OPTIMUM ECONOMY AND EFFICIENCY IN ENERGY CONSUMPTION DURING START-UP AND SHUT-DOWN OF 210MW THERMAL POWER STATIONS

Similar documents
Energy Efficiency: Best Practices Thermal Power Stations

Short Term Training Program for year

NUCLEAR TRAINING CENTRE COURSE 134 FOR ONTARIO HYDRO USE ONLY

BEST PRACTICES IN THERMAL POWER PLANT. Confederation of Indian Industry CII Godrej Green Business Centre, Hyderabad, India

TCN 02, Dated: WITH REFERENCE TO ABOVE FOLLOWING CHANGES MAY PLEASE BE NOTED AND COMPLIED WHILE SUBMITTING THE OFFER FOR THE SUBJECT JOB:

STEAM TURBINE-GENERATOR & AUXILLIARY SYSTEMS Presentation by: RANA NASIR ALI General Manager, Power Plants Projects, at PITCO November 02, 2017

Technology Options for Existing Coal Units

POWER PLANT- BOILER OPERATIONS SIMULATOR

Indo-German Energy Forum: Flexibility Case Study at Dadri and Simhadri An overview. Dr. Claudia Weise, December 1, 2017, Delhi

Boiler Efficiency Testing. To understand the operation of a fire tube boiler To determine the operating efficiency of the boiler

THERMAL POWER PLANT SIMULATOR TPP 200 LABORATORY EXERCISE TUTORIAL N4: INTRODUCTION TO THE HEAT PRODUCTION SYSTEM

Vibration Diagnostics

R13 SET - 1 '' ''' '' ' '''' Code No: RT31035

Your partner for the right solution

NITIN CORPORATION. 402, 4 th Floor, Bezzola Commercial Complex, V.N. Purav Marg, Sion Trombay Road, Chembur, Mumbai , India.

CHAPTER 2 STUDY OF 210 MW BOILER SYSTEM 2.1 DESCRIPTION OF 210 MW BOILER

MARAMA Webinar August 7, Angelos Kokkinos Chief Technology Officer Babcock Power, Inc.


VVER-440/213 - The reactor core

Steam Turbine Performance Improvements Through R&M

Pump selection: a real example

Modeling Techniques for Increased Accuracy

AUXILIARY POWER MEASUREMENT, OPTIMIZATION & ANALYSIS. Steag Energy Training Center EEC WORKSHOP to

Chapter 4.3: Cogeneration, Turbines (Gas, Steam)

Agenda. Two Examples from Sports. Olympic Gold Medal Winners in High Jump. CII Sohrabji Godrej Green Business Centre, Hyderabad. Energy Conservation

Protection and Change over Pump

BEE: Best Practices in Energy Efficiency in Cement Sector Ambuja Cements Ltd., Chandrapur. Presented by: Sheshmani Shukla 7 th July-2016

Best Practices Adopted By Shriram Alkali & Chemicals Jhagadia To improve Energy Efficiency. Navin Jaiswal Addl General Manager DCM Shriram Ltd

Abstract. Operational Aspects of Cycling. Introduction

IMTE AG, Switzerland Power Consulting Engineers DRY SYSTEMS FOR POWER PLANT COOLING. 1. Need for Water Conservation in Power Plant Cooling

Flexible Operation. Integrating thermal power with Renewable Energy & Challenges. Y M Babu Technical Services, Noida

Due Diligence: Efficiency Increase in Existing Power Stations - a Practice Report-

Experimental Analysis of an Regenerative Air Preheater In Boiler TPS- 1 Expansion

Steam Power Station (Thermal Station)

Combined Cycle Power Plants. Combined Cycle Power Plant Overview (Single- and Multi-Shaft) Training Module. ALSTOM (Switzerland) Ltd )*+,

IMPROVEMENTS IN P.F. COAL BOILER FOR BEST HEAT RATE PERFORMANCE VOLUME 1, ISSUE 1 AUTHOR :- A. R. KULKARNI, DIRECTOR PUBLISHED DATE :- 19/09/2009

