Annex F Scoping Checklist

Similar documents
APPENDIX I. (See paragraph 6) FORM 1

FORM-I for seeking clearance for project attracting CRZ notification

APPENDIX I. (See paragraph-6) FORM 1

FORM-I. 13. Name of Applicant District Collector Nasik 14. Registered Address Address : Collector Office, Nasik

FORM I SUBMISSION TO STATE ENVIRONMENT IMPACT ASSESSMENT AUTHORITY, ANDHRA PRADESH. BY. Asst.Director of Mines and Geology, Rajamahendravaram

FORM 1 BASIC INFORMATION S.NO.

APPENDIX I. (See paragraph-6) FORM 1

APPENDIX I (See paragraph 6) FORM 1

Appendix I. Form 1 BASIC INFORMATION PAWA MASONARY STONE MINING PROJECT VILLAGE PAWA, TEHSIL DIDWANA, DISTRICT NAGAUR, RAJSTHAN

FORM 1 & 1 A. Palladium Grand II RESIDENTIAL & COMMERCIAL DEVELOPMENT. Palladium Grand II, S. No. 17/1A/2, Dhanori, Pune, Maharashtra

M/s. Karthika Mines & Minerals Pvt.Ltd.-Colour Granite Quarry Ha. FORM - I

Application Forms for Prior Environmental Clearance as per Environmental Impact Assessment Notification dtd &

Form -1. [Vide Notification dated 1 st December 2009] FOR PROPOSED. COSTAL ROAD AT DRONAGIRI, NAVI MUMBAI Precast RCC Bridges On Holding Ponds-

FORM 1. APPLICATION FOR OBTAINING ENVIRONMENTAL CLEARANCE VIDE PARA 6 OF S.O.1533 OF MOEF NOTIFICATION DATED 14 th SEPTEMBER 2006

Molvan- Chhamuchhal Group Gram Panchayat. Taluka- Mangrol, District- Surat. Ph. No

APPENDIX I (See paragraph 6) Form 1 (I) Basic Information

APPENDIX I (See paragraph 6) FORM 1

Appendix I. Form 1 BASIC INFORMATION MASONARY STONE MINING PROJECT VILLAGE KOLIYA, TEHSIL DIDWANA, DISTRICT NAGAUR, RAJSTHAN

3 SCOPING 3.1 DEVELOPMENT OF SCOPING PROCESS Need for Scoping

FORM I TERMS OF REFERENCE. For. QUARRY OF ROAD METAL (6.265 Ha) Sri K Kasi Raju. PROP: K.Kasi Raju

FORM 1. 8 Does it attract the specific condition? It yes, No Please specify 9 Location At Village Akurli, Akurli Road, Kandivali(E), Mumbai

APPENDIX I (See paragraph 6) FORM 1 (Application for Environment Clearance)

APPENDIX - I (See paragraph 6) FORM 1

Annexure-IV. Form-I for seeking clearance for project attracting CRZ notification. At Thengamputhur Village, Tamil Nadu by

(Residential cum Commercial Project) APPENDIX I (See paragraph 6) FORM 1. Plot area: 37,039 m 2 Built up area: 1,11, m 2

APPENDIX- I FORM- 1. (I) Basic Information:

Sri.T.N.Balasubramanya

APPENDIX I (See paragraph - 6) FORM 1

Submitted To State Expert Appraisal Committee (SEAC), State Environmental Impact Assessment Authority, Andhra Pradesh.

