public water supply field. Therefore, the proposed project will not impact public water supplies. 5.4 Natural and Cultural Resource Areas (15A NCAC 07H.0500) This category of AECs includes fragile coastal natural and cultural resource areas and is defined as areas containing environmental, natural or cultural resources of more than local significance in which uncontrolled or incompatible development could result in major or irreversible damage to natural systems or cultural resources, scientific, education, or associative values, or aesthetic qualities. 5.4.1 Coastal Areas that Sustain Remnant Species (15A NCAC 07H.0505) Coastal areas that sustain remnant species are those areas that support native plants or animals determined to be rare or endangered (synonymous 5

with threatened and endangered), within the coastal area. Such places provide habitats necessary for the survival of existing populations or communities of rare or endangered species with the coastal area. There are no Threatened or Endangered species listed for Perquimans County by the USFWS (database update September 22, 2010). The only federally-listed endangered species for Pasquotank County by the USFWS is the shortnose sturgeon (Acipenser brevirostrum). Habitat for the shortnose sturgeon is not present within the project corridor (Site) and therefore the proposed project would have No Effect on this species. Atlantic Wind has coordinated with the USFWS and North Carolina Wildlife Resource Commission (NCWRC) with regards to avian and bat surveys for the Desert Wind Project. A detailed discussion of the avian and bat survey methodology is included in the in the Individual Permit Support Document. No endangered, threatened, or special concern species were documented during spring and fall migration bird surveys conducted for the project. The state-listed threatened Bald Eagle (a single sub-adult) was documented as a transient during the fall migration survey conducted on November 2, 2010. Although no longer protected under the federal Endangered Species Act, the Bald Eagle is federally protected under the Bald and Golden Eagle Protection Act. Bald Eagles may occasionally occur within the Project Area during spring and fall migration, and as transient individuals throughout the winter. Based on the primarily agricultural nature of the Project Area, it is unlikely that any other state or federally-listed threatened and endangered species would occur on a regular basis within the project area. Therefore, the proposed project will not impact coastal areas that sustain remnant species. 5.4.2 Coastal Complex Natural Areas (15A NCAC 07H.0506) Coastal complex natural areas are defined as lands that support native plant and animal communities and provide habitat qualities which have remained essentially unchanged by human activity. Such areas may be either significant components of coastal systems or especially notable habitat areas of scientific, educational, or aesthetic value. The proposed project is located in an area that historically was the lower portion of the Great Dismal Swamp. However, most of the area has since been converted to active agricultural crop land and silvicultural uses through decades of land clearing, extensive drainage and intensive land management. The project site is currently managed for agriculture (wheat, corn, and soybean) and silviculture. No coastal complex natural areas occur within the project area; therefore, the proposed project will not impact coastal areas that sustain remnant species. 5.4.3 Unique Coastal Geological Formations (15A NCAC 07H.0507) Unique coastal geological formations are defined as sites that contain geologic formations that are unique or otherwise significant components 6

