PIP PCEPA003 Process Analyzer System Field Installation Guidelines

Similar documents
PIP STF05520 Details for Pipe Railing for Walking and Working Surfaces

PIP STF05521 Details for Angle Railings for Walking and Working Surfaces

REAFFIRMATION WITH EDITORIAL REVISION September Process Industry Practices Insulation. PIP INIH1000 Hot Insulation Installation Details

COMPLETE REVISION September Process Industry Practices Piping. PIP PNSM0120 Purchasing Requirements for Bolting

COMPLETE REVISION January Process Industry Practices Electrical. PIP ELIGD000 Grounding Installation Details

EDITORIAL REVISION January Process Industry Practices Vessels. PIP VEFV1100M Vessel/S&T Heat Exchanger Standard Details (Metric Units)

REAFFIRMATION WITH EDITORIAL REVISION October Process Industry Practices Insulation. PIP INIC1000 Cold Insulation Installation Details

PIP STF05511 Fixed Industrial Stairs

PIP VEFV1100 Vessel/S&T Heat Exchanger Standard Details (U.S. Customary Units)

PIP VEFV1100 Vessel/S&T Heat Exchanger Standard Details (U.S. Customary Units)

PIP PNSM0115 Purchasing Requirements for Pipe

Electrical PIP ELILS000 Lighting and Receptacle Installation Details for Class I, Division 2, Class II, Division 2, and Unclassified Areas

COMPLETE REVISION October Process Industry Practices Piping. PIP PNSC0036 High Density Polyethylene (HDPE) Piping Installation Specification

PIP INSA1000 Acoustic Insulation Systems Specification

PIP STE05501 Fixed Ladders and Cages Design Guide

PIP STF05501 Fixed Ladders Fabrication Details

EDITORIAL REVISION August Process Industry Practices Insulation. PIP INEG2000 Guidelines for Use of Insulation Practices

PIP PNC00001 Pipe Support Criteria for ASME B31.3 Metallic Piping

COMPLETE REVISION November Process Industry Practices Architectural. PIP ARS08111 Standard Steel Doors and Frames Supplier Specification

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:

PIP RFTF1000 Ceramic Fiber Refractory Installation Qualification, Inspection, and Testing

PIP RFTA1000 Refractory Anchor and Accessory Installation Qualification, Inspection, and Testing

PIP ARS08111 Standard Steel Doors and Frames Supplier Specification

PIP VESSP002 Supplemental Design and Fabrication Specification for Shell and Plate Heat Exchangers ASME Code Section VIII, Divisions 1 and 2

Pipeline Systems PIP PLSC0013 Non-Destructive Examination of ASME B31.4 and B31.8 Metallic Pipelines

March Process Industry Practices Structural. PIP STE05535 Vessel Circular Platform Detail Guidelines

PIP RFTB1000 Brick Refractory Installation Qualification, Inspection, and Testing

COMPLETE REVISION November Process Industry Practices Structural. PIP STF05530 Grating Fabrication Details

PIP PNEM0001 Piping Service Index

SECTION CONDUITS AND BOXES PART 1- GENERAL. A. Work covered by this section includes the furnishing and installation of conduits and boxes.

PIP INSR1000 Installation of Flexible, Removable/Reusable Insulation Covers for Hot Insulation Service

SECTION GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY

COMPLETE REVISION June Process Industry Practices Architectural. PIP ARS08390 Blast Resistant Doors, Frames, and Related Hardware Specification

COMPLETE REVISION April Process Industry Practices Piping. PIP PNC00004 Piping Stress Analysis Criteria for ASME B31.

This product specification is written according to the Construction Specifications Institute MasterFormat, 2014 Update.

Pipeline Systems PLSC0017 Requirements for Welder Qualifications in Accordance with ASME Section IX

This product specification is written according to the Construction Specifications Institute MasterFormat, 2014 Update.

