Summary. Mini KKP - Assembly and operating manuel Pile guide box. Montage. Implementation. Accessories. Technical data

Similar documents
KS - Assembly and operating manual Trench box

ASSEMBLY AND OPERATING MANUAL LTW SLIDE RAIL SYSTEM - Type FP

ASSEMBLY AND OPERATING MANUAL LTW SLIDE RAIL SYSTEM - Type PV

Edge Support Trench Lining System

ASSEMBLY AND OPERATING MANUAL LTW SHORING BOXES VB 100

manufacturer: 6%+7LHIEDXWHFKQLN*PE+ Ferdinand-Porsche-Str. 8 D HEINSBERG

DOUBLE SLIDE RAIL INSTALLATION METHOD. Double Slide Rail August

Trench Box. Important Notes. Introduction. User Guide

ASSEMBLY AND OPERATING MANUAL LTW EG CORNER - MANHOLE

S-60-MI2 : 500kg mini tower system v.2

Heavy-Duty Braces Triplex Assembly and Operating Instructions

New Zealand s Excavation Safety Specialists.

h Installation Manual

OPERATION MANUAL BISON LIFTER (ABL150)

SHORING SYSTEMS FROM SHORING PROFESSIONALS

Installation Manual. Orion. TL-3 Steel Barrier. VHD (v2)

SP Prop Steel prop. // Versatile, strong, safe

PACIFIC SHORING, LLC ALUMINUM SHORING PRODUCTS ALUMINUM S-PANEL SHIELDS. TABULATED DATA Effective April 01, 2014

TRITEC light Steel Panel Formwork

PERI PD 8 The cost-effective shoring for slab tables and high loads

Shackles. Applications. Range. Design. CAD drawings. Finish

PE45 AMAZON MONKEY BARS OWNER'S MANUAL

MGF TECHNICAL FILE MGF 305 UC BRACE. Description. Product Notes Issue 4

SAFE WORK PROCEDURE LOCATION OF WORK: WRITTEN BY: APPROVED BY: DATE: LAST REVISION: Leon Prevost Brent Vandenbosch

PROLYTE MPT-TOWER MANUAL ASSEMBLY INSTRUCTIONS

OPERATOR S SAFETY MANUAL

Pipes, Piles, and Accessories

MGF TECHNICAL FILE TRENCH BOXES. Description. Product Notes.

Saudi Vitrified Clay Pipe Co.

Section 5B: Floor and Roof Panel Installation Guide

FW66 FORESTRY WINCH FW66. Owner s Manual 19/02/2016

Walco Equipment has grown into a successful Canadian manufacturing & distribution Company.

MGF TECHNICAL FILE MGF 203 UC BRACE. Description. Product Notes.

MGF Laddersafe part of the Shoring Safety Product Range EDGESAFE MGF TECHNICAL FILE Issue 4. Tel

SCAFFOLDING RUNWAY SYSTEM

MANUAL. portrait set-up. landscape set-up. ClickFit Evo mounting system for sloping roofs with roof tiles for solar panels

S-60-TO : 1 ton tower system

MevaFlex Assembly and Operating Instructions

EuropEan lifting devices

lindab we simplify construction LindabSandwichPanels Installation instructions Mineral Wool Panels

PROLYTE ST-TOWER MANUAL ASSEMBLY INSTRUCTIONS

Conergy SolarFamulus II

Contents. Before you begin. Introduction: Installing trench support 1. Element 1: Planning and preparing 3

Aluminum Headache Rack

MGF TECHNICAL FILE WALERS AND STRUTS. Description. Product Notes.

Storage space in steel. Storage Space in Steel. From the market leader!

RAPID Column Formwork For the highest requirements on concrete surfaces and edge formation. Product Brochure Issue 10/2017

R-Group Finland Oy. RTA, RWTL and RWTS Lifting anchors Design instructions

USER S MANUAL. HAKI Loading Tower

built build to FORMWORKS CLIMBING, RETAINING WALLS, SPECIAL

Autolock Tipping Skip

MANUAL. landscape orientation. portrait orientation. metal roof mounting system for solar panels METAL ROOF MOUNTING SYSTEM. Rev

Lifting Appliances of Ships and Offshore Installations

Concrete Framing Systems - Walls and Columns

MGF TECHNICAL FILE SHEET PILES. Description. Product Notes.

