INTEGRATION OF CONSTRUCTION AND TRAFFIC ENGINEERING IN SIMULATING PIPE-JACKING OPERATIONS IN URBAN AREAS. Chi-Sun Poon

Similar documents
DEVELOPMENT OF INTELLIGENT DECISION SUPPORT MEANS FOR EFFECTIVE MICROTUNNELING CONSTRUCTION PLANNING

SIMULATION MODEL OF PREFABRICATED HOUSE FROM MANUFACTURING TO ON-SITE INSTALLATION

SPECIAL PURPOSE SIMULATION TEMPLATE FOR UTILITY TUNNEL CONSTRUCTION

The Simulation Study Of Transport System For Earth Work. Allocation Of Rock-fill Dam. XiaohangMa1, a, KeLi2, b

ATTAINING COST EFFICIENCY IN CONSTRUCTING SPORTS FACILITIES FOR BEIJING 2008 OLYMPIC GAMES BY USE OF OPERATIONS SIMULATION.

Simulation Analytics

Proceedings of the 2017 Winter Simulation Conference W. K. V. Chan, A. D'Ambrogio, G. Zacharewicz, N. Mustafee, G. Wainer, and E. Page, eds.

SIMULATION APPLICATIONS IN CONSTRUCTION SITE LAYOUT PLANNING

Traffic Impact Study Requirements

Proceedings of the 2012 Winter Simulation Conference C. Laroque, J. Himmelspach, R. Pasupathy, O. Rose, and A. M. Uhrmacher, eds.

Reliability Analysis of Dangerous Goods Transportation Network in Container Terminals

Proceedings of the 2016 Winter Simulation Conference T. M. K. Roeder, P. I. Frazier, R. Szechtman, E. Zhou, T. Huschka, and S. E. Chick, eds.

SCHEDULING FOR HIGH-RISE BUILDING CONSTRUCTION USING SIMULATION TECHNIQUES

Analysis of Microtunnelling Using Process Simulation Module

DISCRETE-EVENT SIMULATION MODELLING OF PREFABRICATED WALL PRODUCTION LINE

Simulation of fruit pallet movement in the port of Durban: A case study

Ferry Rusgiyarto S3-Student at Civil Engineering Post Graduate Department, ITB, Bandung 40132, Indonesia

SPECIAL PURPOSE SIMULATION MODELING OF TOWER CRANES

Optimizing Construction Planning and Scheduling through Combined Virtual Prototyping Technology and Building Information Models

Guidelines for the Submission of a Transportation Study Level 2

Dynamic Lane Merge Systems

Special Issue: Intelligent Transportation Systems

Pollutant concentration profiles in vehicular road tunnels

Storage Allocation and Yard Trucks Scheduling in Container Terminals Using a Genetic Algorithm Approach

Concrete Plant Operations Optimization Using Combined Simulation and Genetic Algorithms Cao, Ming; Lu, Ming; Zhang, Jian-Ping

Summary, Conclusion and Outlook

Pipe Jacking v Open-Cut CO 2 Calculator

USE OF DYNAMIC SIMULATION TO ANALYZE STORAGE AND RETRIEVAL STRATEGIES

Modeling Microtunnelling Construction Operations with WebCYCLONE

IMPACT OF DIFFERENT UNLOADING ZONE LOCATIONS IN TRANSSHIPMENT TERMINALS UNDER VARIOUS FORKLIFT DISPATCHING RULES

Scheduling of Three FMS Layouts Using Four Scheduling Rules

Making Better haulage decisions through Discrete Event Simulation

A DECISION TOOL FOR ASSEMBLY LINE BREAKDOWN ACTION. Roland Menassa

Legislative Council Panel on Transport Subcommittee on Matters Relating to Railways. Environmental Measures for New Railway Projects