March Process Industry Practices Refractory. PIP RFIA1000 Refractory Anchor and Accessory Installation Details

A. Product Data: For surface pathways, wireways and fittings, floor boxes, hinged-cover enclosures, and cabinets.

Kaf-Tech Product Specification

SECTION UNDERGROUND ELECTRICAL CONSTRUCTION

DESIGN GUIDELINES WIRING AND CONDUITS PAGE 1 of 7

PIP PNSC0011 Installation of ASME B31.3 Metallic Piping

A. This section is intended to provide design guidelines for Utility Direct Buried Piping and Conduit Systems.

CONDUITS AND FITTINGS

PIP PNSC0035 Steam Tracing Specification

SECTION HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

PIP ARS08710 Standard Steel Door Hardware Supplier Specification

CHAPTER 11 CONDUITS AND FITTINGS

Youngstown State University

EDITORIAL REVISION March Process Industry Practices Refractory. PIP RFSM1000 Monolithic Refractory Material Specification

University of Delaware

Design Standard Conduit for Electrical Systems

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

SECTION HVAC INSTRUMENTATION AND CONTROLS INSTALLATION. (Applicable to IUPUI Only)

GV 001 Equipment Bases and Enclosures General Information

Special Specification 6292 Radar Vehicle Detection System for Signalized Intersection Control

University of Delaware

SENTINEL BARRIER - GENERAL INSTALLATION GUIDELINES

PIP RFTM1000 Monolithic Refractory Installation Qualification, Inspection, and Testing

SECTION AIR TERMINAL UNITS

1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK

SECTION CONDUITS AND BACKBOXES FOR COMMUNICATIONS SYSTEMS

MANUFACTURING TECHNICAL INSTRUCTIONS SAFETY Subject: DESIGN, MAINTENANCE AND INSPECTION OF SECONDARY ELECTRICAL DISTRIBUTION SYSTEMS

University of Delaware

SECTION CONVECTORS

SECTION PATHWAYS FOR COMMUNICATIONS SYSTEMS

SECTION FACILITY LIGHTNING PROTECTION

SECTION COMMON WORK RESULTS FOR FIRE SUPPRESSION

Ice and snow melting Pavements, roads and ramps

SECTION LOW-VOLTAGE TRANSFORMERS

Standards and Procedures Security Room Construction/Renovations At University of North Carolina Wilmington

SECTION AIR-TO-AIR ENERGY RECOVERY EQUIPMENT

SECTION COMPOSITE WALL PANELS PART 1 GENERAL 1.01 SECTION INCLUDES

3. Intermediate metal conduit (IMC). 4. Electric metallic tubing (EMT). 5. Flexible metal conduit (FLEX). 6. Polyvinyl chloride conduit (PVC).

SECTION (Master Template Final-05) ELECTRICAL BOXES. A. Provide boxes for electrical equipment and wiring devices as follows:

SECTION GROUNDING AND BONDING

STATE OF NEW JERSEY DEPARTMENT OF TRANSPORTATION TRENTON, NEW JERSEY 08625

COMPLETE REVISION May Process Industry Practices Piping. PIP PNSM0110 Purchasing Requirements for Valves

SECTION 401 WATER PIPE AND FITTINGS 2.2 POLYVINYL CHLORIDE (PVC) PIPE AND FITTINGS

Copyright 2004 and 2005 by The American Institute of Architects (AIA)

Essex County College - West Essex Campus Addition And Renovations dlb # / 11-14

SECTION COMMON WORK RESULTS FOR FIRE SUPPRESSION

DIVISION 26 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS PART 1 - GENERAL RELATED DOCUMENTS

Installation Guide. Ice and snow melting. Pavements, roads and ramps. Intelligent solutions with lasting effect. Visit DEVI.com

Underground Piping for Private Hydrants & Sprinkler Supply Line

NYULMC AMBULATORY CARE CENTER FIT-OUT PHASE 1 Perkins & Will Architects PC 222 E 41st ST, NYC Project: Issued for GMP March 15, 2017

OSU PROJECT NO PAGE 1 02 NOV 2006 SECTION SUPPORTS AND ANCHORS

D. Provide UL-approved assemblies for pipes and ducts passing through fire-rated floors, walls, or partitions as required.

