Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System

Similar documents
NERC Lessons Learned and Industry Recommendation

ANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM

CENTRE FOR WIND ENERGY TECHNOLOGY CHENNAI INDIAN WIND GRID CODE

SYNOPSIS OF THE THESIS. Enhanced Power Quality Management of Grid Connected Wind Farm

FRCC - PROC - RC - EOP-004. FRCC Disturbance Reporting Procedure

Inverter-Based Resources During a Cascading Failure: Present State and Future State

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017

Reliability Standard Audit Worksheet 1

ReliabilityFirst Regional Criteria 1. Verification and Data Reporting of Generator Gross and Net Reactive Power Capability

Review of AEMO s PSCAD Modelling of the Power System in South Australia

Fault Current Contributions from Wind Plants Dean Miller PacifiCorp July 25, 2012

Approved RMWG Discussion was held. ??? John Simpson need to assign SMART rating

Capacity and Location Effects of Wind Turbine Energy Systems on Power Systems Stability

ISSN Vol.07,Issue.16, November-2015, Pages:

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

WIND TURBINE PLANT CAPABILITIES REPORT

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA

DISTRIBUTED GENERATION AND POWER QUALITY

Standard MH-TPL Transmission System Planning Performance Requirements

Phasor measurement units gain credibility through improved test and calibration standards

Facility Interconnection Requirements

Operations and Maintenance Considerations for Underfrequency Relaying Design

POWER SYSTEM STABILITY GUIDELINES

Standard TPL Transmission System Planning Performance Requirements

Standard Development Timeline

FACILITY CONNECTION REQUIREMENTS NERC TO-FAC 001-0

ADDENDUM TO FINAL REPORT: RECOMMENDED TECHNICAL STANDARDS FOR GENERATOR LICENSING IN SOUTH AUSTRALIA ADVICE TO ESCOSA

Primary Frequency Response Stakeholder Education Part 1 of 2

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

Standard Development Timeline

Principles of modeling large wind parks

What makes a Wind Plant Grid Friendly?

MATL Requirements Facility Interconnection Requirements

Wind Farm Performance on the Grid: Perception and Reality

Regional Impact of Renewables: ERCOT

Generator Assessment & Roles During A Restoration

Reference Document. Interconnected Operations Services

Standard Development Timeline

Transmission Interconnection Requirements. Table of Contents

EAPP interconnection readiness workshop

Comparative Analysis between IG and DFIG for Wind Energy Conversion Systems using STATCOM

Standard Development Timeline

NERC Reliability Initiatives and Smart Grid

Online Security Analysis of Power Grids with High Wind Penetration. By Ivan M. Dudurych, Alan Rogers, Robbie Aherne, Lei Wang, Fred Howell, and Xi Lin

Hydro-Quebec s experience with HYPERSIM Real-time Power System Simulator

Platte River Power Authority. Ten-Year Transmission Plan ( )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Electricity Market Design and Structure ) Docket No.

Wind Turbine Doubly-Fed Asynchronous Machine Diagnosis Defects State of the Art

Comparative Analysis of Wind Energy Conversion System using DFIG and IG

Published on January 16, By Operations Engineering

MOD Data for Power System Modeling and Analysis

Post SAR July day Formal Comment Period with Parallel Ballot July 2013

Mapping Document. Project Phase 2 of System Protection Coordination. Revisions or Retirements to Already Approved Standards

MEASUREMENTS AND SIMULATION FOR POWER QUALITY OF A WIND FARM

Proposed Resource Loss Protection Criteria

MOD Steady-State and Dynamic System Model Validation

Lessons Learned in Wind Integration

Information Document Protection System Information ID# R

TRIP OF ERARING POWER STATION No. 1 GENERATOR TRANSFORMER AND ERARING VALES POINT 330 KV LINE ON 31 JANUARY 2018

by the Transmission Planner or Planning Coordinator.

