DOD MANUAL , VOLUME 12 DOD SUPPLY CHAIN MATERIEL MANAGEMENT PROCEDURES: SALES AND OPERATIONS PLANNING

Similar documents
Department of Defense MANUAL

DOD MANUAL , VOLUME 1 DOD SUPPLY CHAIN MATERIEL MANAGEMENT PROCEDURES: OPERATIONAL REQUIREMENTS

Department of Defense MANUAL. DoD Integrated Materiel Management (IMM) for Consumable Items: Reporting, Auditing, and Financial Management

Department of Defense INSTRUCTION

Department of Defense MANUAL

DOD MANUAL , VOLUME 10 DOD SUPPLY CHAIN MATERIEL MANAGEMENT PROCEDURES: SUPPLY CHAIN INVENTORY REPORTING AND METRICS

Department of Defense DIRECTIVE

Department of Defense MANUAL

DOD MANUAL , VOLUME 2 DOD MANAGEMENT OF ENERGY COMMODITIES: RECORDS RETENTION AND FORMS MANAGEMENT

DOD MANUAL , VOLUME 6 DOD SUPPLY CHAIN MATERIEL MANAGEMENT PROCEDURES: MATERIEL RETURNS, RETENTION, AND DISPOSITION

DCMA INSTRUCTION 2501 CONTRACT MAINTENANCE

Department of Defense MANUAL

OSD SUPPLY CHAIN ENTERPRISE METRICS STRATEGY. Evolving DoD Supply Enterprise Metrics The Maintenance Customer Perspective

DOD MANUAL , VOLUME 11 DOD SUPPLY CHAIN MATERIEL MANAGEMENT PROCEDURES: INVENTORY ACCOUNTABILITY AND SPECIAL MANAGEMENT

Joint Supply Chain Architecture (JSCA)

This training matters, because the auditors are coming.

Department of Defense INSTRUCTION

Department of Defense MANUAL

DCMA Instruction Stewardship

Logistics Community of Interest 2001 General Supply Series Competency-Based Learning Map and Training Strategy. Page 1

Department of Defense INSTRUCTION

SUBJECT: Joint Physical Inventory Working Group (JPIWG) Meeting, September 28, 2010

PROTECTED A. Follow-up on Internal Audit: MWAV ISSC Pre-publication copy not for external distribution Proposed Final January 2014 PROTECTED A

DOD INSTRUCTION BUSINESS SYSTEMS REQUIREMENTS AND ACQUISITION

Standardization Template

Department of Defense DIRECTIVE. SUBJECT: DoD Replenishment Parts Purchase or Borrow Program

Washington Headquarters Services ADMINISTRATIVE INSTRUCTION

Placing a lens on supply chain planning

COMPLIANCE WITH THIS PUBLICATION IS MANDATORY

Department of Defense INSTRUCTION

DOD MANUAL FEDERAL LOGISTICS INFORMATION SYSTEM (FLIS) PROCEDURES

DATA ITEM DESCRIPTION TITLE: TRAINING SITUATION DOCUMENT Number: DI-SESS-81517C Approval Date:

Future Logistics Enterprise

DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION. Performance Architecture

3010 DEFENSEPENTAGON WASHINGTON, DC

Lesson 1: Introduction to Production, Planning, and Control (PPC) Systems

C A L L F O R E N T R I E S

DoD DMSMS Strategic Objectives Update. April 26, DoD DMSMS Lead

Methodology for Selecting the Preferred Networked Computer System Solution for Dynamic Continuous Defense Missions

Enterprise Architecture as an Essential Tool Supporting Army Transformation. Fernando Mezquita

a GAO GAO DEFENSE MANAGEMENT Tools for Measuring and Managing Defense Agency Performance Could Be Strengthened

Logistics Solutions for the Warfighter

3Z0Z 0? W7? TOTAL QUALITY MANAGEMENT MASTER PLAN* (S)l\f> v^n. 0 Department of Defense. AUG 2 ego, August O/ A./ \o V* TECHNICAL LIBRARY

COMPLIANCE WITH THIS PUBLICATION IS MANDATORY

COMPLIANCE WITH THIS PUBLICATION IS MANDATORY

United States Government Accountability Office. Statement of Jack E. Edwards, Director Defense Capabilities and Management

GAO ORGANIZATIONAL TRANSFORMATION. Military Departments Can Improve Their Enterprise Architecture Programs