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY PIPE HANGERS, Section PIPE HANGERS, SUPPORTS, AND RESTRAINTS

Trex Commercial Products page Metal Railing

Design & Construction Standards, Revised January

Engineering Specifications

Engineering Specifications

TERMS OF REFERENCE. Supply and Delivery of Prefabricated Wind Noise Reduction Systems (WNRS) and Equipment Vaults

Essex County College - West Essex Campus Addition And Renovations dlb # / SECTION CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

PATHWAYS FOR COMMUNICATIONS SYSTEMS

Electrical Metallic Tubing (EMT) Fittings

Transcription:

January 2016 Process Control PIP PCEPA003 Process Analyzer System Field Installation Guidelines

PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES In an effort to minimize the cost of process industry facilities, this Practice has been prepared from the technical requirements in the existing standards of major industrial users, contractors, or standards organizations. By harmonizing these technical requirements into a single set of Practices, administrative, application, and engineering costs to both the purchaser and the manufacturer should be reduced. While this Practice is expected to incorporate the majority of requirements of most users, individual applications may involve requirements that will be appended to and take precedence over this Practice. Determinations concerning fitness for purpose and particular matters or application of the Practice to particular project or engineering situations should not be made solely on information contained in these materials. The use of trade names from time to time should not be viewed as an expression of preference but rather recognized as normal usage in the trade. Other brands having the same specifications are equally correct and may be substituted for those named. All Practices or guidelines are intended to be consistent with applicable laws and regulations including OSHA requirements. To the extent these Practices or guidelines should conflict with OSHA or other applicable laws or regulations, such laws or regulations must be followed. Consult an appropriate professional before applying or acting on any material contained in or suggested by the Practice. This Practice is subject to revision at any time. Process Industry Practices (PIP), Construction Industry Institute, The University of Texas at Austin, 3925 West Braker Lane (R4500), Austin, Texas 78759. PIP Member Companies and Subscribers may copy this Practice for their internal use. Changes or modifications of any kind are not permitted within any PIP Practice without the express written authorization of PIP. Authorized Users may attach addenda or overlays to clearly indicate modifications or exceptions to specific sections of PIP Practices. Authorized Users may provide their clients, suppliers and contractors with copies of the Practice solely for Authorized Users purposes. These purposes include but are not limited to the procurement process (e.g., as attachments to requests for quotation/ purchase orders or requests for proposals/contracts) and preparation and issue of design engineering deliverables for use on a specific project by Authorized User s client. PIP s copyright notices must be clearly indicated and unequivocally incorporated in documents where an Authorized User desires to provide any third party with copies of the Practice. PUBLISHING HISTORY August 2000 Issued August 2006 Complete Revision January 2016 Complete Revision Not printed with State funds.

January 2016 Process Control PIP PCEPA003 Process Analyzer System Field Installation Guidelines Table of Contents 1. Introduction... 2 1.1 Purpose... 2 1.2 Scope... 2 2. References... 2 2.1 Process Industry Practices... 2 2.2 Industry Codes and Standards... 2 3. Definitions... 2 4. Pre-Installation... 2 4.1 General... 2 4.2 Receiving... 3 4.3 Civil/Structural... 3 5. Field Installation... 3 5.1 Analyzer Shelter... 3 5.2 Field Hardware... 3 5.3 Utility Piping... 4 5.4 Sample Tubing... 4 5.5 Electric Heat-Traced and Pre-Insulated Tubing... 5 5.6 Steam-Traced Tubing Bundles... 6 5.7 Sample Probe... 7 5.8 Electrical Equipment... 7 Process Industry Practices Page 1 of 8