Vision of Congestion-Free Road Traffic and Cooperating Objects

Simulation and Logistics

1. For s, a, initialize Q ( s,

THE VALUE OF DISCRETE-EVENT SIMULATION IN COMPUTER-AIDED PROCESS OPERATIONS

Determining the Effectiveness of Specialized Bank Tellers

OPTIMIZING JOINT OPERATION OF TWO TOWER CRANES THROUGH LOOK-AHEAD PLANNING AND PROCESS SIMULATION

Optimal Design, Evaluation, and Analysis of AGV Transportation Systems Based on Various Transportation Demands

Legislative Council Panel on Transport Subcommittee on Matters Relating to Railways

Estimating the Size of Temporary Facilities in Construction Site Layout Planning Using Simulation

DIVISION I TRAFFIC IMPACT STUDY GUIDELINES ENGINEERING STANDARDS

CITY OF DRAPER TRAFFIC IMPACT STUDY DESIGN GUIDELINES

TRB WEBINAR PROGRAM Planning and Preliminary Engineering Applications Guide to the Highway Capacity Manual: Contents

A Flexsim-based Optimization for the Operation Process of Cold- Chain Logistics Distribution Centre

OPTIMIZED CONCRETE DELIVERY SCHEDULING USING COMBINED SIMULATION AND GENETIC ALGORITHMS. Ming Lu Hoi-Ching Lam

CHAPTER 2: MODELING METHODOLOGY

Managing Supply Uncertainty in the Poultry Supply Chain

Performance review of a pipe jacking project in Hong Kong

Container Terminal Modelling in Simul8 Environment

A Modeling Tool to Minimize the Expected Waiting Time of Call Center s Customers with Optimized Utilization of Resources

New Stadium Project. Construction Activity Mitigation Program. January 22, 2014

SIMULATION OF TRUCK SAFETY INSPECTION PROCEDURES AT THE TEXAS/MEXICO BORDER

A SORTATION SYSTEM MODEL. Arun Jayaraman Ramu Narayanaswamy Ali K. Gunal

INTERIM ADVICE NOTE 103/08. Advice Regarding the Assessment of Sites for Ramp Metering

Pei Tang Darrell Cass Amlan Mukherjee. Michigan Technological University 1400 Townsend Drive Houghton, MI 49931, USA.

Assistant Professor, Department of Electrical Engineering, Hong Kong Polytechnic University

Proceedings Of The Institution Of Civil Engineers: Transport, 2008, v. 161 n. 2, p

Blocking Effects on Performance of Warehouse Systems with Automonous Vehicles

Transportation and Works Department The Regional Municipality of York Yonge Street Newmarket, Ontario L3Y 6Z1

SIMULATION OF BORED PILE CONSTRUCTION

A Sophisticated Transit Signal Priority System How it Works

ARCHITECTURE OF FMS. Typical Elements of FMS. Two Kind of Integration. Typical Sequence of Operation

FLEXIBLE APPOINTMENT BASED SYSTEM WITH ADAPTIVE RESPONSE TO TRAFFIC AND PROCESSING DELAYS

Ch 15 Manual Assembly Lines

An Adaptive Planning Tool for Ship Construction and Material Logistics

PIPE JACKING. An introduction to pipe jacking prepared by the Pipe Jacking Association

SIMULATION APPROACH TO OPTIMISE STOCKYARD LAYOUT: A CASE STUDY IN PRECAST CONCRETE PRODUCTS INDUSTRY

Sardar Patel College of Engineering University of Mumbai Andheri (West), Mumbai-58

DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS

SIMUL8-PLANNER FOR COMPOSITES MANUFACTURING

EXHIBIT LIST No Exhibit Name Page 1 P5 Traffic Presentation.pdf (P5) 2-20

PULL PRODUCTION CYCLE-TIME UNDER VARYING PRODUCT MIXES

UNIT V TRAFFIC MANAGEMENT

A multi-train movement simulator with moving

GUIDE FOR THE PREPARATION OF TRAFFIC IMPACT STUDIES

The Construction of the Langham Place. An Urban Renewal Project that re-shaped the urban landscape of Mong Kok

A SIMULATION BASED APPROACH FOR DOCK ALLOCATION IN A FOOD DISTRIBUTION CENTER

Simulation Analysis on Alternatives to Accelerate the Passenger Flow in Security Checkpoints

SPORTS ARENA PROJECT BRIEF

PRODUCT-MIX ANALYSIS WITH DISCRETE EVENT SIMULATION. Raid Al-Aomar. Classic Advanced Development Systems, Inc. Troy, MI 48083, U.S.A.

