Micro Planner X-Pert

Similar documents
Implementing Resource Scheduling Techniques

Finally: the resource leveling feature explained May4, 12pm-1pm EST Sander Nekeman

Planning Tools and Techniques Part 2

Plan Your Work, Work Your Plan. Dr. R. Rockland Chair and Professor, Department of Engineering Technology New Jersey Institute of Technology

Vladimir Liberzon Shane Archibald Olga Makar-Limanov INTRODUCTION

Embarking new Project

Hydra White Paper. Scheduling technologies: Resource centric versus Task centric

THE GANTT CHART WHAT IS USED FOR HOW TO MAKE IT WITH EXCEL

MS Project Professional 2007 Schedule Leveling: Tips & Tricks. By Lloyd C. Miller III, PMP

2.1 Project Management tools which project management software packages should be equipped with

Gush vs. Bore: A Look at the Statistics of Sampling

Software Application: Information System Elements

Chapter 5 Project Scheduling. (Source: Pressman, R. Software Engineering: A Practitioner s Approach. McGraw-Hill,

technical tips and tricks

Mastering Microsoft Project 2010

Principles of Planning for Building and. by Eastwood Harris Pty Ltd. Introduction Emergency Evacuation. Course Outline.

ProjectXpert 2017: Behind every successful project, there is a plan.

maconomy people planner for project-oriented organisations that want to optimise planning and management of resources and projects

After solving all the case studies, please forward your answers to for an extra credit.

BUTE Department of Construction Management and Technology

PLANNING & SCHEDULING

MICROSOFT PROJECT 2007 Level 1

MSP How to guide session 3 (Updating)

DAMELIN CORRESPONDENCE COLLEGE

Lecture- 11. Project Scheduling. Dronacharya College of Engineering

MICROSOFT PROJECT 2007 Level 1

PROMASTAR Instructor led Professional Training Services Primavera Accredited/Certified Class Courses

Strategy. Strategy Training Guide

TIMESHEET. Project economy, planning and forecasting AutoPilot

PROJECT TIME PLANNING. Process and Bar Chart Technique

Microsoft Managing Projects with Microsoft Project

Project Time Management

Scheduling Resources and Costs

Scheduling. Why Schedule? Scheduling will: Delivering On Your Promises

Project Scheduling with GanttProject. EGR 386w

Production Activity Control

Microsoft Excel or Microsoft Project? Why Microsoft Office Project 2007 is Easier and More Effective for Managing Projects

Oman College of Management and Technology

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

PROJECT PLANNING AND SCHEDULING

Estimating Project Schedule-Time and Cost

PMP Exam Preparation Course Project Time Management

How to complete an electronic timesheet

Microsoft Project study guide

itaskx 3 Project Management User Manual

MICROSOFT PROJECT 2010 Level 1

GE404 Engineering Management Topic1. INTRODUCTION

Lecture- 10. Project Scheduling. Dronacharya College of Engineering

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course

Project Management Professional (PMP) Exam Prep Course 6 - Project Schedule Management

Microsoft Office Project 2010 Basic Course 01: Getting Started

Consider the duties involved when assigning the type of 3G form to submit teaching, research, or other.

Resource Critical Path Approach to Project Schedule Management

Chapter 3 Managing Systems Projects

Managing Projects with MS Project 2010

Primavera P6 R8.3 Professional Fundamentals Training Course Outline

The Basics 7. Introduction 8 Project Management 9 What s New? 10 Version Comparison 12 The Gantt Chart 14 Getting Help 15 Summary 16

Management of Multi Construction Projects using Primavera

Microsoft Project Tips & Tricks. Project Solutions Group, Inc.

OPERATING CODE NO. 6 (OC6)

Microsoft Project 2013 Core Essentials

5.3 Supply Management within the MES

Avoiding the 'Tipping Point to Failure'

MICROSOFT PROJECT 2002(XP) AND 2003 LEVEL 1

Production Management and Scheduling

Avoiding the 'Tipping Point to Failure'

Internal Medicine Faculty Affairs Staffing Analysis Program & Operations Analysis University of Michigan Health System

Upravljanje softverskim projektima

Information Technology Project Management, Seventh Edition

Establish the Project Schedule

Sales Order Processing

Project Time Management

Basic Economic Concepts Objectives: - For students to understand the basic economic problem. - - For students be able to make rational economic choice

6 PROJECT TIME MANAGEMENT

Welcome to the Eastwood Harris Pty Ltd PRINCE2 TM Revised 2009 and Microsoft Project 2010 training course

Program Evaluation and Review Technique (PERT)

Project 2003 Intermediate

Network Diagram 11/10/2016 WORK BREAKDOWN STRUCTURE (WBS)

Cambridge International AS & A Level Computer Science

How to set up an interview schedule

Project Management LAB

Before you work in Kronos, you should have a Payroll Calendar available to you. From the Ferris

MSP Ongoing Use Tips & Tricks. Your Guides: Rob Greca and Jenn Rinella

The Museum Project. 1. Creating the Project

Capacity Evaluation (PP-CRP- ALY)

Lecture 7 PROJECT SCHEDULING. Ferdinand Fassa

Project Management in Practice Fifth Edition

Printed in the USA by: clubsystems group, inc.