Department of Defense INSTRUCTION

Defense Logistics Agency INSTRUCTION

Department of Defense MANUAL

IUID-Enabled Serialized Item Management in Operations and Maintenance November 2011

FORECASTING & REPLENISHMENT

Department of Defense MANUAL. DoD Integrated Materiel Management (IMM) for Consumable Items: Logistics Reassignment (LR)

Department of Defense. Guidelines for the Virtual Unique Item Identifier (UII)

Cost and Software Data Reporting (CSDR) Post Award Meeting Procedures

Department of Defense INSTRUCTION

ADMINISTRATIVE INSTRUCTION

A Message from the Principal Deputy Assistant Secretary of Defense for Logistics and Materiel Readiness

a. To provide policy and assign responsibilities for the management of depot-level repairables (DLR).

DOD MANUAL , VOLUME 9 DOD SUPPLY CHAIN MATERIEL MANAGEMENT PROCEDURES: MATERIEL PROGRAMS

Requirements Analysis and Design Definition. Chapter Study Group Learning Materials

Creating a Sustainable PMO for Achieving Effective Business Results By Dennis L. Bolles, PMP DLB Associates, LLC

Department of Defense Award for Supply Chain Excellence CALL FOR ENTRIES

INFORMATION ASSURANCE DIRECTORATE

DOD INSTRUCTION , VOLUME 3006 DOD CIVILIAN PERSONNEL MANAGEMENT SYSTEM: CYBER EXCEPTED SERVICE (CES) COMPENSATION ADMINISTRATION

DEFENSE LOGISTICS AGENCY HEADQUARTERS 8725 JOHN J. KINGMAN ROAD FORT BELVOIR, VIRGINIA

Introduction. Table of Contents

Procure-to-Pay (P2P) Standard Operating Procedures (SOP) for Pre-Award Funds Validation ( Handshake 2)

NGB-J6/CIO CNGBI DISTRIBUTION: A 13 August 2012 NATIONAL GUARD BUREAU (NGB) JOINT INFORMATION TECHNOLOGY PORTFOLIO MANAGEMENT

OSD's Ten DMSMS Strategic Objectives. Defense Standardization Program Office OSD DMSMS / Obsolescence Lead (703)

This resource is associated with the following paper: Assessing the maturity of software testing services using CMMI-SVC: an industrial case study

9. What are the activities within the scope of production planning? 1. Aggregate production planning

COMPLIANCE WITH THIS PUBLICATION IS MANDATORY

a GAO GAO DEFENSE INVENTORY Several Actions Are Needed to Further DLA s Efforts to Mitigate Shortages of Critical Parts

DOD Methodology for the Valuation of Excess, Obsolete, and Unserviceable Inventory and Operating Materials and Supplies

DoD M, June 1995

CORROSION PROJECT INSTRUCTIONS

6 Levels of Business Intelligence Value

DoD M ITEM MANAGEMENT CODING CRITERIA

BY ORDER OF THE SECRETARY OF THE AIR FORCE AIR FORCE POLICY DIRECTIVE JANUARY Supply REQUIREMENTS AND STOCKAGE OF MATERIEL

INTRODUCTION TO PARTS MANAGEMENT

Charter for the Information Technology Governance Group (ITGG)

DOD MANUAL , VOLUME 4 DOD MANAGEMENT OF ENERGY COMMODITIES: QUALITY

United States Army Logistics Integration Agency (USALIA)

financial management reform within the Department of Defense. CONTINUING LEADERSHIP COMMITTMENT

Identifying Governance Best Practices in Systems-of-Systems Acquisition

Strategic inventory management through analytics

Efficiency First Program

Defense Logistics Agency INSTRUCTION

Defense Logistics Agency Instruction. Information Technology (IT) Benchmarking

Sales & Operations Planning Trends. Summary Results October 2017

Sales & Operations Planning: An Introduction

Cost-Effective Readiness

Improving Weapon System Investment Decisions A Knowledge-based Approach to Weapon System Acquisitions Could Improve Outcomes

Balanced Scorecards. for Supply Chain Management. Casandra E. O Neall Scott S. Haraburda, Ph.D.