APPENDIX I (See paragraph 6) FORM 1

FORM 1 (As per new Notification of MoEF dated vide S.O 3067 (E))

UPDATED FORM I, (Submitted to State Expert Appraisal Committee, Telangana)

APPENDIX I. (See Paragraph 6) FORM 1

Sand, Stone & Bajri Mining Project Applicant: Shri Ashish Kumar, M/s Ashish Stone Crusher. Form-1 FORM-1 SRUSHTI SEWA, NAGPUR 1

FORM 1. 1 Name of the Project Pinakin Mangubhai Patel 2 S. number in schedule 8 (a)

APPENDIX VIII (See paragraph 6) FORM 1 M APPLICATION FOR MINING OF MINOR MINERALS UNDER CATEGORY B2 FOR LESS THAN AND EQUAL TO FIVE HECTARE

UPDATED FORM-1 EXTENSION OF VALIDITY OF ENVIRONMENTAL CLEARANCE. Sri Fakir Rohidas

FORM I. [Vide M.o.E.F & C.C Notification dated 14 th September, 2006] For Proposed Residential & Commercial Project ALCOVE. M/s.

APPENDIX I (See paragraph 6) FORM 1

APPENDIX I (See paragraph 6) FORM 1. Plot area: 10,439 m 2 Built up area: 50, m 2

No 1 Name of the Project/s M/s. Velchal Laterite Mine 2 S. No in the Schedule 1(a)

Application Form for Obtaining Environmental Clearance from State Level Environment Impact Assessment Authority (SEIAA), Tamil Nadu

Proposed Construction Multi Specialty Hospital Naruvi Hospitals 2. S. No. in the schedule 8(a)

Application Forms for Prior Environmental Clearance as per Environmental Impact Assessment Notification dtd &

APPENDIX VIII (See paragraph 6) FORM 1 M APPLICATION FOR MINING OF MINOR MINERALS UNDER CATEGORY B2 FOR LESS THAN AND EQUAL TO FIVE HECTARE

FORM 1. Basic Information Sr. No. 1 Name of the project River Sand Mining Project of Shree Sabarmati Majur Kamdar Sahakari Mandali LTD.

REPORT OF SAND STONE MINING PROJECT (KHATADARI Q.L. No. 178 FOR

UPDATED FORM I. SUBMISSION To Ministry of Environment & Forests & Climate Change, New Delhi. Prepared by. M/s. VIJAYNAGAR SUGAR PVT. LTD.

FORM 1. Gownivaripalli Village, Tehsil. Gorantla Mandal, District. Anantapur District, State

FORM 1 (As per new Notification of MoEF dated vide S.O 3067 (E))

Renewal of Environmental Clearance for Commercial Complex City Square 2 S. No. in the Schedule 8 (a), Building & Construction project

APPENDIX I (See paragraph 6) FORM 1. Plot area: 13,114 m 2 Built up area: 81, m 2

Project: Bhidauni Khadar Ordinary Sand Mining Project on Yamuna River FORM 1 Applicant: M/s Satyug Foods Pvt. Ltd. FORM- I

ITHC/PRJ/18-19/EIA/138 1 IND TECH HOUSE CONSULT

Revised FORM - I & PRE-FEASIBILITY REPORT

.APPENDIX I (See paragraph 6) FORM 1. Sl. No. Item Details 1. Name of the project/s

FORM 1. No condition? If yes, please specify. 8. Does it attract the specific. No condition? If yes, please specify. 9. Location Geo Coordinates

M/S Overseas Min Tech Consultants, Jaipur 1

FORM-1. PROJECT: Sati & Garhi Sand Ghat,Ulai River (Area-22 Ha), Dist:-Jamui. APPLICANT: M/s Westlink Trading Pvt. Ltd. FORM- I.

FORM 1 FOR PROPOSED CONSCTRUCTION BUILDING PROJECT ( SQ. M) ANAMOL LIFE STYLE

FORM 1 Riverbed Sand Mining Project

APPENDIX I. (See paragraph-6) FORM 1

A 'N 'E B 'N 'E C 'N 'E D 'N 'E

THE SINGARENI COLLIERIES COMPANY LIMITED (A Government Company)

FORM-1. Sr. No 1 Name of the Project Harbour Heights 2 S. No. in the Schedule 8(b) Townships and Area Development projects.