Thermal Power Plants Modeling, Control, and Efficiency Improvement Xingrang Liu, Ramesh Bansal

Reason for variation of PLF, SOC, APC & Heat rate from CERC norms. Bokaro B Thermal Power Station

COMPUTER SKILLS : Windows, MS Office, Internet : EMPAC (Enterprise Maintenance Planning and Control) System

40 MW CPP Chanda. Energy Leadership. Presenter : Sandeep Kumar Garg

PART LOAD OPERATION- EFFICIENT AND INNOVATIVE APPROACHES

2/24/2011. Energy Efficiency. Fluid Sealing Association. The Beginning. Fluid Sealing Association

Low Emissions gas turbine solutions

Drives in Power Generation

Performance Improvement and Efficiency Optimization of an Industry through Energy Audit

Lessons Learned in Solar Thermal Power Plants

VFDs driving the boiler feed water pump of #11-13 Combined Cycled Generation Unit in Yangpu Thermal Power Plant by Bin Li

Coal-Fired Boiler Optimization

RENOVATION AND EFFICIENCY ENHANCEMENT OF PULVERIZED COAL FIRED BOILERS (3 x 35 TPH - RUSSIAN MAKE) - A Case Study

Power Engineering II. Technological circuits of thermal power plants

MEC-OS-E-1999 Deputy Commissioning, Start-up & Operation Manager PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS

OPTIMISATION OF WATER USAGES IN THERMAL POWER PLANTS AND A STUDY ON DRY COOLING SYSTEM

TGG, TBG, TEG, TUG, 3.9 TBS, Gene-Link series

PAT Target Achievement: Strategies and Practices

STORM ONE MORE TIME: FIRST APPLY THE FUNDAMENTALS! S T O R M T E C H N O L O G I E S, I NC.

Thermal Power Plant Performance Centered Operational Recommendations

NOTICE CONCERNING COPYRIGHT RESTRICTIONS

ENCON IN THERMAL SYSTEM

TGG, TBG, TEG, TUG, 3.9 TBS, Gene-Link series

1 Title of Presentation 1 January 2015 EDF Energy plc. All rights Reserved

MODIFICATIONS IN COAL PULVERISERS TO INCREASE AVAILABILITY OF COAL FIRED BOILERS (3 x 35 TPH - RUSSIAN MAKE) - A Case Study

Draft proposals for Test methods for close-coupled solar water heating systems - Reliability and safety

Appendix B. Glossary of Steam Turbine Terms

7 th NATIONAL CERTIFICATION EXAMINATION Nov FOR ENERGY MANAGERS & ENERGY AUDITORS

High Efficient Cogeneration in Seshasayee Paper -Erode

An Introduction to Central Heating Plant Planning

FOURTH-CLASS ENGINEER

METHODOLOGY FOR ENERGY AUDITS IN POWER PLANTS REGARDING ANALYSIS OF ELECTRICAL ENERGY CONSUMPTION

ENERGY EFFICIENCY BENCHMARKING FOR CEMENT INDUSTRY- IMPROVEMENT OPPORTUNITIES

6.1 Introduction. Control 6-1

2nd Sector Learning Group (SLG) meet for Aluminium sector & Second Workshop on Best Practices in Energy Efficiency in Aluminium Sector

NATIONAL POWER TRAINING INSTITUTE (Ministry of Power, Govt. of India) An ISO 9001:2000 & ISO Organization

COMMISSIONING BEST PRACTICES AN EXPERIENCE SHARING

Chapter 3.7: Cooling Towers

GEOTHERMAL POWER PLANTS: OPERATION AND MAINTENANCE

SUMMER 15 EXAMINATION

By Order of A W Graham Esq and R A Croxen Esq of KPMG LLP the Joint Administrators of Aylesford Newsprint Ltd

DONGFANG ELECTRIC CORPORATION LIMITED. Dr. Harry Chen, Vice President April 20 th, 2012

