Behavior of Surrounding Soil during Construction and Its Countermeasures Using Pipe Jacking Method in Deep Strata

Similar documents
ON THE BEHAVIOR OF A STUCK CURVED PIPE JACKING

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Design of pipeline installation. D-Geo Pipeline

Design of pipeline installation D-GEO PIPELINE

Research on the Effects of Foundation Excavation by the Environment

Concrete Pipe Jacking

Pipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2

4D grouting pressure model of a bored tunnel in 3D Tunnel

Relationship between twin tunnels distance and surface subsidence in soft ground of Tabriz Metro - Iran

Experts in tunneling with Tunnel Boring Machines

Evaluation of negative skin friction on sheet pile walls at the Rio Grande dry dock, Brazil

PIPE JACKING. An introduction to pipe jacking prepared by the Pipe Jacking Association

EFFECT OF DEEP EXCAVATION SUPPORTED BY CONCRETE SOLIDER PILE WITH STEEL SHEET PILE LAGGING WALL ON ADJACENT EXISTING BUILDINGS

4D grouting pressure model PLAXIS

Pipe Jacking. Japan Sewage Works Association

SPECIAL CONDITIONS FOR MICROTUNNELING (MT) October, 2006

Performance review of a pipe jacking project in Hong Kong

Developed countries require a modern infrastructure Roads Railways Power Communications Water Wastewater

Numerical Analysis of Pipe Roof Reinforcement in Soft Ground Tunnelling

Comprehensive experimental study on prevention of land subsidence caused by dewatering in deep foundation pit with hanging waterproof curtain

Effect of Cavities on the Behaviour of Strip Footing Subjected to Inclined Load

Numerical Simulation of Liquefaction Deformation of Sand Layer around Bucket Foundations under Dynamic Loadings

Available online at ScienceDirect. Procedia Engineering 189 (2017 ) 11 17

Research on Mutual Influence between Pipes of Curved Pipe-jacking Roof Project

Seepage-Stress Coupled Analysis on Shield Tunnel Face Stability in Layered Soil

An introduction to. pipe jacking

Three-dimensional computer simulation of soil nailing support in deep foundation pit

Misan University - College of Engineering Civil Engineering Department

TBM rescue projects using shafts and ground freezing

Analyzing and Investigating the Effect of Nailing on Stabilization Soil Trenches of Sand with Medium Density via Analytical Limit Equilibrium

EFFECT OF THE GRID-SHAPED STABILIZED GROUND IMPROVEMENT TO LIQUEFIABLE GROUND

Strengthening of Deteriorated Small-Diameter Sewage Pipes for Increasing their Service-Life and Seismic Resistance

SETTLEMENTS DUE TO TUNNEL CONSTRUCTION

NUMERICAL ANALYSIS OF TUNNEL BORING MACHINE IN SOFT GROUND M. E. LEl-Kilany 1, T. A. EL-Sayed 2 *, R. A. Mohab 3

Study on earth pressure acting upon shield tunnel lining in clayey and sandy grounds based on field monitoring

Comparison of the results of load test done on stone columns and rammed aggregate piers using numerical modeling

Analytical and Numerical Solutions of Tunnel Lining Under Seismic Loading and Investigation of Its Affecting Parameters

Modeling of TBM Tunnel Construction for the Greater Cairo Metro Line 3

NUMERICAL ANALYSIS OF GEOSYNTHETIC REINFORCED SOIL ABOVE A TUNNEL

No-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e.

LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL

Numerical Analysis of Piles in Layered Soils: A Parametric Study By C. Ravi Kumar Reddy & T. D. Gunneswara Rao K L University, India

Behaviour of Strip Footing on Geogrid Reinforced Slope subjected to Eccentric Load

Aseismic Capacity of Telecommunication Conduit Repaired with Linings

Mechanical properties of multiple large-diameter corrugate steel pipes in embankment

[Kouravand Bardpareh* et al., 5(6): July, 2016] ISSN: IC Value: 3.00 Impact Factor: 4.116

A THREE DIMENSIONAL STUDY OF THE EFFECT OF SOIL EROSION ON RIGID PIPES

4th International Engineering and Construction Conference - July 28, 2006

Estimation of Lateral Earth Pressure on Cantilever Sheet Pile using Flat Dilatometer Test (DMT) Data: Numerical Study

Mechanical Splice of Grid CFRP Reinforcement and Steel Plate

Development of Flash Setting Material for Temporally Pipeline Restoration after Earthquake

Determining radius of influence of the face in EPB shield tunneling by finite difference method.

