Proposed Changes to the Annual Gas Transmission DOT Report Concerning MAOP Verification. NGA Fall Operations Conference October 4, 2012 Mary Holzmann

Similar documents
Proactive Assessment on Vintage Pipelines 2013 OGA Technical Workshop

PHMSA 2011 reporting requirements March 2012

PHMSA Proposed Rulemaking Safety of Gas Transmission & Gathering Lines Rule. October 2016

Pipeline Records - - Lessons Learned. The Changing Industry Landscape and Transmission Records Implications NGA Operations Conference April 3, 2012

Maximum Allowable Operating Pressure (MAOP) & Integrity Verification Process (IVP)

June 2009 Portland, Oregon Wayne St. Germain U.S. DOT/PHMSA T&Q

Regulatory Update - 1 -

Notice of Proposed Rulemaking (NPRM) Huy Nguyen Western Region

PHMSA Update: Aging Infrastructure and Integrity Verification Process

ASSET INTEGRITY Project Case Studies

BEFORE THE PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION UNITED STATES DEPARTMENT OF TRANSPORTATION WASHINGTON, D.C.

API Pipeline Conference San Antonio, Texas

Regulatory Review PHMSA Regulatory Update. Tom Finch Western Region CATS Manager

SUMMARY OF TRANSMISSION INTEGRITY MANAGEMENT PROGRAM

PHMSA Rule Update. David Johnson November 14, 2018

Delmont Line 27 Incident Update

Pipeline Safety Compliance

U.S. DOT Pipeline and Hazardous Materials Safety Administration

Natural Gas Pipelines The State of Pipeline Safety

Pipeline Safety Update

Pipeline Safety Update

PHMSA rule update. David Johnson November 1, 2017

Integrity Program Evaluation Using Meaningful Performance Metrics

Industry Guidance on Records Review for Re-affirming Transmission Pipeline MAOPs

Public Workshop on Integrity Verification Process (IVP)

Gas Transmission MAOP Verification Integrity Verification Process Oklahoma CC Pipeline Safety Conference

American Petroleum Institute th St, NW Suite L St, NW Washington, DC Washington, DC December 1, 2017

Natural Gas Gathering Lines. John Williams Director Service Monitoring and Enforcement Department

Liquid Petroleum Pipelines Safe, Efficient and Improving

Smart Modernization: Infrastructure Replacement & Expansion Update. NARUC Staff Subcommittee on Accounting and Finance, 2016 Fall Conference

Interstate Natural Gas Association of America. INGAA Action Plan. INGAA Integrity Management Continuous Improvement

Transmission Integrity Planning Best Practices

Before the Pipeline and Hazardous Materials Safety Administration United States Department of Transportation Washington, D.C.

PHMSA = Pipelines and Hazardous. RITA = Research and Innovative Technologies Administration

National Academy of Sciences

Control Information: (copy and fill-in for each Operator)

Gas Pipeline Safety March 2012

The INGAA Foundation

INGAA Foundation, Inc. Construction Safety and Construction QA/QC Workshop Houston, Texas. PHMSA Update on Construction and Inspection March 21, 2012

ILI: An Improvement Over Pressure Testing for Pipeline Integrity Management

PPTS OPERATOR ADVISORY: REPORTING INTEGRITY MANAGEMENT PROGRAM ACTIVITY

Pipeline safety regulations apply to all pipelines that transport either flammable gas or hazardous liquids where the product affects interstate

With New Regulations Coming (Maybe), Will You Adopt or Adapt? Matthew Thomas, Novara GeoSolutions Jacob Parakadan, Enbridge

Preliminary Regulatory Impact Assessment. Notice of Proposed Rulemaking - Pipeline Safety: Safety of Gas Transmission and Gathering Pipelines

An Update on the Gas Industry

From the desk of G. A. Aaker, Jr., PE.

Pipeline Safety: Clarification of Terms Relating to Pipeline Operational Status.

Pipeline Safety Trust Annual Conference New Orleans, Louisiana October 20, 2016

Hazardous Liquid Pipeline Integrity Verification Process (HL IVP) Overview

PIPE GRADE DETERMINATION AND MAOP VALIDATION USING SOPHISTICATED SCRAPER TECHNOLOGY

NAPCA Workshop August 19, 2010 Houston, Texas Kenneth Y. Lee Office of Pipeline Safety

Pipeline Safety: Plastic Pipe

DEPARTMENT OF TRANSPORTATION BEFORE THE PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION

Gas Transmission NPRM. David Johnson November 10, 2016

Russ Davis, Jim Redmon, Nestor S. Makarigakis and Adam Reale, MISTRAS Group, Inc., USA,