of coastal systems, or that are especially notable examples of geological formations or processes in the coastal area. No unique coastal geological formations occur within the project area; therefore, the proposed project will not impact these areas of environmental concern. 5.4.4 Significant Coastal Archaeological Resources (15A NCAC 07H.0509) Significant coastal archaeological resources are defined in areas that contain archaeological remains (objects, features, and/or sites) that have more than local significance to history or prehistory. A Cultural Resource Assessment, Phase I Cultural Resource Survey, and Phase I Archeological Survey, in accordance with a NC Department of Cultural Resources approved work plan have been conducted for the proposed project area. A detailed discussion of these assessments and surveys is included in the in the Individual Permit Support Document. No significant coastal archaeological resources currently listed in the National Register of Historic Places or Eligible for the National Register will be impacted by the project. 5.4.5 Significant Coastal Historical Architectural Resources (15A NCAC 07H.0510) Significant coastal historic architectural resources are defined as districts, structures, buildings, sites or objects that have more than local significance to history or architecture. R. Christopher Goodwin and Associates, Inc. (RCGA) staff examined the site records at the North Carolina Department of Cultural Resources (NCDCR) for architectural resources that have been recorded in and within 1.5 miles of the proposed project area. Research included a review of the architectural quadrangle maps, survey reports, and architectural forms. Fifty-four previously recorded architectural resources were identified within the area. Of the fifty-four properties, none are currently listed in the National Register of Historic Places or Eligible for the National Register. RCGA initiated an Architectural Survey for the Site in late June 2011. This survey was conducted in accordance with the NCDCR approved work plan. A detailed discussion of these assessments and surveys is included in the in the Individual Permit Support Document. No significant coastal historical architectural resources currently listed in the National Register of Historic Places or Eligible for the National Register will be impacted by the project. 5.5 Outstanding Resource Waters (15A NCAC 02B.0225) Outstanding Resource Waters (ORW) is a supplemental surface water classification intended to protect unique and special waters having excellent water quality and being of exceptional state or national recreational or ecological 7

significance. There are no ORWs within or adjacent to the proposed project site; therefore, the proposed project will not impact ORWs. 5.6 High Quality Waters (15A NCAC 02B.0224) High Quality Waters (HQW) is a supplemental surface water classification intended to protect waters with quality higher than state water quality standards. No HQWs within or adjacent to the proposed project site; therefore, the proposed project will not impact HQWs. 5.7 Conclusion The proposed project is outside of any area of environmental concern. As defined in NC General Statute 113A-103(5)a, the project does not require authorization pursuant to the Coastal Area Management Act in that it will not occur in a duly designated area of environmental concern. The proposed project will not impact state designated ORWs or HQWs. 6.0 General Policy Guidelines Atlantic Wind, LLC has reviewed 15A NCAC 07M General Policy Guidelines for the coastal area and has determined that the proposed project is consistent with those guidelines. Certain sections of the Guidelines, specifically, Sections.0200 Shoreline Erosion Policies,.0300 Shoreline Access Policies,.0500 Post-Disaster Policies,.0600 Floating Structures Policies,.1000 Policies on Water and Wetland Based Target Areas for Military Training Activities,.1100 Policies on Beneficial Use and Availability of Materials Resulting from the Excavation or Maintenance of Navigational Channels, and.1200 Policies on Ocean Mining are not applicable to the proposed development activity. The project is consistent Section 7M.0400 Coastal Energy Policies. The proposed wind energy project does not involve off-shore exploration of resources and is sited inland of the shoreline area with no impacts to any area of environmental concern (AEC), barrier islands, or public trust waters or adjacent lands. The proposed project has been located and placed in a manner that allows for protection of the coastal environment and local and regional socio-economic goals as set forth in the local land-use plans and state guidelines in 15A NCAC 07H and 07M. A discussion of the environmental, economic and social consequences, including the cumulative and secondary impacts of the proposed project is included in the in the Individual Permit Support Document. Section 7M.0700 Mitigation Policies are addressed by the mitigation proposal presented to the U.S. Army Corps of Engineers by purchasing non-riparian wetland mitigation credits from the Great Dismal Swamp Restoration Bank Timberlake Farm Site located within the Pasquotank River Basin (HUC 03010205) to compensate for the impacts associated with fill in Section 404 wetlands. Therefore, the mitigation policies in.07m are consistent with the proposed plan for development. 8