1. Introduction 1.1 Purpose 1.2 Scope 2. References This Practice provides guidelines for the field installation of process analyzer systems. This Practice describes guidelines for field installation of process analyzer systems. Applicable parts of the following Practices and industry codes and standards shall be considered an integral part of this Practice. The edition in effect on the date of contract award shall be used, except as otherwise noted. Short titles are used herein where appropriate. 2.1 Process Industry Practices (PIP) PIP PCSPA002 - Process Analyzer System Data Sheet Instructions PIP PCSPA002-D - Process Analyzer System Data Sheet 2.2 Industry Codes and Standards 3. Definitions National Fire Protection Association (NFPA) NFPA 70 - National Electrical Code (NEC) owner: The party who owns the facility wherein the process analyzer system will be installed purchaser: The party who awards the contract to the supplier. The purchaser may be the owner or the owner s authorized agent. supplier: The party responsible for installing the process analyzer system. 4. Pre-Installation 4.1 General 4.1.1 Before installing the analyzer system equipment in the field, a pre-installation meeting should be held between the owner, purchaser, and supplier to review all associated analyzer system installation drawings. 4.1.2 If required to assist with start-up, calibration, and/or initial operation, analyzer original equipment manufacturer (OEM) service representatives and/or analyzer system vendor personnel should be scheduled. Analyzer OEM s assistance may also be required for warranty validation. 4.1.3 Installation of all analyzer equipment should be performed by trained, experienced workers. Process Industry Practices Page 2 of 8

4.2 Receiving 4.2.1 Personnel should be assigned to coordinate the arrival of equipment on site. Coordination instructions should include time, location, and date of scheduled delivery; safety requirements for driver of the delivery truck; unloading plan; storage plan; permits; ancillary equipment, etc. 4.2.2 Personnel should be assigned to verify that all equipment required for unloading and installation is present at the site. 4.2.3 Personnel should be assigned to make provisions for process analyzer systems that require immediate purging and/or power for climate control. 4.2.4 The provisions, associated field requirements, storage, and handling should be communicated to field construction personnel. 4.3 Civil/Structural 5. Field Installation 4.3.1 The analyzer system location should be verified to be in accordance with area space, elevation, and orientation requirements. 4.3.2 The foundation or platform preparation should be verified to be in accordance with purchaser s specifications. 4.3.3 The cylinder rack installation preparation (e.g., ramp access for wheeled cylinder carts, paving, and elevation of cylinder connections) should be verified to be in accordance with purchaser s specifications. 5.1 Analyzer Shelter 5.1.1 Field-mounted analyzer enclosure or shelter should be leveled and secured to support foundation. 5.1.2 Base support structure should be sealed to foundation with appropriate sealing compound. 5.1.3 For installation of a shelter without a floor, the shelter sealing gasket should be checked to ensure proper installation. 5.1.4 Ancillary shelter equipment such as awnings/rain shields, detached cylinder racks, fresh air intake, sample recovery systems, etc., should be installed. 5.1.5 The heating, ventilation, and air conditioning (HVAC) condensate drain line should be connected to the condensate drain header or sewer. Draining condensate freely on a concrete pad should not be permitted. 5.2 Field Hardware 5.2.1 Plate- or cabinet-mounted equipment locations should permit maintenance access. 5.2.2 All components should be in accordance with purchaser s specifications. 5.2.3 Clamps and brackets should be galvanized or stainless steel. Process Industry Practices Page 3 of 8