Installation. Natrix

ABACO LITTLE GIANTLIFTER

TECHNICAL MANUAL. PC Beam Shoe. Hidden Beam Shoe for Corbel System

LK15 PRESTIGE PLAY KITCHEN OWNER'S MANUAL

Question Paper Code : 11410

STRUT METAL FRAMING SYSTEMS

CORNER SLIDE RAIL OPEN PIT INSTALLATION INSTRUCTIONS

PC Beam Shoe. Corbel system to support beams. Technical Manual. Version: DK 4/2012 Design standard: DS EN Eurocodes + NA (Denmark)

PE57 HOLT 2 DOUBLE SWING OWNER S MANUAL

PE21 AMBER DOUBLE SWING OWNER S MANUAL

KEEP FOR FUTURE REFERENCE MRT FORKLIFT ADAPTER READ ALL INSTRUCTIONS AND WARNINGS BEFORE USING THIS PRODUCT

CIRCULAR COLUMN SK 100

Tabulated Data Hydraulic Vertical Shores

UNIVERSITY OF BOLTON WESTERN INTERNATIONAL COLLEGE FZE. BEng (HONS) CIVIL ENGINEERING SEMESTER ONE EXAMINATION 2018/2019

PERI UP Easy * The lightweight and fast frame scaffold for safe working on facades

MGF TECHNICAL FILE MANHOLE BRACE. Description. Product Notes.

Technical File Section 3: Hydraulic Bracing Systems

Goods Cage. Introduction. Important Notes. Key Benefits. User Guide

NCCER Progress Blvd, Alachua, Florida Phone: (888)

Installation Guide. PAROC panel solutions

AR SCAFFOLDING AR ALUMINUM MOBILE AR STEEL MOBILE

Rubbish chute CONSTRUCTION SECTOR SOLUTIONS. INNOVATIVE SYSTEMS Tekcnoplast &

INDUSTRIAL CONSTRUCTION GENERAL MANUFACTURING

SCAFFOLDING RUNWAY SYSTEM

MAXIMO MXH Heated Formwork The cost-effective solution for concreting operations at low temperatures. Product brochure

MODEL : TM-ZR566S(HEF)

Rosette Modular Scaffolding System

fg EIYDQ)oe;;(f ROUND BENDING MACHINE Model: RBM-10 Operation Manual

USER S Manual. HAKI Bridge System (HBS)

I-GUIDE SAFEPASS ROAD BARRIER SAFETY SOLUTIONS JONSEREDS 1/12 IG-SAFEPASS ROAD BARRIER-1710

USER S MANUAL HAKI CONTINENTAL

Installation Manual. ArchCast Bridge. 3-Sided Precast Concrete Bridge Structure

Acrow Slim-Max Soldier System

Design Guide. Original version of the design guide

ENGINEERED SOLUTIONS SAFETY INSTRUCTIONS FOR STRUCTURAL PLATE PRODUCTS

EDILEGNOARREDO/FEDERLEGNOARREDO GUIDELINES ON STEEL DOORS, ONE LEAF, BURGLARY RESISTANCE TEST

BoSS Climalite Camera and lighting tower

SA30 STRONGBOX SQUARE SANDPIT OWNER'S MANUAL

SOLO 700. One Man Aluminium Tower 3T - Through the Trapdoor Method USER GUIDE

Installation INSTRUCTIONS. Use. Maintenance. Care

Rolling Towers. Layher Rolling Towers Uni Wide. Safety Structure Instructions for Assembly and Use. Mobile working platforms to DIN EN 1004:

is generally suitable for trench depths of up to 7.16m, widths of up to 3.92m, pipe lengths of up to 3.0m and a pipe OD of up to 2.6m.

Technical Data Sheet Products

ArmorWire Cable Barrier

Transcription:

Summary Technical data Montage Implementation Accessories p3 p5 p6 p7 KRINGS INTERNATIONAL FRANCE - Mini KKP - 1

Conformité DIN 4124 DIN EN 13331 H L L c b C0 b CU b t pl Plate height Plate length Pipe culvert height Pipe culvert length Working width Shoring width Plate thickness KRINGS INTERNATIONAL FRANCE - Mini KKP - 2

Base plate LxH box Trench sheet No. Pipe culvert length L C Thickness inner plate t pl State design load limit qd [mm] [kg] [KD4] [mm] [mm] [kn/m] KKP 2040x600 560 10 1740 60 92.6 KKP 2440x600 650 12 2140 60 61.8 KKP 2840x600 730 14 2540 60 44.2 Any other dimension, consult us. Tensile forces: lifting eyes at the plate head Rd = 229 kn KD 4/6 Width b Height h Thickness t Section modulus W y Moment of inertia I y Bending moment M d single pile wall [mm] [mm] [mm] [cm 3 /m] [cm 4 /m] [knm/m] [kg/m] [kg/m²] 400 50 6 102 254 25.5 22.1 55.3 Strut type Working width b C Inner working width between sheets b cu Shoring width b [m] [m] [m] [kg] A 0.53-0.63 0.65-0.75 0.89-0.99 12.4 B 0.62-0.81 0.74-0.93 0.98-1.17 13.5 C 0.80-1.17 0.92-1.29 1.16-1.53 15.7 D 1.16-1.89 1.28-2.01 1.52-2.25 19.4 KRINGS INTERNATIONAL FRANCE - Mini KKP - 3