Paper Review: Proactive Traffic Merging Strategies for Sensor-Enabled Cars. Brian Choi - E6778 February 22, 2012

3.6 Construction Methods

Macroscopic and Microscopic Simulation for the Evaluation of People Mover Systems. Dr.-Ing. Peter Mott Sven Beller PTV AG, Karlsruhe, Germany

CIVIL ENGINEERING BENEFITS OF BIM. Helping Civil Engineers do more with BIM

Railway Model Aids Designers and Tenderers

BCEO TRAFFIC IMPACT STUDY GUIDELINES

Performance you can see

4 BUILDING YOUR FIRST MODEL. L4.1 Building Your First Simulation Model. Knowing is not enough; we must apply. Willing is not enough; we must do.

TRAFFIC IMPACT ASSESSMENT GUIDELINE

SIMULATION AS A TOOL FOR RESOURCE MANAGEMENT. Tarek M. Zayed Daniel W. Halpin

Investigating the Impacts of Fixed-Time Ramp Metering through Microsimulation

Deployment and Evaluation of ITS Technology in Work Zones

TUNNEL_SIM: DECISION SUPPORT TOOL FOR PLANNING TUNNEL CONSTRUCTION USING COMPUTER SIMULATION. Mohamed Marzok Moatassem Abdallah Moheeb El-Said

1 Transport. Introduction. 1.1 Lorries have empty or part loads

Industrial Engineering Applications to Optimize Container Terminal Operations

Traffic Management Guide to Concrete Overlay Solutions. Dale S. Harrington P.E. Representing CP Tech Center

Transcription:

Proceedings of the 2011 Winter Simulation Conference S. Jain, R.R. Creasey, J. Himmelspach, K.P. White, and M. Fu, eds. INTEGRATION OF CONSTRUCTION AND TRAFFIC ENGINEERING IN SIMULATING PIPE-JACKING OPERATIONS IN URBAN AREAS Sze-Chun Lau Halcrows China Ltd. Kwun Tong, Kowloon, Hong Kong The Hong Kong Polytechnic University Hung Hom, Kowloon, Hong Kong Ming Lu University of Alberta Edmonton, Alberta Canada Chi-Sun Poon The Hong Kong Polytechnic University Hung Hom, Kowloon Hong Kong ABSTRACT Construction simulation and traffic simulation are complementary to successful planning of microtunneling and pipe-jacking operations in urban areas. With increasing concerns on sustainable development, it is imperative to integrate construction engineering and traffic engineering in simulation modeling in order to plan for efficient site operations while reducing the impact of construction upon traffic. In this research, we demonstrate a larger system simulation approach to effectively plan pipe-jacking operations in urban areas in considerations of (1) truck delivery routes and timing; (2) sizing and location of temporary laydown area on site; (3) traffic lane closure distance; and (4) working hours scheduling, aimed at minimizing the negative impact of construction on traffic. Our research goal is to deliver a temporary traffic arrangement plan along with an efficient site operations plan, thus keeping a balance between construction productivity and traffic mobility. A case study is given based on a pipe-jacking site in the urban area of Hong Kong. 1 INTRODUCTION Construction simulation and traffic simulation are complementary to successful planning of microtunneling and pipe-jacking operations in urban areas. With increasing concerns on sustainable development, it is imperative to integrate construction engineering and traffic engineering in simulation modeling in order to plan for efficient site operations while causing minimal traffic impact. Microtunneling and pipe-jacking operations are commonly classified as trenchless technologies which minimize the open cut area, but lane closure is still required around the jacking and receiving shafts. Extended duration for lane closure leads to traffic queuing, more user delay cost and social cost. Reduced traffic mobility also increases material handling cycle time in construction, holding up ring pipe deliveries. As only limited buffer storage is available onsite, the traffic delay potentially idle the crew and the TBM, lowering productivity while increasing the direct cost and project duration. Planning the temporary traffic arrangement (TTA) involves communication and consultation with relevant authorities (including the traffic department and the police department), and consideration of traffic safety and possible complaints from road users and local businesses. In this research, we demonstrate a larger system simulation approach to effectively plan pipejacking operations in urban areas in considerations of: (1) truck delivery routes and timing; (2) the sizing 978-1-4577-2109-0/11/$26.00 2011 IEEE 3516

