January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT

Similar documents
OMAHA BASEBALL STADIUM. May 21, 2009 Report No. 2

June 10, 2010 Report No. 10 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY

July 15, 2010 Report No. 11 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY

March 24, 2011 Report No. 17 MONTHLY CONSTRUCTION PROGRESS REPORT

Auburn University Construction Project Update March 2010

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

ADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows:

MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07. Latrobe Elementary School. Greater Latrobe School District

Tech Assignment 1 University Medical Center of Princeton. Plainsboro Road, Township of Plainsboro, New Jersey

Subcontractor Pre-Qualification Statement Hunt / Moss, A Joint Venture

Update on FCPS Construction/Renovation Projects. June 2016

4.1.3 Project Manual

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

NEW MIDDLE SCHOOL PROJECT

executive summary Executive Summary University of Florida, Gymnastics Planning Study Project Description

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #142 Douthit Hills Student Community, Clemson University Project Tony Greene

Project Manual Index of Specifications Shenandoah Schools Concession Building

Seattle Public Schools Building Excellence IV Projects Under Construction

CARVER ELEMENTARY SCHOOL PROJECT May 2017 Monthly Status Report

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #135 Douthit Hills Student Community, Clemson University Project Tony Greene

INSPECTION REQUIREMENTS Page 1 of 5. JOB SITE ADDRESS posted during entire construction process.

CALIFORNIA BUILDING PLANS EXAMINER CONTENT OUTLINE 01. GENERAL ADMINISTRATION 3 % Project Administration 3%

G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #134 Douthit Hills Student Community, Clemson University Project Tony Greene

DOCUMENT B. 2. The low bidder shall submit this Expanded Subcontractors Listing to the Owner within 24 hours after the bid opening.

Item # 1: Attached are the revised Table of Contents and Specifications added: Section Cabinets and Vanities

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #154 Douthit Hills Student Community, Clemson University Project Tony Greene

Building Excellence IV Capital Levy Projects Under Construction

Inspection requests submitted by 2:30pm will be scheduled for the following business day unless otherwise requested.

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #158 Douthit Hills Student Community, Clemson University Project Tony Greene

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #133 Douthit Hills Student Community, Clemson University Project Tony Greene

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #92 Douthit Hills Student Community, Clemson University Project Joe Jett

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

CONTRACT ADDENDUM # 1


Prequalification Form

Watercrest - Sand Hill - Columbia, SC TABLE OF CONTENTS PROCUREMENT AND CONTRACTING REQUIREMENTS

MITTERSILL WARMING HUT

Kaiser Permanente Largo Medical Office Building Largo, MD

Appendix J - Custom Uniformat for EDU Migration

Update on FCPS Construction/Renovation Projects. December 2015

ADDENDUM NO. 2 Consisting of 3 pages and Attachments

Doing Business with the Metropolitan Washington Airports Authority

Field House Proposal

STRUCTURAL ABBREVIATIONS S-001 GENERAL NOTES CONCRETE MASONRY NOTES DESIGN NOTES SOF NSWG-10 UAS SUPPORT FACILITY FY 2016 MILCON P-225

Project Status Update & Progress Report

Update on FCPS Construction/Renovation Projects. July 2016

Yardmen Arena Expansion & Renovation Project Update

Project Information Session / Meet and Greet # 3

Auburn University Construction Project Update June 2010

PROJECT COMPLETED. Bayside High School. Comprehensive Additions and Renovations

2016 CDM Smith All Rights Reserved July 2016 SECTION MULTIPLE CONTRACT SUMMARY

NAME OF PROJECT Design Development. General Objectives of Phase. Phase Task Checklist. Quality Management Phase

DESIGN & CONSTRUCTION GUIDELINES

Capital Projects Update

ADDENDUM 2 - JULY 14, 2015

EXPANSION & RENOVATION

MONTHLY STATUS REPORT No.4

UNC Charlotte Science Building Project. Informational Meeting: May 3, 2018

Building Architecture

THE CONSTRUCTION SUPERVISOR

EXHIBIT C GUARANTEED MAXIMUM PRICE TO THE CONTINUING CONTRACT FOR CONSTRUCTION MANAGEMENT SERVICES/RFQ #14-Q-009-KR BY AND BETWEEN

Franklin Hall Renovation TABLE OF Document Indiana University Bloomington

Robinson Landing: Townhouse Pre-Construction Presentation January 9, 2018

NEW MIDDLE SCHOOL PROJECT

University of Central Florida Downtown Campus / Dr. Phillips Academic Commons Pre-Bid Phase II Package Structural, Architectural and MEP