Request for Proposal. Pipeline Safety Management System LDC Development and Implementation Northeast Gas Association

PHMSA Update on Public Awareness

What s Coming Down the Pipe? Pipeline Safety & Natural Gas Utility Efforts M a y 21, 2 0to 15 Upgrade Aging Infrastructure

DEPARTMENT OF TRANSPORTATION

NCSL Natural Gas Policy Institute

Cost of Compliance Challenges with Materials Verification

Gas Gathering Lines - Managing Risk

PIPELINE INSPECTOR TRAINING PROGRAMS

Underground Natural Gas Storage Safety Regulation. Mary L. McDaniel, P.E. Baker Engineering and Risk Consultants, Inc Oakwell Court Suite 100

This Part prescribes requirements for the REPORTING of:

DOT Proposes Tougher Safety Regulations For Hazardous Liquids Pipelines

1155 North State Street, Suite 609, Bellingham, WA Phone Fax

STANDARDIZED PIPELINE RISK COMPARISON AND PREDICTION

PHMSA Pipeline Safety Program Update

PRELIMINARY STATEMENT

Testimony of Ronald W. Jibson Vice President of Operations Questar Gas Company

Re: NARA Incorporation by Reference

PHMSA DIMP AUDIT FORM 24

U.S. Department of Transportation Pipeline and Hazardous Materials Safety Administration

BEFORE THE UNITED STATES DEPARTMENT OF TRANSPORTATION PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION WASHINGTON, D.C.

Kevin C. Connors Pipeline Program Supervisor

Natural Gas Infrastructure Replacement and Expansion Efforts

David Spangler CATS Coordinator Office of Pipeline Safety (202)

1220 L St., NW Washington, DC Washington, DC January 8, 2016

PIPELINE SAFETY MANAGEMENT SYSTEM Annual Report

Agency Request for Regular Processing of Collection of Information by the Office of Management and Budget

40 CFR Parts 1500, 1501, 1502, 1503, 1504, 1505, 1506, 1507, and Update to the Regulations for Implementing the Procedural Provisions of the

API Recommended Practice for Rural Onshore Gas Gathering Lines Forward

Pipeline Surveyor Certification 102

Pipeline Operational Status. API Recommended Practice 1181 First Edition

STATE OF NEW JERSEY Board of Public Utilities Two Gateway Center Newark, NJ

Plastic Pipe Timeline

2012 Distribution Best Practices Benchmarking Company Profile Data Packet

Introduction. Background

Recent & Proposed Rulemakings

Regulatory Agenda and Notices RSPA / OPS

SAN DIEGO GAS & ELECTRIC COMPANY SOUTHERN CALIFORNIA GAS COMPANY

Colonial Pipeline Company - Managing Operational Risk

22 January Division of Dockets Management (HFA 305) Food and Drug Administration 5630 Fishers Lane, rm Rockville, MD 20852

PPTS OPERATOR ADVISORY:

March 6, Docket No. PHMSA : Pipeline Safety: Miscellaneous Changes to Pipeline Safety Regulations

VALLEY LATERAL PROJECT. RESOURCE REPORT 11 Reliability and Safety. FERC Docket No. CP

U.S. DOT Pipeline and Hazardous Materials Safety Administration

Transcription:

Proposed Changes to the Annual Gas Transmission DOT Report Concerning MAOP Verification NGA Fall Operations Conference October 4, 2012 Mary Holzmann

National Grid In the US, we serve 3.4 million customers over a network of nearly 32,000 miles of pipe throughout New York, Massachusetts, Rhode Island. We have just recently sold our New Hampshire Assets. 2

Background Just in case anyone is not that closely involved in with the Annual Report for Gas Transmission and Gathering Systems, Operators went through some major Transmission report changes that PHMSA made to the 2010 Reports. PHMSA combined the Annual Reports with the Transmission Integrity Management Program Reports while also requiring Operators to include far greater detail in the combined report on pipe inventories by class location and %SMYS and additional Integrity inspection and repair details. PHMSA implemented a switch over to using their new Portal process which requires users to obtain Portal access in order to file reports. PHMSA had extended the 2010 Report deadline to August 2011 due to the extent of the changes and switching to their new computer system. The 2011 reports were due March 15, 2012 (as usual, but this resulted in a shortened time frame between the 2010 and 2011 reports. The changes to be discussed here are NEW CHANGES impacting the next Annual Reports which cover 2012 pipeline data and the MAOP verifications as well as pipeline piggability. Operators need to be aware of how this new data needs to be broken down so proper data is collected for submission to DOT/PHMSA. 3