Current Steam Turbine Technology and its Applicability in the Pulp and Paper Market

Chapter Six{ TC "Chapter Six" \l 1 } System Simulation

Downsizing a Claus Sulfur Recovery Unit

NATIONAL CERTIFICATION EXAMINATION 2004 FOR ENERGY MANAGERS

Company Introduction HEATERS. Joint Venture: TIME FOR A COOL CHANGE

Operational flexibility enhancements of combined cycle power plants

SHRI RAMSWAROOP MEMORIAL COLLEGE OF ENGG. & MANAGEMENT B.Tech. [SEM IV (ME-41, 42,43 & 44)] QUIZ TEST-1 (Session: )

NTPC-SAIL POWER COMPANY PRIVATE LIMITED (A Joint Venture of NTPC & SAIL)

ENGENIUS ERECTORS PVT. LTD. POWER PLANT ENGINEERS

Impact of novel PCC solvents on existing and new Australian coal-fired power plants 1 st PCC Conference, Abu-Dhabi

Best Energy Practices Implementation in Seshasayee Paper

Power Optimization Center Leveraging plant process data for advanced analytical diagnostics. June 16, 2016

Energy Analysis of 12.5 MW Co-generation plant at Porbandar

ADVANCES IN HIGH PRESSURE COGENERATION

MEC-MOS-E-2004 Gas Turbine Maintenance Engineer PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS

Pinch Analysis for Power Plant: A Novel Approach for Increase in Efficiency

GLIMPSES OF IMPROPER WATER CHEMISTRY IN A SUBCRITICAL PULVERIZED COAL FIRED BOILER AT A THERMAL POWER PLANT

7 th NATIONAL CERTIFICATION EXAMINATION Nov FOR ENERGY MANAGERS & ENERGY AUDITORS

Savings effected in cost of generation through control of

THERMAL POWER PLANT- 2X17.5 MW

ORGANIC RANKINE CYCLE TECHNOLOGY PRODUCTS AND APPLICATIONS APRIL 2013 EAR 99 - NLR

New Requirements for Steam Turbines due to Renewable Energy Innovative Concepts for Thermal Power Plants

Transcription:

OPTIMUM ECONOMY AND EFFICIENCY IN ENERGY CONSUMPTION DURING START-UP AND SHUT-DOWN OF 210MW THERMAL POWER STATIONS I. P. S. PAUL, 1 S. P. SABBERWAL 2 and S. C. KAUSHIK 2 m Joint Director, Materials Technology Division, Central Power Research Institute, CRTL, P.B. No. 9401, Sir C. V. Raman Road, Bangalore 560 094, India and 2Centre of Energy Studies, Indian Institute of Technology, Haus Khas, New Delhi 110 016, India (Received 31 August 1994; received for publication 9 June 1995) Abstract--The paper reports the results of investigations for reduction in auxiliary power for reliable running of Indian thermal power generation plants with optimum economy and efficiency in power consumption. The problems during start-up, loading and shut-down, leading to delays, thus higher energy consumption, and measures to be adopted to overcome the same have been described. Boiler feed pump Condensate extraction pump Energy conservation Forced draft fan High energy arc Induced draft fan Power station engineer Thermal power station 1. INTRODUCTION Auxiliary power consumption is quite high in all Indian power stations, and as such, there is substantial scope for its minimization. In order to study, analyse and recommend remedial measures, the following three sections are made for 200/210 MW units: (1) Problems during start-up and shut-down leading to delay and measures adopted to overcome the same. (2) Various measures to be adopted for reduction in auxiliary energy consumption during normal load. (3) Factors responsible for low average load operation leading to high auxiliary power consumption as a percentage of generation and remedial measures thereof. 2. SITE TRIALS ANALYSIS OF PROBLEM OF DELAYS The problems contributing to delay in starting/shut-down of the unit, thus leading to high energy inputs without power generation, have been analysed in the following four headings: (1) boiler header blow-down and silica clearance (2) turbine expansion problems (3) problems in ignitors and oil guns (4) longer generator dry out period after overhaul. The time taken from the start of the first auxiliary to full loading of the unit almost always exceeds the given time in standard start-up curves recommended by suppliers like Bharat Heavy Electricals Ltd (BHEL). Since most of the auxiliaries are kept running from the beginning of the start-up period, the extended time calls for analysing the problems. In this regard, cold, warm and hot start-up curves need to be studied. The time taken to start is invariably more than the given time in, say BHEL, start-up curves, as given in Fig. 1. It is possible to avoid the delay if start-up is performed according to the curves supplied by the suppliers. 495