Prestage Farms Subcontractor and Vendor Outreach Fair

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #161 Douthit Hills Student Community, Clemson University Project Tony Greene

TABLE OF CONTENTS DIVISION 1 GENERAL REQUIREMENTS

TABLE OF CONTENTS Public Safety Building

June 12, 2017 Addendum #6 RFP # Modular Relocation & Site Development

WORK AND PROJECT REQUIREMENTS

Woodbridge Redevelopment Update. CLC Meeting #6 Wednesday, December 13, 2017

Texas Tech University Health Sciences Campus - MSBII Supplemental Bid Instructions March 3, 2017

C. Type of Selective Demolition Work: Demolition requires the selective removal and subsequent off-site disposal of:

CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #139 Douthit Hills Student Community, Clemson University Project Tony Greene

Building Excellence IV Capital Levy Projects Under Construction

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #69 Douthit Hills Student Community, Clemson University Project Joe Jett

Construction Update. May 2016

Construction Summary

Technical Assignment #3 Alternate System and Methods Analysis

Overbrook Theater / Fruenthal Foundation Art Center. 1.0 Total Points % 2.1 Building Exterior Elements %

Phase IIA Apartment construction continues despite challenging weather.

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #91 Douthit Hills Student Community, Clemson University Project Joe Jett

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ******************************************************************************

Fleet Elementary School

RESIDENTIAL BUILDING PERMIT GUIDE FOR MULTI-FAMILY DWELLINGS

Residential Building Inspections

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

Capital Projects Progress Report. January Presented by

Show how a KM database impacts: cost, time, and quality. Demonstrate how Parametric Design could be used to save time, money, and improve quality

Invitation to Bid. RLS Construction Group requests your firm to submit a quotation on the following project:

SPACE TYPE: OUTSIDE PARKING (STRUCTURE)

CONSTRUCTION COST BREAKDOWN THIS IS FORM CCB

TRANSLINK LOGISTICS CENTRE

NEW MIDDLE SCHOOL PROJECT

Transcription:

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY

MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority Omaha, Nebraska January 2010 Report No. 7 MECA Board Members Gail Werner-Robertson David Kramer Jennifer Mahlendorf David Sokol Jim Vokal

MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority Omaha, Nebraska January 2010 Report No. 7 TABLE OF CONTENTS Construction Progress Summary... 1-3 Site and Building Photographs... 4-5 Project Schedule... 6-7 Project Cost Summary... 8

CONSTRUCTION PROGRESS

CONSTRUCTION PROGRESS SUMMARY DESIGN SUMMARY Owner, Architect, and Construction Manager (OAC) meetings continue to be held every week to discuss safety, schedules, weather, budget, submittals, and other current issues. Executive meetings, which include the Project Team Leaders from MECA, HDR and Kiewit Building Group, continue weekly to discuss topics such as the budget, contractual situations, schedules and other high level issues that require executive decisions. The Design Advisory Committee (DAC) consists of representatives from the City of Omaha, CWS, Inc., MECA, Heritage Services, Creighton University and the NCAA. Quarterly meetings are held to provide the committee with an update of the stadium design. Several major building systems have been bid or are in the process of bidding, including Structural, Mechanical, Electrical, Plumbing, Elevators and Seating. Final exterior and interior design packages have been completed and reviewed by the Design Team. Design detailing has been completed. The design has several alternates identified which may be implemented as the budget allows. The Design Team continues to review opportunities to promote energy efficiency and provide sustainable design features. Meetings with the Environmental Protection Agency and the Nebraska Department of Environmental Quality have been informative to evaluate programs which will assist in recycling efforts and energy efficient stadium operations. The Design Team has met with City of Omaha Building code officials and City of Omaha Fire Department staff on multiple occasions to discuss code related items and life safety aspects of the stadium. Fire alarm and smoke evacuation design systems have been completed. Coordination continues with City of Omaha officials including the Public Works Department, the Planning Department and the Plumbing Board. The design team has been focused on the finalization of interior material selections and colors. These materials continue to be reviewed and coordinated with the entire facility. Durability and appropriate color themes of materials continue to drive the decisions throughout this process. The interior and exterior signage and graphics were developed and are specific to the stadium design and structure. The exterior signage design and content is under review with the City of Omaha for compliance with zoning ordinances. Scoring boards and video board systems are being developed for the Team s indepth review prior to specifications being released to bidders in February. Detailed coordination, appropriate sizes, viewing angles, locations, etc. of the video boards with signage and auxiliary scoring boards are some of the elements still under review by the Design Team. The timeframe of this bid package is parallel with other projects in the industry which is anticipated to increase competitive strategies for this package. Construction Progress 1

