Research on Mutual Influence between Pipes of Curved Pipe-jacking Roof Project

Similar documents
Behavior of Surrounding Soil during Construction and Its Countermeasures Using Pipe Jacking Method in Deep Strata

Three-dimensional computer simulation of soil nailing support in deep foundation pit

Passage under Lövstavägen at Bypass Stockholm From Design to Realization

THE EXPERIMENTAL STUDY ON INNER SHIFT LINING STRUCTURE OF FREEZING SHAFT IN DEEP THICK AQUIFEROUS SOFT ROCK**

ON THE BEHAVIOR OF A STUCK CURVED PIPE JACKING

STUDY ON THE TUNNEL SECONDARY LINING CONCRETE CRACKING PERFORMANCE DURING SERVICE PERIOD OF WU- GUANG PASSENGER DEDICATED LINE

Mechanical properties of multiple large-diameter corrugate steel pipes in embankment

Numerical Simulation Analysis of the Stability of Heishan Tunnel s Surrounding Loess during Construction1

The New Incremental Launching Construction Technology of Jiubao Bridge Long-span Hybrid Arch-girder Structure

Study on effect of segments erection tolerance and wedge-shaped segment on segment ring in shield tunnel

Seepage-Stress Coupled Analysis on Shield Tunnel Face Stability in Layered Soil

NPTEL Course GROUND IMPROVEMENT USING MICROPILES

NUMERICAL ANALYSIS OF GEOSYNTHETIC REINFORCED SOIL ABOVE A TUNNEL

Numerical Analysis of Pipe Roof Reinforcement in Soft Ground Tunnelling

J.-H. YIN Department of Civil & Structural Engineering, The Hong Kong Polytechnic University Kowloon, Hong Kong, China

TEST STUDY ON BASIC STATIC CHARACTERISTICS OF CABLE SUPPORTED BARREL VAULT STRUCTURE

Relationship between twin tunnels distance and surface subsidence in soft ground of Tabriz Metro - Iran

Journal of Engineering Science and Technology Review 7 (2) (2014) Research Article

BEARING CAPACITY IMPROVEMENT USING MICROPILES A CASE STUDY

Developed countries require a modern infrastructure Roads Railways Power Communications Water Wastewater

TUNNEL LINER PLATE INTRODUCTION GENERAL APPLICATIONS CHAPTER 11

TBM rescue projects using shafts and ground freezing

Research on the Effects of Foundation Excavation by the Environment

SEISMIC SOIL-STRUCTURE INTERACTION IN FULLY INTEGRAL ABUTMENT BRIDGES WITH HP STEEL PILES

RAK Computational Geotechnics 2

Evaluation of negative skin friction on sheet pile walls at the Rio Grande dry dock, Brazil

Large Storage Tanks Foundation Settlement Structural Mechanics Characteristics Analysis

Anti-fatigue Performance Analysis on Steel Crane Beam

EXPERIMENTAL PROGRAMME

Settlement assessment of running tunnels a generic approach

Study of Deformation Control and Rule of Tunnel which Passes Underneath the Existing Tunnel in Underground Excavation of Subway Station

Axially Loaded Behavior of Driven PC Piles

The Effect of Groundwater Seepage on Stability of Tunnel by Using Strength Reduction Method Considering Fluid Solid Coupling

Static Analysis of the Interaction Among Soil, Slab and Piles in Pile-Slab Structure

THE EFFECT OF LATERAL CONFINEMENT ON THE SETTLEMENT CHARACTERISTICS OF SHALLOW FOUNDATIONS ON SAND

Coupled Stress-Seepage Numerical Design of Pressure Tunnels

EFFECT OF DEEP EXCAVATION SUPPORTED BY CONCRETE SOLIDER PILE WITH STEEL SHEET PILE LAGGING WALL ON ADJACENT EXISTING BUILDINGS

A THREE DIMENSIONAL STUDY OF THE EFFECT OF SOIL EROSION ON RIGID PIPES

Research Paper PERFORMANCE OF STRIP FOOTING ON SANDY SOIL DUE TO TUNNELING S.Hariswaran 1, K.Premalatha 2, K.Raja 3

FEATURES & BENEFITS OF ARMTEC TUNNEL LINER PLATE

Solution for the conclusion of the Mackenzie access in Sao Paulo Line 4 Subway.