Update on Annual DOT Report as of 9/21/2012 On April 13, 2012, (77 FR 22387) PHMSA proposed a number of revisions to the Annual Report for Gas Transmission and Gathering Systems (PHMSA F 7100.2-1) some minor, some quite significant. The initial comment period ended 6/12/2012 PHMSA received 12 comments in response to that notice. Operators: Alliance Pipeline, Energy Transfer, National Grid, Paiute, SCANA Corporation, and Southwest Gas Trade Associations: NGA, AGA, INGAA, API, AOPL and Texas Pipeline Association 1 Public commenter 4

Update on Annual DOT Report as of 9/21/2012 Just recently, on 9/21/2012 PHMSA published the 30- day Notice (77 FR 58616) in response to the comments, and provides the public with an additional 30 days to comment on their modified revisions to the forms and the instructions, and to announce that the revised Information Collections will be submitted to the Office of Management and Budget (OMB) for approval. PHMSA s current work on the annual report should be considered as complete. The comments from this thirty day notice go directly to the OMB. 5

Update on Annual DOT Report as of 9/21/2012 Operators should consider these forms to be final because OMB is unlikely to change the forms unless critical changes are deemed necessary. All prior comments and PHMSA s amended Annual Report form and instructions in response to those comments can be found on the docket at: http://www.regulations.gov Docket number PHMSA-2012-0024 Operators should use the revised Report form and instructions to finalize their plans for submitting MAOP verification data (and in preparation for the 2012 Reports). 6

7

There are Other Changes, however. This presentation covers those areas involving the MAOP verifications only. I have provided NGA with the entire Annual Report changes and Instructions. These will be available through NGA after this conference. NGA will discuss if any further comments should be submitted before the deadline (October 19) regarding the new changes in an upcoming conference call. 8

Highlights of the DOT Report Changes and MAOP Verification PHMSA Administrator Quarterman looking on as President Obama signs the Pipeline Safety, Regulatory Certainty, and Job Creation Act in January 2012

Highlights of the DOT Report Changes and MAOP Verification PHMSA has determined that the most appropriate method to collect MAOP verification information is through the next Gas Transmission Annual Report. Owners or operators must submit the required MAOP verification information using the new Parts Q and R of the revised Annual Report. At this time, PHMSA has decided not to extend the Report deadline of March 15, 2013 regardless of the many comments received on the issue. PHMSA is taking this approach to ensure that owners or operators comply with the requirement to submit the data not later than 18 months as per the Pipeline Safety, Regulatory Certainty, and Job Creation Act of 2011(before July 2013). 10

Highlights of the DOT Report Changes and MAOP Verification PHMSA has determined that mileage for records reviews that are not complete should be identified as mileage without records to avoid confusion and comply with the reporting requirements. Therefore, PHMSA has revised the instructions to specify that pipeline segments that have not been verified be reported under the appropriate w/out Recds column. After the March deadline, operators can submit Supplemental Reports if necessary to update their MAOP verification data previously submitted to PHMSA. 11

Major Changes to the Forms and Instructions involving MAOP are as Follows: PHMSA intends for operators to report mileage under the single code section heading used to establish the MAOP. In some scenarios, 49 CFR 192.619(a)(1) through (4) may all have been considered when establishing MAOP, PHMSA expects the mileage to be reported under the single heading for the final methodology that was used to determine the MAOP value. PHMSA has revised the instructions to include this clarification. 12

Where in the Annual Gas Transmission DOT Report do Operators Record the Miles by Method Used to Determine MAOP Verifications? What Changes Were Made or Amended Concerning the Report? Brand new Part Q Gas Transmission Miles by 192.619 MAOP Determination Method

Part Q Gas Transmission Miles by 192.619 MAOP Determination Method In the April 13, 2012 (77 FR 22387) Federal Register notice for this information collection revision, PHMSA expressed intent to collect Part Q data only for Class 1 and 2 HCAs and all Class 3 and 4 locations. All of the Class 1 and 2 not in HCA rows should have been blacked-out in the w/out Recds column. PHMSA has revised the report form and instructions to not collect the reporting of mileage without complete records in Class 1 and 2 locations which are not within HCAs. 14

Part Q The Amended Version 9/21/2012 15

PART Q Gas Transmission Miles by 192.619 MAOP Determination Method Amended Instructions In the Total columns, operators report transmission pipeline miles by the subsection of 192.619 serving as the limiting factor for establishing MAOP and by each combination of class location and HCA. A short explanation of each 192.619 subsection for MAOP determination methodology [follows] 16