CONSTRUCTION PROGRESS SUMMARY CONSTRUCTION SUMMARY Kiewit Building Group has office trailers on the construction site. MECA has offices in one of the on-site trailers and there is an additional general area available for subcontractors on a periodic short-term basis. Kiewit is coordinating construction traffic with MECA s event schedule to limit the affect on traffic flow to and from Qwest Center Omaha. Bids have been issued and received for Structural Steel, Construction Support Services (cranes, bobcats, material hoists, general clean-up, etc.,) Elevators, Shallow Foundations, MSE Walls, Fixed Seating, Relocation and Interior Redesign of the Parking Control Center, Mechanical, Electrical, Site Utilities, Fire Sprinkler, Concrete, Interior and Exterior Masonry, Drywall, Fireproofing, Curtainwall (glass exterior walls), Roofing, Painting, Playing Field, and Doors & Hardware. There are 12 bid packages yet to be distributed for the project and several of those bid packages will be ready for distribution in the near future. Bid packages will be issued for the Overhead Doors, Flooring, Operable Walls, Restroom Specialties, Lockers, Flag Poles in January and proposals are expected shortly thereafter. The response from bidders has been very good for the packages that have been awarded and/or are out for bid. The Perimeter Drainage work that started in early August 2009 has been completed and is operational except for a 75 foot section between two traffic poles on the north side of the stadium. The City will remove these poles in the spring. This drainage system will help drain the site so that work can continue after heavy rains. Structural steel erection started August 11, 2009, which is in line with the timeframe identified in the overall project schedule. Four of the light towers were erected with the finish paint color. Portions of the canopy were installed with the finish paint color (applied in the shop) in areas that would be a challenge to access once the steel is set in place. The structural steel installation is anticipated to be completed in the Spring of 2010. There are several sections of structural steel that have not been erected in order to allow equipment access to the playing field. Concrete on the metal floor deck has been placed behind home plate on all levels and this work will continue down the baselines. Work between the foul lines will be completed within the next month. The main concourse is a split slab, and the base slab has been placed. The placement of the final top slab is scheduled to begin in the Spring of 2010. The concrete flooring work at the street level (service level) started behind home plate and will continue through the winter as areas are enclosed and heated to remove the frost to an appropriate level. The Mechanical, Electrical and Plumbing rough-ins are progressing ahead of the concrete pour schedule. This allows the concrete contractor flexibility to pour these areas sooner than scheduled depending on weather conditions. Construction Progress 2

CONSTRUCTION PROGRESS SUMMARY CONSTRUCTION SUMMARY The first delivery of the finished concrete precast seating slabs will arrive on site within the next few days. Site visits were conducted at the precast plant to assure the quality is what was expected from the Design Team. The exterior brick and interior block work began in November 2009. Work through November and early December continued due to less than extreme winter conditions. This work is scheduled to move forward throughout the winter with temporary partitions/enclosures that have been installed to allow areas to be heated. Fireproofing of the structural steel began in late November and will proceed throughout the winter. Areas of the construction site will be partitioned with heavy tarps and heated to allow work to progress through the cold weather. Spray applied insulation is scheduled to begin within the next week and will be confined to the partitioned and heated areas of the Project. Kiewit and the designers continue to receive detailed shop drawings for Structural Steel, Mechanical, Electrical, Plumbing, Concrete, Curtainwall, Drywall, Masonry, Fireproofing. Roofing, Painting, and the remainder of the exterior closure shop drawings will be submitted in the next several weeks. These drawings will be reviewed to ensure they comply with the intent of the design and will be modified as necessary. Construction Progress 3

SITE & BUILDING PHOTOGRAPHS

Field access tunnel along 1st base Interior stairs construction Pre-assembled restroom plumbing piping Winter enclosures allow work to continue Installation of interior concrete block walls Installation of Suite Level metal stud walls 4

Installation of exterior brick and block walls Finish details of exterior brick at the street View of stadium from outfield access area View through the Suites along 3rd base line Aerial view of the site at 13th Street Aerial view of the entire construction site 5