POSTER PAPER PROCEEDINGS

Pile foundations Introduction

SOIL MECHANICS CIVIL ENGINEERING VIRTUAL LABORATORY

EFFICIENCY OF MICROPILE FOR SEISMIC RETROFIT OF FOUNDATION SYSTEM

Experimental study on shear lag of curved box girder under earthquake excitation

Comparison of the results of load test done on stone columns and rammed aggregate piers using numerical modeling

Prediction of Surface Subsidence Caused by Rectangular Pipe Jacking Construction

Downloaded from Downloaded from /1

Design of pipeline installation. D-Geo Pipeline

4D grouting pressure model of a bored tunnel in 3D Tunnel

Numerical Modeling the Behavior of Ground Improvement in Soft Clay

SEISMIC SOIL-PILE GROUP INTERACTION ANALYSIS OF A BATTERED PILE GROUP

Available online at ScienceDirect. Procedia Engineering 189 (2017 ) 11 17

Finite element analysis of bending performance on polyurethane composite panel

Research on the Key Technology of Hinge Joint Diseases Treatment without Traffic Interruption for Plate Girder Bridge

Numerical Simulation of Liquefaction Deformation of Sand Layer around Bucket Foundations under Dynamic Loadings

Combination of undrained and drained analysis to design the temporary supports of a large diameter tunnel

Performance review of a pipe jacking project in Hong Kong

Numerical Simulation of Soil Nailing Wall in Deep Foundation Pit

STRENGTH CONSEQUENCE MINIMIZATION OF DIGGING OFF BURIED GAS PIPELINE AT ISOLATION COAT RENOVATION REALIZED DURING OPERATION

Study on Shear Lag Effect of Composite Box Girder Bridge with Corrugated Steel Webs

VOL. 11, NO. 16, AUGUST 2016 ISSN ARPN Journal of Engineering and Applied Sciences

Module - CE 3132 Geotechnical Engineering Assignment Triaxial Test Marks 10% Learning Outcome

Analysis of Buried Arch Structures; Performance Versus Prediction

Laser speckle measurements and numerical simulations of the deformation of masonry loaded in compression

Dimensioning and design of the segmental lining

Comparison of strength of artificially frozen soil in two test modes

THE STRUCTURAL ANALYSIS OF STEEL SILOS WITH CYLINDRICAL-WALL BEARING AND PROFILE-STEEL BEARING

Typical set up for Plate Load test assembly

BEHAVIOUR OF GEOTEXTILE REINFORCED STONE COLUMNS MANITA DAS, A.K.DEY ABSTRACT

Deformation monitoring and analysis of deep foundation pit of Xiaoshan rainbow Boulevard

FULL-RING EXPERIMENTAL STUDY OF THE LINING STRUCTURE OF SHANGHAI CHANGJIANG TUNNEL

Tunnel. Immersed Tunnels

Design of pipeline installation D-GEO PIPELINE

twenty six concrete construction: foundation design ELEMENTS OF ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SPRING 2013

Full-Ring Experimental Study of the Lining Structure of Shanghai Changjiang Tunnel

Numerical Analysis of the Durability of Retaining Wall with Anchor

Title. Author(s)BAI, DI; HAYASHIKAWA, T.; MATSUMOTO, TAKASHI; HE, XI. Issue Date Doc URL. Type. Note. File Information

4D grouting pressure model PLAXIS

Jinfeng Zhang 1, Wangsheng Liu 1, Ming Zhao 1 1. College of Civil Engineering, Tongji University, Shanghai , China.

An Analysis on the Transmission Shaft Fracture of Screw Drill. Jian DU

COURSE ON COMPUTATIONAL GEOTECHNICS A Geotechnical Design Tool. Faculty of Civil Engineering UiTM, Malaysia

The Deep Mixing Method

Ground Improvement Prof. G. L. Sivakumar Babu Department of Civil Engineering Indian Institute of Science, Bangalore

SETTLEMENTS DUE TO TUNNEL CONSTRUCTION

Finite Element Simulation of Molding Process of Cold Bending Pipe

Shear Lag Effect for PC Continuous Curved Box-section Girder Bridge under the Moving Vehicular Loads

PARAMETRIC STUDY OF SHALLOW FOUNDATION BEARING CAPACITY IN CLAYEY SOIL

Design of Gravity Flow Pipes 121 = UNIT WT OF SOIL. P d = H H. D = 2r. P x LIVE LOAD PIPE WALLS ARE CLADDING FOR THE SOIL COLUMN SOIL SECTION AA

