Analysis of a Manual Mixed-Model Assembly Line in Food Processing Industry: A Case Study

Similar documents
International Journal of Technical Research (IJTR) Vol. 5, Issue 1, Mar-Apr 2016

Ch 16 Automated Production Lines

PULL PRODUCTION CYCLE-TIME UNDER VARYING PRODUCT MIXES

Manual Assembly Lines

CHAPTER 1 INTRODUCTION

Will Flexible-Cell Manufacturing Revolutionize Carmaking?

Systematic Planning Layout and Line Balancing for Improvement in an Armoured Vehicle Manufacturing Plant

CHAPTER 1 INTRODUCTION

Modelling of Two-sided Assembly Line Balancing Problem with Resource Constraints

Modelling of Two-sided Assembly Line Balancing Problem with Resource Constraints

Methods of Solving Assembly Line Balancing Problem

MANUFACTURING SYSTEM BETP 3814 INTRODUCTION TO MANUFACTURING SYSTEM

MM 323 MANUFACTURING SYSTEMS PRODUCTION AND LAYOUT TYPES

Finished goods available to meet Takt time when variations in customer demand exist.

A Machine Setup Model for TFT-LCD Cell Back-End Process

A CASE STUDY OF PRODUCTION LINE BALANCING WITH SIMULATION

USING SIMULATION TO SUPPORT IMPLEMENTATION OF FLEXIBLE MANUFACTURING CELL. Kambiz Farahmand

Line Balancing in the Hard Disk Drive Process Using Simulation Techniques

Line Balancing in the Hard Disk Drive Process Using Simulation Techniques

Ch 15 Manual Assembly Lines

CAD/CAM CHAPTER ONE INTRODUCTION. Dr. Ibrahim Naimi

7/8/2017 CAD/CAM. Dr. Ibrahim Al-Naimi. Chapter one. Introduction

PLUS VALUE STREAM MAPPING

Mahendra Singh 1, Prof. (Dr.) Archana Nema 2 1 M. Tech (IEM) Student, BIST, RGPV, Bhopal (M.P) IJRASET: All Rights are Reserved

Description of the Rear-Axle Assembly Demo Model for Tecnomatix Plant Simulation March 2013 CONTENT

TYPICAL FACTORY LAYOUT vs THE TOYOTA APPROACH

PRODUCTIVITY IMPROVEMENT IN APPLIANCE MANUFACTURING

Skateboard Assembly Line Balancing High School Student Worksheet

Where to Use Automated Production Lines. Automated Production Lines. Benefits of Automated Production Lines. Automated Production Line - Defined

Line Balancing through Cycle Time Reduction

Factors that influence layout

Analysis and Modelling of Flexible Manufacturing System

Prof. Prakash Girwal Dept of Mechanical Engineering VITM Indor,India

Proceedings of the 2017 Winter Simulation Conference W. K. V. Chan, A. D'Ambrogio, G. Zacharewicz, N. Mustafee, G. Wainer, and E. Page, eds.

Scheduling of Three FMS Layouts Using Four Scheduling Rules

Solution Manual for Automation, Production Systems, and Computer-Integrated Manufacturing 4th editor by Groover

LEAN MANUFACTURING & TPM.

LEAN WAREHOUSE OPERATIONS.

LEAN PRODUCTION FACILITY LAYOUT.

STUDY NO 5 INTRODUCTION TO FLEXIBLE MANUFACTURING SYSTEM

Running Head: Implementing Just-In-Time Production at Toyota

TOPIC 2 : WORK METHODS 2.1 Elemental breakdowns 2.2 Performance rating 2.3 Personal, fatigue, unavoidable delay allowances 2.4 Workload and line balan

PRODUCT-MIX ANALYSIS WITH DISCRETE EVENT SIMULATION. Raid Al-Aomar. Classic Advanced Development Systems, Inc. Troy, MI 48083, U.S.A.