ANALYSIS OF DIFFERENT LOADS AFFECTING THE URBAN RAILWAY TUNNEL SYSTEMS OF CAIRO METRO UNDERNEATH THE RIVER NILE

Analysis of Retaining Structure of Deep Foundation Pit in Soft Soil Stabilization of Pumping Station * Yanming Chen and Wei Wu

INFLUENCE OF GROUND IMPROVEMENT AND CONSTRUCTION MANAGEMENT ON SHIELD TUNNEL EXCAVATION: A CASE STUDY OF KAOHSIUNG MASS RAPID TRANSIT SYSTEM

Axially Loaded Behavior of Driven PC Piles

Concrete Pipe Jacking

BEARING CAPACITY IMPROVEMENT USING MICROPILES A CASE STUDY

Professor, Dept. of Construction, Nihon University Junior College, Japan 2. Manager, Taisei Corporation, Japan 4

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

Research Paper PERFORMANCE OF STRIP FOOTING ON SANDY SOIL DUE TO TUNNELING S.Hariswaran 1, K.Premalatha 2, K.Raja 3

The Application of Foundation Pit Monitoring Technology to the Excavation

Prediction Method for Reservoir Collapse During Earthquakes

Analysis of skin friction in prebored and precast piles

Underground Construction Technology

DIFFICULT GROUND SOLUTIONS:

Tunnels. Introduction in Shield tunnelling Pipe jacking & tunnelling Slurry & hydroshield Slurry versus EPB Principles of support pressure

Development of New H-Section Steel Shape with Inner Rib, J-grip H, and Its Application to Steel Concrete Composite Diaphragm Wall

Zoning Supporting Design of Deep Foundation Pit Based on Controlling Deformation of Surrounding Buildings

Parametric Analysis on the Optimal Dimensions of Steel Sleeve in Swaging Type Anchorage for CFRP Tendon

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

Uplift Pressure Resistant Approach in Diaphragm Wall Excavation-case Study: Imam Hossein Holy Shrine Development -Karbala- Iraq

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by

STUDY ON THE TUNNEL SECONDARY LINING CONCRETE CRACKING PERFORMANCE DURING SERVICE PERIOD OF WU- GUANG PASSENGER DEDICATED LINE

Jinfeng Zhang 1, Wangsheng Liu 1, Ming Zhao 1 1. College of Civil Engineering, Tongji University, Shanghai , China.

Design Data 4M. Jacking Concrete Pipe

Prof. Eng. Daniele PEILA & Prof. Eng. Sebastiano PELIZZA

Load transfer on single pile near new tunneling in sandy ground

UNDERPINNING A CRANE FOUNDATION

REPAIR OF DISPLACED SHIELD TUNNEL OF THE TAIPEI RAPID


LONG-TERM MONITORING AND SAFETY EVALUATION OF A METRO STATION DURING DEEP EXCAVATION

Settlement assessment of running tunnels a generic approach

Damage states of cut-and-cover tunnels under seismic excitation

Evaluation conduct of deep foundations using 3D finite element approach

Numerical Analysis of Face Stability of Slurry Pipe Jacking Tunnel in Frozen Ground

UPSC ESE/IES Civil Engineering Syllabus

Prediction of Surface Subsidence Caused by Rectangular Pipe Jacking Construction

NPTEL Course GROUND IMPROVEMENT USING MICROPILES

QUANTIFYING THE EFFECTS OF LUBRICATION ON JACKING FORCES

The influence of tunnel boring on foundations and buildings in urban areas - A numerical study

Chapter 11 Compressibility of Soil

Numerical Modeling of Soil Improvement for Construction of Tunnels Using Forepole Presupport

SOIL PRESSURE IN EMBANKMENT STABILIZATIONS

Microtunnelling. Building infrastructures and power supply systems underground, while life above continues unaffected.