Modeling of Buried Pipe Deformations

Ground Movement Analysis of Pipe Roof Construction in Soft Clay

Ching Guan Kee ABSTRACT

twenty seven concrete construction: foundation design Foundation Structural vs. Foundation Design Structural vs. Foundation Design

A Comparative Study of Concrete Expanded Plates Pile and Common Pile Uplift. Bearing Capacity

Finite Element Analysis of Flexible Anchored Sheet Pile Walls: Effect of Mode of Construction and Dewatering Naveen Kumar 1, Arindam Dey 2*

Mechanical Behavior and Characterization of Stern-shaft Mechanical Sealing Device. Yongjin Lu a *, Rui Lin

Estimation of Lateral Earth Pressure on Cantilever Sheet Pile using Flat Dilatometer Test (DMT) Data: Numerical Study

Transcription:

International Conference on Mechatronics, Electronic, Industrial and Control Engineering (MEIC 2015) Research on Mutual Influence between Pipes of Curved Pipe-jacking Roof Project Li Jian 1,2 1 Chang an University, Xi an, China 2 Guangdong Nanyue Transportation Investment & Construction Co., Ltd., Guangzhou, China e-mail: lijian0757@126.com Li Zhihong Guangdong Nanyue Transportation Investment & Construction Co., Ltd. Guangzhou, China e-mail: lizhihong0701@163.com Abstract Considering the requirements of water sealing between pipes and control precision, the pipe roof currently implemented are all straight. Due to some special construction conditions, the pipe roof method needs to break the limit of linear condition. This results in several problems such as increasing the difficulty of precision control, enhancing the mutual influence between pipes, increasing the difficulty of forming roof and other issues. This study is based on the curved pipe-jacking roof project of Gongbei Tunnel of Zhuhai Link Road of Hong Kong-Zhuhai-Macao Bridge. Through the model test, numerical simulation and field test, the mutual influence between pipes of curved pipejacking roof is researched, and the laws of cumulative disturbance and strain of soil, pipe-soil contact pressure, influence of trajectory are analysed. The results demonstate that maximum soil cumulative is close to secondly jacked pipe and maximum pipe-soil contact pressure is loacted at horizontal position of firstly jacked pipe. The research provides reference for the construction of curved pipejacking project. Keywords-curved; pipe-jacking; pipe roof; soil box experiment; mutual influence I. INTRODUCTION Pipe-roof method has increasingly application on tunnels and underground engineering because of its advantage such as low noise, on need of lowering ground water or wide range of excavation, few of effects on communal facilities and easy control of subsidence or other impact on the environment. The first record on the application of pipe roof is the traversing channel project of Kawase-Inae in Japan, in 1971[1]. The souterrain construction in HK in 1984 is the earliest usage of this method in China. In 1989, pipe roof method is used with ESA culvert box advancing scheme on souterrain of Taipei Songshan Airport[2]. The same method is applied and achieved a few of scientific payoffs on the tunnel of Shanghai Middle Ring Line with 80 pipes which are 970mm diameter[3-6]. Relevant scholars conducted research on ground deformation caused by pipes construction with the method of pipe jacking[7-10]. At present, the complete pipe roof projects are almost with straight pipes, grouting through locking wellhead because of lack of ground water. However, some pipe roof projects, such as the underground part of Gongbei Tunnel of Zhuhai Link Road on HK-Zhuhai-Macao Bridge, which is built by 255m curved pipe roof and sealed by freezing method, need to be constructed by curve. This way increases the risks of sealing failure, track deflection and interaction of pipes. Based on this pipe roof project, this article analyze the interaction of pipes, which provides reference on this method. II. CURVED PIPE JACKING ROOF OF GONGBEI TUNNEL Gongbei Tunnel is the key project of Zhuhai Link Road of HK-Zhuhai-Macao Bridge. The tunnel is 2741m, which is constructed by the order of parallel-overlapparallel. When pass under the Gongbei Port, excavation is coordinated with 255m curved pipe roof (88m easement and 167m circle) and freezing method. It is the first double-deck highway tunnel constructed by this method. The excavation part of Gongbei Tunnel is 336m 2 oval cross section with double-deck overlap. Soil between 36 pipes, which is 1620mm dia. and constructed by pipe jacking, is frozen to make strong-support waterproof curtain to maintain excavation face (as Fig.1). There is 0.35% grade on track from east to west, which encouters several soil layers, including filling soil, muddy-silty clay, silty soil, medium sand, mucky silt, silty clay, and gravelly sand. The characteristics of soil layers include: weak, waterlogged, rich water supplying, high compressibility, high permeability and low capacity. The thickness of covering soil is 4~5m. The pipe section is 4m long, 20mm of thickness on upper part of pipe-roof and 24mm of thickness on lower half. A test pipe is designed to testing jacking precision, track control, interaction of pipes and some experience parameters. 2015. The authors - Published by Atlantis Press 841

