RIVER PROTECTION PROJECT WASTE TREATMENT PLANT CONCEPT AND APPROACH. M. J. Lawrence, British Nuclear Fuels Ltd., Inc.

Similar documents
Supplemental Treatment Hanford Immobilized Low Activity Waste Discussion National Academies of Sciences, Engineering, and Medicine

WM2016 Conference, March 6 10, 2016, Phoenix, Arizona, USA. Integrated Waste Feed Qualification Program for Direct LAW Feed to WTP 16421

HANFORD TANK WASTE TREATMENT SYSTEM. T. Z. Smith, S. A. Wiegman U.S. Department of Energy, Office of River Protection

Jane Hedges, Manager, Nuclear Waste Program Washington Department of Ecology

Analysis of Approaches for Supplemental Treatment of Low-Activity Waste at the Hanford Nuclear Reservation

THE SAVANNAH RIVER SITE ACCELERATED CLEAN-UP MISSION: SALT WASTE DISPOSAL. P. C. Suggs USDOE Savannah River Site Aiken, South Carolina

WM2011 Conference February 27 - March 3, 2011, Phoenix, AZ

Hanford Overview. SITE OWNER US Dept of Energy. SIZE 586 square miles. NEARBY TOWNS Richland, Pasco, total pop ~250,000 WORKFORCE ~11,000

WM2016 Conference, March 6 10, 2016, Phoenix, Arizona, USA

Hanford Low Activity Waste Historical Overview. David Swanberg February 2018

Hanford Tank Wastes from Past Production of U.S. Nuclear Weapons: Statutory Authorities and Related Issues

GESTION DES DECHETS RADIOACTIFS AUX USA

PROTECTING NORTHWEST STAKEHOLDERS FROM HANFORD S TANK WASTE Suzanne Dahl Washington State Department of Ecology

WM2015 Conference, March 15-19, 2015, Phoenix, Arizona, USA

WM Symposia AND FY 2013 Budget Overview. David Huizenga Senior Advisor for Environmental Management February

Vitrification of Three Low-Activity Radioactive Waste Streams from Hanford

The following assumptions apply for the immobilization alternatives:

Tank Waste and Nuclear Materials Disposition. Steve Schneider Director, Office of Tank Waste Management (EM-21) March

The Waste Treatment Plant, a Work in Progress

Recycling of UNF. Paul Murray

West Valley Demonstration Project Overview

Hanford Site Outlook

Waste Management Fiscal Year 1998 Progress Report

DOE ORDER "RADIOACTIVE WASTE MANAGEMENT" SRS & DOE COMPLEX IMPLEMENTATION ISSUES AND COSTS. W.T. Goldston Westinghouse Savannah River Company

WM2012 Conference, February 26 March 1, 2012, Phoenix, Arizona, USA

Overview of the U.S. Department of Energy Office of Environmental Management Mission

DOE Environmental Management Clean Up Focus for FY

Full Focus Needed on Finishing Hanford s Waste Treatment Plant

WM2016 Conference, March 6 10, 2016, Phoenix, Arizona, USA

Analysis of Approaches for Supplemental Treatment of Low-Activity Waste at the Hanford Nuclear Reservation

Low Activity Waste Pretreatment System (LAWPS) Conceptual Design Approach David J Houghton

WM 05 Conference, February 27 March 3, 2005, Tucson, AZ THE ARCHIMEDES FILTER PLANT: A NEW CONCEPT FOR REDUCING THE AMOUNT OF HLW AT HANFORD

DOE Environmental Management Brief

RADIOACTIVE WASTE MANAGEMENT PROGRAMMES IN OECD/NEA MEMBER COUNTRIES UNITED STATES NATIONAL NUCLEAR ENERGY CONTEXT

SRS Liquid Waste Program

In the early 1990s, KHNP considered vitrification technology as a prospective candidate for the

Technical Aspects of the Plutonium Vitrification Option (u)

Attachment 51 River Protection Project Waste Treatment Plant 09/02. Appendix 3B. 2 Quality Assurance Project Plan for Waste Analysis Plan.

With this FY 2007 budget request, we are proposing several shifts between program offices with the completion of cleanup.

ORPHAN RADIOACTIVE WASTE: INDEFINITE STORAGE OR TRANSITION TO DISPOSAL?