April 26, PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination 2750 Monroe Blvd. Audubon, PA 19403

Investigation of Wind Farm Interaction with Ethiopian Electric Power Corporation s Grid

Power and Energy Systems Engineering

PRC Under Voltage Load Shedding

POWER QUALITY ASPECTS IN A WIND POWER PLANT IMAMHUSEN M PATIL. MASTER OF TECHNOLOGY IN ELECTRICAL ENGINEERING (Computer Controlled Industrial Power)

Impacts of the Decentralized Wind Energy Resources on the Grid

ELG4126 Distributed Generation and Renewables

Connection Study Requirements

Impact of Wind Integration on National Transmission Network

JOURNAL OF APPLIED SCIENCES RESEARCH

SOUTH AUSTRALIA SYSTEM STRENGTH ASSESSMENT

NERC-led Review Panel Decision on the Request by Orange Grove Energy, L.P.

STATCOM for Improved Dynamic Performance of Wind Farms in Power Grid

IRA & COP Survey Questions

PRC-006, PRC-007, and PRC-009 Mapping to Proposed Continent-Wide Standard

Control of a Microgrid in Islanded Mode

NERC Planning Committee Report

Mapping Document for FAC-010-3

ISSN Vol.09,Issue.04, March-2017, Pages:

Ancillary Service. the WEM System Management. June 2018

SPP RTO Compliance Forum TPL Jason Terhune

Criteria. C~/v~ ~ ~ ~ G! " A1A "~"" T"""g"'~10N COr'P""''~ P LG -C R-0001-V T~c~e: Transmission System Planning Criteria

Wind turbine model validation with measurements

NERC PLANNING STANDARDS

Introducing GE s

Investigation of 2006 Oahu Island-Wide Power Outage PUC Docket Number

WIND AND SOLAR FARMS TESTING REQUIREMENTS FOR CONTINGENCY FCAS REGISTRATION

Harnessing Renewables in Power System Restoration

AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS

Power system dynamic security assessment with high penetration of wind generation in presence of a line commutated converter DC link

FRCC Requirements for Analysis of Protection Misoperations and Corrective Actions Reporting

SECURITY ASPECTS OF MULTI AREA ECONOMIC DISPATCH WITH RENEWABLE ENERGY AND HVDC TIE LINES.

Low SCR Wind Identification and Mitigation. Will Lovelace MIPSYCON 2015 November 11 th, 2015

GUIDE. Part 11.1: Applicability Criteria for Compliance with NERC Reliability Standards and NPCC Criteria PUBLIC

AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES GAINESVILLE RENEWABLE ENERGY CENTER

California Independent System Operator Renewable Integration Study

Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES

Definition of Adequate Level of Reliability. Industry Webinar May 23, 2012, 1:00-3:00 p.m. ET

Transcription:

Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System Primary Interest Groups Balancing Authorities (BAs) Transmission Operators (TOPs) Generator Operators (GOPs) Generator Owners (GOs) Reliability Coordinators (RCs) Problem Statement Voltage disturbance events on the transmission system in Australia and Texas have highlighted concerns with voltage ride through and in some wind turbine control system parameters. Details South Australia Blackout Event 1 On September 28, 2016, five transmission system faults occurred within a period of 87 seconds, leading to six voltage disturbances on the South Australian (SA) grid. The SA grid has one synchronous connection to the rest of the Australian National Electricity Market grid through a 275 kv double-circuit, single-tower ac transmission line (the tie line ). At the time of the event, total load in SA was 1826 MW with 330 MW being provided by a few synchronous generators, 883 MW coming from wind, 114 MW being imported on a DC interconnector, and 499 MW being imported on the tie line. Investigations showed that there was a total sustained reduction of 456 MW of wind generation across nine wind plants, plus further transient reductions of 42 MW during each of the voltage disturbances. The sudden loss of 456 MW of generation increased import flows on the tie line, and the increased flow caused the protection system to disconnect the tie line to avoid damage, resulting in system separation from the rest of the Australian grid. The combined loss of the tie line and wind generation created a sudden supply deficit on the order of 50 percent of the pre-disturbance load. This large supply deficit resulted in very rapid system frequency decrease to below 47 Hz (Australia operates at nominal 50 Hz), causing the remaining generation and the DC interconnector to trip as expected. This resulted in the blackout of the South Australian grid. ERCOT Events Although outcomes have not been as severe as was observed in the Australian event, ERCOT has observed several situations where line faults or bus faults resulted in temporary loss of wind generation. These events provide additional understanding of the causes and recommended actions. Event 1: A 138 kv multiphase bus fault resulted in seven voltage disturbances within a ten-minute period. Investigations showed a total reduction of 475 MW of wind generation across nine wind plants during the event (approximately 56 percent of their pre-event output). The loss of generation, 1 AEMO Report Black System South Australia September 28, 2016 published March 2017