Figure 2. The soil box model test (a) This soil box test sets three ground settlement monitoring sections. In the process of group of pipe jacking, in order to monitor changes of strain of soil around the pipe jacking, respectively from the up and down the 225 mm pipe jacking axis laid fiber optic strain monitoring, as shown in Fig.4. (b) Figure 1. Schematic diagram of curved pipe-jacking roof project in Gongbei Tunnel Figure 3. Monitoring points of soil pressure III. SOIL BOX MODEL TEST AND RESULT ANALYSIS Soil Box Model Test To study the mutual influence between pipe jacking, we carry out a soil box model test according to the similarity theory. As the Fig.2 shows, the test chamber wall is 3000mm long, 1800mm wide, 1500mm high. The diameter of steel pipes is 324mm, wall thickness is 4mm, and length of the pips is 1500mm. The distance between the two pipes is 72mm. The combination of cutter and screw drill pipe device is as test simulation jacking device. The diameter of the cutter is 335mm. Test soil is 1500mm of sand layer. Test data including posterior pipe jacking acts additional stress on the prior pipe jacking, ground surface deformation and the internal strain of soil, etc. 5 soil pressure sensors are set on the prior pipe jacking close to the posterior pipe jacking side respectively at 0, ±45 and ±90 positions, as Fig.3 shows. Figure 4(a). Ground settlement monitoring section Figure 4(b). Strain monitoring 842

Analysis of test result Fig.5(a) is the deformation of settlement monitoring section 1 when the prior pipe jacked forward 10cm and 50cm. The figure shows that soil uplift occurred in front of the pipe jacking machine, which is due to the additional thrust acted on the jacking machine cutter front. The maximum uplift above the top tube axis is 0.14mm when jacking forward 10cm. When jacking forward 50cm, section 1 settlement occurred and the maximum settlement is 0.74mm. Fig.5(b) is the deformation of settlement monitoring section 1 when the posterior pipe jacked forward 10cm and 50cm. After the completion of prior pipe jacking, monitoring section 1 were in an overall settling state. With the jacking of the posterior pipe, the settling tank developed continuously from 0.88mm to 2.34mm. Surface subsidence demonstrated the cumulative effects and the maximum settlement position moved to near the top of the tube axis of the posterior pipe. of second row fiber optic are also the same law with less strain changes. The strain of third row fiber optic is between -500με to -600με, without concentration phenomenon. The strain influence on the longitudinal optical fibers is mainly concentrated from first column to fourth column, as shown in Fig.6 (b). It is shown that the longitudinal optical fiber strain upper prior pipe decreases, which is due to the surrounding soil compression under effect of positive additional thrust of pipe jacking machine cutter and the side friction, making previously optical fiber strain decrease. In the soil away from cutter, the strain affected by pipe jacking is smaller. Figure 6(a). Strain increment of transverse fiber when the prior pipe jacked at 60cm Figure 5(a). Settlement curve of monitoring section 1 when jacking at 10cm and 50cm for prior pipe Figure 6(b). Strain increment of longitudinal fiber when the prior pipe jacked at 60cm Figure 5(b). Settlement curve of monitoring section 1 when jacking at 10cm and 50cm of for posterior pipe According to the results of the monitoring, the soil strain changes are more obvious in front of the pipe jacking machine. When First pipe jacked 60 cm, the lateral optical fibers of strain changes mainly are concentrated in the front three rows, shown in Fig.6 (a). The strain of first row fiber optic increases near the front of jacked pipe axis, but decreases at both sides of the pipe jacking axis, which is due to the both sides extrusion effect of front soil by pipe jacking machine cutter. So the soil near the pipe axis makes the optical fiber emerging tensile strain. But the soil on both sides is under compression and the originally tensile strain existing in fiber decreases. The strain changes IV. NUMERICAL SIMULATION OF SOIL BOX MODEL TEST A. Result and Analysis of Numerical Simulation In order to compare with the box model test, a numerical simulation model of soil box test is performed. The calculation of soil parameters include elastic modulus (30 MPa), poisson's ratio (0.3), density (1650 kg / m 3 ), internal friction angle (35 ) and cohesion (1 kpa). The calculated parameters of pipe are elastic modulus (210 GPa), poisson's ratio (0.3) and density (7800 kg / m 3 ) after 0.3. In the numerical simulation model, the soil is using Mohr-coulomb model and pipe is using elastic model. For the boundary conditions, all direction displacements of 843