Unit WorkBook 1 Level 5 ENG U48 Manufacturing Systems Engineering UniCourse Ltd. All Rights Reserved. Sample

LEAN PRODUCTION SYSTEM

A Heuristic Approach for Vehicle Scheduling Problem with Time and Capacity Constraints

Computer Integrated Manufacturing (CIM)

Short-Term. Scheduling

AssemblyLineBalancingtoImproveProductivityusingWorkSharingMethodinApparelIndustry

PRACTICE PROBLEM SET Topic 1: Basic Process Analysis

The Performance Analysis of a Fettling Shop Using Simulation

Simulation and Optimization of a Converging Conveyor System

A Variable Capacity Parallel Machine Scheduling Problem

Outline. Pull Manufacturing. Push Vs. Pull Scheduling. Inventory Hides Problems. Lowering Inventory Reveals Problems

SIMUL8-PLANNER FOR COMPOSITES MANUFACTURING

Practical Application of Training tasks Based on Flexible Manufacturing System Hongmei Fan

LET S TRY AN EXERCISE: [& Learn some economic concepts]

SOLVING LOGISTICS AND TRANSPORTATION PROBLEMS IN A JOB SHOP. Kambiz Farahmand Arun Balasubramanian

Chapter 11. In-Time and Lean Production

Improvement and Simulation of Rear Axle Assembly Line Based on Plant Simulation Platform

Charting and Diagramming Techniques for Operations Analysis. How to Analyze the Chart or Diagram. Checklist of Questions - Example

A DECISION TOOL FOR ASSEMBLY LINE BREAKDOWN ACTION. Roland Menassa

Investigating the Influences of Automated Guided Vehicles (AGVs) as Material Transportation for Automotive Assembly Process

Flow and Pull Systems

Proceedings of the 2012 Winter Simulation Conference C. Laroque, J. Himmelspach, R. Pasupathy, O. Rose, and A. M. Uhrmacher, eds.

Chapter 3 Assembly Systems. Screen Titles

ARCHITECTURE OF FMS. Typical Elements of FMS. Two Kind of Integration. Typical Sequence of Operation

A TUTORIAL ON ERGONOMIC AND PROCESS MODELING USING QUEST AND IGRIP. Deidra L. Donald

Manufacturing Systems & Single Station Manufacturing. Lecture 2

Optimize Assembly Production Line using Line Balancing

Ch 19 Flexible Manufacturing Systems

Application of Stateflow Diagrams in Production Line Modeling

A Computer based novel approach of ergonomic study and analysis of a workstation in a manual process

International Journal of Advanced Engineering Technology E-ISSN

LEAN PROCUREMENT.

Chapter 5 Location and Layout Strategies

Lean and Agile Systems. Rajiv Gupta FORE School of Management October 2013 Session 6

Lecture 9 MBF2213 Operations Management Prepared by Dr Khairul Anuar. L9: Lean synchronization

Productivity Improvement of a Fan Manufacturing Company by using DMAIC Approach A Six-Sigma Practice

SCREENING CELL DESIGNS BASED ON SYNCHRONOUS MANUFACTURING

Case on Manufacturing Cell Formation Using Production Flow Analysis

INTRODUCTION TO FMS. Type of Automation. 1. Fixed automation 2. Programmable automation 3. Flexible automation Fixed Automation

IARJSET. International Advanced Research Journal in Science, Engineering and Technology AGNI-PANKH 16

Available online at ScienceDirect. Procedia Engineering 100 (2015 )

Simulation and Optimization in Production Logistics Based on em-plant Platform

A Flexsim-based Optimization for the Operation Process of Cold- Chain Logistics Distribution Centre

Assembly line balancing in textile industry

Real Time Management of All Operational Domains and Workflows in Your Laboratory. Chris Christopher Csquared Global Healthcare Consulting

Lecture 6. Capacity and Facilities. Lecture Outline. Capacity. Maximum capability to produce Capacity planning

USING SIMULATION TO SCHEDULE MANUFACTURING RESOURCES. Hank Czarnecki Bernard J. Schroer M. Mizzanur Rahman

Computer Aided Process Planning(CAPP) By: Dhiman Johns M.E.(PIE), Thapar University, Patiala