in addition to the loss of a static var compensator in the area, caused a low-voltage condition on the local transmission system. This resulted in the operation of under voltage load shed (UVLS) relays that disconnected 92 MW of firm load. Event 2: A 138 kv line fault caused a low-voltage excursion, resulting in the loss of 342 MW of wind generation across seven wind plants (a loss of approximately 36 percent of pre-event output). Five of these wind plants were connected to the 345 kv transmission grid. System frequency dipped to 59.905 Hz as a result of the loss of generation and recovered to 60 Hz in less than three minutes. Event 3: A 345 kv line fault caused a single-phase low voltage excursion (see Figure 1), resulting in the loss of 343 MW of wind generation across seven wind plants (a loss of approximately 48 percent of the pre-event output). Phasor measurement unit (PMU) data in the vicinity of the disturbance showed a voltage oscillation between 0.78 and 1.07 per-unit for less than 0.5 seconds. System frequency dipped to 59.864 Hz as a result of the loss of generation and recovered to 60 Hz in less than four minutes. Figure 1 (Event 3) Event 4: A 69 kv bus fault caused a low-voltage excursion, resulting in the loss of 230 MW of wind generation across seven wind plants (a loss of approximately 85 percent of the pre-event output). All of these wind plants were connected to the 138 kv transmission grid. PMU data from the 138 kv system in the area showed a low-voltage magnitude of 0.86 per unit and recovery to pre-event magnitude in 0.2 seconds. Event 5: A 138 kv line fault caused a low voltage excursion, resulting in the loss of 404 MW of wind generation across six wind plants (a loss of approximately 53 percent of the pre-event output). Five of these wind plants were connected to the 345 kv transmission grid. PMU data from the 345 kv system in the area showed a voltage oscillation between 0.84 and 1.09 per-unit for approximately Lessons Learned: Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System 2

0.2 seconds (see Figure 2). System frequency dipped to 59.902 Hz as a result of the loss of generation and recovered to 60 Hz in five minutes. Figure 2 (Event 5) Corrective Actions The following corrective actions were taken by the Australian Energy Market Operator (AEMO) after the September 28, 2016 event: Of the 13 wind plants that were on-line, nine did not ride through the six voltage disturbances during the event. In the days following, AEMO identified this issue and reclassified the simultaneous trip of these wind plants as a credible contingency. AEMO then worked with each of the operators of these wind plants and determined that their voltage ride-through settings were set to disconnect or reduce turbine output when between three and six voltage ride-through events were detected within a given time frame. The investigations also found that information on the control system and these parameter settings were not included in the information provided to AEMO during the registration process prior to interconnection. The wind plant operators and the turbine manufacturers proposed improved voltage ride-through settings for consideration by AEMO. As the wind plants were reconfigured with these new settings, the plants were removed from the contingency group and returned to normal operation. Lessons Learned: Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System 3

During a subsequent event on March 3, 2017, 2 the failure of a 275 kv capacitor voltage transformer resulted in a series of three transmission voltage disturbances within a 1.6 second period. All of the wind plants in the South Australia grid rode through the transmission faults with no identifiable reduction in output, indicating that the changes made since the September 28, 2016, event were successful in improving the ride-through characteristics of the wind plants. The following issues were noted by wind plant owners following the ERCOT events: During Event 2, one wind plant owner noted that 12 turbines tripped due to the failure of the wind turbine auxiliary uninterruptible power supplies (UPS) devices. UPS devices provide clean power and ride-through power for critical wind turbine auxiliary controls such as blade pitch, nacelle yaw, and brake control. UPS devices may also provide power for SCADA, metering, and other controls. The most frequent UPS failures are battery failures and environment-related (humidity, temperature, vibration) circuit board failures. The owner is investigating the cause of these particular UPS failures. One wind plant owner noted that 11 turbines tripped due to failed crowbar components in the wind turbine during Event 2. (See Attachment 1 for an explanation of crowbar circuit use in wind turbines). The facility owner updated the wind turbine semiannual maintenance process to add inspections of the Smart Crowbar circuits. During Event 5, 29 turbines tripped that did not have functioning Smart Crowbar hardware, meaning that they will only ride through voltage excursions within +/-10% of nominal voltage. During Event 1, wind plant owners noted that 130 turbines tripped due to the repeated voltage fluctuations during a particular event. The magnitude of the individual voltage disturbances were within the no trip zone of regional low-voltage ride-through requirements; however, the turbines tripped due to voltage ride-through parameters that were set to disconnect or reduce turbine output when a specified number of voltage excursions were detected within a given time frame (note that Figure 3 on the next page comes from four-second data sampling, so the actual magnitude of fluctuations may be greater than indicated). The rationale for this setting was to prevent damage to the turbine when there was insufficient recovery time between the voltage excursions. This is similar to the experiences reported by AEMO during the September 28, 2016, South Australia event. 2 AEMO Report Fault at Torrens Island Switchyard and Loss of Multiple Generating Units on 3 March 2017 published March 2017 Lessons Learned: Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System 4