FORM 1. /area/length/tonnage. No condition? If yes, please specify. 8. Does it attract the specific

JSW DHARAMTAR PORT LIMITED

Rajarhat-Bishnupur 1 No.Gram Panchayat Tehsil - District

Environmental Checklist:. 10.Ports and Harbors (1) Yes: Y No: N (a) (b) (c) (d)

Proposed Ordinary Sand Mining Project at Gata No.- 8Ka/195, Village- Ratauli, Tehsil- Laharpur, District- Sitapur, U.P. FORM 1

APPENDIX I. (See paragraph -6) FORM- 1. S.No. Item Details 1 Name of the projects/s: Flag Stone Quarry

APPENDIX I (See paragraph - 6) FORM 1

M/s. SURYA ENTERPRISES H.No: , Sri Paradise Apartments, New Andhra Bank Colony, Anantapuramu District

(I) Basic Information:

Haridarshan Residency ( Row Type House & School Building )

9 Plot/Survey/Khasra No S.No: 153/1, 153/2, 171/1, 171/2A, 172/1B1, 172/1B2, 172/C1, 172/1C2, 172/2A, 172/2B, 172/2C & 180/1.

FORM 1 Riverbed Sand Mining Project

Proposed Multiplex & Commercial Complex FORM I

FORM 1 Riverbed Sand/Morrum / Mining Project

FORM-I Basic Information

Annexure-IV. Form-I for seeking clearance for project attracting CRZ notification

APPENDIX I (See paragraph - 6) FORM 1

APPENDIX I (See paragraph - 6) FORM 1

APPENDIX I. (See paragraph 6) FORM 1

30 TPH Fertilizer Blending unit for Customized NPK Production at Zuarinagar, Sancoale, Marmugao, SouthGoa, Goa

Details required for submitting Fresh EC Application. (Category B2 Projects: Mining of Minor Minerals)

Form I. for. Proposed Construction of High Rise Residential Cum Commercial Building Eco Gardens

Application for Prior Environmental Clearance (EC)

FORM min Village. Chowgund, Tehsil. Doru District. Anantnag State

UPDATED FORM I 433 TPD CALCINED PETROLEUM COKE PLANT WITH 9 MW COGENERATION OF POWER PROPOSED AT

Form - 1 Appendix- I (See Paragraph-6)

FORM-I. Environmental Clearance (EC)

Form 1, Form 1(A) and Proposed ToR for Residential Project Pramukh Aura at Chala, Taluka: Vapi & District: Valsad, Gujarat.

Expansion of MDI Complex, Plot No 25, Sector 16A, Noida, Uttar Pradesh

APPENDIX I. (See paragraph 6) FORM 1

FOR THE PROPOSED EXPANSION IN BACKWARD INTEGRATION PROJECT FOR

MANAKAWAS PLOT-1 TEHSIL-DADRI, DISTRICT-BHIWANI, HARYANA

Form 1, Form 1(A) and Proposed ToR for Residential Project at Chala, Taluka: Vapi & District: Valsad, Gujarat.

FORM 1 SRI LAKSHMI GAYATRI HOSPITAL (P) LTD.

APPENDIX I (See paragraph - 6) FORM 1

Transcription:

Scoping Checklist

Table F1: Scoping Checklist Table. Questions to be considered in Scoping /? Which Characteristics of the Project 1. Will construction, operation or decommissioning of the Project involve actions which will cause physical changes in the locality (topography, land use, changes in waterbodies, etc)? 1.1 Permanent or temporary change in land use, landcover or topography including increases in intensity of land use? Loss of existing habitat including agricultural land for the windfarm turbines, access tracks and associated infrastructure 1.2 Clearance of existing land, vegetation and buildings? vegetation would be affected. Some degraded and improved agricultural land would be affected. The foundations of a remnant homestead is located within one of the central field boundaries and may require excavation although it is possible that works could avoid this recorded feature Site visits have indicated that there is a lack of peat on site. Landuse is predominantly grazing on degraded and improved farmland and land take would be restricted to only that needed for the wind farm development 1.3 Creation of new land uses? Turbines would displace some grazing land generally land use would continue 1.4 Pre-construction investigations e.g. boreholes, soil testing? Some Project engineer would undertake peat probing; and check the turbine locations for method of construction etc ground investigation works would be small scale 1.5 Construction works? Changes in land uses, potential effects on hydrology etc 1.6 Demolition works? 1.7 Temporary sites used for construction works or housing of construction workers? 1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations? As 1.1 Work to date suggests that impacts would not be significant if adequately mitigated Areas still to be identified but would be small would be sited to mitigate against significant effects Land use, landscape, hydrology, habitats, important species etc Generally no as impacts can be mitigated. Uncertain for landscape until further work completed - dependent on Natural Capital Ltd F - 1 wpd Scotland Ltd

. Questions to be considered in Scoping /? Which Characteristics of the Project 1.9 Underground works including mining or tunnelling? 1.10 Reclamation works? 1.11 Dredging? 1.12 Coastal structures eg seawalls, piers? 1.13 Offshore structures? 1.14 Production and manufacturing processes? 1.15 Facilities for storage of goods or materials? Temporary construction compound and storage of rock could affect peat (if any) and habitat 1.16 Facilities for treatment or disposal of solid wastes or liquid effluents? ability of landscape to accept change and potential for mitigation Careful siting of facilities and control of drainage and implementation of best would prevent significant impacts Uncertain Construction welfare facilities to be confirmed - careful siting and implementation of best practice measures would prevent significant impacts 1.17 Facilities for long term housing of operational workers? 1.18 New road, rail or sea traffic during construction or operation? Construction traffic using new sections and upgraded access tracks 1.19 New road, rail, air, waterborne or other transport infrastructure including new or altered routes and stations, ports, airports etc? Minor movements once operational New access tracks could affect existing habitats and landscape 1.20 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? 1.21 New or diverted transmission lines or pipelines? utilities identified. Connection to existing line - minor works required 1.22 Impoundment, damming, culverting, realignment or other Construction works may impact on the changes to the hydrology of watercourses or aquifers? hydrology of the site and the current passage of surface drains and informal water features Increases in traffic minor - significant noise and air quality impacts would be unlikely Implementation of mitigation measures and detailed design would minimise impact on habitats and landscape Unlikely Water features survey would identify all known and unknown drainage ditches. If any watercourse Natural Capital Ltd F - 2 wpd Scotland Ltd

. Questions to be considered in Scoping /? Which Characteristics of the Project crossings required mitigation would reduce impacts 1.23 Stream crossings? As 1.22 As 1.22 1.24 Abstraction or transfer of water from ground or surface waters? 1.25 Changes in waterbodies or the land surface affecting drainage or run-off? 1.26 Transport of personnel or materials for construction, operation or decommissioning? 1.27 Long term dismantling or decommissioning or restoration works? 1.28 Ongoing activity during decommissioning which could have an impact on the environment? Potential for changes to hydrology due to construction near surface water features and marshy land (also where there is potential for peat) Construction workers and deliveries of construction materials Significant effects would be avoided with careful siting of infrastructure, and implementation of mitigation and best practice Unlikely to be significant given temporary and small numbers Issues similar to construction (see 1.5) See construction effects (see 1.5) Unlikely Small scale works; would have some impacts on landuse 1.29 Influx of people to an area in either temporarily or permanently? Construction work force and very limited employment during operation 1.30 Introduction of alien species? Unlikely Vehicles accessing the site could bring in species but risk unlikely to be significantly greater than at present decommissioning would be short term over very small time period. Careful restoration would be required as numbers low and period of construction short assuming best site adopted to control risk of alien species 1.31 Loss of native species or genetic diversity? 1.32 Any other actions? 2. Will construction or operation of the Project use natural resources such as land, water, materials or energy, especially any resources which are nonrenewable or in short supply? 2.1 Land especially undeveloped or agricultural land? Predominantly degraded and improved agricultural land used for grazing. Small forestry plots bound the site to the east and west Further engineering investigations which are to be commissioned would be used to ensure infrastructure is sited to avoid areas the highest Natural Capital Ltd F - 3 wpd Scotland Ltd