Transcription:

DOD MANUAL 4140.01, VOLUME 12 DOD SUPPLY CHAIN MATERIEL MANAGEMENT PROCEDURES: SALES AND OPERATIONS PLANNING Originating Component: Office of the Under Secretary of Defense for Acquisition, Technology, and Logistics Effective: March 22, 2016 Change 1 Effective: November 27, 2017 Releasability: Approved by: Change 1 Approved By: Cleared for public release. Available on the Internet from the DoD Issuances Website at http://www.dtic.mil/whs/directives. Cleared for public release. This volume is available on the Directives Division Website at http://www.esd.whs.mil/dd/. David J. Berteau, Assistant Secretary of Defense for Logistics and Materiel Readiness Judy Dahlgren, Director for Administration, for the Under Secretary of Defense for Acquisition, Technology, and Logistics Purpose: This manual is composed of several volumes, each containing its own purpose. In accordance with the authority in DoD Directive 5134.12 and DoD Instruction 4140.01: The manual implements policy, assigns responsibilities, and provides procedures for DoD materiel managers and others who work within or with the DoD supply system consistent with DoD Instruction 4140.01, and establishes standard terminology for use in DoD supply chain materiel management. This volume implements the policies established in DoD Instruction 4140.01, assigns responsibilities, and prescribes procedures for the DoD supply chain materiel management processes associated with the business management decision framework known as sales and operations planning (S&OP).

TABLE OF CONTENTS DoDM 4140.01, Volume 12, March 22, 2016 SECTION 1: GENERAL ISSUANCE INFORMATION... 3 1.1. Applicability.... 3 SECTION 2: RESPONSIBILITIES... 4 2.1. Assistant Secretary of Defense Logistics And Materiel Readiness.... 4 2.2. DoD Component Heads.... 4 SECTION 3: PROCEDURES... 5 3.1. S&OP.... 5 a. Demand Planning.... 5 b. Demand Validation.... 6 c. Supply Planning.... 6 d. Supply Response.... 7 e. Preparatory S&OP.... 7 f. Executive S&OP.... 8 g. Decision Implementation.... 9 3.2. Maturity Self-Assessment.... 9 GLOSSARY... 12 G.1. Acronyms.... 12 G.2. Definitions.... 12 REFERENCES... 14 FIGURES Figure 1. S&OP Overview... 5 Figure 2. Business Management Decision Framework Maturity Stages Overview... 10 TABLE OF CONTENTS 2

SECTION 1: GENERAL ISSUANCE INFORMATION 1.1. APPLICABILITY. This volume applies to OSD, the Military Departments, the Office of the Chairman of the Joint Chiefs of Staff and the Joint Staff, the Combatant Commands, the Office of the Inspector General of the Department of Defense, the Defense Agencies, the DoD Field Activities, and all other organizational entities within the DoD (referred to collectively in this volume as the DoD Components ). SECTION 1: GENERAL ISSUANCE INFORMATION 3

SECTION 2: RESPONSIBILITIES DoDM 4140.01, Volume 12, March 22, 2016 2.1. ASSISTANT SECRETARY OF DEFENSE LOGISTICS AND MATERIEL READINESS. Under the authority, direction, and control of the Under Secretary of Defense for Acquisition, Technology, and Logistics, the Assistant Secretary of Defense for Logistics and Materiel Readiness monitors progress towards attaining strategic objectives by reviewing DoD Component self-assessments annually. 2.2. DOD COMPONENT HEADS. The DoD Component heads must: a. Implement the procedures prescribed in this volume and ensure that supplemental guidance and procedures are in accordance with this volume. b. Establish strategic objectives for the inventory control point (ICP) that align to with overarching strategic objectives of the DoD Component and the DoD, such as those documented annually in the national security strategy, military strategy, and defense planning guidance. c. Establish key performance indicators, such as the supply chain enterprise metrics identified in Volume 10 of this manual, to measure progress toward the achievement of strategic objectives. d. Implement and use a business management decision framework to produce a balanced and actionable demand and supply plan that aligns with strategic objectives. e. Assign responsibilities for producing a balanced demand and supply plan that aligns with strategic objectives. These responsibilities will ensure there is representation from finance, acquisition, supply chain, logistics, programs, and other functional organizations deemed appropriate throughout the entire sales and operations process. f. Brief self-assessment results to Office of the Assistant Secretary of Defense for Logistics and Materiel Readiness annually. g. Maintain documentation to: (1) Monitor Component progress toward attaining strategic objectives. (2) Ensure the proper use of the business management decision framework to produce a balanced and actionable demand and supply plan that aligns with strategic objectives. (3) Ensure that ICPs conduct self-assessments of the maturity of their business management decision framework. SECTION 2: RESPONSIBILITIES 4