Figure 3 During Event 4, multiple wind plant owners indicated that the voltage ride-through tolerance for their turbines was insufficient for the magnitude of the voltage disturbance. Those ride-through capabilities ranged from: Less than 0.80 per-unit for 0.08 to 0.2 seconds Between 0.80 and 0.90 per-unit for up to 60 seconds As noted above, ERCOT Event 1 shows similarities to the South Australia event in that it was related to repeated, rapid voltage fluctuations. The other ERCOT events, while more general in nature, provide additional support for the Lessons Learned that follow. Lesson Learned Wind generation owners should review and verify the voltage ride-through capabilities of their equipment, clearly communicate those capabilities to their BA and connected TOPs, and ensure that the models provided to the BA and TOPs correctly reflect those capabilities. If BAs and TOPs are notified by the wind generation owners that units lack ride through capability, BAs and TOPs should communicate to their RC and BAs, TOPs, and RC should consider in their daily resource plan the potential for the loss of these resources during transmission faults on the power system. BAs, TOPs, and RCs should take appropriate mitigating measures. Lessons Learned: Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System 5

Wind generation owners should review and verify that UPS and Smart Crowbar systems within the wind turbines are maintained and functioning properly. High speed PMU data is critical for visibility into the magnitude of voltage disturbances related to the loss of wind turbines (or grid resources of any type). References: AEMO Report Black System South Australia September 28, 2016 AEMO Report Fault at Torrens Island Switchyard and Loss of Multiple Generating Units on 3 March 2017 NERC s goal with publishing lessons learned is to provide industry with technical and understandable information that assists them with maintaining the reliability of the bulk power system. NERC requests that you provide input on this lesson learned by taking the short survey provided in the link below. Click here for: Lesson Learned Comment Form For more Information please contact: NERC Lessons Learned (via email) David Penney (via email) or (512) 583-4958 Source of Lesson Learned: Lesson Learned #: 20170701 Texas Reliability Entity Date Published: July 11, 2017 Category: Generation Facilities This document is designed to convey lessons learned from NERC s various activities. It is not intended to establish new requirements under NERC s Reliability Standards or to modify the requirements in any existing Reliability Standards. Compliance will continue to be determined based on language in the NERC Reliability Standards as they may be amended from time to time. Implementation of this lesson learned is not a substitute for compliance with requirements in NERC s Reliability Standards. Lessons Learned: Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System 6

Attachment 1: Simplified DFIG Wind Turbine diagram for explaining Crowbar Circuit use Most recently built wind turbines use Doubly Fed Induction Generators (DFIG) that have their stator windings connected directly to the grid, making the rotor winding susceptible to high currents induced during grid faults. The back-to-back converter subsystem (variable-ac to DC to fixed-ac) is very sensitive to over-currents. Various methods have been used to provide low voltage ride-through capability and some ability to contribute to voltage support during and after grid faults. One method is to dump excess energy with a crowbar system, which intentionally shorts out the rotor windings through large resistors when predetermined thresholds of measured parameters are reached, usually based on the DC-link voltage level in the back-to-back conversion system. In addition, a combination of blade pitch control and braking is typically used to quickly reduce the mechanical energy input. Lessons Learned: Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System 7