Aspen Revisited. By Alfred F.A. Patzig, HYDROPOWER TURBINE SYSTEMS INC. (HTS INC), Richmond, Virginia, USA

Similar documents
Range of utilization. Envelope

Electricity from a movable power source

Water Power. Modern plant & DAM CONSTRUCTION. New equipment at the Blue Lake Expansion Project. Serving the hydro industry for 67 years

Compact - Effi cient - Reliable. DIVE-Turbine An innovative turbine concept for small hydro power plants

TURBINE VENTING FOR DISSOLVED OXYGEN IMPROVEMENTS AT BULL SHOALS, NORFORK, AND TABLE ROCK DAMS

Micro Hydro In a Municipal Water and Power System

EXAMPLES OF BENEFITS FROM EFFICIENCY EVALUATION USING COMPARATIVE TESTS

compact efficient reliable

Code No: R Set No. 1

Increasing hydro-equipment value with field measurements. P. Weibel, J. Contreras, S. Lais, E. Parkinson. ANDRITZ HYDRO Switzerland

Powering a better future

Fig Micro-hydro s economy of scale ( based on data in 1985)

Florentin POP Project Manager Hydro- Engineering Romania

USE OF WHATSAPP MOBILE APPLICATION IN PROJECT MANAGEMENT OF LARGE INFRASTRUCTURE PROJECT

INTERNATIONAL STANDARD

Pipelines and Penstocks Avoiding operational issues throughout the life of your project

N N O V A T I O N E F F I C I E N C Y Q U A L I T Y VTG. Vertical Turbine Generator

Tender Call No.: Likhu/GVN/Pkg-03/2012 OLUME III A 1 TABLE OF CONTENTS SALIENT FEATURES 1.0 SCOPE SALIENT FEATURES... 1

Economic concrete distribution with stationary booms

Report on the completion of HPP POBREG RAIFFEISEN BANK SH.A. ALBANIA. Evaluation and Business Plan Supervision of Hydropower Plants

Power Recovery Turbines

Data acquisition and processing system for small hydro power plants

HYDROPOWER SYSTEMS BY APPOINTMENT TO H.M. THE QUEEN WATER TURBINE ENGINEERS, GILBERT GILKES & GORDON LTD, KENDAL

Voith s StreamDiver solution for decentralized low head hydropower plant operations

Flygt N-Pumps 3085, 3102 & For reliable and efficient wastewater handling

National Hydropower Association Operational Excellence Event Report. Environmental

IMPACT AND PUNCTURING OF JARI TUNNEL AND ENLARGEMENT OF EXISTING TAPPINGS FOR ADDITIONAL WATER SUPPLY AND POWER GENERATION

Refurbishment of the Pant yr Afon Hydro Scheme By Matt Palmer and John Howarth, Dulas Ltd. September 2007

Online flowrate monitoring experiences at Hydro-Québec

Hydraulic turbines, storage pumps and pump-turbines Rehabilitation and performance improvement

ErcoleMareliGroup. GreenPowerGenera on HYDROPOWERPLANTTURBINES

3. Design of Generation Equipment. 3.1 Turbine (1) Turbine Types Turbines are classified into two types according to their water energy utility:

MEMORANDUM. The general findings of the assessment are as follows:

Effect of a Prototype Surface Collector and Juvenile Fish Diversion Screens on Turbine Efficiency Measured at Unit 5, Bonneville Dam

MATERIAL PROCESSING GUIDE

HYDROPOWER AND WATER RESOURCES

Friction Reduction of Unlined Power Tunnels for Increased Power and Energy Production

Alden Turbine Development: Overview of Preliminary Engineering

Small Hydro based energy generation

Sharing Experiences of the World s Largest Tidal Power Plant in Lake Sihwa, South Korea

Hydropower & Dams Services

Engineering for SH Operations Voith s new StreamDiver technology. StreamDiver B Murtha, NWHA Sisters Oregon

Code No: R Set No. 1

6 District heating Substation District Heating Training Course

(a) the inlet and exit vane angles, (b) work done (c) Efficiency of the system. [16]

Intro to. Part 1: Systems Overview. Dan New

3- Hydropower. Energy conversion and hydropower principles

THE VERY BEST IN HIGH PRESSURE WATER JETTING SYSTEMS INNOVATION THROUGH EXPERIENCE.