SECTION 3: PROCEDURES DoDM 4140.01, Volume 12, March 22, 2016 3.1. S&OP. The DoD Components will use the procedures for the business management decision framework described in this section. This exception based framework, as depicted in Figure 1, is intended to provide the DoD Components with a method to balance demand and supply at the product family level that works toward the achievement of strategic objectives. This framework includes procedures for demand planning for product families, demand validation, supply planning, supply response, preparatory S&OP, executive S&OP, and decision implementation. The outcome of each process step is communicated to all stakeholders, with the focus being on addressing any identified imbalances between demand and supply. Figure 1. S&OP Overview a. Demand Planning. Each ICP will: (1) Conduct demand planning for product families: (a) On a recurring basis. At least quarterly, review the demands that are expected to occur during the next 24 months. A more frequent cycle, such as monthly, may be implemented. (b) For the planning time horizon of demands that are expected to occur during the next 4 to 24 months, at minimum, implement a longer planning time horizon to accommodate the demands for product families (e.g., long lead time items, demand sources, and assumptions driving demands). The 0 to 4 month time horizon is execution-focused and not part of this demand planning process. SECTION 3: PROCEDURES 5

(2) Produce a single, unconstrained demand plan that combines recurring and nonrecurring demand requirements for product families. (3) Communicate the single, unconstrained demand plan to those responsible for its validation. b. Demand Validation. The DoD Components will validate the single, unconstrained demand plan on the same recurring basis as demand planning. Each ICP will: (1) Review key performance indicators relevant to demand plan validation, such as materiel readiness, responsiveness, reliability, cost, and planning and precision identified in Volume 10 of this manual. (2) Agree on and validate the single, unconstrained demand plan, considering key performance indicators and focusing on the demand for product families, not individual items. (3) Agree on assumptions about future events and use them to develop a single, unconstrained demand plan that aligns with historical trends and planned changes in operational tempo. (4) Prioritize the demand for product families after validating product support data, such as the bill of materials, according to the procedures specified in this manual. Use key performance indicators, assumptions about future events, and strategic objectives to prioritize the demand for product families. (5) Communicate the validated demand plan and the prioritization of demands at the product family level rather than item level. (6) Communicate the validated demand plan and the prioritization of demands to all stakeholders, while addressing any identified imbalances between demand and supply. c. Supply Planning. The DoD Components will develop a supply response to support the validated demand plan on the same recurring basis as the other procedural elements of S&OP. Each ICP will: (1) Ascertain and validate the cost of materiel required by the validated demand plan; available budget and resources, such as labor, equipment, and capacity; and stock requirements. (2) Identify: (a) Imbalances in demand and supply at the product family level. (b) Possible courses of action that could be taken to resolve the identified demand and supply imbalances. These courses of action may, for example, include expediting materials from third party suppliers, adding workbench or labor capacity, procurement, repair, termination, or disposal. SECTION 3: PROCEDURES 6

(3) Analyze the cost of each identified course of action and its likely impact on the achievement of strategic objectives. (4) Communicate to those responsible for preparing a supply response: (a) The identified demand and supply imbalances at the product family level. (b) The analysis of the different courses of action that can be implemented to help produce a balanced demand and supply plan that aligns with strategic objectives. d. Supply Response. The DoD Components will develop a response to the identified demand and supply imbalances on the same recurring basis as other procedural elements of S&OP. Each ICP will: (1) Review: (a) Key performance indicators relevant to developing the supply response, such as materiel readiness, responsiveness, reliability, cost, and planning and precision identified in Volume 10 of this manual. (b) The identified demand and supply imbalances at the product family level. (c) The analysis of the possible courses of supply planning actions. (2) Agree on a supply response that satisfies demand requirements that is executable without additional external review and approval. (3) For the elements of the supply response that require additional review and approval, prioritize the different, possible courses of action for addressing these remaining demand and supply imbalances at the product family level. (4) Communicate to those involved in preparatory S&OP: (a) Any remaining demand and supply imbalances at the product family level. (b) The prioritized courses of action to those involved in preparatory S&OP. (c) The agreed upon supply response that satisfies demand requirements and is executable without additional review and approval. e. Preparatory S&OP. The DoD Components will work to resolve remaining demand and supply imbalances on the same recurring basis as other procedural elements of S&OP. Each ICP who have the decision authority to resolve demand and supply imbalances will: (1) Review: (a) Key performance indicators that measure the progress towards achieving strategic objectives, such as materiel readiness, responsiveness, reliability, cost, and planning and precision identified in Volume 10 of this manual. SECTION 3: PROCEDURES 7