496 PAUL et al.: ENERGY CONSUMPTION OF THERMAL POWER STATIONS ~For gas/\rt ap ~ [ Air inlet temp. AI\I\ 163 "-' c Outlet Instrument~~air supply - ~ ~-i?qting~ Welding generator set Fig. 1. Generator dry-out by hot air circulation-scheme. 2.1. Header blow-down and continuous blow-down (CBD) operation (1) BHEL had earlier recommended blow-down at 10, 20, 30, 40 and 60 kg/cm ~. Delay was being caused as the boiler was required to be banked every time. Now, it is recognized that the number of blow-downs can be reduced without adverse effects on boiler water quality and silica clearance. Only one header blow-down at 20 kg/cm 2 is sufficient. (2) Flushing of high pressure (HP) heaters during cold start-up should be continued. (3) Continuous blow-down (CBD) flow at equilibrium conditions can be calculated as per the formula given below: CBD flow Concentration of solids in feed water Total steam flow. Concentration of-concentration of solids in CBD solids in feed water The concentration of solids/litre of water can be determined by evaporating the water and weighing the solid residuals. (4) Unit drain tank should not be allowed to get contaminated, which may result from undesirable mixing of general service (GS) water lines with demineralized (DM) water circuits. 2.2. lgnitors and oil guns After trip-out of the unit, the re-light of the boiler gets delayed due to a problem in establishing the ignitors and oil guns. It affects, in turn, turbine parameters, resulting in delay of unit start-up. Ignitors need consistent high field maintenance. 2.3. Problems and remedial measures The problems and remedial measures for three types of ignitors, i.e. oil ignitors (which use differential pressure for flame scanning), ionic flame monitoring (IFM) and high energy arc (HEA), are analysed below: (1) Chocking off/leaking off differential pressure (d.p.) lines. (2) Deformation of ignitor horns causing variation in d.p. settings. (3) Clinker formation at the tip. (4) James Burry valves gear train jamming and motor brush damages. (5) Soot deposits in spark gaps requiring frequent cleaning of spark plugs.