How does the WIPP shutdown Impact New Mexico, Idaho, and South Carolina?

Key Functions and Activities for the Office of Nuclear Materials Disposition Within the Environmental Management Program

WM2015 Conference, March 15 19, 2015, Phoenix, Arizona, USA

WM2008 Conference, February 24 28, 2008, Phoenix, AZ. Sodium Recycle Economics for Waste Treatment Plant Operations 8341

Department of Energy Spent Nuclear Fuel - Update. Outline

WM2013 Conference, February 24 28, 2013, Phoenix, Arizona USA. Waste Feed Delivery Planning at Hanford 13232

OFFICE OF INSPECTOR GENERAL U.S. Department of Energy. AUDIT REPORT OAI-L September 2017

WM2013 Conference, February 24 28, 2013, Phoenix, Arizona, USA

System Plan 8 Baseline Case Supplemental LAW Sizing

Waste Management Idaho Lessons Learned

FFTF DECOMMISSIONING. FFTF Decommissioning Alternative 1: No Action. FFTF Decommissioning Alternative 2: Entombment

Radioactive Waste Determination Process Plan for Waste Management Area C Tank Waste Residuals

APPENDIX G IMPACTS OF PLUTONIUM DISPOSITION OPTIONS

Technical Summary Report For Surplus Weapons-Usable Plutonium Disposition

THE AMERICAN REINVESTMENT AND RECOVERY ACT: U.S. DEPARTMENT OF ENERGY ENVIRONMENTAL CLEANUP OPERATIONS

Radioactive Tank Waste from the Past Production of Nuclear Weapons: Background and Issues for Congress

Demonstration Bulk Vitrification System (Dbvs) External Review

Radioactive Waste Management Offering Integrated Governance and Experience for International Nuclear Solutions. Tim Milner Atkins Fellow

RADIOACTIVE WASTE MANAGEMENT PROGRAMMES IN OECD/NEA MEMBER COUNTRIES UNITED STATES [2011]

STGWG Open Session with Environmental Management

Infrared Thermography at the Savannah River Site

Headlines. Industry news. WCS Receives LLW, Hazardous Waste Permits. DOE Reports to Congress on Interim Storage, Second Repository

Vitrification Technology for Treating Low-Level Waste from Nuclear Facilities

Deployment of Performance Management Methodology as part of Liquid Waste Program at Savannah River Site 12178

History of Supplemental LAW Treatment Reviews. David Swanberg February 2018

WM2013 Conference, February 24 28, 2013, Phoenix, Arizona, USA. Observational Approach to Chromium Site Remediation 13266

Savannah River Site Missions, Accomplishments and Funding

DISPOSAL OF NONROUTINE HIGH LEVEL WASTE IN DWPF CANISTERS AT SAVANNAH RIVER SITE A PRECEDENT THROUGHOUT THE DWPF COMPLEX

Control of the Reduction/Oxidation State of the High Level Waste Form in the Defense Waste Processing Facility at the Savannah River Site

FISCAL YEAR 2013 ANNUAL Report

DEVELOPMENT OF WET-OXIDATION TREATMENT SYSTEM FOR FILTER BACKWASH SLUDGE AND ION EXCHANGE RESINS

Tank Farm Remediation Technology Development Project: An Exercise in Technical and Regulatory Collaboration

WIPP and Surplus Plutonium

R & D to Support Management of the Nuclear Legacy

Reprocessing and Spent Nuclear Fuel Management at the Savannah River Site

Development of a Crossflow Filter to Remove Solids from Radioactive Liquid Waste: Comparison of Test Data with Operating Experience

Headlines. House Appropriations Committee Passes Energy Budget. Hanford Vit Plant Project to Restart in Autumn; Other Hanford Updates

Transportation in Environmental Cleanup

INTRODUCTION. Note: The following is based on The Principles of Radioactive Waste Management [1].