(b) The prioritized courses of action for reconciling remaining demand and supply imbalances at the product family level. (c) Any ongoing initiatives intended to resolve demand and supply imbalances. (2) When possible, resolve any remaining demand and supply imbalances by deciding on courses of action that maximize the possibility of achieving strategic objectives. (3) Recommend courses of action for addressing any remaining demand and supply imbalances at the product family level. (4) When applicable, propose modifications to ongoing initiatives intended to resolve recurrent demand and supply imbalances. (5) Reach decisions, recommendations, and proposals through consensus, when possible. (6) Communicate to those involved in executive S&OP: (a) Progress towards achieving strategic objectives. (b) Any remaining demand and supply imbalances at the product family level and recommendations on how they should be addressed. (c) The progress of any ongoing initiatives intended to reconcile recurrent demand and supply imbalances at the product family level and, when applicable, any proposed modifications to ongoing initiatives. (d) The agreed upon supply response that satisfies demand requirements and is executable without additional review and approval. f. Executive S&OP. On the same recurring basis as the other procedural elements of S&OP, the DoD Components will work to finalize a balanced demand and supply plan that aligns with strategic objectives. In each ICP, senior decision-makers from finance, acquisition, supply chain, logistics, programs, and other functional organizations deemed appropriate will convene to: (1) Review what has been communicated by those involved in preparatory S&OP. (2) Decide on the recommended courses of action to take in response to any remaining demand and supply imbalances at the product family level. (3) Decide on any proposed modifications to ongoing initiatives intended to prevent recurrent demand and supply imbalances. (4) Decide on any changes to future strategic objectives. (5) Communicate to all relevant stakeholders: SECTION 3: PROCEDURES 8

(a) The agreed upon, balanced, and actionable demand and supply plan that aligns with strategic objectives. (b) Any changes to future strategic objectives. (c) Any agreed upon modifications to ongoing initiatives intended to resolve recurring demand and supply imbalances at the product family level. g. Decision Implementation. On the same recurring basis as other procedural elements of S&OP, the DoD Components will: (1) For the relevant period, implement the agreed upon, balanced and actionable demand and supply plan that aligns with strategic objectives. (2) Monitor and communicate to all relevant stakeholders the progress toward achieving strategic objectives. (3) When applicable, implement changes to ongoing initiatives that were decided on in executive S&OP. Monitor and communicate the progress of these initiatives to all relevant stakeholders. (4) When applicable, document changes to strategic objectives. 3.2. MATURITY SELF-ASSESSMENT. Business management decision frameworks can exist at different stages of maturity. a. ICPs will: (1) Assess the maturity of their business management decision framework at least once every 24 months or when changes occur to: (a) Organizational or supply chain configuration. (b) Alignment between supply chain output and strategic objectives. (c) Supply chain performance indicators such as materiel readiness, responsiveness, reliability, cost, and planning and precision identified in Volume 10 of this manual. (2) Determine whether their business management decision framework is of limited, basic, or advanced capability. (3) Document the result of their self-assessment. (4) Use the business management decision framework maturity stages overview in Figure 2 as a guideline for gauging the results of the self-assessments. This issuance does not require ICPs to have a business management decision framework at a particular stage of maturity. SECTION 3: PROCEDURES 9

Figure 2. Business Management Decision Framework Maturity Stages Overview (5) Have a business management decision framework in place that is of a maturity stage that makes most business sense for them. (6) Implement a significant change or invest resources, when necessary, to move from limited to basic to advanced capability. (7) Use the results of their maturity self-assessment to help with the identification of improvement opportunities. The results of the maturity self-assessment are not necessarily intended to be used to indicate the health of the business management decision framework. The improvement opportunities identified may be realized when their potential returns outweigh the required investment. b. ICPs may self-assess their business management decision framework maturity in sstages 1, 2, or 3. (1) Stage 1 wwith llimited ccapability. (a) Business management decision framework of a limited capability has all of the procedural elements of S&OP in place. However, the different procedural elements will not be synchronized or integrated. (b) Supply planning and demand planning exists as discrete planning processes. (c) Collaboration amongst stakeholders tends to be bilateral, on an as-needed basis. SECTION 3: PROCEDURES 10