Section 7M.0800 Coastal Water Quality Policies have been addressed. Atlantic Wind, LLC met with NCDWQ staff from the 401 Certification and the Stormwater units on June 13, 2011 to discuss stormwater management design considerations for the project. The Desert Wind project is a Low Density Development since the total developed impervious area is minimal (9%) compared to the project s limits of disturbance. A detailed discussion of the proposed stormwater quality measures for the proposed project is included in the in the Individual Permit Support Document. Atlantic Wind, LLC will obtain a State Stormwater Permit prior to the initiation of construction of the proposed project. The project is consistent with Section 7M.0900 Policies and Use of coastal Air Space. Atlantic Wind, LLC has been in coordination with the Department of Defense (DOD) to ensure the proposed project is compatible with naval air space requirements. Studies conducted by the DOD indicated that the proposed project would not interfere with the Navy s operations. 6.1 Conclusion Based on the review of the General Policy Guidelines for Coastal Areas, we assert that the proposed project is consistent with T15A NCAC Subchapter 07M. 7.0 Land Use Plan Review The project area includes approximately 24,242 acres of land located in two counties, Pasquotank and Perquimans, in northeastern North Carolina. None of the project is within an incorporated municipality. Both Counties have Zoning Ordinances that indicate a Conditional Use Permit would be required for development of a wind farm. Perquimans County Atlantic Wind LLC filed a conditional use permit application (CUP) with the Perquimans County Planning Department on April 25, 2011. The Properties subject to the CUP Application (the Properties ) are zoned RA-Rural Agriculture ( RA ). Large Wind Energy Facilities are among the uses permitted on the Properties pursuant to the applicable provisions of the Zoning Ordinance. The CUP was issued by Perquimans County on July 6, 2011. Pasquotank County Atlantic Wind LLC filed a conditional use permit application (CUP) with the Pasquotank County Planning Department on April 25, 2011. The Properties subject to the CUP Application (the Properties ) are zoned A-2-Agricultural ( A-2 ). Large Wind Energy Facilities are among the uses permitted on the Properties pursuant to the applicable provisions of the Zoning Ordinance. The CUP was issued by Pasquotank County on June 13, 2011. 7.1 Conclusion It is our determination that the proposed project is consistent with the Perquimans and Pasquotank County Land Use Plans. 9

8.0 Other State Permits Atlantic Wind, LLC will obtain all permits and approvals required by the state prior to the construction and operation of the Facility. 8.1 State Water Quality (401) Certification The NCDWQ 401 certification application is submitted concurrent to this 404 permit application. DWQ will also review the proposed plans for compliance with state stormwater requirements. 8.2 State Stormwater Permit The NCDWQ state stormwater application is submitted concurrent to this 404 permit application. It is anticipated that the application will be submitted through the State stormwater express review program. 8.3 Sedimentation and Erosion Control Permit As part of the 401 General Certification requirements, a Sediment and Erosion Control Plan will be required from the Division of Land Resources (DLR), which includes a NPDES General Stormwater Permit. Atlantic Wind will coordinate with the DLR regarding approval of a Sediment and Erosion Control Plan and NPDES General Stormwater Permit. 8.4 North Carolina Utilities Commission Certificate Atlantic Wind, LLC filed an application with the N.C. Utilities Commission on January 27, 2011 for a Certificate of Public Convenience and Necessity for the construction of a merchant plant and registration as a new renewable energy facility. This certificate was awarded to Atlantic Wind on May 3, 2011. 8.5 Driveway Permit The North Carolina Department of Transportation (NCDOT) will require a Driveway Permit for any new roads that connect to an existing NCDOT right of way (ROW). A driveway permit will typically also be required if the use of an existing private road (driveway) that has a change in use (example from private to commercial) or has planned improvements. 9.0 Project Consistency Conclusion These supporting documents, in accordance with 15 CFR 930.58 put forth the data necessary to assess our assertion of the project is consistent with the Federal Coastal Zone Management Act of 1972, as amended and the enforceable policies of the North Carolina approved Coastal Management Program. We request that the North Carolina Division of Coastal Management concur with our Consistency Certification that the proposed activity complies with the enforceable policies of the North Carolina Approved Management Program and will be conducted in a manner consistent with such Program 10

APPENDIX A NCDCM AND NCDWQ PROJECT REVIEW LETTERS