Rheology of Sa Sludge

Progress on Footprint Reduction at the Hanford Site

TRADEMARK DISCLAIMER. Printed in the United States of America

Emerging Issues With U.S. DOE Prime Contractors

WM2013 Conference, February 24 28, 2013, Phoenix, Arizona, USA. NRC Monitoring of Salt Waste Disposal at the Savannah River Site 13147

HANFORD S GROUNDWATER/VADOSE ZONE INTEGRATION PROJECT PROTECTING THE COLUMBIA RIVER

CHAPTER 5 QUANTITIES, SOURCES, AND CHARACTERISTICS OF SPENT NUCLEAR FUEL AND HIGH-LEVEL WASTE IN THE UNITED STATES

U.S. Nuclear Regulatory Commission Standard Review Plan for Activities Related to U.S. Department of Energy Waste Determinations

CONTENTS ACRONYMS AND ABBREVIATIONS... 5

Acceptance and Disposition of Department of Energy Spent Nuclear Fuel

HANFORD SITE WASTE TREATMENT/STORAGE/DISPOSAL INTEGRATION. Kent M. McDonald Waste Management Federal Services of Hanford, Inc. Richland, Washington

Overview of Spent Fuel Management Programs

Washington Closure Hanford: Cleaning up the River Corridor

Notice of Availability of the Final Environmental Impact Statement for the Disposal of Greater-

A Brief, Draft Overview June 3, 2017 Comments Welcome

Salt Processing through Ion Exchange at the Savannah River Site Selection of Exchange Media and Column Configuration

Mini-project report. Life Cycle Analysis of the Nuclear Fuel Cycle. Sellafield High Level Waste Plants 2010/11

Glass Formulation Requirements for Hanford Coupled Operations Using Crystalline Silicotitanates (CST)

EM Transportation Update

For a Cleaner Future. Founded: 2008 Today: 200 know-how experts and growing. Irvine HDQR. Tokyo, Japan. Sellafield, UK

Strategy for the Management and Disposal of Used Nuclear Fuel and High Level Radioactive Waste

Transcription:

RIVER PROTECTION PROJECT WASTE TREATMENT PLANT CONCEPT AND APPROACH M. J. Lawrence, British Nuclear Fuels Ltd., Inc. ABSTRACT The River Protection Project Waste Treatment Plant (RPP-WTP) is a privatized facility to be built for processing and vitrifying of radioactive tank waste at the U.S. Department of Energy s (DOE) Hanford Site in Richland, Washington. As the leader of the RPP-WTP Project team, British Nuclear Fuels Ltd., Inc., entered into contract with DOE for a 24-month design period (August 1998 to August 2000). Information derived during this design period will be used as the basis to establish fixed-unit prices for the waste treatment services. This paper describes the concept of the RPP-WTP Project, outlines the privatization approach, presents the strengths behind this approach, and summarizes the technical progress that has been made toward accomplishing the cleanup goals. INTRODUCTION In August 1998, the U.S. Department of Energy (DOE) signed a privatization contract with British Nuclear Fuels Ltd., Inc. (BNFL). This contract authorized a 24-month design period for the RPP-WTP. The RPP-WTP is the facility to be used for treatment of tank wastes at DOE s Hanford Site, located in southeast Washington State (Fig. 1). The design period, ending in August 2000, is expected to result in sufficient engineering and financial maturity to establish fixed-unit prices for treatment services and to finalize project financing. Based on the design, development, and testing performed during this period, BNFL is expected to submit a firm fixed price proposal to DOE by April 24, 2000. DOE will decide, by August 24, 2000, whether to proceed with the subsequent construction and operation portion of the RPP-WTP Project. If DOE decides to proceed, BNFL will build and operate the RPP-WTP for a minimum of 10 years during which approximately 10 percent of the Hanford tank waste by mass and up to 25 percent by radioactivity will be processed and vitrified. PROJECT CONCEPT The proposed RPP-WTP will be located at the center of the Hanford Site, adjacent to the 200 East Area and in the vicinity of the underground storage tanks (see Fig. 1). Under DOE management, the contractor responsible for storage and retrieval of the tank waste, CH2M HILL Hanford Group, Inc. (CHG), would provide selected tank waste for treatment at the RPP-WTP. Treatment of the tank waste comprises two major steps: 1. Pretreatment to minimize waste volume and separate the tank waste into high-level waste (HLW) and low-activity waste (LAW) streams. 2. Vitrification of the HLW and LAW.

