Jim Alexander Director of Design and Engineering, Southwest Light Rail Transit Project

Similar documents
Southwest LRT Update Freight Rail Technical Issue #21 City of St. Louis Park Council Study Session

SOUTHWEST LRT (METRO GREEN LINE EXTENSION)

Woodburn Interchange Project Transportation Technical Report

LAS VEGAS STREET RAILROAD CROSSING RR/PUC CONNECTION AND PRELIMINARY DESIGN

VIII. LAND USE ISSUES

DRAFT. SR-60 7 th Avenue Intersection Control Evaluation (ICE) I-605 Corridor Improvement Project (CIP) I-605/SR-60 EA# 3101U0

Supplemental Draft Environmental Impact Statement (EIS) Executive Summary

TCWR Route Alternatives Study St. Louis Park Presentation November 29, Mark Amfahr Amfahr Consulting

Estimating Work Zone Performance Measures on Signalized Arterial Arterials

Minnesota Statewide Freight Bottlenecks

Alternatives Evaluation Report. Appendix C. Alternatives Evaluation Report

Environmental Consequences and Mitigation

CHAPTER 2: MODELING METHODOLOGY

BCEO TRAFFIC IMPACT STUDY GUIDELINES

MEMORANDUM: INITIAL CONCEPTS SUMMARY

Southeastern Minnesota Freight Rail Capacity Study

LA 23 NOGC Railway Relocation PE/NEPA Project. Public Meeting

I-35/80 Operations Study: Douglas Avenue to NW 86 th Street FOR

SWLRT Community Advisory Committee Meeting. March 28, 2013

OPTIONAL STATIONAVIATION/MANCHESTER

Appendix B. Benefit-Cost Technical Memorandum

Pottstown Pike Congestion Mitigation Feasibility Study

Access Operations Study: Analysis of Traffic Signal Spacing on Four Lane Arterials

Community Advisory Committee. May 24, 2016

Exposition Light Rail Transit Project

2017 TIGER DISCRETIONARY GRANT APPLICATION

WELCOME. Public Meeting for I-35 / I-44 Interchange. October 6, 2015

12 Evaluation of Alternatives

5.0 Test Plan for Field Data Collection

M D 355 [FR E D E R IC K R O A D] OVER

APPENDIX A. City of Hudson LWRP and. O&G Truck Route Alternatives- Traffic Analysis

LA 23 NOGC Railway Relocation PE/NEPA Project

Final Recommendations Identification of Improvements, Strategies, and Solutions

MEMORANDUM. Date: July 14, 2006 Project #: To: US 97 & US 20 Refinement Plan Steering Committee

Final Air Quality Report

Civil Construction Pre-Bid and DBE Meet and Greet. November 13, 2017

Twin Cities-Milwaukee-Chicago Intercity Passenger Rail Phase I Study Twin Cities- Milwaukee High Speed Rail to Chicago Corridor Study

Goleta Ramp Metering Study

Air Quality Analysis Technical Memorandum

Air Quality Analysis Technical Memorandum

DRAFT. Draft Carbon Monoxide (CO) Traffic Air Quality Analysis

Joint Report of the Transportation and Management Committees For the Metropolitan Council meeting of March 21, 2018

Air Quality Analysis Technical Memorandum

Project Title: Using Truck GPS Data for Freight Performance Analysis in the Twin Cities Metro Area Prepared by: Chen-Fu Liao (PI) Task Due: 12/31/2013

Conceptual Design Report

FOR INTERSTATE 81 AND ROUTE 37 INTERCHANGE FREDERICK COUNTY, VIRGINIA MILEPOST 310

3. STATION SPACING AND SITING GUIDELINES

SOUTHWEST LRT (METRO GREEN LINE EXTENSION)

CHAPTER 5 PARALLEL PARKWAY CORRIDOR IMPROVEMENTS

DRAFT AIR QUALITY TECHNICAL MEMORANDUM

Appendix K Public Notices

Military Highway Interchange

AGENCY MEETING. I-10E Planning & Environmental Linkages Meeting #1 TxDOT Houston District

Evaluation of Alternatives

5.4.1 METHODOLOGY AND PERFORMANCE CRITERIA

TRANSFORM66: OUTSIDE THE BELTWAY

Air Quality Analysis Technical Memorandum

Supplemental Environmental Assessment. Southwest Light Rail Transit. February 16, METRO Green Line LRT Extension (SWLRT)

Exposition Light Rail Transit Project

Zoo Interchange Reconstruction

MONTGOMERY COUNTY CIRCUIT COURT (Subdivision Plats, MO) Plat 13750, MSA_S1249_ Date available 1982/01/05. Printed 08/05/2016.