5.2.4 Tubing supports should be provided and installed with fittings, spacers, clamps, guides, and other accessories as required. 5.2.5 All sample-wetted materials should meet or exceed the materials of construction described in the purchaser s piping specifications. 5.3 Utility Piping 5.3.1 Utility piping should be in accordance with the purchaser s piping specification. 5.3.2 Utility piping should include local isolation valves, drain valves, and check valves, as specified. 5.3.3 Piping to drains should be routed under the slab or in such manner that the piping is not a tripping hazard and does not limit access around the analyzer shelter. 5.3.4 The utility piping specification break should be at the connecting flange to the analyzer shelter. 5.3.5 If steam is required for heating remote analyzer equipment, each user should have an individual supply with an isolation valve and trap. 5.3.6 Threaded piping connections should be sealed with PTFE sealing tape or equivalent tape-type sealer. 5.3.7 Piping should be leak-checked according to project/location procedure and analyzer specification. The piping should be repaired, flushed, and dried as required. 5.3.8 Utility piping should be cleaned and degreased before final connection to the utility headers of the analyzer system. 5.4 Sample Tubing 5.4.1 Sample tubing should be in accordance with process analyzer system data sheet (e.g., PIP PCSPA002-D), purchaser s specification, size, and material. 5.4.2 Only pre-cleaned tubing should be used for sample-wetted surfaces. Specific applications may require post-installation cleaning. 5.4.3 Field-tubing runs should be grouped to benefit from use of common support members and to present a finished installation that is routed in a neat and orderly manner. 5.4.4 Tubing spacing should be adequate and uniform. Tubes should not be permitted to cross over one another. 5.4.5 Only industry-standard tools should be used for bending to avoid flat spots and kinks. Bent tubing should be de-burred to the original internal diameter and blown free of particles. 5.4.6 Tubing supports should be installed in accordance with specification, tube material, and service. Tubing trays or perforated angle supports should be used as needed. Galvanic isolation is needed when tubing and support are dissimilar metals. Process Industry Practices Page 4 of 8

5.4.7 High-quality two-ferrule tube fittings should be used for gas cylinders and for all sample-wetted lines. 5.4.8 Continuous tubing runs should be used wherever possible to minimize the number of tubing unions. 5.4.9 If run in trays, tubing should be equally spaced on the same plane leaving a ¼-inch air gap. If tubing unions are used, the unions should be installed in a raised and staggered fashion away from the plane, using short 45 bends for ease of assembly and disassembly. If possible, tubing unions should be visible. 5.4.10 All installed tubing should be pressure-tested and leak-checked. 5.4.11 Pressure sensitive instrumentation should be isolated before pressure testing. 5.4.12 If a vapor sample can contain liquids or condensables, the sample line should be sloped. The sample line may slope in two directions (toward the sample tap and toward the analyzer), but both slopes should be continuous from the high point. Traps in the sample line should not be permitted. 5.5 Electric Heat-Traced and Pre-Insulated Tubing 5.5.1 Manufacturer s instructions should be used for proper installation of electrically heated and/or pre-insulated sample lines and bundles, including the following: a. Minimum bending radius b. Spacing between bundles c. Maximum spacing of supports d. Use of terminator kits e. Connections to electrical supply f. Penetrations through enclosures, e.g., safety precautions 5.5.2 Both ends of heat-traced sample tubing should be sealed with the manufacturer s recommended kits to prevent moisture damage. 5.5.3 The circuit for electrically heat-traced tubing should include equipment for ground fault protection in accordance with NFPA 70. 5.5.4 Heat-traced and pre-insulated tubing should be installed in accordance with the purchaser s specifications. 5.5.5 Tubing trays or perforated angle supports should be used as needed. 5.5.6 Sample lines should be properly secured. To prevent the creation of hot spots, care should be taken to ensure that the sample line securing devices do not deform the tube bundle. 5.5.7 Manufacturer s instructions should be checked before shortening electrically heated self-regulating sample line. 5.5.8 Heat-treated and pre-insulated tubing should be run directly to the device it serves. Process Industry Practices Page 5 of 8