and location of temporary laydown area on site ; (3) the traffic lane closure distance; and (4) working hours scheduling, aimed at minimizing the negative impact of construction on traffic especially during the peak hours. Our research goal is to deliver a temporary traffic arrangement (TTA) plan along with a site operations plan, thus reaching a balance between construction productivity and traffic mobility. A case study is given based on a pipe-jacking site in the urban area of Hong Kong. The construction simulation platform of SDESA (simplified discrete event simulation approach) is utilized to simulate the larger pipejacking system integrating construction engineering and traffic engineering. 2 RESEARCH NEEDS FOR INTEGRATION OF CONSTRUCTION AND TRAFFIC ENGINEERING TTA planning involves work zone establishment, lane closure design, and traffic throughput reduction analysis, which plays a pivotal part in achieving smooth and successful operations at microtunneling sites. Owing to the limited road width in the urban area, the traffic impact induces prolonged queuing to road users, potentially leading to public complaints and substantial social cost. The TTA plans are usually prepared by traffic consultants based on available traffic flow information and previous TTA plans in the vicinity. In order to verify the effect of the TTA plans at critical locations, trial runs in the first one or two days before the actual project commencement would be requested by relevant traffic authorities. However, this practice entails experimentation of the TTA in the real world, possibly causing major traffic disruptions and incurring exorbitant social cost. In view of the public interest, modeling the trafficconstruction interaction on pipe-jacking sites situated in dense urban areas is well warranted, as echoed at the Research Needs for New Construction using Trenchless Technologies conference held on 17th June 2003 at the University of Birmingham UK (Chapman et al. 2007). On the conference, the whole life costing of trenching and trenchless technology including social cost ranked the highest during the voting on generic issues of planning, design and monitoring. The present research applies discrete simulation modeling to automate the lane closure layout design and investigate the impact of construction upon the traffic. 3 PREVIOUS RELATED RESEARCH Lau et al. (2009) established a framework for developing intelligent decision support tools in order to facilitate effective microtunneling construction planning with a focus on general site operations planning. Lau et al. (2010A) implemented a simulation model for a microtunneling site and demonstrated the application values of the simulation model for construction planning. To assess the traffic impact imposed to road users and formulate material delivery schedules after the implementation of TTA plans on the microtunneling site, Lau et al. (2010B) proposed an simulation model for lane closure planning in congested urban areas. 4 CONSTRUCTION SIMULATION APPLICATION A simulation model of typical microtunneling operations was set up using simplified discrete event simulation approach (SDESA), which is an activity-based simulation modeling platform developed from inhouse research for both detailed construction operations simulation and critical path method (CPM) based scheduling simulation. Interested readers may refer to Lu (2003) and Lu et al (2007) for details on simulation algorithms and generic process mapping. The site operations model portrays logical sequences, resources, technical constraints, and common activities on microtunneling sites. Further site-specific constraints can be added to individual simulation cases. At the planning stage, the simulation tool is used to investigate the effects of various combinations of resource allocations, pipe section delivery cycle times and site layout designs. The statistical distributions of the pipe-section installation cycle time provide input models for detailed jobsite planning. Before the project commences, the project planner could take a typical microtunneling model template for a quick launch of simulation modeling. The simulation model is fine-tuned based on the actual site layout plan 3517