South Dakota Department of Transportation. Interchange Modification Justification Report. Interstate 90 Exit 44 (Bethlehem Road - Piedmont)

DEVELOPMENT, ANALYSIS, AND DESIGN OF A NEW PARKWAY AT GRADE INTERSECTION (PAGI)

2004 FEASIBILITY STUDY UPDATE

3.6 GROUND TRANSPORTATION

NORTHWEST CORRIDOR PROJECT. NOISE TECHNICAL REPORT 2015 Addendum Phase IV

The Folded Interchange: An Unconventional Design for the Reconstruction of Cloverleaf Interchanges

NEPA and Design Public Hearings

Attachment E2 Noise Technical Memorandum SR 520

Regional Cashless Tolling Planning Study ASSESSMENT OF FUTURE IMPACTS TO I-76 INTERCHANGES AND ADJACENT ROADWAYS

III. ENVIRONMENTAL IMPACT ANALYSIS F. TRAFFIC

WOO-SR Feasibility Study (PID 90541) Feasibility Study Report April 22, 2011

Florida Park Drive. City Council Workshop February 12, 2019

Business Advisory Committee. July 12, 2016

6.2.2 Environmental Consequences and Mitigation Measures

Community Advisory Committee Meeting No. 2. June 22, 2006

Environmental Analysis, Chapter 4 Consequences, and Mitigation

What is the Dakota County Principal Arterial Study?

9.0 I-26 & I-526 Interchange Improvements

PORT OF FERNANDINA TRUCK CIRCULATION STUDY

CONTAINER TERMINAL ACCESS STUDY Year 2003 Update

A Unique Application of Railroad Preemption with Queue Mitigation at a Roundabout Interchange

NATIONAL WESTERN CENTER

Route 7 Connector Ramp MODIF IE D I N T ER C H A N G E M OD IFICATIO N R E PO RT TRA N S F O R M I : I N S ID E THE BE LTWAY

PUBLIC HEARING April 24, 2017

I 95 EXPRESS LANES SOUTHERN TERMINUS EXTENSION TRAFFIC OPERATIONS AND SAFETY ANALYSIS REPORT

Chapter 4 Construction Effects and Mitigation

TH 13 Port of Savage Truck Access Study

Executive Summary. Overview

1.0 PURPOSE AND NEED FOR THE PROPOSED ACTION

APPENDIX A TIER 1 ANALYSIS

ALBION FLATS DEVELOPMENT EXISTING TRAFFIC CONDITIONS AND POTENTIAL IMPACTS

Functional Planning Study Highway 15:06 From Range Road 220 to Highway 830

Overall project. The $288 million Phase 2 DesignBuild project starts construction. this spring, with completion by December 31, 2016

Calibration of a Micro-Simulation Model in a Large Urban Network

TRANSPORTATION PROJECT REPORT DRAFT CONCEPTUAL ACCESS MODIFICATION PROPOSAL OCTOBER 2002

UPTOWN TRAFFIC IMPACT ANALYSIS

Air Quality and Greenhouse Gases Analysis, Methodology, and Results Technical Memorandum. May Southwest LRT Project Technical Memorandum

SOUTHWEST LRT (METRO GREEN LINE EXTENSION) Final Environmental Impact Statement (EIS) Executive Summary

Transcription:

Memorandum Date: January 15, 2014 To: CC: From: Subject: Jim Alexander Director of Design and Engineering, Southwest Light Rail Transit Project Paul Danielson, P.E. Project Manager, Southwest Light Rail Transit Preliminary Engineering Contract - East Segment JoNette Kuhnau, P.E., PTOE Kimley-Horn and Associates, Inc. Freight Alignment Traffic Impact Evaluation This technical memorandum summarizes the traffic impact evaluation of the currently proposed Freight Co-Location and Relocation alignments. The expected traffic impacts were previously presented in the Southwest LRT Draft Environmental Impact Statement (DEIS); however, the proposed alignments have since been adjusted and updated alignment and traffic volume information is now available regarding the proposed alignments and freight rail volumes. This memorandum serves to update the analysis and documentation of the expected impacts of the proposed freight alignments, as well as compare these impacts to those previously documented in the DEIS. A full evaluation of the preferred alternative for freight rail will be part of the Final Environmental Impact Statement (FEIS). 1.0 Freight Co-Location Alternatives The Freight Co-Location alternatives include the Kenilworth Deep Bore LRT Tunnel (LRT 3A-1-SLP/MPLS-A2) and the Kenilworth Shallow LRT Tunnel (LRT 3A-1-SLP/MPLS-A1). Both alternatives include at-grade freight rail and LRT crossings at Wooddale Avenue and Beltline Boulevard in St. Louis Park. In Minneapolis, both alternatives include at-grade freight rail crossings and grade separated LRT crossings (tunnels) at Cedar Lake Parkway and 21 st Street, which from a traffic and freight perspective is similar to the existing and No Build conditions. Therefore, from a vehicular traffic perspective, the two freight rail alternatives would both be expected to have similar impacts. The analysis presented in the DEIS is based on the expected maximum queue resulting from a freight train arrival during the peak 15-minute period. A similar approach has been used for the current alignments, since the delay from a single freight event is more accurately represented by the maximum queues than the level of service at the crossing, which is based on vehicle delay averaged 1

over an hour. Minor adjustments in the LRT alignment or crossing configuration that have occurred as the project was refined since the DEIS have not been included in this analysis. The specific alignment of the LRT tracks relative to the freight rail tracks does not influence the travel of freight traffic through the crossing, therefore these minor changes in the LRT alignment are not expected to result in significant differences in the impacts of the freight rail alternatives. As stated in Chapter 6 of the DEIS, the DEIS analysis included analysis of existing freight traffic at Wooddale Avenue and Beltline Boulevard, assumed to consist of a 30-car train at 10 miles per hour (mph), and a 2030 worst case scenario of a 50-car train traveling at 10 mph. The freight rail crossings at Cedar Lake Parkway were analyzed for a 50-car train at 10 mph for both existing and 2030 conditions. From a traffic perspective, the Freight Co-Location Alternative has not changed substantially from what was defined in the DEIS. However, as described in the following paragraphs, additional and more refined information is available from which to better define the potential impacts. Vehicle traffic counts were conducted at each crossing in 2013, and data was also gathered about the length and arrival time of freight trains. This data has been included in the Appendix. Data collected at the crossings in 2013 showed that the 30-40 car freight trains typically travel through the corridor after the AM peak hour and after the PM peak hour. The longer 80-125 car freight trains can arrive at any time during the day, including overnight. Current information from the Twin Cities and Western Railroad (TC&W) indicates that 14 weekly trains (2 per day) with 65-75 cars and 5-6 weekly unit trains with 80-125 cars are expected. For the purposes of the analysis, all train cars were assumed to be 85 feet in length. This is a conservative assumption given that a typical grain car is approximately 65 feet in length, and the DEIS assumed a 60-foot rail car. Freight trains are allowed to travel up to 25 mph under existing conditions at the Wooddale Avenue and Beltline Boulevard crossings and assumed to be able to travel up to this speed under Build conditions as well. In addition, rail sidings will be removed in the Build conditions along the entire Bass Lake Spur from approximately TH 169 to Beltline Boulevard, eliminating the backing of trains at freight crossings that occurs under existing conditions. Note that although the freight rail infrastructure is being improved and will be designed to accommodate freight traffic up to 25 mph, the freight rail operator, Twin Cities & Western, has indicated that they would continue to travel through the Cedar Lake Parkway and 21 st Street crossings at 10 mph. Therefore, the expected maximum vehicle queues based on both 10 mph and 25 mph freight travel speeds are shown at Cedar Lake Parkway and 21 st Street, in order to capture the worst case. The impacts of a freight crossing are based on three primary factors: Time of day at which the train arrives Length of the train (number of cars) Speed at which the train travels through the crossing Relative to time of day, the current data shows it is rare for a train to 2