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES)

Ching Guan Kee ABSTRACT

THE STUDY OF t-z AND q-z CURVES ON BORED PILE BASED ON THE RESULTS OF INSTRUMENTED PILE LOAD TEST IN MEDIUM AND STIFF CLAYS

Design Data 4. Jacking Concrete Pipe

Comparison of geotechnic softwares - Geo FEM, Plaxis, Z-Soil

Transcription:

Open Journal of Geology, 2013, 3, 44-48 http://dx.doi.org/10.4236/ojg.2013.32007 Published Online April 2013 (http://www.scirp.org/journal/ojg) Behavior of Surrounding Soil during Construction and Its Countermeasures Using Pipe Jacking Method in Deep Strata Takashi Senda, Hideki Shimada, Takashi Sasaoka, Kikuo Matsui Department of Earth Resources Engineering, Kyushu University, Fukuoka, Japan Email: m-sen@obayashi-road.co.jp Received February 4, 2013; revised March 8, 2013; accepted April 8, 2013 Copyright 2013 Takashi Senda et al. This is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited. ABSTRACT In Japan when urban infrastructures need to be constructed, the difficulty of utilizing the ground or shallow strata will lead to a more frequent use of the deep strata. The common construction methods are open-cut, pipe jacking, and shield methods. In recent years, a new pipe jacking method has been established that can be adapted to 20 m below the ground or more. Using this method, the drivage machine and the jacking pipe continue to move an underground until the completion of the driving. Therefore an over-cutting area (so-called tail-void) must be formed to lower the friction between the ground and the pipe. The tail-void is filled with lubrications. However, because the stress release from the ground continues to advance when the tail-void is formed, hence there are some challenges required to cope with the stability of the surrounding ground. In order to utilize the pipe jacking method in the deeper strata layers, the theory, analysis and installation of tail-void have to be systemized, and such systematic data must be stored. Therefore, the conditions of tail-void in the deep pipe jacking method are discussed using numerical analyses. Keywords: Pipe Jacking System; Deep Strata; Tail-Void 1. Introduction In Japan, the land of large metropolitan areas is highly utilized in increasingly complex conditions; therefore, the underground area is used to establish social infrastructures because of difficulties to use on the ground. Even in the publicly used shallow strata such as road sections, social infrastructures including subways, water and sewage systems, electrical equipment, communications facilities, and gas pipelines have already been installed and are very congested. Nowadays, when urban infrastructures need to be further constructed, the difficulty of using the ground or shallow strata will lead to the more frequent use of the deep strata. The general advantages of using the deep strata which will help maintain the quality of social capital include stability, earthquake resistance, constant temperature and humidity, and blockages of vibration and noise, all of which will not affect the view on the ground. A good quality of social infrastructure can be installed by taking advantages of the deep strata construction. Consequently, the development of an effectively, appropriately designed deep strata will be strongly encouraged. Generally used construction methods include open-cut, pipe jacking, and shield methods. In the past, even during construction of the shallow strata, open-cut methods were widely used because construction had to be precise, reliable, and economically efficient. However, due to the neighboring construction it is difficult to secure road traffic, prevent construction hazards such as vibration and noise, and to also take steps to protect the existing congested underground installations. On the other hand, the pipe jacking method has been widely adopted as a general construction method owing to its recent marvelous technological development [1]. Nowadays, in order to grasp the ground constructions after using the shield method, the movement of the ground is frequently predicted by numerical analysis. Many cases are recognized as plain strain and axisymmetric problems in the sectional and vertical directions in the shield construction. In this paper, various factors that may influence the deformation of the surrounding ground are simulated and analyzed. These factors include the balancing between the pressure of cutting face and the earth pressure, the cutting condition of the face, ground deformation by excavation, the friction between the surround-