RPP-WTP Project Site RPP = River Protection Project WTP = Waste Treatment Plant 1,450 km 2 Fig. 1. Location of the Hanford Site in Washington State, showing the location of the River Protection Project Waste Treatment Plant. The treatment process begins with CHG transferring the liquid fraction from the Hanford Site tanks to an evaporator feed tank at the RPP-WTP. The liquid feed is concentrated through a forced circulation evaporator and cooled to about 30 ºC. The concentrated liquid then is processed through a cross-flow filter unit to remove solids. For a part of the liquid containing strontium and transuranic elements, a precipitation process is used to remove these constituents. The resulting filtrate is fed through ion exchange columns (organic-based resins) to separate out cesium and technetium. Sulfate is also removed by means of a precipitation process and disposed of as radioactive mixed solid waste. After removal of all these elements, the liquid becomes decontaminated LAW and is concentrated in a forced circulation evaporator. Glass formers are added to this concentrate, and the mixture is vitrified into LAW glass that is poured into containers. The HLW sludge from selected Hanford Site tanks is slurried and transferred through doublewalled underground pipeline to the HLW feed receipt tanks at the RPP-WTP. This slurry along with radionuclides removed from the LAW pretreatment process are blended with glass formers, vitrified into HLW glass, and poured into canisters. After vitrification, all glass containers/canisters are sealed, decontaminated, and delivered by BNFL to CH2M Hill. The DOE disposes of the LAW containers on site and ships the HLW canisters to an onsite storage facility for interim storage, then to a geologic repository in accordance with requirements of the Nuclear Waste Policy Act. The project concept is depicted in Fig. 2.

Hanford Tank Farms (177 tanks) BNFL = British Nuclear Fuels Ltd., Inc. DOE = U.S. Department of Energy HLW = high-level waste LAW = low-activity waste DOE ships HLW canisters to offsite repository Fig. 2. The River Protection Project Waste Treatment Plant Project Concept. Vitrification of HLW has been done successfully in the United Kingdom, France, Japan, and in the U.S. at the West Valley Project at West Valley, NY, and the Defense Waste Processing Facility (DWPF) Project at the Savannah River Site, SC. Vitrification of LAW has been demonstrated successfully at the M-Area melter at the Savannah River Site, SC. The West Valley melter and the M-Area melter were used as the basis for design of the proposed HLW and LAW melters, respectively, at the RPP-WTP. In addition, an HLW pilot melter at Washington, D.C., and an LAW pilot melter at Columbia, MD, are being used to test the design concept and verify the proposed melter capacities. Summaries of the melter experience and the RPP-WTP Project melters appear in Tables I and II. Conceptual design of the RPP-WTP includes a pretreatment building, an HLW vitrification building, an LAW vitrification building, and allocated space for a future LAW vitrification building the same size as the existing one (so that the throughput can be doubled). A site model for the RPP-WTP is shown in Fig. 3. Initially, 10 percent of the tank waste containing up to 25 percent of the total radioactivity will be immobilized by 2018 for an estimated $6.9 billion (in 1997 dollars). The plant is designed to vitrify HLW at 1.5 metric tons per day and LAW at 30 metric tons per day. One HLW melter and three LAW melters will be used to meet this generation rate. The base load over the initial period is 600 HLW canisters (1,860 metric tons glass) and approximately 6,000 LAW containers (40,400 metric tons glass).

Location La Hague, France Sellafield, United Kingdom Pamela, Belgium West Valley, New York DWPF at SRS, South Carolina M-Area at SRS, South Carolina a Still in operation. Melter Type Inductively Inductively Table I. Summary of Melter Experience. Waste Type Melter Capacity (t/day) Number of Melters Number of Years Total Glass Produced (t) HLW 0.6 6 10? HLW 0.4 2 10 750 a HLW 0.25 1 6 490 HLW 0.9 1 2 640 HLW 2.4 1 3 1,500 a LAW 4.8 1 0.9 1,000 DWPF = Defense Waste Processing Facility HLW = high-level waste LAW = low-activity waste SRS t = Savannah River Site = metric ton Location HLW Pilot Melter at Washington, D.C. RPP-WTP at Hanford Site, Washington LAW Pilot Melter at Columbia, Maryland RPP-WTP at Hanford Site, Washington Table II. River Protection Project Waste Treatment Plant Melters. Melter Type a Still in operation. HLW = high-level waste LAW = low-activity waste Waste Type HLW Simulant Melter Capacity (t/day) Number of Melters Number of Months Total Glass Produced (t) 1 1 1 a 5 a HLW 1.5 1 Proposed LAW Simulant 3.3 1 11 a 490 a LAW 10 3 Proposed RPP-WTP = River Protection Project Waste Treatment Plant t = metric ton