arrive during the peak hour. Even if the overall number of freight trains per day were to increase, the arrival of more than one freight train during the peak hour is extremely unlikely due to the distance that trains must travel on the single track configuration through the corridor. Therefore the analysis presented in the DEIS relative to one train arriving in the peak 15-minute period is still considered to be the worst case. The factors of train length and travel speed are integrally related, because together they determine the amount of time a crossing is blocked. The arrival of any freight train in the peak hour would represent the worst case condition in terms of time of day. However, this is not likely to occur given the current schedules of the freight rail operators and the Northstar commuter rail, but if it were to occur the likely train length would be 65-75 cars based on the frequency of these trains. Therefore, a 75-car freight train arriving in the peak 15 minutes of the peak hour was chosen for the freight analysis. Although the absolute worst case condition would be the arrival of a 125-car freight train during the peak hour, this scenario would be unlikely based on the other freight rail traffic and the schedule of the 125-car trains, which can arrive at any time of the day or night. Since the arrival of a 125-car freight train during the peak hour is not expected to occur under typical conditions, this scenario was not analyzed. Table 1 below shows the crossing block times analyzed in the DEIS for 2030 conditions compared to the updated crossing block times based on updated freight traffic and alignment information. Table 1. Freight Co-Location Crossing Blockage Times Location 2030 DEIS Crossing Analysis 2030 Updated Crossing Analysis Wooddale Avenue Beltline Avenue Cedar Lake 50-car train at 10 mph = 232 seconds 1 75-car train at 25 mph = 177 seconds Parkway 75-car train at 10 mph = 441 seconds 21 st Street Not Analyzed 75-car train at 25 mph = 177 seconds Based on the estimated crossing block times, the estimated maximum vehicle queues at the Wooddale Avenue and Beltline Boulevard crossings are estimated to be less than documented in the DEIS analysis (177 compared to 232 seconds). However, based on the longer 75-car train, the estimated maximum vehicles queues near the Cedar Lake Parkway crossing would be expected to be 1 As documented in Table 1 of Cedar Lake Parkway At-grade Analysis by WSB and Associates, Inc. dated April 20, 2010 and updated on March 2, 2012, which is included in Appendix H of the Southwest Transitway Draft Environmental Impact Statement dated September 2012. The DEIS documentation for the analysis of the Wooddale Avenue and Beltline Boulevard crossings does not specify the length of time the crossings were analyzed for a 50- car train at 10 mph, therefore the same value of 232 seconds was assumed for the purposes of this comparison. 3

greater than documented in the DEIS, due to an estimated crossing duration of 441 seconds compared to 232 seconds in the DEIS. Table 2 shows the estimated queues at or near the Cedar Lake Parkway and 21 st Street crossings as documented in the DEIS and the updated queues based on the current analysis. Table 2. Summary of Queuing Analysis near Cedar Lake Parkway and 21 st Street Crossings Estimated Maximum Queue (vehicles) Location Burnham Road at Cedar Lake Parkway Xerxes Avenue at Cedar Lake Parkway Cedar Lake Parkway at Rail Crossing Time of Day Direction 2030 DEIS Crossing Analysis* 50-car Train at 10 mph 2030 Updated Crossing Analysis 75-car Train at 10 mph AM SB 3 3 1 PM SB 6 4 2 AM NB 7 5 2 PM NB 5 5 2 AM PM EB 22 34 14 WB 33 80 32 EB 53 74 30 WB 21 51 20 Not EB 1 0 analyzed AM Not 21 st Street at WB 0 0 analyzed Rail Crossing Not EB 4 2 analyzed PM Not WB 4 2 analyzed *DEIS maximum queue length includes both freight and LRT crossings 75-car Train at 25 mph Based on the estimated maximum queue lengths, the westbound traffic queue on Cedar Lake Parkway for a 10-mph train would be expected to reach past the Dean Parkway intersection in both the AM and PM peak hours, adversely impacting the intersection operations at Xerxes Avenue, Benton Boulevard, and Dean Parkway. The eastbound queue for a 10- mph train on Cedar Lake Parkway would be expected to impact the intersections at Burnham Road and Sunset Boulevard in both the AM and PM peak hours. Vehicle traffic could potentially use Burnham Road, which is grade separated over the freight rail, to avoid the Cedar Lake Parkway 4