and estimated activity durations. Further site constraints such as the installation of spacers due to shaft size limitation or the number of intermediate jacking stations are defined in the model. Spatial constraints can be introduced according to the maximum quantities of pipe sections to be stored on site. This would further pose a logistical constraint to the project planner who aims to achieve just-in-time deliveries. Figure 1: Simulation Model for microtunneling construction The site operations model was defined during the site planning stage, consisting of logical sequences, activity durations and resource allocation. The Jack workflow was the major workflow in the model and facilitated by other supporting work flows such as Mix Lubrication and Empty Spoil Tank, and Pipe delivery and Crane (lifting). The stochastic activity durations for site operations were entered into the model for statistical analysis of overall system performances. The daily site working cycle is defined as follows: 1) Preparation time (Warm-up period): 0800-0830; 2) Working time 1: 0830-1230 (240 minutes); 3) Lunch hour: 1230-1330; 4) Working time 2: 1330-1730; 5) Cool-down time: 1730-1800. The statistical distribution of working time is shown in Figure 5. 3518

5 WORK ZONE TRAFFIC THROUGHPUT SIMULATION At the site planning stage, the Temporary Traffic Arrangement (TTA) is planned based on 1) the required location and size of the jacking pit; 2) site access, including point of ingress and egress, any time restrictions; 3) the temporary storage or lay down areas near the jacking pit. The road between Entry and 25m away from exit as shown in Figure 4 is divided into 25 metre long sections, from Chainage 0 to Chainage 225. The location set is defined in the model as shown in Figure 2. All sections consist of two lanes in the baseline case, while one lane will be closed for the section between Approaching Taper & End Taper (i.e. L1, L2 and L3) when implementing the TTA plan in the work zone. Figure 2: Location Set for TTA plan of Microtunneling Site Table 1 summarizes the traffic flow details for various TTA sections, providing simulation input models. L i is the length of a particular lane section is defined as 25 metres along the road; L v is the length of a standard vehicle + gap between vehicles and is specified as 12.5m. Therefore, the traffic carrying capacity for a particular road section can be determined (Q i ) = L i /L v * number of lanes (1 or 2 for lanes within and outside the work zone). Chainage Table 1: Simulation Model Input for Traffic Flow Details at the Concerned TTA Section. Length (m) Speed (km/h) Number of cars per lane No. of lane Total Number of cars 50m from Entry to Approaching Taper Ch.0-25 25 24-30 2 2 4 Ch.25-50 25 24-30 2 2 4 Approaching Taper to End Taper Ch.50-75 25 24-30 2 2 (1 with TTA) 4 (2 with TTA) Ch.75-100 25 24-30 2 2 (1 with TTA) 4 (2 with TTA) Ch.100-125 25 24-30 2 2 (1 with TTA) 4 (2 with TTA) Ch.125-150 25 24-30 2 2 (1 with TTA) 4 (2 with TTA) End Taper to Traffic Light Ch.150-175 25 24-30 2 2 4 Ch.175-200 25 24-30 2 2 4 Traffic Light to Exit Ch.200-225 25 24-30 - 2-3519