Microsoft Project 2010 Project Essentials Planning, Communicating, Tracking

Morningstar Direct SM Asset Allocation June 2014 Release

1Z

Planning & Scheduling

Project Management Techniques

Modern Systems Analysis and Design Seventh Edition

Next select the Add button. Then select Add Blank button. The following screen will appear. Chemical Scheduling-1

MBP1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar

Scheduling Work at IPSC

User Guide Project Manager

Gantt chart for bpm'online. User manual

Transcription:

Micro Planner X-Pert V3.5.1 Overview Presenter: Patrick Weaver PMI-SP Micro Planning International Asia Pacific Cell:+61 418 53 1111 raf@microplanning.com.au.

Arrow Diagram

Precedence Diagram

Working Days Gantt

Why the Need to Plan Resources? In the US and generally within Australia, there is a shortage of skilled tradespersons within the construction industry Client s still want their projects delivered on time and within budget Shortages of resources generally cause delays and increases in cost So what is the project manager to do?

Why the Need to Plan Resources? Need to know what resources are required by your project Thus the project manager MUST carry out resource planning

Resource Planning When you analyze a project on timing alone, the results show how soon the project can complete and what the deadlines are for each operation. Analysis of time does not tell you whether there are enough people to meet this schedule or whether the available machines can cope or how much cash you need. Time Analysis calculates when each operation could happen but to find out when each operation should happen, you need to consider resources.

Time Vs Resources Note: In calculating task durations some consideration has been made about resource levels what we are discussing today is the optimisation of time and resources.

Defining Resource Information Before you can allocate resources to individual operations and analyze the workloads, you need to know the following information The resources available to the project The cost of each resource (optional)

Resource Profile Need to define the name of the Resource and how much is available and when e.g.

Resource Types Having named the Resource need to know whether it is either Normal Pool

Normal Resources Normal resources are those which are available for work each time period (day) as in people

Pool Resources Pool resources are ones which are actually consumed, e.g bricks Which may be replenished at various time periods

Utilisation of a Pool Resource

Replenishing the Pool Resource

Resource Usage Method Before you enter a quantity, decide whether to specify how many resources are required (as a Rate) or whether to enter the Total number of People Days (or machine days, bricks, cash etc.) for the entire duration. (Also known as Level of Effort)

Rate or Total (1)? Specifying usage as a Rate means the specified resource quantity will be used at a steady rate, regardless of length of day, week or duration. If the duration changes so does the total resource usage the resource allocation is variable.

Rate or Total (2)? If you specify a Total allocation then a specific amount of work time is spread evenly over the duration. As a result, no matter how much the duration changes, the overall allocation does not it is constant. For example, imagine you have an operation that would take 1 person 4 days and you want it done in 2 days

Rate or Total (3)?

Rate or Total (4)? You could express the work content either as a Rate of 2 people per day, or as a Total of 4 Man Days. At this point, the resource allocation is the same 2 people per day for 2 days.

Rate or Total (5)?

Rate or Total (6)? However! If the duration were greater, say, 4 days then the Rate method uses 2 people per day for 4 days a total of 8 man days. Whereas a Total allocation of 4 man days does not change allocating 1 person per day for 4 days.

Resource Analysis Resource Analysis is the process by which you examine the availability of resources and figure out when tasks should be scheduled to work within that availability. During this process, the analysis tends to level out the usage of resources.

Resource Analysis (Cont) Resource Analysis produces a schedule of dates for every task in the project showing when they should start and finish and also produces totals for the usage of resources throughout the project.

What Does Resource Analysis do? The Parallel Scheduling by Resource Analysis could best be described as a bulldozer technique. Imagine that every task on a project is able to happen at its earliest time as calculated by Time Analysis. The result could be usage which fluctuates regardless of how many resources are available.

Preparing to Resource Schedule

What Does Resource Analysis do (2)? The availability of resources can be set at a specific level like a bulldozer blade. As the Resource Analysis bulldozer starts up and moves forward from Time Now, it pushes the peaks of excess resources into the troughs of unused resources.