bottom are constraint, but normal direction displacement of surrounding constraint and free on the surface. Before pipe jacking construction, the initial form of interaction between pipe and soil is set up. The pipe jacking construction process is simulated by displacement dynamic injection method with 8 excavation step, each step in jacking construction of 0.2 m (as shown in Fig.7). The total units are 85320. Prior pipe Jacking direction (a) Figure 9(a). Contact pressure of the prior pipe before the posterior pipe 管土接触压力增大区域 jacked (a) Increase area 管土接触压力增大区域 of contact pressure Posterior pipe Figure 7. Excavating model According to the calculation results, the maximum soil subsidence upper first pipe is up to 2.196 mm and the subsidence curve is deviation to first pipe. The soil subsidence increases during second pipe jacked, which reflects the cumulative effect of soil disturbance. The largest settlement reaches 2.659 mm. The soil displacement curve is approximately symmetrical with center of soil box, after the completion of two pipe jacked, as shown in Fig.8. Figure 8. Settling tank when the posterior pipe jacked Change of the contact pressure between prior jacking pipe and soil before and after the construction of posterior jacking pipe is shown in Fig.9(a) and Fig.9(b). The figures show that after the completion of prior pipe jacking, distribution of the contact pressure between pipe and soil is relatively uniform as about 4kPa and that after the completion of posterior pipe jacking, the contact pressure near the side of posterior pipe increases and the maximum pressure is about 6.35kPa. (b) Figure 9(b). Contact pressure of the (b) prior pipe after the posterior pipe jacked B. Comparison with the result of soil box test The subsidence comparison of numerical simulation results and model test on monitoring section one is as shown in Fig.10. It shows that both surface deformation curve trends are relatively close especially the maximum subsidence is close, while the results of soil-bin test are slightly larger than that of numerical simulation and compared with numerical simulation results the maximum settlement location of model test is closer to the pipe axis of posterior pipe, which is coincide with actual construction monitoring results. Besides, it is obtained that in a location near the walls on both sides there is comparatively large difference between each surface deformation with that the surface deformation of numerical simulation is obviously larger than that of soil-bin test. This is because that during the test process the friction force between soil and the walls limit the soil subsidence on both sides of walls to a certain extent, thus the numerical simulation result has more reference value. Figure 10. The contrast curve of simulation and model tests at No.1 settlement monitoring section Fig.11(a) and Fig.11(b) show the law of later horizontal optical fiber strain in row 1 and 2 during jacking of prior pipe. It is obtained that the strain increment measured by optical fiber in soil-bin test is basically the 844

same as that of numerical simulation, especially strain concentration occurred in soil that are right ahead of the prior pipe. The numerical difference of the two kinds strain is likely to be caused by the lack of coupling effect between soil and fiber. The contrast curve of the prior pipe additional stress is shown in Fig.12, and additional stress curves of numerical simulation and soil-bin test have similarity. The additional soil pressure of prior pipe during the jacking process of posterior pipe at the horizontal position (0 degree) is the largest. However, the minimum additional soil pressure of soil-bin test occurs at the top and bottom of pipe while the minimum additional soil pressure of numerical simulation occurs where are plus-minus 45 degree of the pipe, and additional pressure of the bottom of pipe is less than that of the top of pipe. Due to the effect of pipe bearing load, soil in the bottom is less affected by disturbance, thus additional soil pressure is smaller accordingly. Figure 12. The contrast curve of superimposed soil pressure V. FIELD TEST The field tests were carried out in Gongbei tunnel construction site to have a further study on the interaction of pipes of the pipe-jacking roof, the 0# test pipe and 5# pipe are as shown in Fig.1. The test pipe is 255 meters long and about 7~8 meters deep. It is in the transition curve and circle curve, the curvature radius of which is 885.852m~906.298m. The pipe s diameter is 1620mm, and the thickness is 20mm, each pipe is 4 meters long, the spacing of the two test pipe is 35.7cm. The test pipe 0# was jacking first, and then jacked pipe 5#. The 0# pipe s trajectory was measured and reviewed, as shown in Fig.13, while it was finished. Figure 11(a). The contrast curve of strain increment of transverse fiber when the first pipe jacked at 40cm in row 1 (a) level curve comparison Figure 11 (b). The contrast curve of strain increment of transverse fiber when the first pipe jacked at 40cm in row 2 (b) height curve comparison Figure 13. The curve of 0# pipe s trajectory and design axis 0# pipe s trajectory was resurveyed while 5# pipe was finished. The analysis shows that the 5# pipe has little effect on 0# test pipe. After the 5# pipe was finished, the maximum deviation of the 0# test pipe is 12mm, and the average deviation is 4mm, as shown in Fig.14. 845