A. General The monoblock K.I.F box, appears under the shape of 2 panels of the same dimensions put face to face. The space between the panels is adapted with rigid mechanical jacks. For the assembly, it is necessary to plan: - A mean of handling (mechanical shovel, forklift truck or a mobile crane), - Two workers accompanying the driver of the handling machine, - 4 leg chain/slings with 4 safety hooks / standards (DIN 5687 / DIN 5688 / ISO 3076 NF 818 4/+A1), - A sledgehammer, a steel bar, or a jack key. Some ropes to help the rotation of the box, when it is handled under the bucket of the excavator - Our standard equipment does not require any keys for bolting. Standards must be respected: - DIN 4124 Excavations and open air trenches - DIN IN 13331 parts 1 and 2 trench shoring systems. - Safety regulations of the occupational health. - Instructions for the prevention of the accidents / instructions relative to the safety at work. Our trench shoring system carries the GS initials (certified Safety), which means it is in compliance with the current European Standards. B. Lifting and transport Only the handling rings can be used for lifting (hooks, ropes). The means of handling must be adapted to the weight to be transported. By security measure, only hooks provided with a screed can be used (safety hooks). The transport should be made as close as possible of the ground to avoid any useless and dangerous pendular movement. It is forbidden to stay in the zone of gyration of the hoisting device as well as under raised loads. Be very careful with the existing areal electric lines! A permanent eye contact must be maintained between the driver and the person who guides him. C. Measures to reduce hazards: The construction site must be well bounded and secured (ribbons, barriers or other means of protection). The surrounding road traffic must be secured if necessary, by additional staff. The staff has to wear safety clothes (helmet, safety footwear, gloves). Possible instabilities due to the wind which can arise during the assembly or the installation of the trench shoring equipment must be considered (use of ropes). The trench shoring systems and parts should be stored in a horizontal way, on a stable ground. During the installation, the instructions of the mode of use must be respected. D. Maintenance & repair Normaly, the different parts of the equipment should be checked before installation. Original KIF spare parts can be used during repairs. We draw your attention on the fact that any repair made by yourself and if you use spare parts from other manufacturers, will cancel the guarantee. Due to the intense utilization of the equipment, all parts should be repainted with anti-rust paint, every two years. KRINGS INTERNATIONAL FRANCE - Mini KKP - 4

E. Montage: - The panels are lying flat on the ground. - Set up the spindle supports in the sliding guide where the drillings are located. - Fix the spindles with the bolt Ø20mm and the supplied safety clips. Head upwards for the bolt Ø20mm. - Prepare the second panel with the spindle supports. - Renew the operation in order to set up the trench box with the bolts and safety clips. Be sure to adjust the jack bottom with a few centimeters more than the top (box-shaped A). The assembly made the handling of the box assembled and its implementation can be made. The panels are equipped with lifting rings at each end, it is FORBIDDEN to sling chains to the jacks. 1 Strut 2 Safety clip Béta 3 Bolt Ø20 KRINGS INTERNATIONAL FRANCE - Mini KKP - 5

F. Mise en place 1. Make a pre-excavation on the length of a box on a maximum depth of 1.0m, never more than the height of the guide panel. 2. Hang your chain slings four strands handling points provided for this purpose, and position the box preset to the correct width in the pre-excavation with the handling equipment. Make sure the horizontality of the latter. Do not leave space between the walls of the trench and guide signs. 3. Using suitable lifting equipment (sheet piles clamps, shackles, chains, for example), proceed to the introduction of sheet piles in the alveoli. 4. The excavation is done by successive layers of about 50cm, the sheet piles are driven with the bucket of the excavator simultaneously. When an obstacle is encountered, the corresponding sheet pile will not be lowered. The underside of the crossing network will then be shield in traditional (wood or other avoiding landslide). 5. Depending on the soil condition, the depth and the immediate environment of the trench, low wailer may be necessary to use the cantilever forces applied to the sheet piles profiles. KRINGS INTERNATIONAL FRANCE - Mini KKP - 6

G. Accessories Mandatory accessory for jobs requiring handling of sheet piles or sheet piling, this clamp secures automatic dropping of sheet pile or pile away. Model Pulling force Sheet piles Sheet pile thickness LZ-1 1 000 kg CR440 - KD4 or similar 4mm 4kg DZ-3 3 000 kg KD6-8 or similar 8mm 15kg KRINGS INTERNATIONAL FRANCE - Mini KKP - 7

How to use a clamp Automatic sheet piles DZ3? Unlock the bolt by a single 180 rotation. Drag the clip to the hole in the sheet pile. Ensure that the axis is to the right of the hole. Lock the axis with a simple 180 rotation. The sheet pile fixed, secure handling can be done. The sheet pile up and stable stall. Pull the string to carry out remotely of 180 rotation of the axis. The clamp releases the sheet pile. Automatic clamp sheet piles avoids climb to win the profiles. Do not use the automatic clamp sheet piles for removal profiles. Do not stand under the load being handled. (we offer extraction clamps) KRINGS INTERNATIONAL FRANCE - Mini KKP - 8