High-Level Waste Vitrification Bldg Pretreatment Building Service Building N Melter Assembly Building Low-Activity Waste Vitrification Bldg Future Low-Activity Waste Vitrification Building Site Fig. 3. Site Model of River Protection Project Waste Treatment Plant. The RPP-WTP is designed for a 40-year life and can be expanded to deal with the remainder of the tank waste at a significantly lower unit cost since the plant s capital cost will be paid for in the initial phase. PROJECT APPROACH Administration Building The RPP-WTP Project is being implemented through privatization. Specific provisions were built into the contract between DOE and BNFL to develop the necessary technical, operational, regulatory, and business elements to reduce uncertainties and provide performance assurance for the project. Financial risks are being shared by DOE and BNFL to provide incentives as well as a balance between the two parties. Under this approach, the project includes the following major features: BNFL owns, designs, constructs, operates, and deactivates the RPP-WTP. The DOE is the customer and regulates radiological, nuclear, process, and industrial safety. The Washington State Department of Ecology, Washington State Department of Health, and the U.S. Environmental Protection Agency issue environmental permits. The U.S. Department of Transportation and the Washington State Department of Ecology regulate offsite waste shipment.

BNFL performs design and development before both parties commit to the price and schedule of the treatment services. The DOE buys services at fixed prices. Congressional appropriations are only set-asides and will not be expended until BNFL delivers the conforming product. Using this project approach to complete treatment of the prescribed tank waste by 2018 requires that a number of milestones be accomplished. The target dates for accomplishing these milestones are listed in Table III. Table III. Milestone Dates for River Protection Project Waste Treatment Plant. Milestone Contract Target Date Begin construction (first pour) July 2001 Pretreatment hot start April 2006 Begin pretreatment service November 2006 HLW hot start February 2007 LAW hot start January 2008 Begin HLW treatment service July 2008 Begin LAW treatment service April 2009 Complete all treatment services February 2018 Complete RPP-WTP deactivation February 2019 HLW = high-level waste LAW = low-activity waste RPP-WTP = River Protection Project Waste Treatment Plant STRENGTHS OF THE PROJECT Implementing the above project approach is a tremendous challenge that requires a long-term commitment from both parties. For BNFL, the first step in demonstrating its capabilities and commitment to meet this challenge is to assemble a world-class team. This team consists of BNFL, Bechtel, Science Applications International Corporation (SAIC), and GTS Duratek. BNFL is a pioneer in the nuclear industry with over 50 years of experience in fuel cycle operation and waste management, including radioactive waste processing and vitrification. Created out of United Kingdom Atomic Energy Authority in 1971 to operate commercially in a privatized manner, BNFL has processed more than 400 million curies since 1990. This amount is more than double the Hanford Site tank waste inventory of 190 million curies. Bechtel is the most experienced and successful nuclear construction company in the world, with experience both in commercial and in DOE nuclear facilities. SAIC is a world leader in regulatory compliance; it has performed nuclear compliance and permit application at the Hanford Site for