INVITATION OF BID (INTERNATIONAL COMPETITIVE BIDDING)

Discharge systems for difficult to handle bulk materials

Your defined goals and objectives:


Flow measurements at two 1.4 MW units of the T.W. Sullivan Plant of Portland GeneralElectric

AN EXPERIENCE IN THERMODYNAMIC TEST OF LOW HEAD TURBINE IN THAILAND THE CASE OF MAE NGAT HYDRO POWER PLANT

From Wikipedia, the free encyclopedia

BEAR FORCE AND RELIABILITY

Customer-specific pump engineering

Renewable and Alternative Energies

Eska Creek Preliminary Feasibility Analysis

Chris le Grange & Pierre Pisterman Project Manager Hydro Tasmania & CEO HPP South Africa & France

Vibration Certification Case Studies Vertical Pump Machinery Controlled with Variable Frequency Drives

Optimizing your hydro power plant

u m p a n d u m p i n g y s t e m p e c i a l i s t s i n c e

Observations from Several Condition Assessments of Prestressed Concrete Cylinder Pipe used at Energy Generation Facilities

CASE STUDY JHIMRUK, NEPAL

Flygt hydro turbines SMART AND COMPACT HYDROPOWER. 50 Hz

PARR. PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No SC JANUARY 2013

Consulting Services for the Planning of the Upper Kotmale Hydroelectric Power Station in Sri Lanka.

Converting Non-Powered Dams to Produce Electricity Andrew Scott HSA10-7 The Economics of Oil and Energy March 7, 2014

Hydro Turbines ENERGY AND SAVING FROM THE WATER

Pump Vibration. Related Considerations and How Much is Too Much? MWEA Collection Systems Seminar. Steve Fehniger, P.E.

Neal E. Cammy, BLAC INC. Engineering Manager

Turbo Machines Pumps and Turbines ME 268

RELIABLE WOOD CHIPPING PTO PRODUCT CATALOGUE. Reliable machines designed for demanding users

BEAR FORCE AND RELIABILITY HORIZONTAL SHREDDER. RLZ - RHZ and RHZ plus

VALVES FOR HYDROPOWER PLANTS

CF100 BAND SCREENS REDUCE MAINTENANCE COSTS & DOWNTIME... INCREASE CAPTURE RATIO & EFFICIENCY

A few tips to be sure that rolling windtowers becomes a profitable business. (Pictures and Video are courtesy of EWP Sweden)

EXHIBIT C CONSTRUCTION SCHEDULE

Types of Hydropower Facilities

Energy 3 Frequently Asked Questions

Current meters and Pressure - Time flow measurement comparison

11/10/2009. Lake Uist - BAKER PT. Distributor from bore to penstocks Lowest level in draft tube FSL Top of surge tank.

Hydroelectric power plants

FINAL LICENSE APPLICATION Exhibit C Construction History

Power Plant History of the Pikes Peak Region. Presented by Chris Thompson

SHRI RAMSWAROOP MEMORIAL COLLEGE OF ENGG. & MANAGEMENT

SECTION PACKAGE BOOSTER PUMP STATIONS

L e s s o n 1 INTRODUCTION TO HYDROELECTRIC POWER

RESEARCH PUBLICATION NO. 18 A COMPARISON OF CATCH BASIN INLET GRATE EFFICIENCIES

Reclaiming system for flat storage applications

CUP-CVP CONCRETE VOLUTE COOLING WATER PUMP

Turbine hydraulic assessment and optimization in rehabilitation projects

STANDARDS / MANUALS / GUIDELINES FOR SMALL HYDRO DEVELOPMENT

High-powered and compact

6) Penstocks 3.25m dia and 965m long to lead a design discharge of cumecs

THE 14TH R EFUELING outage at Diablo

THE WORLD LOOKS UP TO COMPOSITE ELEVATED TANK

SPECIFICATIONS - DETAILED PROVISIONS Section Progressing Cavity Pump C O N T E N T S