crossing when it is occupied by a freight train. However, the existing counts did not appear to show an increase in vehicle traffic turning from eastbound Cedar Lake Parkway onto Burnham Road or from southbound Burnham Road onto westbound Cedar Lake Parkway during the 15-minute periods when the freight crossing was occupied. In addition, only the first one or two vehicles in the eastbound queue could access Burnham Road, due to the proximity of the intersection to the crossing. In addition, Burnham Road is a one-way eastbound roadway at the bridge over the freight railroad and therefore not available as a cut-through route for westbound traffic. These factors make Burnham Road an unattractive route for most drivers, even when the freight crossing is blocked for an extended period. Therefore, impacts due to cutthrough traffic on Burnham Road during freight crossing events are not expected to be significant. The estimated queues at the 21 st Street crossing were not documented in the DEIS, but are not expected to be significant or impact upstream intersections. The results of the Freight Co-location Alternatives analysis relative to impacts on vehicle traffic can be summarized as follows: 1. At the Cedar Lake Parkway crossing, a freight train that arrives during the peak hour potentially has more impact than stated in the DEIS based on the assumption of a longer freight train. 2. The movement of freight trains at the Cedar Lake Parkway and 21 st Street crossings in the Build conditions will be substantially the same as the No Build conditions based on the grade separation of LRT at the crossings. 3. At the Wooddale Avenue and Beltline Boulevard crossings, a freight train that arrives during the peak hour is expected to have less impact than stated in the DEIS due to higher assumed operating speeds that can be achieved with an upgraded rail facility and alignment. 2.0 Freight Relocation Alternative The analysis of the Freight Relocation alternative as documented in the DEIS included at-grade crossings at Walker Street, Lake Street, Library Lane, Dakota Avenue, and 28th Street in St. Louis Park. The 29th Street crossing in St. Louis Park was proposed to be closed. The analysis included the queuing impacts in the Build conditions of a 50- car train at 15 mph and a 120-car train at 10 mph. Elements of the Freight Relocation alignment have changed substantially since the DEIS and the current Brunswick Central alignment (LRT 3A-SLP-MPLS- A) includes at-grade crossings only at 28 th Street in St. Louis Park, with the 29 th Street crossing still proposed for closure. All other crossings would be grade separated. Updated traffic counts were conducted at these locations in 2013, and data was also gathered about the length and arrival time of freight trains. This data has been included in the Appendix. The Canadian Pacific Railroad (CP) currently operates one 30-car train per day through this area. In addition, current information from the Twin Cities and Western Railroad (TC&W) indicates that 14 weekly trains (2 per day) with 65-75 cars and 5-6 weekly unit trains with 80-5

125 cars should be expected. The freight trains are assumed to be able to travel at 25 mph based on the design speeds of the new alignment. For the purposes of the analysis, all train cars were assumed to be 85 feet in length. This is a conservative assumption given that a typical grain car is approximately 65 feet in length, and the DEIS assumed a 60-foot rail car. The impacts of a freight crossing are based on three primary factors: Time of day at which the train arrives Length of the train (number of cars) Speed at which the train travels through the crossing Relative to time of day, the current data shows it is rare for a train to arrive during the peak hour. Even if the overall number of freight trains per day were to increase, the arrival of more than one freight train during the peak hour is extremely unlikely due to the distance that trains must travel on the single track configuration through the corridor. Therefore the analysis presented in the DEIS relative to one train arriving in the peak 15-minute period is still considered to be the worst case. The factors of train length and travel speed are integrally related, because together they determine the amount of time a crossing is blocked. The arrival of any freight train in the peak hour would represent the worst case condition in terms of time of day. However, this is not likely to occur given the current schedules of the freight rail operators and the Northstar commuter rail, but if it were to occur the likely train length would be 65-75 cars based on the frequency of these trains. Therefore, a 75-car freight train arriving in the peak 15 minutes of the peak hour was chosen for the freight analysis. Although the absolute worst case condition would be the arrival of a 125-car freight train during the peak hour, this scenario would be unlikely based on the other freight rail traffic and the schedule of the 125-car trains, which can arrive at any time of the day or night. Since this condition is not expected to occur under typical conditions, this scenario was not analyzed. Table 3 shows the crossing block times analyzed in the DEIS for 2030 conditions compared to the updated crossing block times based on updated freight traffic and alignment information. All other roadway crossings that are part of the Brunswick Central alignment are proposed to be grade separated. Therefore, there would be no impacts to vehicular traffic at these locations under the updated analysis. 6