T. SENDA ET AL. 45 ing surface of drivage machine and its contact ground, generation of tail-void, and lubricant. Those analysis were considered using the finite element method, which produce great results for the prediction of deformation behavior of the ground during the shield construction. From this point of view, this method was adopted for analyzing the pipe jacking method [2]. 2. What is the Pipe Jacking In the pipe jacking method, drivage machine is set at the head of the pipeline and the pipes are jacked forward with the hydraulic jack, located at the starting shaft. The pipe jacking, like many other methods of below ground construction, is best employed in stable, water free soil conditions. Unfortunately, with the demands on available space and the need to provide more services, it is not always possible to select stable strata, which means that contractors have to contend with difficult ground below the water table [3,4]. The slurry pipe jacking system is applicable to the above situations. Figure 1 shows the pipe jacking system scheme. This system can be used to construct pipe tunnels up to 3000 mm in diameter and construct both long (maximum length: 1000 m) and curved tunnels (minimum curvature radius: 25 m). Recent technological developments have led to successful methods for stabilizing unstable strata by excluding water from excavations by means of tail-void with mud slurry. This system meets modern environmental standards. This type of mud slurry is formed by water, decomposed granite soil, carboxyl methyl cellulose, lost circulation control material, bentonite, fine aggregate, and other materials. Figure 2 shows an illustration of the pipe and the soil in this system. The proportional mixes vary the viscosity and the seepage capacity of the mud slurry and will be determined by whether mud slurry is required to strengthen the soil. This system is used as follows: 1) Install the pushing equipment in the starting pit, and then set the drivage machine. 2) Extend the rear-end pushing jack and push the dri- vage machine. 3) By repetition of the pushing process, if the rear-end driving after one concrete pipe length (2.5 m) is driving in, connect another pipe. 4) After driving is completed, recover the drivage machine from the arrival pit. More widely used techniques that are now being used elsewhere for micro-tunneling, use remote control drivage methods in conjunction with pipe jacking. During the pushing processes, the mud slurry is injected into the face and tail-void, which is between the pipe and the soil. After tail-void is filled by the slurry, soil is stabilized due to the slurry pressure. To minimize ground deformation in the pushing process, it is necessary to maintain the slurry pressure that was kept on the underground water pressure at plus 20 kpa [5]. Thus, tail-void plays an important role in reducing the friction resistance in pushing the pipes and maintaining earth covering pressure. 3. Numerical Analysis The boundary conditions of the ground, where the pipe jacking construction is made, are so complex and wideranging that in many cases 3-dimentional effect cannot be ignored when considering the design of the pipe jacking construction. Therefore, excavation elements were used to create a 3-dimentional finite element method considering the actual construction process of pipe jacking construction. 3.1. Outline of Analysis In the pipe jacking construction, just after the drivage machine passes by the tail, the tail-void is generated due to the difference of the outer diameter of each pipe, which releases stress in the ground. As the actual construction lubricant is injected into the tail-void to prevent the ground from deformation due to stress release caused by formation of the tail-void in the ground. To simulate this situation in the analysis, a nodal force equivalent to the injection pressure is applied to the soil element where Figure 1. Pipe jacking scheme.