Saluda Hydro Operations. William R. Argentieri, P.E. Fossil & Hydro Technical Services

Transcription:

Aspen Revisited By Alfred F.A. Patzig, HYDROPOWER TURBINE SYSTEMS INC. (HTS INC), Richmond, Virginia, USA ABSTRACT Only ten years after installing a new turbine system at their Maroon Creek hydroelectric facility in 1986, the City of Aspen, Colorado was faced once again with deciding what is the best turbine selection, after the original unit failed to meet expectations. HTS INC was asked to make recommendations and concluded that replacement with a new OSSBERGER Cross-Flow Turbine would remedy the operational problems experienced at this site with a healthy dose of reliability. What follows should serve as a guide on how to avoid costly mistakes by selecting suitable equipment the first time around, based on performance and reputation, not price alone. Figure 1: Turbine out of Commission again - this time a broken runner shaft - after ten years of intermittent operation - off to the scrap yard The Background The City of Aspen, Colorado investigated the feasibility of power generation at their existing water supply line and, in 1985, developed specifications for a Turbine/Generator package, including commissioning and start-up. After extensive information exchange between the consulting engineering firm and OSSBERGER TURBINES of Virginia, it was concluded, that a Cross-Flow Turbine was ideally suited for the variable flows that characterised this site. Flow to the Maroon Creek site is not only seasonably variable, but is also determined by the City s varying water consumption. Only water in excess of the demand for consumption could be diverted for power generation. Thus, with its high and flat efficiency curve the Ossberger Cross Flow design seemed a perfect match. Aspen Revisited page 1 1-02-11

Unfortunately, when the project was sent out for bids in 1986, price was the determining factor in awarding the bid. Instead of Ossberger, the lowest bidder, a local manufacturer who was affiliated with the Consultant, was selected to build and install the turbine with associated equipment. Figure 2: Space for the new Cross-Flow turbine is limited. The water intakeflange on the left side, the floor opening for the turbine discharge and thegenerator shaft in the background. Turbine and gearbox had to fit between. For the next ten years, site operation was unreliable and, even when in operation, the equipment underperformed. Broken turbine runners and shafts were repaired, but the repairs or replacements were short lived. Perhaps more importantly, the shortfall in electric generation at full and partial flows, even when the unit was operational, ended up representing a significant economic loss which could no longer be overlooked. The City finally made the decision to remedy the situation or scrap the hydro scheme altogether and asked HTS INC. for suggestions. A field trip by the Author to the Maroon Creek hydro station (Aspen revisited - 10 years later) led to a proposal to replace the broken turbine with an OSSBERGER unit. This proposal was accepted at the City Council Meeting in November of 1997 and HTS began immediately to provide the necessary services and machinery. The Challenge The powerhouse is fairly small and located near several impressive residences, occupied by the celebrated rich and famous of Aspen. Therefore, it was constructed as a log cabin in order to blend with its rustic, wooded surroundings Besides budget limits, the biggest challenge was to use as much of the existing equipment as possible without sacrificing reliability and without making major changes to the powerhouse or civil structure. Complicating the challenge was the existence of a long penstock which carries flows at high velocities and pressures, and creates the possibility of extreme overspeed conditions during emergency shut-downs. The water supply line for the City of Aspen is buried beneath a site access road and consists of a two-mile long, 39 inch concrete pipe which bifurcates and is reduced to a 30 inch steel pipe that extends to the hydro plant. Aspen Revisited page 2 1-02-11