Lean Manufacturing Implementation in Small and Medium Industry

Set-up Reduction for Lean Cells and Multi- Machine Situations

Planning manufacturing systems

IT 470a Six Sigma Chapter X

Job Batching and Scheduling for Parallel Non- Identical Machines via MILP and Petri Nets

COMPUTER INTAGRATED MANUFACTURING

Motion and Time Study

Line Balancing on AUDI B8 Cable Assembly Line using MUDA: A Case Study

A SORTATION SYSTEM MODEL. Arun Jayaraman Ramu Narayanaswamy Ali K. Gunal

Transcription:

Analysis of a Manual Mixed-Model Assembly Line in Food Processing Industry: A Case Study Mehmet Savsar, Angie K. Elsaadany, Rana Hassneiah and Altaf Alajmi Kuwait University College of Engineering & Petroleum Industrial & Management Systems Engineering P.O. Box 5969 Safat 13060 Kuwait E-mails: msavsar@gmail.com, angiie.94@hotmail.com, rana_hassneiah@hotmail.com, al6afn@gmail.com Abstract- Several factors affect productivity of Food Processing Assembly Lines (FPAL). Engineers and line managers usually do not recognize some of these factors and underutilize their production/assembly lines. In this paper, a special food processing assembly line is studied in detail and procedures are presented to illustrate how productivity and efficiency of such lines can be increased. The assembly line considered produces ten different types of freshly prepared salads on the same line, which is called mixed model assembly line. Problems causing delays and inefficiencies on the line are identified. Line balancing and related tools are used to increase line efficiency and minimize balance delays. The procedure and the approach utilized in this paper can be useful for the operation managers and industrial engineers dealing with similar assembly lines in food processing industry. Keywords- Mixed-Model Assembly Line, Line Balancing, Line Efficiency, Productivity. I. INTRODUCTION Manufacturing assembly lines were first introduced by Henry Ford in 1900s for assembling automobiles in mass production and to take into consideration the effects of learning curve of the workers on the line. Ever since, assembly lines have been applied to all types of manufacturing systems, including food industry. In today s consuming society and ever increasing demand for products, only mass production can cope with high demand in competitive environment. Assembly lines in Food Processing Industry (FPI) are designed to assemble a huge variety of food products on the same line since it is extremely expensive to use a dedicated assembly line for each food product. These lines are called mixed model assembly lines. A very common mixed-model assembly line in FPI is manual mixed-model assembly line. Manual assemblies are preferred since the quality of different ingredients must be inspected visually while assembling the final product. It is difficult to automate the quality control procedures in many cases. However, one of the first drawbacks in using workers for manual assembly is that the workers get fatigued easily and their assembly speed is limited. Also, high percentage of waste, non-value added activities, bottlenecks and congestions can occur within stations when using manual assembly. Each worker on the assembly line usually represents a workstation. The speed or the throughput of each 5689