Table 3. Freight Relocation Crossing Analysis Estimated Maximum Queue (vehicles) Location 2030 DEIS Crossing Analysis 50-car train at 15 mph = 198 seconds 2 28 th Street 5 16 120-car train at 10 mph = 702 seconds 2 2030 Updated Crossing Analysis 75-car train at 25 mph = 177 seconds AM EB = 2 WB = 2 PM EB = 3 WB = 5 29 th Street Proposed for Closure Proposed for Closure Closure of the 29th Street grade crossing would be expected to result in the diversion of through vehicles, which would represent only a portion of the total daily traffic on 29th Street, to one of the adjacent roadways. The two adjacent roadways would continue to have crossings, with 28th Street at-grade and Minnetonka Boulevard grade separated. Even if all traffic from the 29th Street crossing diverted to either 28th Street or Minnetonka Boulevard, this would be an increase of only 10 to 15 vehicles in each of the peak hours. Therefore, no adverse traffic impacts are expected as a result of the closure of 29th Street at the railroad crossing. The results of the Freight Relocation Alternatives analysis relative to impacts on vehicle traffic can be summarized as follows: 1. At the 28 th Street crossing, a freight train that arrives during the peak hour is expected to have less impact than stated in the DEIS based on the assumption of higher operating speeds for the freight traffic. 2. The closure of 29 th Street at the railroad crossing is not expected to substantially impact vehicular traffic on adjacent roadways. 3. The overall impacts to vehicular traffic of the updated Freight Relocation alignment are less than stated in the DEIS due to the elimination of the at-grade crossings at Dakota Avenue, Library Lane, Lake Street, and Walker Street. 2 The values of 198 seconds and 702 seconds are not documented in the DEIS, but were calculated based on the information provided in Table 6.2-8 of the DEIS. 7

APPENDIX

AM Peak Hour Turning Movement Volumes (7:30-8:30) From North From East From South From West Intersection Right Thru Left Right Thru Left Right Thru Left Right Thru Left Total 06B Wooddale Ave & TH 7 Frontage Road 37 652 12 44 1 19 3 638 21 32 0 7 1478 08B Beltline Blvd & South Frontage Rd 52 374 16 13 1 10 23 503 13 1 1 11 1021 10B Cedar Lake Pkwy & Burnham Rd 17 0 5 55 492 0 0 0 0 0 246 33 862 10C Cedar Lake Pkwy & Xerxes Ave 0 0 0 0 500 0 10 0 48 1 254 0 817 12 21 St W & LRT Xing 0 0 0 0 1 1 0 0 0 1 6 0 163 27 29th St & RR Xing 0 0 0 0 5 0 0 0 0 0 4 0 10 28 28th St & RR Xing 0 0 0 0 38 0 0 0 0 0 17 0 55

PM Peak Hour Turning Movement Volumes (4:45-5:45) From North From East From South From West Intersection Right Thru Left Right Thru Left Right Thru Left Right Thru Left Total 06B Wooddale Ave & TH 7 Frontage Road 16 542 37 20 0 7 17 565 18 43 1 10 1276 08B Beltline Blvd & South Frontage Rd 3 401 3 4 0 18 31 425 1 10 0 18 914 10B Cedar Lake Pkwy & Burnham Rd 7 0 4 36 306 0 0 0 0 0 492 95 940 10C Cedar Lake Pkwy & Xerxes Ave 0 0 0 0 313 0 7 0 22 0 477 0 819 12 21 St & LRT Xing 0 0 0 0 32 0 0 0 0 0 27 0 59 27 29th St & RR Xing 0 0 0 0 6 0 0 0 0 0 9 0 15 28 28th St & RR Xing 0 0 0 0 73 0 0 0 0 0 50 0 123

Existing Railroad Crossings Intersecti on Direction Da te Time of Train Duration of Train Number of Crossing Crossing Train Cars SB 2/13/2013 10:04 AM 35 s econds 7 28th St RR Xi ng NB 2/13/2013 1:19 PM 12 s econds 3 SB 2/14/2013 10:38 AM 22 s econds 5 NB 2/14/2013 1:16 PM 89 s econds 19 SB 2/13/2013 10:03 AM 28 s econds 7 29th St RR Xi ng NB 2/13/2013 1:17 PM 15 s econds 3 SB 2/14/2013 10:37 AM 19 s econds 5 NB 2/14/2013 1:14 PM 64 s econds 19 Wooddal e Ave RR Xing EB 2/13/2013 9:57 AM 70 s econds 37 EB 2/13/2013 6:01 PM 290 s econds 83 NEB 2/13/2013 10:07 AM 148 s econds 37 NEB 2/13/2013 6:12 PM 411 s econds 83 Ceda r La ke Pkwy RR Xi ng SWB 2/13/2013 8:24 PM 133 s econds 30 SWB 2/14/2013 3:51 AM 510 s econds 135 NEB 2/14/2013 9:49 AM 115 s econds 27 SWB 2/14/2013 6:39 PM 105 s econds 26