PROJECT SCHEDULE

PROJECT SCHEDULE SUMMARY SUMMARY OF CURRENT CONSTRUCTION ACTIVITY TARGET START TARGET COMPLETION TASK DESCRIPTION Miscellaneous Scheduled Items 3/09 City of Omaha to add temporary traffic light poles and remove existing poles; Move existing traffic light controllers to new locations; Abandon and remove utilities within 12th Street between Cuming and Webster so that it can be vacated 1/10 MECA to work with Union Pacific to remove and relocate the railroad crossing controllers Design Package Schedule 7/08 11/08 Schematic Design Documents developed and incorporated into GMP Manual 11/08 01/09 Design Development Documents delivered to Project Team 1/09 Varies Construction Documents and Bid Packages developed and distributed to Project Team for review prior to final development of various specialty Bid Packages Bid Package Schedule 2/09 Bid 3/09 Elevator Bid Package 2/09 Bid 3/09 Construction Support Services Bid Package 3/09 Bid 3/09 Shallow Foundations Bid Package 4/09 Bid 4/09 Structural Steel Bid Package 3/09 Bid 4/09 MSE Walls Bid Package 4/09 Bid 5/09 Fixed Seating and Bleachers Bid Package 4/09 Bid 6/09 Mechanical/Plumbing Bid Package 4/09 Bid 6/09 Electrical Bid Package 5/09 Bid 5/09 Parking Control Building Interior Construction Bid Package 6/09 Bid 7/09 Precast Bid Package 7/09 Bid 8/09 Masonry Bid Package 7/09 Bid 8/09 Concrete Bid Package 7/09 Bid 8/09 Fire Sprinkler Bid Package 7/09 Bid 9/15/09 Curtainwall 7/09 Bid 9/15/09 Drywall and Fireproofing 10/09 Bid 11/3/09 Roofing 10/09 Bid 11/3/09 Painting 12/09 Bid 1/7/10 Playing Field 12/09 Bid 1/7/10 Doors & Hardware 12/09 Bid 1/12/10 Overhead Doors 1/10 Bid 2/4/10 Restroom Specialties 1/10 Bid 2/4/10 Flooring 1/10 Bid 2/4/10 Operable Walls 1/10 Bid 2/4/10 Lockers 1/10 Bid 2/4/10 Flag Poles Construction Progress 6

PROJECT SCHEDULE SUMMARY SUMMARY OF CURRENT CONSTRUCTION ACTIVITY TARGET START TARGET COMPLETION Construction Schedule TASK DESCRIPTION 12/08 Notice to Proceed to Kiewit Building Group 2/09 4/09 Completion of Piling 3/09 7/09 Slabs on Grade Surcharge Installation and Removal 3/09 9/09 Parking Control Building Relocation and Interior Redesign 6/09 1/10 Shallow Foundations-Main Building Structure 6/09 11/09 MSE Walls - Outfield 6/09 12/09 Placement and Removal of Surcharge 8/09 3/10 Steel Erection 8/09 TBD Perimeter Drainage System (Install areas as they become available) 8/09 2/10 Infield Mechanical/Electrical Underground Utilities 10/09 2/10 Concrete on Metal Deck (non-outfield) (Concourse, Suite/Club, and Press Levels) 10/09 2/10 Concrete Slab on Grade (non-outfield) (Street Level) 11/09 8/10 Masonry (Brick and Block) 1/10 2/10 Precast Seating Tubs/Risers 3/10 3/11 Doors & Hardware 7/10 11/10 Overhead Doors 8/10 11/10 Field Installation 9/10 4/11 Flooring 9/10 4/11 Restroom Specialties 9/10 4/11 Operable Walls 9/10 4/11 Lockers 10/10 10/10 Flag Poles 4/11 Substantial Completion of TD AMERITRADE Park Omaha Construction Progress 7

PROJECT COST SUMMARY

PROJECT COST SUMMARY BUDGET An estimate was prepared by Kiewit from the Schematic and Design Development documents. As with most construction projects, costs were identified and Value Management items were developed. This process that the entire Project Team is involved in will ensure that the facility is constructed with quality materials while providing the most flexibility and the latest in technologies as reasonably possible. The entire team is currently evaluating options to ensure the project is delivered within the designated budget. As with other construction projects of this magnitude using this Fast Track process, new items that are required for the building to function are being realized, priced and evaluated. The team is researching other opportunities to reconcile the overall GMP. ARCHITECTURAL AND ENGINEERING MANAGEMENT HDR Architecture, Inc. has requested $6,539,204.54 for work completed through November 2009. This represents a little over 90% of their design work. The architectural fee represents the following design packages: Schematic Design and Validation of GMP Manual Design Development Phase Construction Document Phase Construction Administration Phase Services CONSTRUCTION AND CONSTRUCTION MANAGEMENT Kiewit Building Group has billed $27,805,908 ($25,490,613 less $2,315,295 retainage) for work completed through the end of December 2009, representing 30% completion. ALLOWANCES Within Kiewit s GMP there are contractual allowances for multiple items including: Parking Control Center Relocation Site Lighting Stadium Field Lighting Subsurface Water Barrier Drainage Landscaping Natural Grass Playing Field PA/Sound System CONTINGENCY Nothing to report Construction Progress 8