5.5.9 Bulkhead tubing unions should not be permitted for cabinet or enclosure penetrations. 5.5.10 Bundle(s) should penetrate the walls of the enclosure using heat-shrink entry seals to ensure that the sample temperature is uniformly maintained. 5.5.11 Tubing connections for electrically traced tubing should be installed inside the enclosure. 5.5.12 The power source for traced tubing should be provided at either of the following locations: a. Analyzer enclosure b. Dedicated heat-tracing panel 5.5.13 Traced sample lines that have exposed surface temperatures exceeding plant safety standards should, for personnel protection, be shielded or routed away from normal reach. 5.5.14 Electrically traced tubing bundles should be checked for proper resistance or continuity before being powered. 5.6 Steam-Traced Tubing Bundles 5.6.1 Manufacturer s instructions should be used for proper installation of steamheated sample lines and bundles, including the following: a. Minimum bending radius b. Spacing between bundles c. Maximum spacing of supports d. Use of terminator kits e. Penetrations through enclosures f. Safety precautions 5.6.2 If steam is used for heat tracing, the sample line should be sloped. 5.6.3 Unions and splices in the steam lines should be minimized. 5.6.4 Steam traps should be located and steam lines should be insulated in accordance with manufacturer s recommendations. 5.6.5 Steam-traced tubing should be installed in accordance with the purchaser s specifications. 5.6.6 Tubing trays or perforated angle supports should be used as needed. 5.6.7 Sample lines should be properly secured. To prevent the creation of hot spots, care should be taken to ensure that the sample line securing devices do not deform the tube bundle. 5.6.8 Steam-traced tubing should be installed directly to the device it serves. 5.6.9 Bulkhead tubing unions should not be permitted for cabinet or enclosure penetrations. Process Industry Practices Page 6 of 8

5.6.10 Bundle(s) should penetrate the walls of the enclosure using heat-shrink entry seals to ensure that the sample temperature is uniformly maintained. 5.6.11 The steam source should be provided at either of the following locations: a. Analyzer enclosure b. Other appropriate source 5.6.12 Traced sample lines that have the exposed surface temperatures exceeding specified safety standards should, for personnel protection, be shielded or routed away from normal reach. 5.6.13 Each steam line should have a dedicated trap located in accordance with manufacturer s recommendation. The traps should not be insulated and should be installed at the lowest convenient point. 5.6.14 Seal kits should be installed on each end of steam-traced sample lines to prevent corrosion. 5.7 Sample Probe 5.7.1 Flanged sample probes used to extract the sample from the process line should be installed before hydraulic testing of the lines. 5.7.2 Proper isolation of the analyzer system should be verified. 5.7.3 Retractable insertion probes should be retracted before leak testing. Any support requirements for installations in the horizontal plane should be verified. 5.7.4 In-situ analyzer-sensing elements such as ph, conductivity, chlorine, viscosity, etc., should be installed only after leak testing. 5.7.5 Orientation of the sample probe or sensor installation should be verified. 5.7.6 Sample-conditioning equipment at the sample tap should be close-coupled to the tap and mounted and installed in accordance with purchaser s drawings. 5.7.7 Heating requirements for the sample probe and conditioning equipment, if any, should be verified. 5.8 Electrical Equipment 5.8.1 Electrical components should have a nationally recognized testing laboratory approval. 5.8.2 Conduit, metal-clad, or tray cable wiring can be used. 5.8.3 AC and DC wiring sizes and color codes should be in accordance with purchaser s requirements. 5.8.4 Field wiring and connections should be loop-checked for continuity and conformance to purchaser s drawings. 5.8.5 Junction box or electrical cabinet penetrations should be through the sides or bottom only. Process Industry Practices Page 7 of 8

5.8.6 If conduit wiring is used, covers on conduit fittings should be checked to ensure that they are properly secured. After all inspections are complete, conduit seals should be poured and marked. 5.8.7 Conduit drains should be used at each low point. 5.8.8 The shelter and all electrical equipment should be grounded. Process Industry Practices Page 8 of 8