workstation on the line is the numbers of products produced in a set time. The speed may differ between workstations which results in a bottleneck and congestion. Line balancing is necessary to minimize bottleneck effects, to reduce wasted time, and to increase line productivity. Assembly lines have been studied by several researchers. Each researcher considered a different problem with specific set of goals, or the objectives. Production efficiency is one of main objectives for a manufacturing company. Cycle time is also an important factor that most authors have mentioned. Different authors define the cycle time differently. Zupan and Herakovic [1] considered production efficiency and improved the throughput through production leveling. They defined the cycle time as the time between end products that is pre-determined by the production rate. Adnan, et al. [2] defined the cycle time as the time it takes to do a process. It includes the time from the start of an operator until the work is ready to be passed on. The cycle time for each workstation is measured from the start of picking a part until it arriives at the next workstation. Adnan, et al. [2] and Zhang and Kucukkoc [3] studied the issue of how to reduce either the cycle times or the number of work elements. Zhang and Kucukkoc [3] considered work order constraints to reduce workstations and work-elements. Peng [4] found out that two-sided assembly lines should be preferred, in which work is added on both sides of the conveyor. Peng [4] also stated that to increase the production capacity, number of workstations must be minimized. Most authors agreed on grouping work families and taking their sequences into consideration. Perishability of a product is another issue in multi-product assembly lines. Buyukozkan et al. [5] considered product quality defects caused by stations and the importance of line reliability. He also stated that if the workload is different between the workstations, the cycle time will become more critical. Grzechca [6] also defined the cycle time as Zupan and Herakovic [1]. He indicated that if processing time of a workstation is more than the cycle time, then the workstation would become idle and have to wait. A useful time measurement tool is takt time. Adnan et al. [2] defined it as the maximum time allowed in a workstation to meet the demand. The takt time and conveyor speeds are used to determine the production plan. Performance of the system is also measured differently depending on the objective being considered. Zupan and Herakovic [1] and Adnan et al. [2] agreed that throughput is a very efficient way of measuring system performance. Adnan et al. [2] defined throughput as the average number of jobs produced per hour. Adnan et al. [2] also defined efficiency as the ratio of current productivity to the largest productivity achievable. Grzechca [6] said that a good performance measure, especially for systems with conveyors, is to find the smoothness index. Zupan and Herakovic [1] and Grzechca [6] both conceded that arrangement or order of tasks that must be performed on the line is another important issue to consider. In this paper, several problems causing inefficiencies and delays on the assembly lines are determined and procedures are proposed to increase production efficiency and balance delays on the lines. Line balancing tools are utilized to distribute the workload evenly and eliminate the bottleneck from the assembly line in order to increase its efficiency and productivity. Furthermore, various types of products are scheduled for production on the same line in such a way as to reduce the average work flow time. 5690

II. MIXED MODEL ASSEMBLY LINE The company selected for this case study was one of the biggest food processing industry in the Middle East. It had several assembly lines. However, one of the most intriguing lines was the manual salad production line. Ten different salad variants are produced on the same line with 9 workers. The products are all perishable and cannot be made-to-stock. Therefore they are made-to-order. The main processes on the salad assembly line are all in series. These main processes usually start with the plastic bowl, manually handled and filled with the core ingredient; then a plastic separator is manually added along with the specified dressing according to the salad variant; and then finally rest of the ingredients are consecutively added. After the main assembly of the variant, a salad sleeve is placed around the closed salad bowl. Every 12 finished salad bowls are manually placed in a carton box, where it is then stored in a chilled storage area waiting to be distributed during the night shift to local stores. Figure 1 shows the layout of the salad line. Figure 1: assembly line layout A shift analysis was conducted on the line in order to identify the bottleneck. As seen from Table 1, 23.42% of total time was lost due to minor stoppages. Figure 2 shows the distribution of minor stoppage percentage with respect to workers. 67% was due to sleeve worker while about 13% was due to packaging labor, who puts the finished products into the carton box. Table 1. Shift Analysis for salad line Line Status State Activity Duration (Hours) Total Duration (Hours) Percentage of Total (Hours) Run/Up Processing 3.36 3.36 43.47% Down Minor Stoppages 1.81 23.42% 2.1 Wasted Time 0.29 3.75% Preparation 0.35 4.53% Setup Changeovers 0.5 1.27 6.47% Cleaning 0.42 5.43% Break Lunch break 1 1 12.94% Total 7.73 100% 5691