Figure 3: Installation completed with the 450 kw induction generator in front HTS INC supplied an Ossberger Cross Flow turbine with a maximum flow rating identical to the original specification (43 cfs or 1220 lit/sec at 156 ft. or 47.5 m of head), but we made use of the existing 450 kw induction generator. The existing switchgear, head level controller and hydraulic power unit, and the pressurised pipe with by-pass line and pressure reducing valve were all left in place and reused. However, the existing butterfly/shut-off valve had to be replaced by a new gate valve designed to maintain a uniform flow pattern. Likewise, a new speed increaser with flexible couplings was needed to step-up the turbine speed to match the 1200 rpm generator speed. In order to fit the new turbine and discharge tube in the existing floor opening, it was also necessary to design and install a transition piece to connect the existing round pipe flange with the rectangular turbine intake flange. The Execution After the equipment was delivered to the site in the fall of 1998, installation was carried out by the City s Water Department under the supervision of HTS INC. The butterfly valve was replaced with a knife type valve, to fit inside the powerhouse. The Ossberger Cross Flow turbine design, which is remarkable for its efficient use of widely varying flows is equipped with two individual guide vanes, which permit effective utilisation of flows varying between 16 and 100 % of rated flow. Regulation of these guide vanes is accomplished by two hydraulic cylinders with counterweights mounted onto each guide vane arm to effect fail-safe shutdown in case of load rejection or emergency shutdown. In addition, the parallel shaft, single stage gearbox is equipped with a watercooling coil embedded in the sump. Aspen Revisited page 3 1-02-11

Figure 4 The new OSSBERGER Cross-Flow Turbine with FLENDERGearbox and flexible coupling installed at Maroon Creek Hydro offeran ideal combination to guarantee reliability and performance. Installation was quite simple, only requiring field welding of the transition piece counter flange; and the generator had to be moved a few inches back to fit. Start-up and commissioning procedures went according to plan, except for required modifications to the existing hydraulic power unit, including larger hoses and control valves to achieve the oil flow necessary for faster turbine shutdown. Due to the two-mile length of the water supply line and the high flow velocities experienced during the high flow season, it took some time to adjust the pressure release by-pass valve settings, in order to limit penstock pressure rise and generator run-away speeds during load rejection tests. The Results The refurbished Maroon Creek Hydro station has now been in continuous operation for over a year. The new installation has been very reliable and output has increased as maintenance requirements have declined. Even a famous neighbor by the name of Jack Nicholson, whose home is near the powerhouse, appears to be pleased, since he has had no more complaints about excessive noise levels after the new turbine went on line. The following table shows the dramatic increase in output and proves, that it is wiser not to select equipment by price only To have a successful hydro project it is necessary also to pay attention to product quality and the reputation of the manufacturer. Flow in cfs before(kw) after (kw) Increase (%) 43 370 465 25 21.5 150 300 100 11.3 50 150 200 Table 1: Summary of Generator Output Increase at various flows Aspen Revisited page 4 1-02-11

Figure 5: OSSBERGER Cross-Flow Turbine Type G6.039/12g Figure 6: OSSBERGER Patented Cross-Flow Turbine View of flow intake side with guide vanes split at a 1:2 ratio Drive shaft with coupling half visible on left hand side The Author Alfred F.A. Patzig is Senior Engineer and President of HYDROPOWER TURBINE SYSTEMS, INC. (HTS INC), the authorised General Representative of OSSBERGER GERMANY for North America and can be reached at TEL (804)360-7992 or htsinc@erols.com. OSSBERGER GmbH + Co Phone: 00 49 91 41 / 9 77-0 Otto-Rieder-Str. 7 FAX: 00 49 91 41 / 9 77-20 91781 Weissenburg ossberger@ossberger.de Germany www.ossberger.de Aspen Revisited page 5 1-02-11