PAUL et al.: ENERGY CONSUMPTION OF THERMAL POWER STATIONS 497 2.4. Remedial practices (1) Daily cleaning of ignitor spark plugs. (2) Daily checking of cleaning of James Burry valves, i.e. cleaning of gear trains, checking of motor brushes, etc. (3) Daily blowing of d.p. sensing lines by air and sometimes cleaning by rods. (4) Oil guns be purged continuously for 8 h by steam whenever it is withdrawn or on boiler tripping, thereby no delays in next light-up or for taking guns in service. (5) Regular maintenance will increase their availability. (6) James Burry valves be modified with ball bearings, and there will be no jamming problems. (7) For frequent failure of IFM cards, replacement of transformers is the only solution. 3. DELAY DUE TO TURBINE EXPANSION AND ASSOCIATED PROBLEMS The expansion problem of the turbine during rolling causes delay in start-up and loading of the unit which in turn, causes unnecessary auxiliary energy consumption. The problems are listed and analysed below: (1) Flange and stud heating is given during cold rolling at about 1200 RPM to arrest turbine expansion. For early effect, both HPT and IPT stud and flange heating is given simultaneously. Delay in boiler light-up after trip-out of the unit causes severe negative expansion problems. Rotor heating is given every time during hot rolling. (2) Common rotor heating systems for all 210 MW units need to be introduced so that, during hot rolling, rotor heating steam of desired parameters can be made available. Proper isolation between units needs, however, to be ensured. (3) Operating instructions of suppliers like BHEL, ABB, NEI, Siemens and GEC, needs to be followed for flange, stud and rotor heating. 4. DELAY DUE TO GENERATOR WINDINGS DRY-OUT Generator windings need to be dried after long shut-down/overhaul in the shortest possible time. It is done by rolling the turbine, running it for hours, causing enormous fuel and auxiliary power consumption. In spite of satisfactory values of insulation resistance (IR) and absorption coefficient, the polarization index (PI) remains low, necessitating drying out of the generator by rolling with dry compressed air at 0.2 kg/cm 2. It generally takes 24 h or more to get suitable PI values of more than two, leading to undesirable fuel oil consumption. It clearly requires study to minimize the dry-out time as developed in a power plant mechanism illustrated in Fig. 1, eliminating the need for rolling the unit for dry-out. 5. STARTING/LOADING AND STOPPING OF POWER GENERATING UNIT WITH MINIMUM NUMBER OF AUXILIARIES Higher consumption of works power during starting of the unit is compounded by starting both ID-FD fans, CW pumps, etc. and being kept running throughout the extended start-up period. During the start-up period, one set of auxiliaries is required to save energy. Two pumps or fans running in parallel, when only one is required, amounts to wastage equivalent to the "no load losses" of the second auxiliary. The utility of the second pump running is just about 30% benefits as compared to the first pump only in operation. No load losses, in the case of pumps, are more than 50% of the full load power. This requires studies for standardization of starting and stopping of various auxiliaries which is discussed below: 5. I. Timely running pays Starting of the auxiliaries much earlier than required times MUST NOT BE DONE.

498 PAUL et al.: ENERGY CONSUMPTION OF THERMAL POWER STATIONS 5.2. Air cycles Only one cycle, i.e. one induced and forced draught (ID and FD) fan, should be run during cold and warm periods. 5.3. PA fans Both primary air (PA) fans are started before putting in the first coal mill, while only one fan is sufficient for two mills operation. 5.4. Boiler feed pump (BFP), condensate extraction pumps (CEP) and starting oil pumps (SOP) The BFP is not required to be run during initial light-up of the boiler. Boiler filling can be done by emergency lift for filling pump. The first BFP can be started at about 20 kg/cm 2 boiler pressure, while the second is required after 80-100 MW load for 210 MW unit. Both CEPs may not be necessary during steam conditioning of the turbine. It is better to avoid the practice of starting the SOP during withdrawal of turbine and continuing its operation for hours together. At the time of turbine trip, the SOP is not required to be started. The a.c. lube oil pump needs to be started as soon as the speed reaches 2800 RPM and continued until the turbine cools down properly by barring gear. 5.5. Circulating water pumps (CWP) Both CW pumps are not required during start-up, except in isolated cases. CW pumps, in general, should be taken into service just before steam conditioning. Only one pump may be sufficient during rolling, synchronization and part load operations. The second pump is needed when improvements in vacuum will offset the heat equivalent of power consumption by the second pump. The running cost must be offset by extra output from the main unit. 5.6. Cooling tower (CT) fans operation Operate cooling tower (CT) fans, say five initially, and later additional fans may be run depending upon the CW temperature and condenser vacuum. CT fans should be stopped one after another on withdrawal of the unit. 5. 7. Forced cooling of boiler and turbine Sufficient time can be saved within the constraints of the cooling curves (Fig. 2) by forced cooling of the boiler during outage. It would benefit in reduced shut-down time and, hence, early availability of the unit. For turbines, natural cooling is preferred. The key analysis of reductions in auxiliary time for ENCON (energy conservation) leads us to standardization of practices, which is presented below. 6. STANDARDIZATION APPROACHES FOR MINIMUM NUMBER AND TIMELY RUNNING OF AUXILIARIES WHILE START-UP/SHUT-DOWN OF UNIT Keeping in view safety, reliability and efficiency, the following standard practices are suggested. (1) Run only one air cycle for boiler light-up and till synchronization, while the second ID fan is run before taking the first coal mill and the second FD fan starts at about 50 MW. (2) One PA fan may be taken on load in the beginning for taking the first coal mill, the second taken by PA header pressure as the subsequent coal mills are cut-in. However, they may perform suitable to individual TPS needs. Air heater seals and damper leakage shall be attended during every shut-down of sufficient duration. (3) Boiler filling initially should be done by fill pump. The first BFP can be started at 20 kg/cm 2 and the second at about 100 MW. (4) Operate only one CW pump during starting while the second pump is run at a point when the heat rate increases due to loss of vacuum exceeding the additional CW pump's electricity use. At times, both CW pumps are required to be run for vacuum pull-up. However, the economical unit load for start of the second CW pump may be ascertained for a particular power station. It can be around 90 MW, but must withdraw one pump after the unit is shut-down. Also both CW pumps should be stopped if the unit is stopped for maintenance beyond 36 h.