80% 70% 67.02% 60% 50% 40% 30% 20% 10% 12.59% 8.24% 8.24% 3.90% 0% Sleeves ( labor) Packaging (labor) Inspection (labor) Cover (labor) Ingredients (labor) Figure 2: Pareto analysis of line stoppage reasons The salad line consisted of nine workstations with one worker in each station. Each work station consisted of maximum of two work elements, which is the smallest division of a task. Added work elements in the same work station make up one task. The defined cycle time [Tc] is the time it takes to produce one product. Allowances are very important when deciding a standard cycle time, which is used to balance the line. In order to get the workstation cycle time, each work element must be observed and enough data should be collected. For our purpose, we have collected 35 data values for each work element in each station. The minimum time value represents the best processing time observed for each work element. It is combined with an allowance to give workstation cycle time. Using the observed data for the assembly line for different types of products, allowances are calculated for each work element, which are then utilized to calculate work element cycle times, as well as the cycle time of each station (task). Table 2 shows the related times for different types of salads, assembled on the same line. The first row for each salad in the table is the sum of minimum observed times for the station i cycle time; the second row shows the calculated cycle time for station i (Tci) after adding the allowances in each case. III. ASSEMBLY BALANCING AND IMPROVEMENT Computer Method of Sequencing Operations for Assembly Lines (Groover [7]) was used to balance the line based on the station (task) cycle times obtained in the previous section. After line balancing, number of workers for some salad variants decreased. Number of workers for four season salad and Mexican salad decreased from 9 to 8 workers while for pasta salad it was decreased from 9 to 7 workers. The packaging labor had to assemble the box, fill it with salad products, seal it and sign it off. This caused many stoppages on the line. The best solution is to use two workers at the beginning of the shift to start opening the boxes. After that, one will continue assembling the boxes while the other will go on to the production line. Since opening the box is not done on the line, related work element is removed from line system. Another problem for the minor stoppages was due to the sleeves worker s workload, which was distributed between the original worker and the inspection worker. Inspection worker was already putting sleeves for some products in some cases. By fractioning the workload, sleeve worker will be able to keep up with the line speed and reduce the minor stoppages. Calculated cycle time for each workstation was used to balance the line with an efficiency of 31.9%, cycle time 0f 7.85 seconds and 5692

9 workstations. After modifying and improving the workstations, and rebalancing the line, efficiency was increased to 47.7% which was an increase of almost 50%. Number of stations was 8 and cycle time was 4.73 seconds. Work elements for mixing of some salad ingredients were combined and number of workers for some variants were removed and made as external work. Table 2. Station/task cycle times calculated from data Worker/Station/ Task No 1 2 3 4 5 6 7 8 9 Caesar Min Value 1.46 2.38 1.28 1.27 1.2 1.33 1.06 6.53 - Cycle Time 1.46 2.66 1.28 1.27 1.2 1.33 1.06 7.86 - Chickn Caesar Greek Pasta Four Season Tabul. Corn Mexic. Seafd. Fatosh Min Value 1.46 2.38 1.73 1.32 1.2 1.33 1.06 6.53 - Cycle Time 1.46 2.66 2.35 1.32 1.2 1.33 1.06 7.86 - Min Value 1.46 2.38 2.25 0.93 1.2 1.33 1.06 6.53 - Cycle Time 1.46 2.66 2.49 0.93 1.2 1.33 1.06 7.86 - Min Value 1.43 2.38 1.16 0.97 0.86 1.2 1.33 1.06 6.53 Cycle Time 1.43 2.66 1.16 0.97 0.86 1.2 1.33 1.06 7.86 Min Value 1.46 1.73 2.38 3.63 2.73 1.2 1.33 1.06 6.53 Cycle Time 1.46 1.99 2.66 3.96 3.81 1.2 1.33 1.06 7.86 Min Value 1.61 2.38 1.84 1.24 1.2 1.33 1.06 6.53 - Cycle Time 1.61 2.66 1.84 1.24 1.2 1.33 1.06 7.86 - Min Value 1.45 1.59 2.38 2.66 1.56 1.2 1.33 1.06 6.53 Allowances 0 0.38 0.29 0 0 0 0 0 1.33 Cycle Time 1.45 1.97 2.66 2.66 1.56 1.2 1.33 1.06 7.86 Min Value 1.49 2.38 2.99 2.66 1.24 1.2 1.33 1.06 6.53 Cycle Time 1.49 2.66 3.02 2.66 1.24 1.2 1.33 1.03 7.86 Min Value 2.78 3.99 2.38 1 2 2.36 1.2 2.39 6.53 Cycle Time 3.07 3.99 2.66 1 2.37 2.61 1.2 2.79 7.86 Min Value 2.66 1.71 1.6 3.02 0.46 1.81 1.2 2.39 6.53 Cycle Time 2.9 1.82 1.83 2.43 2.48 2.25 1.2 2.79 7.86 Line balancing was applied on each salad product. Table 3 summarizes the efficiency improvements after balancing the workload. Cycle time was reduced from 3.8 seconds to 2.3 seconds per product. In addition, shift time was reduced from 7.73 hours to 4.29 hours. After reduction of shift time by removing minor stoppages, line efficiency was increased from the varying range of 27% to 55% for different salads (average of 40% for all salads) to about 61%. Furthermore, sequencing the variants of salads based on the number of workers while taking into consideration the shared ingredients between variants was also implemented for productivity improvement. Line 1 needed 7 workers, Lines 2-7 needed 8 workers; and lines 8-10 needed 9 workers and ordered in this sequence. 5693