Limited vehicle positions are defined to model the queues in traffic flows. Note that only when the previous position is cleared the current position would be released. Thus, the logical connection between consecutive road sections is that an empty spot in the next road section triggers the move-in of one vehicle from the previous road section, which releases the spot in the previous road section. The incoming traffic flow data for the simulation model in the morning (0600-1200) is summarized in Table 2. The peak hours (0800-1000) and non-peak hours (0600-0800 and 1000-1200) are defined by uniform distributions of inter-arrival time being [1,2] min and [2,4] min respectively. The traffic flows are equivalent to 1200 and 2400 vehicles per hour (two lanes) accordingly. Table 2: Simulation Model Input of Incoming Traffic Flow. Simulation Time Peak hour/ Inter-arrival Average Interarrival Time (s) Non-peak hour Time (s) Vehicle/hour 0600-0800 Non-peak UNIF[2,4] 3 1200 0800-1000 Peak UNIF[1,2] 1.5 2400 1000-1200 Non-peak UNIF[2,4] 3 1200 For the outgoing traffic flow, the vehicles pass through the work front and stop at a traffic light with the following details: the traffic light cycle time is 60 seconds; the green light phase (Tg) is 18 seconds; and the red light phase (Tr) is 42 seconds. Qg is the quantity of vehicles that can exit during the time period of Tg, which estimated to be 38 on average. The traffic simulation model is established using SDESA (Lu 2003; Lu et al. 2007) as shown in Figure 3. The flow entity diamonds leading a series of activity blocks denote the number of vehicles (vehicle arrival in different timeslots) or the quantity of traffic signals (e.g. the quantity of green light cycles for each hour) to pass through the system. The activity blocks represent activities that consume time and resources in processing a flow entity. Reusable resources (the number of traffic lanes along the chainage, the space blocks available for vehicle occupancy in the lanes) are defined in the resource pool to model traffic spatial constraints. The top left corner of activity blocks shows the resources required to execute an activity. Disposable resources are differentiated from reusable resources by its temporary nature in form of intermediate products or information units generated by an activity (e.g. car at different chainages, CAR_0 at the right bottom of an activity Vehicle arrival ) and requested by another (as shown in the top left corner of the activity block (Vehicle Travel) From Ch.0 to Ch.25 and prefixed with + ). An activity would commence as soon as all the logical criteria (resources, signals) specified on an activity block are satisfied. Upon the completion of an activity, the reusable resources (the available space blocks in lanes in this traffic model) would be released and disposable resources generated at the top and bottom right corner of activity blocks, respectively (those disposable resources are usually signals to link up different flow entities according to the logical sequences, for example, a vehicle travels across a section and then enters into the next section). The top three flow entities initiate vehicles entering the system during the timeslots 0600-0800, 0800-1000 and 1000-1200 respectively with the pre-defined vehicle inter-arrival time distributions based on the peak-hour and non-peak-hour traffic statistics. Note one car at Chainage 0 (CAR_0) is generated at the right bottom corner of three activities Vehicle arrival at 0600-0800, Vehicle arrival at 0800-1000 and Vehicle arrival at 1000-1200. The subsequent flow entity Vehicle Approaching can then be activated once the signal is passed to the activity (Vehicle Travel) From Ch.0 to Ch.25 which commences when the all resources required are ready including an empty lane 1 LANE 0 and one Car at Chainage 0 +1 CAR_0. The completed activity would further trigger its subsequent activity (Vehicle Travel) From Ch.25 to Ch.50. 3520

Figure 3: Traffic Model Using SDESA for TTA of Microtunneling Site It is noteworthy that a Start-Finish relationship is defined in the model for the queuing activity. Unlike typical construction processes where the activities are usually linked up by Finish-Start relationship (e.g. form working, concreting and removal of formwork), traffic modeling is on the opposite. The queue builds up from the front while the vehicles approaching behind wait until the vehicles in front are cleared. As shown in Figure 3, a position at Ch. 50 + 1 POST_50 is generated upon the completion of Activity 7: Approaching Taper Ch. 50 to Ch.75. The signal would in turn initiates Activity 6: Queue at Approaching Taper since the space in front is ready for a car to move in. The initial traffic model is defined as a two-lane carriageway as a baseline for traffic impact assessment. The traffic flow information including incoming, passing and outgoing flows is given in the tables above. The model is then modified according to the TTA plan, for which one of the two lanes is closed during the course of construction. The traffic statistics of the system before and after TTA implementation can be compared during the peak and non-peak hours. The traffic impact measures including the queue length and the Added System Residence Time of Each Car can be obtained from simulation outputs. 3521