46 T. SENDA ET AL. the stress is released after the tail of the drivage machine passes by. 3.2. Input Parameters Tables 1 and 2 show the input parameters used in the analysis. The appropriate pressure of the cutting face must be applied against the earth covering. The material values of the lubricant were the ones that are illustrated graphically with the logarithmic functional approximation value of Young s modulus and Poisson s ratio according to the result of the uniaxial compression test as shown in Figure 3. Figure 4 shows analysis model. A half section model with a length of 40 m and a width of 150 m was used as the analysis range because both loading and structural systems were symmetrical. 4. Results and Discussion Figure 5 shows the deformations of the crown at the tailvoid during pipe jacking of 10, 20 and 30 m. The pressure of the cutting face was acted against the front face of Figure 3. Young s modulus and Poisson s ratio elapsed time after injection. Figure 4. Analysis model. Young s modulus: E (MPa) Poisson s ratio: ν Density (MN/m 3 ) Figure 2. Illustration of a concrete pipe and soil. Table 1. Properties of soils, pipe and lubricant. Mud-stone Clay Sand Earth covering: H Pipe After injection Lubricant 1 month passed 74 50 55 2.2 10 3 9.8 10 4 0.43 0.30 0.33 0.35 0.20 0.45 0.39 0.021 0.024 0.021 0.080 0.021 0.021 Table 2. Cutting face pressure. Cutting face pressure (MPa) 20 m 0.44 40 m 0.86 60 m 1.28 excavation, causing upheaval before settlement starts. After the drivage machine passes by, settlement is generated from 30 to 35 mm. Constructing tail-void cause large deformation. Therefore, this phenomenon should be taken care in pipe jacking. Figure 6 shows the deformations of the crown at the tail-void when pipe jacking has reached a 30 m point of excavation at the various earth coverings of 20, 40, and 60 m. As the earth covering increases, the deformation amount of tail-void also increases. At the earth covering of 40 m, settlement has reached a maximum of about 34 mm. Figure 7 shows the deformation amount dependency to the soil properties. A tendency was found that the larger the cohesion is, the smaller the deformation amount. In particular, the deformation amount of sandy soil and cohesive soil reached 50 mm or more, which is generally a value that cannot secure an effective area of tail-void. The analytical results this time show that even under the conditions of easy-to-collapse soil and high water pressure, if mud screen is able to retain the area of surrounding pipes with enough pressure to cope with the earth pressure and hydraulic pressure, then it can decrease fric-

T. SENDA ET AL. 47 tional forces on pipelines. This is very effective in construction. Based on the analytical results shown in Figure 5, Figure 8 shows that the range, affected by the amount of surface settlement of the ground surface and the top layer at the center of drivage machine, became smaller, if the earth covering became larger. It was 3.4 mm at an earth covering of 60 m. It is presumed that the range affected by the ground subsidence in the horizontal direction should be on a straight line of about 42 degree. 5. Conclusion Based on the analytical results, it was found that if the earth covering in the deeper ground increases, the surrounding soil during the pipe jacking construction, and Figure 5. Effect on the deformation by differences of thrust length: L (m). Figure 6. Effect on the deformation by differences of earth covering: H (m). Figure 7. Effect on the deformation by differences of soils. Figure 8. Relationship between the vertical displacement on the surface and the distance from the center. the tail-void in particular, must be looked at, due to the increased deformation. Now that long distance and narrow curve jacking techniques have been established and watertight joints for installation have been rapidly developed, the pipe jacking method can be applied to the pipe installation in underground deeper than 20 m of earth covering. However, the stress release of the ground continues along with the formation of tail-void. Therefore, there are many challenges to cope with for the improvement of stability in the surrounding ground. While the drivage machine approaches and passes by, the stress and strain conditions change with time. Plural factors, such as changing position of drivage machine and surrounding friction, can often affect the ground simultaneously. In addition, a long-term ground subsidence followed by the ground deformation at the time of construction can be caused directly by the soil disturbance resulting from the ground deformation during construction. Therefore most of the ground deformations caused by the pipe jacking construction may be caused by changing stress and strain conditions over the course of construction. That is why the discussion of appropriate lubricants and injection methods, etc. in preparation for such changes is inevitable. REFERENCES [1] Japan Tunneling Association, Trend of Using Deep Underground and Activity Report, 1997. [2] H. Akagi and K. Komiya, Ground Behavioral Analysis in Consideration of the Construction Process of Shield Tunneling in Finite Element Method, Journal of Japan Society of Civil Engineers, Vol. III-25, No. 481, 1993, pp. 59-68. [3] J. M. Cole, Pipe Jacking Case Histories, Tunnels and Tunneling, 1977. [4] C. M. Hough, Pipe Jacking Case Histories, Tunnels and

48 T. SENDA ET AL. Tunneling, 1978. [5] S. Katano and T. Ogawa, Effect of Slurry Shield Tunneling in Soft Alluvial Clay on an Adjacent Underground Subway Structure, Proceedings of International Con- gress on Tunneling and Ground Conditions, Cairo, April 1994, pp. 151-156.