simulation results, the results of numerical simulation has very high reference significance. (5) Through the analysis of the monitoring data of the field tests, on the condition of the pipe jacking construction parameter effectively controlled, properly construction measures, through measuring deviation in time, the accuracy of pipe jacking can meet the engineering requirements, the mutual influence between the pipe jacking roof pipes can be effectively reduces and controlled, which can ensure the nest of pipes forming pipe jacking roof. REFERENCES Figure 14. The influence of 5# pipe on 0# test pipe VI. CONCLUSION The paper had a preliminary study on the interaction of pipes of the pipe-jacking roof, with the means of model test, numerical simulation and field in-situ test. The conclusions are as follows: (1) In the process of pipe jacking, the surface in front of the pipe jacking machine cutter uplift and the lateral strain of soil increase. While both sides soil strain decreased or changed less. The soil longitudinal strain increased near front of the pipe jacking machine cutter, soil strain of the area away from that changes less. (2) According to the results of soil box test numerical simulation, while the prior pipe was finished, the soil settled and the maximum subsidence happened above the pipe jacking, the value reached 2.196 mm. The posterior pipe led to further subsidence of soil, the soil s maximum settlement reached 2.659 mm, which reflecting the disturbance of soil cumulative effect. Settling tank curve roughly symmetrically distributed about the model. (3) According to the numerical simulation, while the prior pipe finished, the contact pressure distribution on the prior pipe is relatively uniform, which is about 4kPa; the posterior pipe makes the pressure of the prior pipe increased to 6.35kPa. (4) The soil displacement and strain change rules of the model test are relatively consistent with the numerical [1] C. Philip J., G. David, and C. Abbott. Microtunneling Techniques to Form an in-situ Barrier around existing structures,. High Level Radioactive Waste Management-Proceedings of the annual international conference, Las Vegas, NV, USA, pp. 386-394. [2] X. Guyi. Plan and design of North Fuxing Road Tunnel underpassing Songshan Airport in Taipei,. Journal of Fuzhou University (Natural Science Edition), vol.25(s1),1997, pp. 56-60. [3] G. Jinke. Research on construction scheme of pipe roof tunnel in saturated soft soil,. Shanghai Highway, vol.1, 2004, pp. 38-43. [4] L. Xiangyang, Y. Zhiguo, Z. Hehua, C. Yongchang, and L. Xuezeng. Excavation numerical simulation of culvert box advanced in pipe-roof in saturated soft soil layer,. Underground Space, vol. 24(5), 2004, pp. 688-691. doi: 10.3969/j.issn.1673-0836.2004.z1.027. [5] L. Ming, Z. Zuxi, and C. Hong. Discussion of waterproofing design in box culvert jacking plus pipe curtain method,. China Building Waterproofing, vol. 9, 2006, pp. 39-42. doi: 10.3969/j.issn.1007-497X.2006.09.010. [6] S. Jun, Y. Xingfu, S. Min, and L. Xiangyang Analysis and prediction on soft ground deformation of a super-large shallow buried pipe-roofing and box-culvert jacking project under construction,. Rock and Soil Mechanics, vol. 27(7),2006, pp. 1021-1027. doi: 10.3969/j.issn.1000-7598.2006.07.001. [7] C. Sagaseta. Analysis of undrained soil deformation due to ground loss,. Geotechnique, vol. 37(3),1987, pp. 301-320. [8] N. Loganathan, and H. Poulos. Analytical prediction for tunneling-induced ground movements in clays, Journal of Geotechnical and Geoenvironmental Engineering, vol. 124(9), 1998, pp.846-856. [9] G. Wei. Theoretical study on behaviors of soil and structure during pipe jacking construction,, Zhejiang University, 2005. [10] F. Li., S. Shen., and C. Luo. Prediction approach of ground deformation induced by pipe jacking construction considering grouting pressure. Rock and Soil Mechanics, vol. 33(1), 2012, pp. 204-208. doi: 10.3969/j.issn.1000-7598.2012.01.032. 846