. Questions to be considered in Scoping /? Which Characteristics of the Project 2.2 Water? The southern area of the site is particularly marshy and there are a number of drainage ditches, a burn to the south and springs to the centre of the site which may be affected by the proposals 2.3 Minerals? 2.4 Aggregates? Stones required for access tracks and turbine foundations 2.5 Forests and timber? 2.6 Energy including electricity and fuels? Energy required for fabrication in turbines etc and to use during construction value habitat Further engineering investigations would be required to ensure any changes to hydrology do not affect the flow or quality of water draining from the site into the SAC and SPA to the south east t known but unlikely if works mitigated stone to be brought in from a local quarry if not borrow pit is constructed on site Unlikely - project would be self-sustaining in the longer term and would offset that used in construction 2.7 Any other resources? 3. Will the Project involve use, storage, transport, handling or production of substances or materials which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health? 3.1 Will the project involve use of substances or materials which are hazardous or toxic to human health or the environment (flora, fauna, water supplies)? 3.2 Will the project result in changes in occurrence of disease or affect disease vectors (eg insect or water borne diseases)? 3.3 Will the project affect the welfare of people eg by changing living conditions? 3.4 Are there especially vulnerable groups of people who could be Some fuels and oils etc would be stored and used on site during construction and operation affected by the project eg hospital patients, the elderly? 3.5 Any other causes? 4. Will the Project produce solid wastes during construction or operation or decommissioning? 4.1 Spoil, overburden or mine wastes? Earthworks for access tracks and foundations would produce waste -provided best site implemented Impacts would depend on type of construction and use of materials in restoration, Natural Capital Ltd F - 4 wpd Scotland Ltd

. Questions to be considered in Scoping /? Which Characteristics of the Project however impacts are unlikely to be significant 4.2 Municipal waste (household and or commercial wastes)? 4.3 Hazardous or toxic wastes (including radioactive wastes)? 4.4 Other industrial process wastes? 4.5 Surplus product? Removed materials from construction would be reused on site 4.6 Sewage sludge or other sludges from effluent treatment? 4.7 Construction or demolition wastes? On decommissioning would be some wastes produced 4.8 Redundant machinery or equipment? As 4.7 As 4.7 4.9 Contaminated soils or other material? 4.10 Agricultural wastes? 4.11 Any other solid wastes? 5. Will the Project release pollutants or any hazardous, toxic or noxious substances to air? 5.1 Emissions from combustion of fossil fuels from stationary or mobile sources? 5.2 Emissions from production processes? 5.3 Emissions from materials handling including storage or transport? 5.4 Emissions from construction activities including plant and equipment? Emissions from construction and operation traffic Dust could be produced if dry during construction Unlikely - however impacts would depend on potential for re-use and recycling Unlikely given small vehicle numbers Unlikely. Best site would be implemented on site Emissions from construction traffic and plant Unlikely given small vehicle numbers and implementation of best site to control emissions 5.5 Dust or odours from handling of materials including As 5.3 As 5.3 construction materials, sewage and waste? 5.6 Emissions from incineration of waste? 5.7 Emissions from burning of waste in open air (eg slash material, construction debris)? 5.8 Emissions from any other sources? 6. Will the Project cause noise and vibration or release of light, heat energy or electromagnetic radiation? 6.1 From operation of equipment e.g. engines, ventilation plant, Treatment of aggregates on site would be Unlikely as best site Natural Capital Ltd F - 5 wpd Scotland Ltd