more than 10 years. GTS Duratek is a national leader in LAW and mixed-waste vitrification; it has successfully vitrified LAW at the Savannah River Site under a privatization contract. At the present, the RPP-WTP Project team comprises more than 600 professionals (including 100 from the United Kingdom) doing the design and development work necessary to support a firm fixed-price proposal to DOE in April 2000. In addition, the project team is involved in research, development, and laboratory testing of pretreatment and vitrification technologies using expertise from around the country. Individual groups supporting this effort include members from the Savannah River Technology Center, Pacific Northwest National Laboratory, and Vitreous States Laboratory at Catholic University. This design and development phase before the fixed-price proposal is a critical difference between this and previous DOE privatization contracts; it will lead to a realistic cost/schedule estimate and build confidence that the project can meet its cleanup goals. Based on our current estimates, BNFL expects its proposed fixed-unit price will be less than half the unit cost of vitrifying waste at Savannah River (Table IV). Under the contract with DOE, BNFL is taking cost, schedule, and operational performance risks associated with the RPP-WTP Project. For example, the BNFL team is making an equity commitment of up to $500 million -- at risk to fund the project and is borrowing the balance from financial institutions. The taxpayer will pay for this service only when the product is delivered. Table IV. Unit Cost of Vitrification. Average Unit Cost Product Cost High-level Waste Vitrification Project (dollars per Ratio t glass) Proposed River Protection Project Waste 300,000 1 Treatment Plant at Hanford Site, Washington Defense Waste Processing Facility at Savannah River Site, South Carolina West Valley Demonstration Project at West Valley, New York t = metric ton 670,000 2.2 1,228,000 4 A benefit of the privatization contract is that it provides BNFL with the flexibility to follow best commercial practices and procure at best value. The project will create a large number of domestic jobs over its lifetime. Employment level will grow to more than 3,500 at the peak of construction in 2003, then level out with an operations staff of approximately 500 from 2010 on. Local wages during the design and construction phase will be $60 million to $90 million per year with an estimated $50 million of non-labor services purchased. RECENT PROGRESS Since the beginning of the project, BNFL has spent more than $50 million on development and laboratory testing and has invested another $34 million in private funding on pilot melters to test

the RPP-WTP vitrification concepts. The HLW pilot melter (two-thirds scale) located at Catholic University, Washington, D.C., has produced 5 metric tons of glass in the first10 days of operation. Test results have been analyzed for use in the design of the full-scale HLW melter. Performance of the LAW pilot melter at Columbia, MD, has been spectacular. The full-scale, one-third-length pilot melter has produced more than 330 metric tons of glass in the first nine months with a glass production rate of 4.8 metric tons per day, exceeding its design capacity by 50 percent. Pretreatment testing of both HLW and LAW is also underway. The purpose of pretreatment is to reduce the volume (waste minimization) and improve the quality of the glass. The test strategy includes simulant and actual tank waste samples supplied by DOE through CH2M HILL. Simulant tests provide a range of variation, while tank waste tests provide verification. For HLW pretreatment testing, DOE selected five candidate tanks for removal of constituents such as sodium and aluminum. BNFL has completed testing samples from three tanks, and results indicated that the pretreatment process was working well within expectation. Testing of all candidate tanks will be completed and the results reported by August 2000. For LAW pretreatment testing, DOE selected up to ten candidate tanks for removal of various elements including cesium, technetium, strontium, transuranic elements, and sulfate. Testing to date has shown that products from the ion exchange and precipitation processes proposed for the RPP-WTP can comply with regulatory requirements. However, trials have shown difficulty in meeting product and process control limits for sulfate. The ion exchange method established as the baseline process for sulfate removal failed to achieve the removal requirements. Alternative approaches are being evaluated at this time. As we discussed earlier, under the privatization contract BNFL performs design and development before both parties commit to the price and schedule of the treatment services. The benefit of this contracting approach is demonstrated in the selection of a suitable process for sulfate removal. Results of the sulfate removal testing and all other LAW pretreatment testing will be reported by August 2000. CONCLUSION Cleaning up Hanford Site tank waste is the most challenging environmental project facing the United States today. The Clinton Administration continues to fully support the River Protection Project, and an outstanding team of DOE Office of River Protection (ORP), CH2M HILL, and the BNFL team is dedicated to meet this challenge. The RPP WTP will be the largest capital project in the federal government. The project team led by BNFL is making progress to demonstrate its capabilities and commitment to accomplish the cleanup goals. This progress also indicates that a privatization approach can be successful if risks are shared efficiently and the required project funding is set aside by Congress as planned. The initial single shell tanks are over twenty years past their design life, and almost half have leaked. Further failure of these tanks and transfer lines are inevitable. Delaying cleanup will only result in greater costs and environmental damage. On April 24, 2000 BNFL will submit a

fixed price proposal to DOE ORP to begin treating this waste. After negotiation and Congressional review we hope to receive Authorization to Proceed by August 24, 2000. The Hanford Site tank waste was created in the winning of both World War II and the Cold War, and we must complete the process of safely disposing of it. There is a childhood saying that goes When you re finished playing, put away your toys. It certainly applies to the Hanford waste. We have the best available means to do it now. Let s get on with it!