(d) Management focus tends to address issues of the day, rather than on forwardlooking issues. While performance is reviewed, it is not actively managed. (2) Stage 2 wwith bbasic ccapability. (a) Business management decision framework of basic capability has all of the procedural elements of sales and operations integrated and synchronized so that senior decision makers can actively manage performance. (b) Cross-functional stakeholders are actively involved in all procedural elements. (c) Senior decision makers clearly communicate decisions and actively monitor progress toward the achievement of strategic objectives. (3) Stage 3 wwith aadvanced ccapability. (a) Business management decision framework of advanced capability that is continuously improving the integration and synchronization of its constituent processes by making use of external benchmarks, such as other ICPs within the DoD Component or organizations external to the DoD. (b) Information systems are used to seamlessly integrate demand and supply planning processes and to implement and track the outcome of decisions reached. (c) Third party suppliers, customers, and, when applicable, other DoD Components are involved in the business management decision framework. SECTION 3: PROCEDURES 11

GLOSSARY DoDM 4140.01, Volume 12, March 22, 2016 G.1. ACRONYMS. ICP inventory control point S&OP sales and operations planning G.2. DEFINITIONS. These terms and their definitions are for the purpose of this issuance. business management decision framework. A series of processes or guidelines designed to provide the structured flow of information required for informed decision making. The processes and guidelines are documented, repeatable, and consistent across the organization. demand. An indication of a requirement, a requisition, or similar request for an item of supply or individual item. Demands are categorized as either recurring or non-recurring. executive S&OP. The process used by cross-functional, senior decision makers to review the progress of the demand and supply plan toward achieving the strategic objectives. They then decide how to address any remaining demand and supply imbalances and agree upon the strategic objectives and ongoing initiatives. ICP. An organizational unit or activity within the DoD supply system assigned the primary responsibility for the materiel management of a group of items either for a particular Military Department or for the DoD as a whole. In addition to materiel management functions, an ICP may perform other logistics functions in support of a particular Military Department or for a particular end item (e.g., centralized computation of retail requirements levels and engineering tasks associated with weapon system components). individual item. A single instance of a stock-numbered item, a single assembly, or a single subassembly. inventory. Materiel, titled to the U.S. Government, held for sale or issue, held for repair, or held pending transfer to disposal. This definition covers the same population of items as the definition for inventory in Chapter 4 of Volume 4 of DoD 7000.14-R. Inventory does not include tangible personal property to be consumed in normal operations, operating materials, and supplies as defined in in Chapter 4 of Volume 4 of DoD 7000.14-R. item of supply. A category of items identified by a national stock number with the same form, fit, and function. The individual items (units) included in this category could be manufactured by multiple sources. materiel management. The phase of military logistics that includes managing, cataloging, demand and supply planning, requirements determinations, procurement, distribution, overhaul, and disposal of materiel. GLOSSARY 12

preparatory S&OP. The process used by cross-functional stakeholders with the authority to resolve remaining demand and supply imbalances to conduct a review of the supply response progress toward achieving objectives or to recommend actions to resolve imbalances to the executive S&OP level. product family. A group of items associated with a weapon system, have similar physical characteristics, or share customer segments. single, unconstrained demand plan. The plan to produce items of supply for all demands anticipated to occur during the next 24 months without any limitations due to restraints such as funding levels. supply chain strategic objective. An objective to improve the supply chain that relates to and supports the accomplishment of a strategic objective for DoD or for the organization. For example, DoD has a strategic objective to decrease DoD expenditures on unnecessary inventory. The DoD Component supply chain strategic objective is to improve forecasting accuracy as measured by metrics for forecasted versus actual demand. GLOSSARY 13

REFERENCES DoDM 4140.01, Volume 12, March 22, 2016 DoD 7000.14-R, Department of Defense Financial Management Regulations (FMRs), dates vary by volume DoD Directive 5134.12, Assistant Secretary of Defense for Logistics and Materiel Readiness (ASD(L&MR)), May 25, 2000, as amended DoD Instruction 3000.04, DoD Munitions Requirements Process (MRP), September, 24, 2009 DoD Instruction 4140.01, DoD Supply Chain Materiel Management Policy, December 14, 2011, as amended REFERENCES 14