Ch.0 Entry Ch.50 Approaching Taper Ch.150 End Taper Ch.200 Traffic Light Ch.225 25m from Exit Lau, Lu and Poon Based on simulation results, the site planning engineer can revise the site configuration, adjust the time for TTA implementation (e.g. 24/7 or 1000-1600 at working day) and schedule loading / unloading of equipment and material deliveries (e.g. only during non-peak hours). The expected queuing time can be also used as a reference for planning the construction delivery cycles. For example, given expected delay of [20, 30] minutes during the peak-hours resulting from simulation, the site engineer can consider non-peak hour deliveries so as to avoid the delay or arrange for material deliveries only to other sites with less traffic congestion in peak hours. For a multiple-lane carriageway as shown in Figure 4, the planner can make use of the simulation tool for simulating the closure of two of three lanes during the off-peak hours for loading/ unloading of jacking equipment at a congested site in which there is not enough space for the accommodation of a large crane within the site. 45 W=3.7m Loading/ Unloading Approach Taper L 1 =32m Works Area L 2 =50m End Taper L 3 =4m Low intensity battery operated lamps High intensity battery operated lamps Figure 4: TTA plan of Temporary Loading / Unloading Beside a Microtunneling Site 6 INTERGRATION OF CONSTRUCTION SIMULATION AND TRAFFIC SIMULATION The construction simulation is then integrated with the traffic simulation through linking the pipe delivery trucks into the traffic model. Different delivery patterns, including all-day delivery and non-peak hour delivery only, are tested in the integrated model. Such integration produces a prediction of pipe delivery delay for construction management and a prediction of traffic delay for traffic management. The integrated model facilitates arriving at a win-win solution in regard to construction productivity and traffic mobility. 7 RESULTS AND DISCUSSION The behavior of logistic cycle times and resource utilization rates in different simulation scenarios would vary considerably. The simulation model can be used as a platform for productivity analysis based on different jacking cycle times (or advance rates for the tunnel boring machine). Further decisions can be made based on the utilization rate of resources resulting from the simulation model as shown in Figure 6. For example, when long cycle time is foreseen, the manager may consider revising the material delivery schedule while reallocating any under-utilized resources on site in order to increase cost efficiency. In this sense, the simulation models can render competent decision support to project planners in optimizing microtunneling production parameters. 3522

Figure 5: Histogram of actual cycle time at So Kwun Wat microtunneling site Figure 6: Screenshot of SDESA model outputs on activity duration and resource utilization statistics From the simulation results, the baseline case was found to carry the smooth traffic, as indicated by a maximum queuing length of 5 vehicles throughout the whole construction period. On the other hand, the traffic queuing was observed with the implementation of TTA plan as shown in Figure 7, the queue length builds up starting from 08:00 with the introduction of the peak hour traffic flow and reaches a maximum quantity of 255 vehicles per lane at 10:00. The digestion of the whole queue length requires further 30 minutes after the incoming traffic flow changes from peak-hour rate to non-peak hour rate. The effect of construction on traffic can also be indicated by the "Added System Residence Time of Each Car" statistics, which measures the additional time for the road user to spend in passing through the system. In this case, the average "Added System Residence Time of Each Car" is 189 seconds and the standard deviation is 231 seconds. With the assistance of the simulation tool, the construction planner can review the possibility of extending Tg for increasing the Qg (which is equivalent to distributing the queue length between the two directions of traffic flows by adjusting traffic light cycle times at the intersection.) The 3523

"Added System Residence Time of Each Car" would be used as an effective indicator for resource planning and logistics planning on site. For example, given the pipe sections would be delivered to site in the morning, the planner should assign the delivery the day before in order to avoid the peak hours during which the queuing time would significantly increase. He or she may re-schedule the material delivery plan for different concurring construction sites so as to prevent prolonged idling time of critical construction equipment resources, such as TBM, site crews, and trucks. Another potential application on the simulation results is to forecast the expected driving delay to the road users based on the queue length and the Added System Residence Time of Each Car. For example, threshold values can be defined as: the Amber driving delay signal for expected queue length longer than 100 vehicles; the Red driving delay signal for expected queue length longer than 200 vehicles; and the Black driving delay signal for expected queue length longer than 300 vehicles. The expected driving delay can be updated on the Google Map such that the road users can decide whether to use the route passing through the TTA plan or choosing alternative driving routes. Red Driving Delay Signal Amber Driving Delay Signal No signal Figure 7: Queue length against time with TTA plan 8 CONCLUSION Construction simulation and traffic simulation are complementary in successful planning of microtunneling and pipe-jacking operations in urban areas. With increasing concerns on sustainable development, it is imperative to integrate construction engineering and traffic engineering in simulation modeling in order to plan for efficient site production while causing minimal traffic impact. Planning the temporary traffic arrangement (lane closure) involves communication and consultation with relevant authorities (including the traffic department and the police department), and consideration of traffic safety and possible complaints from road users and local businesses. In this research, we have demonstrated a larger system simulation approach to effectively plan pipe-jacking operations in urban areas factoring in: (1) truck delivery routes and timing; (2) temporary laydown area on site in terms of sizing and location; (3) traffic lane closure distance; and (4) working hours scheduling, all aimed at minimizing the negative impact of construction on traffic especially during the peak hours. Our research goal is to deliver a temporary traffic arrangement plan along with a site operations plan, thus keeping a balance between construction efficiency and traffic mobility. A case study is given based on a pipe-jacking site in the urban area of Hong Kong. The construction simulation platform of SDESA (simplified discrete event simulation approach) was utilized to simulate the larger pipe-jacking system integrating construction simulation and traffic simulation. 3524