PAUL et al.: 165 150 2 0 0 ~ ENERGY CONSUMPTION OF THERMAL POWER STATIONS Time lapse - pressure reduction (rain) 135 120 105 90 75 60 45 30 15 0 499 100 90 80 70 60 50 Note: time lapse from 0.7 to 0 ATG on decreasing pressure = 56 min 40 30 < I.o 20 10 9 8 7 6 5 ~' Note: time lapse from :~-~ ~ 0 to 0.7 ATG on increasing ~ pressure = 42 min 4 1 0 42 60 75 90 105 120 135 150 165 180 Time lapse - increasing pressure (min) Fig. 2. Maximum allowable rate of pressure change for normal start-ups and shut-downs. (5) The starting oil pump should not be started during withdrawal of the turbine. Only the a.c. lube oil pump needs to be started at 2800 rpm. (6) On an average, for all plants, all CT fans initially need not be taken into service. (7) Both CEPs should be taken into service before vacuum pulling. (8) Forced boiler cooling be done within the constraints of cooling curves given by suppliers (say BHEL, ABB, etc.). 7. BENEFITS OF STANDARD PRACTICE Depending upon the site equipment conditions above stated standard operation practices should be followed for generating more power, and its applied benefits are detailed below:

500 PAUL et al.: ENERGY CONSUMPTION OF THERMAL POWER STATIONS (1) By adopting single cycle operation, a saving of 15% energy consumption by the second sets of FD, ID, PA fans and CW pumps is ensured during light-up and loading periods. (2) The time taken for unit start-up is reduced, leading to savings in auxiliary energy consumption. 8. CONCLUSIONS (1) With the site investigations conducted and discussions held, it has been found that, during light-up and withdrawal of the unit, only one set of auxiliaries should be run to economize on power consumption. (2) Since the time taken to start the unit is invariably more than the given time in the start-up curves supplied by manufacturers, the delay can be curtailed to the maximum extent possible by performing timely operations. (3) Poor maintenance or delayed mal-operations cause longer start-up and loading of the unit. This delay leads to unproductive auxiliary energy consumption. Analysis of the problems, followed by proper remedial measures, would help in immense savings of energy. (4) Specific action oriented strategies can deliver excellent results, except whenever implemented in isolation, as plant operations are inter-linked and inter-dependent. Acknowledgement--I. P. S. Paul expresses his sincere thanks to the authorities of CPRI for their valuable encouragement and kind permission to publish this paper. REFERENCES 1. Thermal Power Station Generation Course Manuals of NPTI--units at Badarpur (New Delhi), Durgapur, Nagpur and Neyveli (1985-1992). 2. CBIP Report on study of minimum running of auxiliaries for safe running of power stations with best economy in power consumption, pp. 40-89 (1991). 3. S. P. Sabberwal, S. C. Kaushik and I. P. S. Paul. Indo-Japan International Conference in Petroleum and Petro Chemical Sectors, New Delhi, pp. 40-44 (1990).