192.619 Methodology Description Given in Part Q Instructions 17

Review of Class Location and HCA definitions are Given in Part Q Instructions 18

Part Q - Instruction Detail Transmission miles may only be entered under a single subsection of 192.619. In some scenarios, 192.619(a)(1) through (4) may all have been considered when establishing MAOP, but PHMSA expects that one value is lower than the others and was used to establish MAOP. In other scenarios, 192.619(c) could be used to set MAOP, regardless of the values in 192.619(a)(1) through (4). For each combination of class location and HCA shown on the form, report the miles in each MAOP category. The sum of all Total columns for 192.619 subsections and Other for each class location must be consistent with the class location data reported in Part K. If miles are entered in the Other column, enter text describing the Other method(s) used to establish MAOP. 19

Part Q Instruction detail continued For each combination of class location and HCA, except Classes 1 and 2 outside HCAs, report the transmission miles for which the operator lacks complete records to verify the MAOP in the w/out Recds column. The value in the w/out Recds column must be less than or equal to the value in the Total column for each combination of class location and HCA. For the purpose of this part, verification records are records that can be used to validate the MAOP for the subject pipelines such as: as-built drawings, alignment sheets, specifications, and all design, construction, inspection, testing, maintenance, manufacturer, or other related documents. These records should be traceable, verifiable, and complete. For miles of transmission pipeline for which the operator has not completed the records review, include these miles in the w/out Recds column. See PHMSA Advisory Bulletin (ADB) 2012-06 for additional details: http://www.phmsa.dot.gov/staticfiles/phmsa/downloadablefiles/pi peline/regulations/advisorybulletins/ad-12-06.pdf 20

Reporting of miles MAOP using 192.619 (d) When reporting transmission miles for which 192.619(d) was used to establish MAOP, include miles of pipeline installed pursuant to a PHMSA special permit allowing operation up to 80% SMYS in Class 1 areas. From 2006 through 2010, PHMSA issued fifteen of these special permits with conditions equivalent to pipeline installed under 192.619(d). 21

Where in the Annual Gas Transmission DOT Report do Operators Record the Miles Pressure Tested? What Changes Were Made or Amended Concerning the Report? Brand new Part R - Gas Transmission Miles by Pressure Test (PT) Range & Ability to use Internal Inspection Tools

Part R - Gas Transmission Miles by Pressure Test (PT) Range and Internal Inspection PHMSA agrees with the commenters and has expanded Part R to collect data about the mileage of pipe in three bands of pressure tests; miles tested to more than 1.25 times the MAOP, miles tested to less than 1.25 times the MAOP but greater than or equal to 1.1 times the MAOP, and miles with a pressure test less than 1.1 times the MAOP or no pressure test. PHMSA also agrees that the test medium is irrelevant and has amended the form and instructions accordingly. 23

Part R continued Operators are required to report in each pressure test band the number of miles able to accommodate internal inspection and the number of miles not able to accommodate internal inspection. PHMSA has amended the form and instructions for Part R in response to comments to clarify the phrase not able to accommodate the passage of instrumented internal inspection devices. As a result, PHMSA has revised Part R to collect Miles Internal Inspection ABLE and Miles Internal Inspection NOT ABLE. The instructions include the following definition for Internal Inspection ABLE A length of pipeline through which commercially available devices can travel, inspect the entire circumference and wall thickness of the pipe, and record or transmit inspection data in sufficient detail for further evaluation of anomalies. 24

Part R - Amended version 9/21/2012 25

Part R Amended Instruction Details 9/21/2012 For Part R, enter miles of gas transmission pipe in each of the three pressure test ranges with each range divided into miles able to be internally inspected and miles unable to be internally inspected. All gas transmission miles must be reported in this part. The miles entered for each class location must be consistent with the class location data entered in Part K. If an operator is uncertain whether a gas transmission pipeline has been subjected to a post-construction pressure test, report the miles in the PT < 1.1 or No PT section. 26

Part R Amended Definition for Clarification Miles Internal Inspection ABLE means a length of pipeline through which commercially available devices can travel, inspect the entire circumference and wall thickness of the pipe, and record or transmit inspection data in sufficient detail for further evaluation of anomalies. If an operator is uncertain whether a gas transmission pipeline is able to be internally inspected, report the miles in the Miles Internal Inspection NOT ABLE column. 27

Older Versions of Sections Q & R as Proposed in June 2012 Notice have been Changed Be Sure to use the Revised Format and Amended Instructions to Ensure Proper Data is Collected for DOT Reports due March 2013

Part Q originally proposed - since revised. Be sure to use newest version 29

Part R originally proposed - since revised. Be sure to use newest version 30

Questions? Comments? Discussion? 31