ACKNOWLEDGEMENT The authors are grateful to Mr. Eric Lo, Technical Director of Black & Veatch Hong Kong Ltd., for his valuable input that was conducive to the identification, definition and validation of this research. REFERENCES HyD 2006. Code of practice for the lighting, signing and guarding of road works, Fourth issue 2006, Highways Department, HKSARG. Lau, S. C., Lu, M., Ariaratnam S.T. 2009. Development of intelligent decision support means for effective microtunneling construction planning. Proceedings of Global Innovation in Construction Conference 2009, 13-16 September 2009, Loughborough, UK, 556-565. Lau, S. C., Lu, M. and Lo, E. K. I. 2010A. Planning pipe-jacking operations through simulation modeling based on a twin-tunnel microtunneling site in Hong Kong. Proceedings of International No-Dig 2010, 28th International Conference and Exhibition, 8-10 November 2010, Singapore, 313-319. Lau, S. C., Lu, M., Ariaratnam, S. T. 2010B. Simulation-Based Approach to Planning Temporary Traffic Arrangement for Microtunneling Operations in Urban Areas. 10th International Conference on Construction Applications of Virtual Reality 2010, 4-5 November 2010, Sendai, Miyagi, Japan. Lu, M. 2003. Simplified discrete-event simulation approach for Construction Simulation. Journal of Construction Engineering and Management, ASCE, 129(5):537-546. Lu, M., Chan, W. H., Zhang, J. P. 2007. Generic process mapping and simulation methodology for integrating site layout and operations planning in construction. Journal of Computing in Civil Engineering, ASCE, 21(6):453-462. AUTHOR BIOGRAPHIES SZE-CHUN LAU is now a Tunnel Engineer in Halcrow China Ltd. working on the detailed design of MTRC Shatin-Central Link project in Hong Kong. He is a part-time Ph.D. candidate in the Department of Civil and Structural Engineering of the Hong Kong Polytechnic University. He received his Bachelor and Master Degrees in Civil and Environmental Engineering from the Hong Kong Polytechnic University in 2006. He attained his professional qualifications in 2009. His current research interests are: Productivity analysis of trenchless technologies, simulation modeling of trenchless site operations and artificial neural network modeling of tunneling construction. His email address is samuel_lsc@yahoo.com.hk. MING LU had worked as site engineer and project manager for three years in the construction field prior to beginning his pursuit of Ph.D. in Construction Engineering and Management at the University of Alberta in Aug. 1997. In Nov. 2000, Dr. Lu joined the Department of Civil and Structural Engineering of Hong Kong Polytechnic University. In September 2010, Dr. Lu assumed a position of Associate Professor based in the Department of Civil and Environmental Engineering, University of Alberta, Canada. His email address is mlu6@ualberta.ca. CHI-SUN POON obtained his Ph.D. from Imperial College, London. He joined the Hong Kong Polytechnic University in 1992 and is now a Professor and Associate Head (Research) at the Department of Civil and Structural Engineering. His email address is cecspoon@polyu.edu.hk. 3525