Table 3. line variant and average efficiency Variant Current LB Adjusted LB Adjusted Number of Workers Greek 30.9% 44% 8 Fatoush 38.6% 54.5% 9 Chicken Ceaser 30.6% 42.6% 8 Four Season 35.8% 53.4% 8 Ceaser 28.8% 39.6% 8 Seafood 38.5% 53.7% 9 Corn 34.9% 46.4% 9 Mexican 31.9% 47.7% 8 Taboula 29.9% 41.4% 8 Pasta 26.2% 46.5% 7 Average 32.61% 46.98% IV. CONCLUSIONS Mixed-model assembly lines must be very carefully analyzed and various available tools, including line balancing tools, must be utilized in order to increase line efficiency and its production rate. Manual mixed-model assembly lines are straightforward, where the workload and worker processing time defines many attributes for the assembly line. Line-balancing techniques are the best approach to solve most problems related to time and bottleneck analysis. As it has been shown in the analysis of a relatively simple assembly line in food processing industry in this paper, line efficiency was increased by as much as 44% and cycle time, as well as the required shift time, was reduced by as much as 40% and 45% respectively. The procedures and concepts presented in this paper can be utilized by operations managers and production engineers in order to improve their assembly lines and achieve higher efficiency and production output rate. REFERENCES [1] Zupan, H., Herakovic, N. (2015), "Production line balancing with discrete event simulation: A case study", Elsevier, vol. 48, Issue 3, pp. 2305-2311. [2] Adnan, A. N., Arbaai, N. A., Ismail, A. (2016), "Improvement of overall efficiency of production line by using line balancing", ARPN Journal of Engineering & Applied Sciences, vol. 11, no. 12. [3] Zhang, D. Z., Kucukkoc, I. (2013), "Balancing Mixed-Model Parallel Two-Sided Assembly Lines", 5th IESM Conference, Rabat, Morocco. [4] Peng, T. (2014), "A Firing Sequence based Algorithm for Two-Sides Assembly Line Balancing", IEEE 18th International Conference on Computer Supported Cooperative Work in Design. [5] Buyukozkan, K., Kucukkoc, I., Satoglu, S., Zhang, D.Z (2016), "Lexicographic bottleneckmixed model assembly line balancing problem: Artificial bee colony and tabu-search approaches with optimized parameters", Elsevier, vol.50, pp. 151 166. 5694

[6] Grzechca, W. (2015), "Assembly Line Balancing Problem with Quality Inspection Stations", Cybernetics and Intelligent Systems (CIS) and IEEE Conference on Robotics, Automation and Mechatronics (RAM), IEEE 7th International Conference. [7] Groover, M. P., Automation, Production Systems, and Computer-Integrated Manufacturing (4 th Edition), Pearson, 2015. Biograpy Mehmet Savsar is a professor of Industrial Engineering at Kuwait University since 1997. He was a professor at King Saud University, Riyadh, Saudi Arabia during 1984-1997 and Assistant Professor at Anadolu University, Turkey during 1982-1894. He received his MSc and PhD degrees from Penn State University in 1978 and 1982 respectively in the areas of Industrial Engineering and Operations Research. He has over 180 publications in various international journals and conference proceedings. He works and teaches in the areas of manufacturing systems modeling, reliability, maintenance, facility planning, and simulation. Angie K. Elsaadany, Rana Hassneiah and Altaf Alajmi are Industrial Engineers graduated from Kuwait University in 2016. They all work in the areas of production and operations management. They have worked on a project related to assembly line balancing and roductivity improvement in food processing industry under the supervision of Prof. M. Savsar. 5695