What Does Resource Analysis do (3)? There will be times when there is too much earth for the required level to be reached. There may also be insufficient earth to maintain continuity at the required level. That is the theory, in practice it works like this

The Time Analysis Schedule of Tasks

Resourcing After Day 1

Resourcing After Day 2

Resourcing After Day 3

Resourcing After Day 4

Splitting

Defining Minimum Split

Stretching Tasks in Resourcing

Resourcing after Day 1

Resourcing after Day 2

Resourcing after Day 4

Full Impact of Stretching Schedule by Day 7

Deadlines or Resources? During Resource Analysis, you may meet a situation in which there are insufficient resources available for an task which has no more float. You are, therefore, faced with a decision do you delay the task so that the project completion or some other deadline is delayed, or do you overload the available resources?

Types of Resource Analysis The answer comes in the form of two types of Resource Analysis Deadline Critical and Resource Critical. Deadline Critical calculates how many extra resources, if any, are needed to finish the project on time. Resource Critical calculates how much extra time, if any, is required for the existing resources to complete their allotted workloads.

Deadline Critical

Resource Limited

Time and Resource Thresholds From the previous slides you may have imagined a certain amount of anarchy when the chips are down. First, during a Deadline Critical analysis, the resources can be overloaded. You may have asked yourself two questions: 1. Can I limit this overloading so that, at least, it is within reason? 2. Is it possible to specify that some resources cannot be overloaded even during Deadline Critical analysis a kind of selective Resource Critical analysis?

Time and Resource Thresholds (2) During Resource Critical analysis, the project can be delayed beyond its deadline. You may have asked yourself: Is there any way that I can limit this delay? The answers to these questions come in the shape of Thresholds

Resource Thresholds in Deadline Critical

Time Thresholds

Unavoidable Split/Overload When you choose a Resource Critical Resource Analysis, you specify that the resources must not be overloaded and, under certain circumstances, the only way of achieving this may be the interruption of one or more tasks...... but what happens if these tasks are Non- Split or Consecutive?

The Solid Fixed Block: Imagine that tasks A and B require the same resource and that task B is forced to start on day 3 because of a Fixed Earliest date. A fixed date takes priority over everything else

Resource Distribution

Deadline Resource Histogram

Resource Limited Resource Histogram

Cost Forecasting Cost Analysis

Costing Rates

The Cost of Each Task

Costing Details

Daily Wastage Costs

Total Estimated Costs or Cash Flow Profile

Comparing Schedule Costs

Updating a Micro Planner X-Pert Project Plan Reporting Progress on Tasks, Resources and Costs

Reporting Progress Opened the file, go to the Analysis menu and highlight Progress Details and click.

Reporting Progress

Reporting Progress Enter the appropriate Time Now date, Eg 15-Sep-03

Reporting Progress Go to File on the Menu bar and select Save As.. Eg HOMUpdt1.xpj

Reporting Progress Go to the desktop and open the sub project to be progressed

Reporting Progress X-Pert shows all the tasks and events which should have started and finished since the last Time Now, with a cross or diagonal line through the task box

Reporting Progress Double Click on the first event/task to be progressed Click on the Progress Button

Reporting Progress The progress cells now appear

Reporting Progress Enter the actual achieved date for the Start event; eg 18Aug03

Reporting Progress Progressing Tasks Double Click the first task to be progressed

Reporting Progress Enter the Task s Actual Start and / or Actual Finish Dates Eg Actual Start was 18Aug03 and Actual Finish was 22Aug03

Reporting Progress Reporting Actual Resources Used Click on the Resource Usage button

Reporting Progress Click on Actual Usage

Reporting Progress Click on Copy Planned to Actual

Reporting Progress Note that cells are filled for you, with the data originally entered Click OK and the progress data is now entered

Reporting Progress Continue to report progress For a Task which has started but not finished, you must report a balance to go or a % Done to date, as shown

Reporting Progress Note: A task should not have a balance duration reported if both the started and finished dates have been entered. Also % Done will not be used as reporting percentage work done is rather subjective and the more objective form of estimating time to complete a task is preferred. If a task is reported with an Actual Start Date and the rest of the fields are left blank, X-Pert will assume progress has occurred since the reported Actual Start Date and Time Now. Should there be insufficient balance left at Time Now, then the task will be assumed completed

Reporting Progress Run a Analysis to view the results of Progress eg. Resource Analysis Deadline Critical

Reporting Progress

Reporting Progress

Thank You Questions?