. Questions to be considered in Scoping /? Which Characteristics of the Project crushers? detailed as part of the EIA, if required. Some noise from operation of turbines would be implemented on site. 6.2 From industrial or similar processes? ise from turbines and substation during operation 6.3 From construction or demolition? ise from construction could affect nearby residents or recreational users of the site Impacts of noise from operation of turbines would be assessed as part of detailed EIA ise assessment as part of detailed EIA would demonstrate impacts considered will meet ETSU requirements Unlikely with adequate mitigation and works small scale 6.4 From blasting or piling? Unlikely It is unlikely that any blasting or piling works would be required To be assessed as part of the detailed EIA 6.5 From construction or operational traffic? As 5.1 As 5.1 6.6 From lighting or cooling systems?? Lighting needs to be defined To be assessed as part of the detailed EIA anticipated to be unlikely 6.7 From sources of electromagnetic radiation (consider effects on nearby sensitive equipment as well as people)? 6.8 From any other sources? 7. Will the Project lead to risks of contamination of land or water from releases of pollutants onto the ground or into sewers, surface waters, groundwater, coastal waters or the sea? 7.1 From handling, storage, use or spillage of hazardous or toxic materials? 7.2 From discharge of sewage or other effluents (whether treated or untreated) to water or the land? 7.3 By deposition of pollutants emitted to air, onto the land or into water? 7.4 From any other sources? 7.5 Is there a risk of long term build up of pollutants in the Oils and fuels on site Unlikely as best site would be implemented on site Natural Capital Ltd F - 6 wpd Scotland Ltd

. Questions to be considered in Scoping /? Which Characteristics of the Project environment from these sources? 8. Will there be any risk of accidents during construction or operation of the Project which could affect human health or the environment? 8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous or toxic substances? 8.2 From events beyond the limits of normal environmental protection e.g. failure of pollution control systems? 8.3 From any other causes? 8.4 Could the project be affected by natural disasters causing environmental damage (eg floods, earthquakes, landslip, etc)? Unlikely Extent of peat and risk of peat slip is considered to be low and unlikely Risk of peat slide would be assessed if peat was found on site as part of detailed EIA and any necessary mitigation identified 9. Will the Project result in social changes, for example, in demography, traditional lifestyles, employment? 9.1 Changes in population size, age, structure, social groups etc? 9.2 By resettlement of people or demolition of homes or communities or community facilities eg schools, hospitals, social facilities? 9.3 Through in-migration of new residents or creation of new communities? 9.4 By placing increased demands on local facilities or services e.g. housing, education, health? 9.5 By creating jobs during construction or operation or causing the loss of jobs with effects on unemployment and the economy? Some opportunity for local employment during construction and possibly during operation Unlikely because only limited numbers of jobs likely to be created in construction and operation 9.6 Any other causes? 10. Are there any other factors which should be considered such as consequential development which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality? 10.1 Will the project lead to pressure for consequential development which could have significant impact on the environment eg more housing, new roads, new supporting industries or utilities, etc? 10.2 Will the project lead to development of supporting facilities, ancillary development or development stimulated by the project which could have impact on the environment eg: supporting infrastructure (roads, power supply, waste or waste water treatment, etc)? Could lead to further windfarm proposals t known Natural Capital Ltd F - 7 wpd Scotland Ltd

. Questions to be considered in Scoping /? Which Characteristics of the Project housing development extractive industries supply industries other? 10.3 Will the project lead to after-use of the site which could have Site likely to return to present use-grazing Unlikely an impact on the environment? 10.4 Will the project set a precedent for later developments?? Could stimulate further windfarm development Uncertain 10.5 Will the project have cumulative effects due to proximity to other existing or planned projects with similar effects? in the area Could be cumulative effects on landscape and visual amenity, ecology, tourism etc with other windfarm proposals (i.e. Causeymire etc) Uncertain - to be assessed as part of detailed EIA Natural Capital Ltd F - 8 wpd Scotland Ltd